Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1.0 JOB SPECIFIC DATA TRANSIENT HEATER Non IBR W0082101001 Thyssenkrupp Industries India Pvt. Ltd. Red Sugar , Russia : Centrifugal spares KA-3715-3/0 Thyssenkrupp Industries India Pvt. Ltd. 2500004140 Dt. 13/06/2011 EPE/2K10/008 -01,02,03,04
Name Of Equipment Drawing Number Client Project Part No. Inspection Agency Owners P.O.Number W.O. Number 2.0 ABBREVIATIONS
Design Department Procedure Qualification Record Penetrant Testing Quality Control Department Company Acceptance Standard Welders Performance Qualification Welding Procedure Specification Work Instruction
3.0
INSPECTION POINTS
R Review
H under control by column indicates authorized inspectors hold point This means the job cannot proceed further unless cleared by authorized Inspector. W under control by column indicates that authorized inspector shall be notified and he may exercise his option to witness and verify a specific operation. further operation shall proceed where the authorized inspector does not validate his option. R under control by column indicates that only documents will be submitted to authorized inspector for review.
0 Rev No
20/06/11 Date
NSP Prepared By
Approved By
Remarks
1 of 3
Review of QAP Indication of Hold, Review, & Witness Points Review and approval of detailed drawing
Scope
Design
Material Chemical & Identification (plates, Physical tubes, pipes, flanges) Properties Dimensions
100%
QA
Tube Sheet
4 Dimensions Hole Size No. Of Holes Pitch Straightness Measurements Scale Drawing 100% Standard QA H R
Flange-Pipe Assembly
5 Weld set up Groove Angle Root Gap Root Face Weld size , visual inspection Measurement Measurement Visual 100% 100% Drawing QA H R
Welding of above
Drawing
QA
Casing
7 Dimensions Weld set-up of Casing Nozzles to Casing weld set up Welding of above Size Bevel Angle Root Gap Root Face Bevel Angle Root Gap Root Face Weld size , visual inspection Measurement Measurements Scale Measurements Scale Measurement Visual 100% Drawing 100% Standard Drawing 100% Standard Drawing QA H R
QA
100%
QA
1 0
Drawing
QA
0 Rev
20/06/11 Date
NSP Prepared By
SP Checked &
Approved By
Remarks
2 of 3
Sr N o
ACCEPTANCE STANDARD
CHECK BY
Final Assembly
13 14 15 Hydro test Shot Blasting Painting Welding leakages Surface roughness Surface Finish 100% 100% 100 % Drawing Drawing As per Standard Method QA QA QA H H H R/W R R
0 Rev No
20/06/11 Date
NSP Prepared By
Approved By
Remarks
3 of 3