Week No. Operation Contract awarded to RAD by Seeda and Mr.

Baker

Site Preperation / Set-up


1 2 3 4 5 6 7 Set-up and organise access from road to site Location of working facilities: Toilets, Changing Rooms Location for stock of building materials Set-up site hoarding and safety signs, PPE storage areas Connect utility supply for building works On-site waste control: place waste skips Early drainage planning and setting-out

Main Structure - Internal - Swimming Pool


8 Clear out and prepare all internal surfaces for building works 9 Stripping Out - Soft - Remove all partitions ### Stripping Out - restore window frames internally ### Reinforce all arches and support structures ### Break out ground floor slab ### Level out swimming pool trench to be used for storage ### Cast new ground floor slab ### Complete the drainage works ### Reinforce swimming pool trench: tanking ### Services & Cellar Hoist System, Air Cooling system, Pumping System ### Install balustrades ### Install new partitions: WC, staff room, security boxes, DJ booths ### Add services to partitions: water pipes, electrics, ventilations ### Close partitions ### Install tiles and floor systems : dancefloor ### Install wall fittings ### Joinery: doors, screens and bar counter ### remaining fixtures and fittings : dcor All ### Lighting, Sound equipment and Stage ### Clear and clean up

Main Structure - Internal - Restaurant / Bar


### Clear out and prepare all internal surfaces for building works ### Stripping out - soft ### Break out floor brickwork and concrete bed ### Level out and cast new concrete floor slab ### Install kitchen services and electric and bar services ### Complete drainage ### Install new partitions and glass screen fittings ### Add electric services to partitions

### Close partitions ### Install floor system - tiles (kitchen) hardwood (bar / restaurant) ### Walls masonry ### Joinery - doors and worktops and bar counter ### Integrate acoustic systems ### Dcor and lightings fixtures and fittings ### Clear and clean up

Roof Work (External)


### Installation of scaffolding ### Remove existing damaged roof tiles and framework ### Install waterproof membranes ### Install new framework and patch repair to some tiles, install new tiles ### (Scaffolding to remain for external restoration work)

Roof Work (Internal)


### Install roof insulation ### Close pitched roof panels ### Install suspended ceiling framework / fixture hangers ### Install lighting and audio and ventilation / Air Conditioner ### Install acoustic ceiling tiles

External Restorations
### Repair of cracked brickwork: Crack stitching required throughout ### Stonework around windows and openings to be repointed ### Plant and fungi growth to be treated ### Ventilators cleaned and air bricks need to be installed ### Woodwork: Window frames ### Window glass replacement / fitting ### New doors to be installed to all openings ### Down-pipes, eaves gutters de-rusted and painted

External Landscape Access


Final clean and clear out of entire site Handover upon completion