Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
europe
GENEVA 2009
2009, CErn, HEg, AutHors - tHis mAtEriAl is proVidEd CourtEsy of EVA EuropE 2009, tHE EuropEAn orgAnisAtion for nuClEAr rEsEArCH(CErn), tHE gEnEVA sCHool of businEss AdministrAtion (HEg) And tHE AutHors. All rigHts rEsErVEd. tHE ContEnts mAy not bE rEproduCEd witHout pErmission of tHE AutHors And EVA EuropE.
EVA EuropE 2009 wAs jointly orgAnisEd by gold sponsors pArtnErs
Technique...integrates project Scope, Cost and Schedule measures to help the project management team assess project performance.
PMBOK Guide, 2008
EVM History
EVM emerged as a financial analysis specialty in United States Government programs in the 1960s on DoDs programs (Polaris missiles) EVM was not limited to the DoD for long. It was quickly adopted by the National Aeronautics and Space Administration also received greater attention by publicly traded companies in response to the Sarbanes-Oxley Act of 2002
Actual Cost (AC) Planned Value (PV) Cost Variance = EV - AC Actual Time Variance Schedule Variance = EV - PV
Data Date
Time
Planned Value (PV) = [(BAC/Project Duration) x Elapsed time units] Actual Cost (AC) Earned Value (EV) = BAC x Physical % Complete Cost Variance (CV) = EV - AC Schedule Variance (SV) = EV - PV Cost Performance Index (CPI) = EV / AC Schedule Performance Index (SPI) = EV / PV Estimate at Completion (EAC) = AC+ETC Estimate to Compete (ETC) = BAC EV To Complete Performance Index (TCPI) = (BAC-EV)/(EAC-AC)
Acronyms, see PMBOK Guide
Cost
1
Time
(-)
(+)
Cost
2
Time
(+)
(+)
No action needed (unless spending customers money is an issue!) Under-achieving on the project, but overachieving for the spend Team performing well but under-resourced Under-achieving, and overspending for the achievement Team under-resourced and under-performing
Cost
3
Time
(+)
(-)
Cost
4
Time
(-)
(-)
Progress Measurement
Progress measurement : difficulties to define a precise and accurate way of estimate the work performed Existing ways of measurement:
Physical % Complete (ex. 42.5% of task) Defined Steps (25/25/30/20) 0/100 Custom % Complete (n/y, ex. 20/80) Level of Effort (EV=PV) eg. Management tasks
References
ISO/WD 21500, International Organization for Standardization, to be published. Project Management Guide to Project Management. ISO 10600, International Organization for Standardization, 1997. Quality Management Guidelines to Quality in Project Management. American National Standard Institute, 1998. ANSI/EIA 748 EVMS Standard. AACE, Association for Advancement of Cost Engineering, 1956 2002. Project Management Using Earned Value, Gary C. Humphreys Humphreys & Associates, 2002. PMI , Project Management Institute, 2005. Practice Standard for Earned Value Management. PMI, Project Management Institute, 1996-2008. A Guide to the Project Management Body of Knowledge. Sarbanes-Oxley Act, 2002. Office of the Secretary of Defense & National Aeronautics And Space Administration, 1962. DOD & NASA Guide PERT COST.