LARSEN & TOUBRO CEYLINCO (PVT) LIMITED

CLIENT

AES KELANITISSA (PVT) LIMITED

PROJECT

AES KELANITISSA 168.1 MW CCPP - COLOMBO

TITLE METHOD STATEMENT FOR ERECTION OF UNIT AUXILLARY TRANSFORMER 8/10MVA

DOCUMENT NO: AESK L&T 02, 2002


REV DATE PREPARED DESCRIPTION

Issue Date : MAR


CHECKED APPROVED

02.0 3.20 02

KSN

KS

KSV

1.0 FORWARD:
Erection of UT Transformer 8/10 MVA.

2.0 SCOPE
To drag the transformer which is placed on the rails to position & erection of the accessories .

3.0 ERECTION SCHEME.


The location were the transformer is to be positioned the area to be prepared/cleared & cleaned. The transformer is dragged on the rails to the position by chain pulley/hookchuk. Once the transformer in position the transformer wheels are locked. Before the erection of accessories is commenced the bushings are checked for any transport damages. The radiators are opened from the crates and checked for any damages thoroughly cleaned with clean dry air. During transportation blanking plates which are provided on the oil circulation pipes the same to be removed both in the radiators and transformer main tank. The radiators are mounted on to the transformer main tanks necessary gaskets are also fixed as per the drawing. The valves are opened which are on the main tanks so that checks can be made for any leakages. The conservator is erected and its associated piping are also done. The leakages are checked. The marshalling box is mounted/erected at the location. The cooling fans control cabinets are mounted. Wiring from the devices like OTI, WTI, BUCHLOZ, are done. Topping of oil: Since the transformer are transported with oiled filled up to the core level. The BDV is to be checked for the transported oil along with the transformer before topping up. The oil topping to be done conservators and radiators through filter machine the level to be maintained as per the oil level indicator. The filtration to be carried out for the total oil. The Neutral grounding resistor are shifted to site from the stores. In the neutral grounding resistor the checks are carried to assure that there is no obstruction. The resistance values are noted for any open circuit and ohmic values. Neutral grounding resistor is be installed at the at appropriate location. The primary and the secondary cable are connected.

The neutral point of the transformer are connected to NGR and the connections are made from NGR to dedicated earth pits. The Transformer is earthed at two dedicated points which are provided on the transformer. The Transformer HT Cable box are also earthed from the main earth. The transformer is checked finally & cleared for testing purpose.

4.0 SAFETY :
All the equipment to used for the complete erection shall have proper and valid test certificates. The complete erection activity will be supervised by experienced engineer All personals deployed to carry out the erection shall use the personal safety appliances. First aid facilities will kept available.