DEPARTMENT OF
(Internship Program Report) UNITED REFRIGRATOR COMPANY LTD. NO. OF WEEKS :- 1 WEEKS INTERSHIP PROGRAM Date : 13-06-2011 To 18-06-2011 Submitted To:
HUMAN RESORCE DEPARTMENT
Submitted By:
MOHAMMAD YOUNUS JASWANT MANOJ KUMAR THAKUR (08IN70) (09IN03) (09IN46)
INTERNSHIP PROGRAME
PREFACE
This report contains the information about those departments which are visited by the internees. Whatever the machinery seen and the processes are observed, attracting the human mind and realizes the men what science has achieved and what kind of mericals has been done by it. Basically United refrigerator company ltd. (dawlance) is quite attention attracting industry it provides lot of opportunities to see, to observe, to achieve and to get the lot of experience about the industry as well as about the machinery. The technology installed at United refrigerator company ltd. (dawlance) is the latest one and it includes the hardworking labors, employess who give their best for the over all effectiveness of the company. This report may also contains the facts and the real figures of the various departments which are very beneficial for our experience and the also for the practical knowledge. The functions and the details of their working and the process as well as the timing and work break down structure is also mentioned in this report. This is edit by the students of the INDUSTRIAL ENGINEERING AND MANAGEMENT DEPARTMENT of the nominated university of jamshoro named MEHRAN UNIVERSITY OF ENGINEERING AND TECHNOLOGY JAMSHORO SINDH PAKISTAN. The details of the students are as under:MUHAMMAD YOUNUS (08IN70). MANOJ KUMAR THAKUR (09IN46). JASWANT SINHA (09IN03).
INTERNSHIP PROGRAME
ACKNOWLEDGEMENT
We are very thankful from the core of my heart to honorable ASSITANT VICE PRESIDENT , United Refrigerator company ltd. (DAWLANCE) , ABDUL ALEEM KHAN for providing us opportunity for training and whose intelligent, wise and sound leadership has converted manpower into wining combination by this industry into a gold mine. We wish to express my deep gratefulness to Whole HRD)for their consideration and supervision. It was a memorable time in United refrigerator company ltd. (Dawlance) due to his kind concern. We are also thankful to all concerned manufacturing supervisor and engineers for their precious advice and for the great encouragement and cooperation, because of which We have successfully completed our internship training of UNITED REFRIGRATOR COMPANY LTD. (DAWLANCE ) where we learned a lot.
INTERNSHIP PROGRAME
CONTENTS
Days of internships Day no. 1 Departments Production II (shearing, sheet Metal and welding ) Shearing section Sheet metal section Welding section Cabinet PC sheet Freezer door Basic panel side panel Compressor support Ref door and many more PRODUCTION III ( THE PAINTING SHOP ) CABINET painting shop EVAPORATER painting shop CONDENSOR painting shop DIP- COATING (Shelf painting shop ) Page no.
7 to 11
Day no. 1
12 to 16
INTERNSHIP PROGRAME
DAY NO. 2
PROUCTION IV (CONDENSOR MANUFACTURING AND OTHERS ) Shelf making section 17 to 23 Condenser making Iron handing section Chrome section U-V Light section. PROUCTION V ( PRE FOAMING ) What is PRE FOAMING ?? Process of PRE FOAMING & Stages. PRODUCTION V ( FOAMING ) What is FOAMING ?? Process of FOAMING ?? PRODUCTION VI ( ASSEMBLY LINE ) What is Assembly line ??? PRODUCTION I (PLASTIC MOULDING SECTION) Compounding section Injection section Hot stepping section Steam print section. Extrudes section Cable section MAINTENANCE What is MAINTENANCE ?? Objective of Plant Maintenance ?? Importance of maintenance.
UNITED REFRIGRATOR COMPANY LTD. DAWLANCE PREPARED BY MOHAMMAD YOUNUS (08IN70)
Day no. 3
24 to 27
Day no. 3
28 to 29
Day no. 3
30 to 31
Day no. 4
32 to 36
Day no. 5
37 to 39
5
INTERNSHIP PROGRAME
Methods of maintenance. Maintenance at Dawlance. Day no. 6 QUALITY CONTROL DEPARTMENT QUALITY AND CONTROL (Definations) What is QUALITY CONTROL ??? Quality Control At Dawlance. Quality Engineering Cell. Incoming Quality Control. Self Quality Inspection. SUGGESTIONS
40 to 48
INTERNSHIP PROGRAME
INTERNSHIP PROGRAME
SHEARING, SHELF METAL AND WELDING Shearing => To shear off the requires size of sheet is called a shearing
process.
Sheet -Metal => the various process that has been perform over the metal sheet
sop that give is the requires shape is to be called a sheet metal.
Welding => A process of permanent fastening important type used the most
important type used in dawlance is tug welding. It is the refer color; production eleven is the section where the man body of refrigerator is to be manufactured. Though the production elevens section is used to manufacture a lot of component put the cabinets is of the important component of production eleven section. RAW-MATERIAL OF PRODUCTION - II The raw- material of production of to (in the sheet form) 1) Metal steel 2) Galvanized iron 3) Vinyl coated Material (VCM) 4) Aluminum SHEARING SECTION: One the raw-material is receive from the store the sharing section is something that actually share of the sheet according to the requires size of specifications. The cabinet sheet is to be share of the sizing of Length = 3824mm Width = 655mm Thickness = 0.4mm Other thing also shares off according the specifications. SHEET METAL SECTION: There are basically no of parts has manufactured in this section. The sheet metal section is basically best upon the 4 major area which are as follows. 1: Automatic sheet feed 2: Whole processing and notch (bending) 3; forming section 4. Pressing section The sheet metal is basically used to produces a no of parts of refrigerator, such as
UNITED REFRIGRATOR COMPANY LTD. DAWLANCE PREPARED BY MOHAMMAD YOUNUS (08IN70)
8
INTERNSHIP PROGRAME
1. 2. 3. 4. 5. 6. 7.
Cabinet PC sheet Freezer door Basic panel side panel Compressor support Ref door and many more
CABINET: The cabinet is to manufacturing once the sheet is receive from sharing the automatic sheet feeder suck the sheet and feed the sheet then sheet through crame is to be shift into the forming section where the form of profile and embossing can take place and after ward that formed embossed is equally bended to form a cabinet. PC-SHEET: The pc sheet is the sheet that makes separates the freezer unit ref :a in other word we can say that the I.C sheet is used to make separate n/n ref and free from the upper side of refrigerator PROCESS: It can be making by follow the following operation. 1. Notching process 2. Forming process 3. embossing process 4. Whole process BACK PANEL: It is back side of refrigerator body that is to be attached with the cabin net. It is to be noted that is in small size refrigerate there Is only back panle and there is no need for the bottom end as it also requirement in the refrigerator. PROCESS: The back panel is to be made by the 1) Drilling the piece of M.S of sheet 2) Notching that piece 3) Whole also with the machine 4) first bending 5) 2nd bending After that this do of is to welded with the cabinet by spot welding process. SODE RANGE:
UNITED REFRIGRATOR COMPANY LTD. DAWLANCE PREPARED BY MOHAMMAD YOUNUS (08IN70)
9
INTERNSHIP PROGRAME
It just like the side panel it also require 1st cutting and the 2nd cutting and then just and 2nd pending. FREEZER DOOR: it is the front door of the refrigerator and it is to be made by the VCD material sheet. The size of VC sheet used a freezer door Length = 546 mm Width = 768 mm PROCESS OF FREEZER DOOR The freezer door is according following the process 1: Notching 2: Handle pressing 3: Embossing 4: first banding 5: final banding REFRIGRATOR DOOR: It is also be made with the VCD type of material and it make we of same process as that of freezer door each and every step in same. COMPRESSOR SUPPORT: It is the part that can be placed in the both part of the ailment and it support the compressor. PROCESS: The process to manufacture the compressor is as 1: whole plating 2: further 2 more whole 3: just bending 4: final banding WELDING SECTION: Basically welding is the process of permanent fastening therefore is the section all or same part are to fastened by tug welding so that the required type and shape of cabinets is to be shift the painting shop. Basically at sheet metal the welding section is used to perform that activity so that the form bended and imposed cabinet is to be welded with the back panel and sight panel and the it is screwed with the compressor support. At the end of the welded section the welded cabinet is to be shift to the paint shop for the further paint processing.
10
INTERNSHIP PROGRAME
11
INTERNSHIP PROGRAME
PRODUCTION III THE PAINTING SHOP It is basically the painting section used to paint the various iron so that it could be transfer into the final assembly shop. It includes the, CABINET painting shop EVAPORATER painting shop CONDENSOR painting shop DIP- COATING (Shelf painting shop ) We had already discussed the dip-coating (shelf painting) and were here now we learned the cabinet and evaporator painting
STAGES # 2 PHOSPHATING
The phasphating process is actually though the following tank There are basically 4 different tankers. Out of them 2 of the chemical tank , 1 of water tank and 1 of di-ionized tank. The phosphating process begins after following the first step now the cabinet is dipped into the tank 1 ( which has the metaphoric chemical ) and then dipped into the tank2 ( which Laos has the same chemical ). Once the cabinet taken off from the tank 2 then it is to be dipped into the tank 3 which has the raw water. Finally the cabinet is to be placed into the di-ionbized tank and then the cabinet is to be phosphated.
INTERNSHIP PROGRAME
fisrt it is use to dry the water and moisture and secondly it is also make able the cabinet sheet to be attain the more powder ( as in next step ).
IMPORTANT TO REMEMBER
The cabinet paint shop has the capacity to paint 1800 to 1900 cabinet paint per 24 hours i-e capacity = 1800 to 1900 cainets paint per 24 hours.
13
INTERNSHIP PROGRAME
CONDERSOR PAINTING
Like all other painting section shops the condenser painting is also follwed the same process as that of other painting process.
INTERNSHIP PROGRAME
ii)
Painting
PHOSPHATING
The phosphating if condenser is to be done by passing through the no. of condenser to various chemicals which is in the tank . First of all the manufactured condenser is dipped into the metaclean 375 tank and it stayed over there at 1 to 5 min. Now the condenser is then dipped into the fresh rinsing water into the 2nd tank. After that it is to be dipped into the tank of metaphor 247 chemical tank. And after that through pressure vessel it is to be dried. At the end of phosphating the condenser suppose to shift into the dry oven and where the all moisture are dried from the phosphate condenser.
PAINTING
The painting begins when JOTUN powder is to be paint over the condenser after phosphating on both sides of condenser and this condenser with the help of crank is to be inserted into the back oven so that powder is to be converted into the layer of painted color. The temperature of back oven is about to be of 250 degree centigrade and it is placed within the back oven for the period of 11 min. It is important that the JOTUN powder use in condenser painting section if of different form and have it own load.
Important to Remember .. The capacity of condenser paint shop is 1700 condenser paint per day.
15
INTERNSHIP PROGRAME
16
INTERNSHIP PROGRAME
Like all other production section the PRODUCTION IV is also on e of the most important section of refrigerator production. It is use to make some important and value able item of refrigerator. There are various sections those are comes under production IV category i) Shelf making section ii) Condenser iii) Bottom condenser iv) Iron handle making section v) Galvanized section vi) Chrome section vii) U-V light section Through out all section of PRODUCTION IV have their own importance and without them the processing is incomplete but the most importance item produce by production iv is the condenser because without the functioning of refrigerator is impossible. Now we shall discuss each section in detail.
EQUPMENT IN USE
The shelf manufacturing makes use of different machines and welding device. Starter and cutting machine Pressing machines of different type Tag welding
INTERNSHIP PROGRAME
the requirement ) , now the cutted coil is then bended and it is to be welded now the frame of the shelf is been and also ready for the further processing. Now again the no. of strip is also to be cutted so that there can fixed into the shelf and then the shelf is to be welded by the tug welding process. Now in order to support the shelf various section of straight shapes, L shapes, Z- shapes, the basic purpose of these section is that they used to provide the support to the shelf of the refrigerator.
CONDESNSOR MANUFACTURING
Every manufacturer knows the importance of condenser in refrigeration process and without condenser the existence of the refrigerator is almost impossible because it is something that maintain the refrigeration cycle. Therefore in order to make the condenser manufacture the condenser much careful analysis are required. This section is use to make two different condenser. i) Back panel condenser ( actually called as condenser ) ii) Bottom condenser The actually the first step towards condenser manufacturing is taken by the engineering department.
UNITED REFRIGRATOR COMPANY LTD. DAWLANCE PREPARED BY MOHAMMAD YOUNUS (08IN70)
18
INTERNSHIP PROGRAME
Engineering department through critical analysis used to check the actual condenser and then give the effective and efficient proposed way to manufacturing in the shape of drawings, equipments etc.
BOTTOM CONDENSOR
Most of people even dont know is there any condenser in the refrigerator that place in the bottom of the refrigerator. The basic function of this condenser is also to reduce the temperature like other condenser do so .
INTERNSHIP PROGRAME
Now at the end the strip of MS also welded so that to provide the proper reinforcement to the condenser . By following the above stages the condenser is said to be manufactured.
GALVANIZED SECTION
It is the very little type of section and its purpose is to nickel the various parts such as i) leg holder ii) top middle bottom hinchees. iii) Screws and others parts. The basic behind this section is to do the nickel plating so that to remove all the abrasive material, oil, Greece etc. CHEMINCAL IN USE Following ar he chemical those are used in this section Zinc brightener Zinc Californiazinc anodenitric acid
CHROME SECTION
Once the handle cover is been made by the modeling section to make the handle cover then the crossing of that part is to be taken place.
PRCESS OF CHROMESECTION
The chroming is to be done by following the certain steps
INTERNSHIP PROGRAME
STEP # 4 :- After wards it is to be placed into the activation bath which also
include certain amount of HCL. STEP # 05 :- Now at this the nickel sulphate electroplating is to be done. STEP $ 06 :- after that the it is to be dipped into the copper the layer of copper in comes over the handle. STEP # 07 :- Nickling is to be done at this stage hence the nickling also to be placed over the handle. STEP # 08:- At the very last stage the chroming is to be done over the handle.
21
INTERNSHIP PROGRAME
22
INTERNSHIP PROGRAME
PRODUCTION V
(PRE- FOAMING)
Till production we are making, painting the certain parts so that they should combined to form the original product. The production V ( i-e PRE FOAMING ) as the name suggest it is the pre of the foaming that is it the place where the various operation is to carried before it is to be placed to formed. At the pre foaming the necessary item such as the liner, freezer and antimoisture tube, evaporator are to be inserted into the actual body of cabinet.
PREFOAMING PROCESS
The actual process of pre-foaming is starts when the painted cabinets from the cabinet painting shop are comes to the pre-foaming zone. We can underline the each and every step of pre foaming now STEP # 01:- First of all the compressor support is un-screwed from the painted cabinet.
STEP # 02:- The gum- type material named as slent is to be inserted into the corner edge of the painted cabinet in order to make proper isolation. STEP # 03:- Washer type material is tape within the four whole if the back panel
so that condenser is to be screwed easily in it.
STEP 04:- Bottom profile is inserted within the embossing area in the bottom. STEP 07:- spaces in fixed in the back panel so that the pipe which is fitted in it. STEP 06:- Groemr also fitted with the wholes. STEP 07 :- Anti moisture strip a black pipe is to be inserted within the profile
cabinet. The anti-moisture strip has two functions first as the name suggest its used to prevent from the corrosion effect also the gas kit ( rubber type ) within the door is causes to crack because of cooling inside so it is also prevent this as it is connected with the compressor. STEP # 09 :- the freezer box is to be further includes the following sub- systems Sub step 1:- the painted evaporator from the EMD is bend by the press machine. Sub-step 2:- the bended evaporator is then to be check for the little inspection. There are basically two different inspection tests,
23
INTERNSHIP PROGRAME
i)
A machine which is used to detect the all the pipe and join of the evaporator by inserted the Freon gas. The detector even has the capability to detect 1.0 micro gram of area. Once the evaporator is OK then it is to be shifted for the next test. The statistics show that there are basically 8 to 10 evaporators rejected in lead detector test. Once the purpose is established hen the Freon gas is to be ejected and stored and from the evaporator. ii) The 2nd inspection include is to check the mass flow rate within the evaporator and it is to be done by inserting the Nitrogen gas from the capillary. It is also gives the benefits in the shape that it tends to clean the evaporator by the nitrogen gas. Sub- stage 03:- Obtaining a evaporator frame. The evaporator from is to be make by joining the evaporator the side plate thorough a silicon type of material. Now this flow is to be fitted with the freezer side of the cabinet. STEP # 10:- The ref portion of the refrigerator is to be undertaken and it can be divided into the following sub steps. Sub step 01:- the liner which is come form the thermosetting section is first sized and cutted by the press machine. With the size the whole also produce which is of evaporator and thermocouple. Sub-system 02:- after that the head after and thermostat cover is taped within the liner. Sub- system 03:- a light pipe is having the wire which is the fitted with the thermostat on one hand and head after on the other hand. STEP # 11:- Liner is fitted within the cabinet i-e liner completely fitted within the cabinet. Thats the end of the pre-foaming suction.
24
INTERNSHIP PROGRAME
25
INTERNSHIP PROGRAME
FOAMING SECTION
The foaming section is a place when the pre-foamed cabinet is to foamed by the automated machine. The foam which is to be inserted within the pre-foamed foam than it is solidifying within a few minutes. The foam is basically made of two different type of chemicals. i) Polyoal ii) Iso cynate iii) R141B ( a gas whch is used as a catalyst ) The foaming section has the capacity to filled 81 mould foam per hour i-e capacity = 81 mould foam per hour.
PROCESS OF FAOMING
The process of foaming section begins by fixing the jigs and fixture within the ref section so that while foaming the inside the refrigerator is not bend etc. After that the highly automated the mixture of foam is to be inserted within the cabinet. The dawlance has 9 moulding foam hangers which is highly automated and used to operate according to the sensors and actuators and various other things. Basically the mixing of chemicals as to form the foam is to be as
P 100 :
g 16
: 1260
26
INTERNSHIP PROGRAME
27
INTERNSHIP PROGRAME
ASSEMBLY LINE
This is the very last portion of this shop also the refrigerator manufacturing. At this stage the all parts that we have made in deferent section such as sheet items or main body items we made in sheet metal section, plastic items we have marked in moulding, condenser e have made in production IV , shelf we have make in production IV , freezer and ref door also assembled Therefore is assembling shop we are the assemble all items to make the refrigerator. At the end certain inspection made refrigerator takes such as vacuum generation and then the Freon gas is also inserted into the refrigerator. At the end of assembled line the refrigerator are to be packed and transferred to the store room as a inventory so that it is it be distributed.
28
INTERNSHIP PROGRAME
INTERNSHIP PROGRAME
As the name suggest plastic molding the production is said to manufacture all plastic type of equipment that can be used in refrigerator manufacturing. There are 6 section includes in moulding each section have its own task to with they can act these are as follows, i) Compounding section ii) Injection section iii) Hot stepping section iv) Steam print section. v) Extrudes section vi) Cable section The compounding and injection are the most basic sections and these are those which used to produce they different plastics items in proper quality and quantity.
COMPOUNDING SECTION
The raw material of various plastics material in the form of huge grain is received in compounding portion through store room. These raw materials includes, PS ABS HIPS LIPS PC NYLONE & PP. The compounding section used to mix the raw material with the pigment so that required color of particular item is obtained. The mixing can be done by two different type of devices. i) DRUM MIXTURE ii) VERTICAL MIXTURE
DRUM MIXTURE
Drum mixture is a device which consist of two different drum and b/w the there is a motor that has the rotatory function. The motor used to rotate the drum. Each drum has the capacity to take two beg ( each beg of 25 kg i-e 50 kg ) so we can say that drum mixture can take 100kg of a material in a time.
INTERNSHIP PROGRAME
pigment according to the standard weighted and insert into the drum and then again another beg also inserted into the drum and similarly the next drum also filled. Now the drum mixture start rotating and mixed the material with the pigment and in 5 min the material is kept out just within the 5 min. Therefore we can say that the drum mixture has the capacity of 100 kg of material to be mix in 5 min.
VERTICAL MIXTURE :
It is also the mixing device and used to mix the material with the pigments go that the required material can be obtained. Though it can be used to mix all type of material but in compounding section of dawlance it is specifically used to mix the poly storing (IS) material with the pigment of T- brown , T green, smooth gray. Height impact poly strien (HIPS) material with the pigment of brilliant white.
INJECTION SECTION:
It is heart of the moulding section here all plain parts are been manufacture through injection mould mallina. The highly automated machine CLF- INJECTION MOULDING MACHINE use in this section. The machine can varies clapping force i.e the injection moulding machine (CLF- 8OT) has the minimum clapping force injection moulding machine (CLF- 800T) has the maximum clapping force. There are basically 52 CLF-MOULDING MACHINES are used and can vary in diff: clapping force to make very small item to the heavy plastic item.
1. HOOPER:
First of all material (mixed material) has come from the compounding section. Hooper actually use to collected the inserted material alive is the shifted in to into the bassel.
2. BASSEL:
UNITED REFRIGRATOR COMPANY LTD. DAWLANCE PREPARED BY MOHAMMAD YOUNUS (08IN70)
31
INTERNSHIP PROGRAME
After Hooper the material hydraulic piers machine comes into the bassel. In bassl this material first heated thorough 7- different zone and reach zone has two heaters.
3. INJECTION:
Once the material is to be melted with the help of heated now the material is to be injected through layer 6 to 7 different stage into the injected mould.
EJECT:
After completing the ague the maked part in then eject from the machine so that to perform the work. From all these the other part i-e. carriage is used to be mixed
EXTRUADES SECTION:
It is the of section actually injection moulding process and it is also used to make the profile that has been mould plastic material and give the shape of profile.
CABEL SECTION:
The refrigerator wire connection from the electric require a plug and cable so in this there things are to manufactured. Once the wire (cables to be purchased that first of on this cable are cables are to cutted the required size and then the folly steps are to be taken 1. Core stepping 2. Wire stepping 3. Pinch moulding 4. Pinch foulding 5. Princh moulding machine
SCREEN PAINTING:
As one have seen that there is numbering over thermometer regulator, also we have is painting over the shelf wider shelf similarly these is certain coding we have seen, so in thing reaction i-e screen painting , there coating has been painted over the items.
32
INTERNSHIP PROGRAME
MAINTENANCE
UNITED REFRIGRATOR COMPANY LTD. DAWLANCE PREPARED BY MOHAMMAD YOUNUS (08IN70)
33
INTERNSHIP PROGRAME
Today, in modern industry, equipment and a machinery are a very important part of the total productive effort than was the case years ago. Moreover, with the developments of special purpose and sophistical machines, equipment and machinery cost a lot more money and there fore their and does time becomes much more expensive. For this reason, it is vitally important that the plant machinery should be properly maintained. OBJECTIVES OF PLANT MAINTENANCE
i) ii) The objective of plant maintenance is to achieve minimum breakdown and to keep the plant in good working condition at he lowest possible cost. Machines and other facilities should be kept in such a condition which permits them to be used at their optimum (profit making) capacity without any interruption or hindrance. Maintenance division of factory ensures the availability of the machines, buildings, and services required by other section of the factory for the performance of their function at optimum return on investment whether this investment be in material, machinery or personnel.
iii)
iv)
METAINENCE METHODS
i) ii) There are basically two different maintenance methods i-e Tribology Tero technology
TRIBOLOGY
UNITED REFRIGRATOR COMPANY LTD. DAWLANCE PREPARED BY MOHAMMAD YOUNUS (08IN70)
34
INTERNSHIP PROGRAME
It is the method of maintenance that deals with the lubrications impact of the machine by proper maintenance. It includes oiling, greasing etc.
TETO-TECHNOLOGY
It is also the methods of maintenance that deals with the mechanical effect of the maintenance such as repairing of the part of machine, overhauling of the machine.
35
INTERNSHIP PROGRAME
36
INTERNSHIP PROGRAME
QUALITY CONTROL DEPARTMENT QUALITY:Though there are no. of definition of quality but in very simple works it can be term as To meet the customers specification .
CONTROL:The provision to control the action or plan is to be control so that to meet the requires as per planned.
QUALITY CONTROL:Quality control refers to the control level of quality si that to lead to the customer satisfaction. It is the provision under which the proper and effective quality it to be obtain so that to lead the market position. In an organization the term quality is as big as it can and under a no. of quality units are working their work to inspect the ongoing activity as per standard and then mark as OK, HOLD, USAI, REOWRK & SCRAPE.
INTERNSHIP PROGRAME
QUALITY STATUS
While inspected anything the doud full item are to be taken into 4 basic consideration rather than just to be called as scraped i-e by reviewing whole parameter the decision regarding the item is to be taken. There are basically four quality status . i) HOLD ii) UAI (use as is) iii) REWORK iv) S CRAPED It can be illus trade as ,
HOLD
UAI
REWORK
SCRAPED
HOLD =
INTERNSHIP PROGRAME
USE AS IS (UAI) = Though the part is not fully mismatched with the standard but the negotiation between the manufacture and quality incharge is to be taken and the item is it be USE AS IS (UAI). REWORK = There are few items those are require to rework so that to be come into the required expectation . SCRAPE = The item is to be scarped. QUALITY CONTROL MANUAL
It is basically a manual that can help the operator to perform the work takes as it includes all type of activities. These are those type of manual which use to perform the training function to the operation because its includes set of instruction of every used item.
SAMPLING TABLE
As we know when raw material receive there are basically a no. of lots and each lot having a no. of item therefore is extremely difficult to check each and every item and also time consuming because if we are doing to inspect every item so it is very difficult for us to meet the required demand. Therefore the process begins by checking first 3 lots completely i-e 100 % and then if the fault rate is same or reducing the accordingly move toward the sample mood in which according to lot size the item are randomly selected. The sampling mood sheet can be illustrate as ,
SAMPLING TABLE
LOT SIZE 2 to 8 51 to 90 500001 to over SAMPLE SIZE 2 3 13 ACCEPT QUALITY LEVEL ACCEPT 0 0 1 REJECT 1 1 2
39
INTERNSHIP PROGRAME
DC / IDC FORM
DC = DECIPLANE CHECK
INTERNSHIP PROGRAME
sample mood when according to the lot size sample is randomly selected and then be inspected. It is very much important to remember the incoming Q.C is not able to inspect all items just like chemical type of material is to be inspected in Q.C lab and hence the C-FORM is to be make for that. Incoming Q.C usually make visual dimensional inspection. Now we shall discuss the item as follows,
EVAPORATER
Evaporator is the type of item which is no. of time to be inspected starts from the Q.C and then final assembly inspection. The dawlance exports evaporator from china the suppler name Jau-su-shanfe. Though testing supplier are also inspected but the existing supplier Jau-su-shanfe is the major and more reliable supplier of evaporator. Evaporator is 100% inspected and there is no concept of sample mood.
JOTUM POWDER
We know the usage of JOTUN powder i-e its use for the paining purpose if items . The inspection of JOTUN is begins by batch the powder in term of their respective code and colors. After that the C- form is made and its sample of every batch shifted to the Q.C lab where the chemical is to be inspected in order to match the existing composition with the standard one.
INTERNSHIP PROGRAME
Every manufacturing side have its own self quality section whose purpose is to check the quality of manufactured item that make in his section as per required specification. There are basically two different type of inspection is to be taken place i) First piece Inspection ii) Roval inspection
FRONT SIDE
UNITED REFRIGRATION INDUSTRIES LTD
IN PROCESS QUALITY CONTROL DEPARTMENT
(SHEET METAL)
FIRST PIECE / MACHINES SETTING CERTIFICATE DATE___________________SHIFT______________________ TIME_______________________ MACHINE:______________________________________________________________________ PART____________________________OPERATION____________________________________ DIE/ MACHINE SETTER__________________________________________________________ DRAWING NO.___________________________MODEL_________________________________ SIGNATURE PROD. SUPERVISOR _________________________________________________
INTERNSHIP PROGRAME
SIZE
TOOL NAME
ROVAL INSPECTION
As we know that the variation over the item can be occur at any stage because of any fault in an machine therefore after first piece inspection the roval inspection i-e after every hour of same item also done to maintain the quality. The roval inspection certificate is filled according to the dimension.
43
INTERNSHIP PROGRAME
44
INTERNSHIP PROGRAME
INTERNSHIP PROGRAME
engineers of manufacturing staff and this meeting every supplier is interacting with his customer so that to know the current situation of each other and share their problems to each other. Hence just based on the general meeting the result as any stoppage or draw back in production they used to blaming to one another which in term leads to create conflict. Therefore if there will be a supply chain department so I think is a perfect accountability of each section and hence over all performance get improved.
The maintenance compliance that, They dont have enough work force to reduce the causes of unhappenings. Manufacturing too easily too band toward their improvemental thinking and its being extremely difficult to maintenance to meet all this. And there are various other factor that lead to create the conflict among the manufacturing and maintenance section.
UNITED REFRIGRATOR COMPANY LTD. DAWLANCE PREPARED BY MOHAMMAD YOUNUS (08IN70)
46
INTERNSHIP PROGRAME
SOLUTION
The main dramatic lack is also that there is no shutdown maintenance of machine been allow by administration because shutdown maintenance required 2 to 4 hours and obviously while doing shutdown maintenance the production gets stops and management not want any action that leads to stop the production . But if wee look from a close eye the machines get stops any time because of any lack then to give ordering to the maintenance and then it assign the optimal crew according to the work and then act this also requires a lot of time and in this period also gets stops therefore I think there ha to be same period of shutdown maintenance.
47
INTERNSHIP PROGRAME
PREPARED BY
Name: Mohammad Younus Fathers Name: Mohammad Anwar Qureshi Surname: Qureshi Nationality: Pakistani Date of birth: 24th November 1988 Place of Birth: Hyderabad Domicile: Hyderabad Urban Profession: Student Degree: Graduation (B.E Industrial Engineering & Management) Year of Study: Final year. Roll No. 08IN70 University: Mehran University of Engineering and Technology (M.U.E.T) Jamshoro.