Final Subcontract Sum
= 16 million
17 million
= 14 million 13 million
Installations = 12.5 million 12.975 million
systems installation were executed by the main contractor and that the
Profit and attendance on subcontractor work are 5% and 2.5%,
P a sional Sums (PSs) in the BOQ Actual Expenditure on PSs
{ i Additional foundation =3.3 million 3 million
ii, Steel burglar proof
.2 million 2.9 million
iii, Entrance canopy = 1.5 million
1.7 million
iy. External works 5 million 38 million
Re-measurement of Provisional Quantities:
1 Bill of Quantities Re-measurement.
“i, Substructure =31.6 million 28.5 million
ii. Staircase Balustrade = 1.25 million 1.8 million
Contractor’s Claims
Fluctuation =3.55 million
Approved loss & expenses = 1.25 million
y 2
1 4
i
AS i
7)
hy
22
Scand th Conseanner{ Final Account
Particulars Omission ®%) ‘Addition ®)
Contract sum| ie = 320,000,000.00
Less contingencies 25,000,000.00
Adjustment of Prime Cost Sum
Electrical installations 16,000,000.00 17,000,000.00
Profit 5% 800,000.00 850,000.00
Attendance 2.5% 400,000.00 425,000.00
AJC installations 14,000,000.00 13,000,000.00
Profit 5% 700,000.00
Attendance 2.5% 350,000.00
Security Gadgets installations 12,500,000.00 12,975,000.00
Profit 5% 625,000.00 648,750.01
Attendance 2.5% 312,000.00 324,370.00
Adjustment of Provisional Sum
a, Additional foundation 3,300,000.00 3,000,000.00
b. Steel burglar proof 3,200,000.00 2,900,000.00
, Entrance canopy 1,500,000.00 1,700,000.00
4. External works 35,000,000.00 38,000,000.00
Re-measurement of Provisional Quantities
a, Substructure 31,600,000.00 28,500,000.00
b. Staircase balustrading 1,250,000.00 1,850,000.00
Fluctuations 3,550,000.00
Approved loss & expenses 1,250,000.00
Less VAT 5% 16,000,000.00 445,973,120.00
{ 162,537,500.00
Less omission 162,537,500.00
283,435,620.00
Add VAT 5% 14,171,782.00
Anticipated final account 297,607,402.00
Less original contract sum 320,000,000.00 :
Cost savings 22,392,598.00
234.0 ANALYSIS OF TENDER AND EVALUATION OF BUILDING PROJECTS
4.1 Analysis of Tender
‘Tender analysis refers to the systematic process of scrutinizing the tender documents in
order to determine the responsive tenderer for the purpose of awarding contract. The
following are steps involved in analysis of tender;
Opening of tender
Examination and evaluation of tender
Adjudication of tender
iv. Preparation of tender report and recommendation
Factors /Criteria for Selection of Tenderer/Contractor
1. Adequacy of the tender figures/accuracy of estimate.
2, Commencement and mobilization percentage required.
3, Completion time especially when contract duration is of essence.
4.
Ability to work without relying on client’s finance.
4.2. Valuation of building projects.
Valuation is the formal and periodic assessment of the total value of construction project
properly executed to date for the purpose of stage certificate payment. Valuation is
carryout by measuring the wok executed to date, materials ordered both on/offsite and
other relevant documents relating to construction project.
Documents needed for the preparation of valuation.
The following constitute documents required for the valuation of construction project;
i, Contract bill of quantities
ii, Contract drawings
Approved claims
24
‘Scand th Conseanneriv. | Previous valuation report
v. Minutes of the meeting
vi. — Subcontractor/supplier account
Vii. Variation order
viii. Fluctuation account
ix. | Day work sheet
X. List of materials off/onsite
Work Examples:
Following the breakdown of the works: executed by ABZ Concept Nig. Limited for the
Constfuction of Female Hostel in Nigerian Army University Biu , with the contract sum
to the tune of 334,503,687.50 contract period of ten month, Calculate the amount due
to valuation nine (9).
i Preliminaries 15,623,750.5
ii, Main contractor’s work (100%) = 249,635,750.00
iii. Nominated Subcontractors’ work (80%) 12,850,000.00
iv, Previous payment (cert. 1 & adv. payment) = —__247,500,000.00
V. Amortization of advance payment 100,000,000.00
Note: 10% retention limit, VAT 5%. Work out for preliminaries at valuation 9 is Baio
SOLUTION:
VALUATION
Project Tittle: Construction of Female Hostel
Client: Nigerian Army University Biu
Contractor: ABZ Concept Nig. Limited
Contract Sum: ® 334,503,687.50
Contract Period: Ten (10) Months
Valuation Number: Nine (9)
25,
‘Scand th ConseannerPreliminaries
Measured work 14,842,562.50
Net soar
, __ Value of work done 274,758,312.50
ess retention (10%) aa
5.184.
Add VAT (5%) 257,533,128.00
12,876,656.41
270,409,784.53
100,000,000.00
a 370,409,784.53
Tess amortization 4 x100,000,000 100,000,000.00
270,409,784.53
Add advance payment
Less previous payment 147,500,000.00
Add VAT (5%) —_7,375,000.00
100,000,000.00
254,875,000.00 254,875,000.00
Amount due to valuation No. 9 15,534,787.53
26
‘Scand th ConSeanner