Reliability, Availability and Maintainability (RAM) Studies

Pöyry Energy (Calgary)


Independent Expert Support

Introduction Concept Selection Tool Rigorous Process and Methodology

Reliability, Availability and By considering the planned and Pöyry uses a structured workshop
Maintainability (RAM) Studies are unplanned downtime of the asset, an approach to generate plant reliability
conducted throughout the oil and gas overall predicted availability can be data. Reliability Block Diagrams are
industry to provide a quantifiable determined. With the integration of generated to facilitate plant
assessment of the effectiveness of an economic data, the availability can be assessment and develop appropriate
operating asset. assessed on an opportunity cost basis. sensitivities for evaluation. Pöyry
This data driven process is highly simulates actual plant operation using
To assure that the right decisions are valuable in both the design and a Monte Carlo mathematical model
made requires appropriate definition operation phases of projects to with a commercial reliability simulation
and consistent, rigorous, robust and determine investment decisions. packages such as AvSim or Raptor.
auditable processes. Pöyry have such
processes including expert utilisation of Pöyry are experienced in conducting Added Value
commercial tools and proven analytical reviews of process units with
methodologies to assist clients in stakeholders. Failure models, The combination of Pöyry’s systematic
making investment decisions at the predicted maintenance and regulatory approach and past experience allows
conceptual and operating phases of inspection schedules are developed accurate evaluation of plant availability
projects. This leads to maximum return and accessed against the and identification of improvement
on investment. consequences of these activities. opportunities. Optimising availability
Pöyry consults industry standard maximises client return on investment.
reliability databases and in-house data A clearly defined and auditable trail is
to assist in the evaluation of equipment created to justify capital investment in
failure probability and impacts. Pöyry facility improvement. Risk reduction is
uses leading commercial simulation achieved by evaluating equipment
packages to evaluate failure cases to sparing and redundancy.
determine plant availability and
economic impact.

Application to In-Situ Thermal Oil Sands Developments

 OPEX & Lifecycle costs.  CAPEX minimisation.  Technology Selection.


 Development concepts.  Resource Planning  Fit for purpose design.
Reliability, Availability and Maintainability Sudies
Details of the RAM Study
Reliability Block Diagram Example
Plant ESD
Shown here is a typical Reliability Block Diagram Major Failure
(RBD) developed prior to a Pöyry RAM workshop.

In the workshop failure modes with occurrence Emulsion / BFW


FWKO FWKO Emulsion /
probabilities, consequences and durations are Exchanger
Solids Planned Diluent Mixers
Planned
developed. From this Pöyry are able to model the Maintenance
Deposition Maintenance
entire facility. The graph below shows output for a
typical SAGD system on an annual production
impact basis.
Diluent
Pipeline

B it um e n S e pa ra t io n

FWKO Planned M aintenance


The analysis generated can be presented on
an impact basis, lost production days or lost
Emulsion/ BFW Exchanger Planned M aintenance revenue, over the project life.

Critical and high impact equipment items and


FWKO Soilds Depost ion Slowdown
Worst
systems can be quickly identified.
Nor mal
Plant Inlet ESD M ajor Failure
Best

0.0 0.5 1.0 1.5 2.0

Annual Pr oduct ion Impact (Days)

Clustering Scenarios - Results Summary


92% 40
Pöyry evaluates maintainability by optimising 91% 35
maintenance clustering and opportunistic maintenance 90%
events to maximise availability while balancing the 30
89%
labour resource constraints of the facility. 25
88%

Pöyry can provide a sparing philosophy and complete 87% 20


labour plan for the facility, based on best in class 86% 15
reliability methods. 85%
Overall Availability 10
84%
The collation of all the facility components presents an Peak Labour Demand 5
83%
overall availability, considering the reliability and 82% 0
maintainability of all contributory parts. Unclustered Basic Advanced Optimal

For more information, contact:

Pöyry Energy (Calgary)


Suite 1610, 700 - 6th Avenue S.W, Calgary, Alberta, T2P 0T8
Tel: +1 403 283 3600. Fax: +1 403 532 2595, www.poyry.com, www.iglconsultants.com