In the 15th WASH Cluster meeting the WASH cluster coordinator suggested TWG sanitation
for identifying uniform latrine designs. The partners were nominated and UNICEF was
requested to chair the TWG sanitation meeting. The participants included UNICEF, WHO,
UN-HABITAT, Save the children, ACTED, LPP, BLCC and People In Need. In this regard
two meetings were held at WHO on 20th October, 2010 Multan office where the final designs
of latrines were finalised especially for areas where water table is high.
The methodology adapted by TWG on sanitation was presentations on various latrines design
and discussions according to the criteria set by WASH cluster coordinator in the agenda to
select unified design and inputs for inter cluster (especially shelter cluster).
LPP BOQ:
Toilet
1 excavation 2 5.5 1.125 1.25 15.47
2 3.25 1.125 1.25 9.14
24.61
2 BB 2 5.5 1.125 0.25 3.09
2 3.25 1.125 0.25 1.83
1 4 4 0.25 4.00
8.92
Pacca Brick work in 1:4 C/S
3 mortar 2 5.5 1.125 0.5 6.19
2 3.25 1.125 0.5 3.66
2 5.125 0.75 0.5 3.84
2 3.625 0.75 0.5 2.72
2 4.75 0.375 1.5 5.34
2 4 0.375 1.5 4.50
2 4.75 0.375 6 21.38
2 4 0.375 6 18.00
Stairs 1 2.5 0.75 1.5 2.81
1 2.5 0.75 0.75 1.41
69.84
D/D 1 2.5 0.375 6 5.63
64.22
4 Plaster 1:5 4 4 1 6 96
4 4.375 1 0.375 6.56
102.56
D/D 1 2.5 1 6 15.00
87.56
5 Flooring concrete 1:2:4 1 4 4 0.25 4.00
T-Hudai
1 excavation 1 4 4 3.5 56.00
56.00 cft
2 BB 1 4 4 0.25 4.00
4.00 cft
Pacca Brick work in 1:4 C/S
3 mortar 2 3.75 0.375 3 8.44
2 3 0.375 3 6.75
15.19 cft
4 Plaster 1:4 4 3 1 3 36
4 3 1 0.375 4.50
40.50 sft
5 Flooring concrete 1:2:4 1 3 3 0.25 2.25 cft
6 RCC 1:2:4) 1 3.75 3.75 0.25 3.52 cft
7 Steel bars @7.5lb per cft 26.37 lb
11.96 Kg
Analysis
Brick Stone
Excavation Balast Cement Sand Bricks crush Steel
Excavation 80.61 cft 100 0 0 0 0 0 0
BB 12.92 cft 0 20 0 0 0 0 0
Pacca Brick work in 1:5C/S
mortar 79.41 cft 0 0 4.0 22.6 1191 0 0
Plaster 1:5 87.56 sft 0 0 0.7 4.0 0.0 0 0
Plaster 1:4 40.50 sft 0 0 0.4 1.8 0.0 0 0
concrete 1:2:4 10.77 cft 0 0 2.1 4.7 0.0 9.5 0
Steel 11.96 Kg 0 0 0 0 0 0 12
100 20 7.21 33 1191 9.5 12
Abstract
Detailed BOQ and cost of a toilet made with T haudi & Pacca
bricks on concreted plateform
Excavation 100 cft
Brick Balast 20 cft 6 119
Cement 7.21 bags 350 2524
Sand 33 cft 10 330
Stone crush 9.5 cft 50 474
Bricks 1191 Nos 3.5 4169
Steel 12 Kg 65 780
WC 1 No. 450 450
P trap 1 No. 90 90
Soil Pipe 10ft 1 No. 15 150
Vent Pipe 2 inch dia 7ft 1 No. 12 84
Ts 2 Nos 45 90
Drain Pipe 5 ft 1 No. 15 75
Wooden Door 3*5 1 No. 1000 1000
Labour 3600
13935
Save the children Pit Latrine and Bathroom (Combined set) Design:
Side view
Top sectional view
a. Cost of wood
Wood Size (Sectional) Length (ft) No. Required Total Length ft Cost PKR/ft Total cost
2"*2" 8 7 56 40 2240
2"*2" 6.17 5 30.85 40 1234
2"*2" 4.42 5 22.1 40 884
2"*2" 2 10 20 40 800
2"*2" 4 1 4 40 160
3"* 1/1/2" 5.66 2 11.32 35 396.2
3"* 1/1/2" 1.75 3 5.25 35 183.75
4'*2" 8 1 8 70 560
Net Total
PKR 6457.95
d. Cost of Labour
No. of days of
Type of Labour Daily wage work Total Cost
Carpenter 800 2 1600
Masons 600 2 1200
Unskilled Labour 300 6 1800
Net Total PKR 4600
Combined
Total Cost
PKR
(a+b+c+d) 29277.95