Sei sulla pagina 1di 2

Mean -> Average

Mode -> The "most found" number


Range -> Largest - Smallest Measure.
Medium -> No in the middle or avg. of 2 middle Nos
Earned Value (EV) = % Complete * BAC
Cost Variance (CV) = EV – AC (>0 Good)
Schedule Variance (SV) = EV – PV (>0 Good)
Cost Performance Index (CPI) = EV / AC (>1 Good)
Schedule Performance Index (SPI) = EV / PV (>1 Good)
Estimate at Completion (EAC) = AC + Bottom up ETC
= BAC / CPI
= AC + (BAC - EV)
= AC + (BAC - EV) / (CPI * SPI)
Estimate to Complete (ETC) = EAC - AC
Variance At Completion (VAC) = BAC – EAC
To Complete Performance Index (TCPI) = (BAC - EV) / (BAC - AC) - Using P
lanned Budget (PMBOK)
To Complete Performance Index (TCPI) = (BAC - EV) / (EAC - AC) - Using E
stimated Budget
Normal Distribution
-------------------------
1 sigma = 68.26%
2 sigma = 95.46%
3 sigma = 99.73%
6 sigma = 99.999%
Communication Channels = [ N (N - 1) ] / 2
Expected Monetary Value (EMV) = Impact * Probability
Point of Total Assumption = [(Ceiling Price - Target Price)/buyer'
s Share Ratio] + Target Cost
PERT (EAD) = (O+ 4M + P) / 6
SD of Activity (SD) = (P - O) / 6
Variance of Activity = [SD]2
= [(P - O) / 6]^2
Range of an Activity Duration = EAD +- SD
PERT Project Duration = Sum of PERTS of Activities on Critical Path
SD of Project = Square Root of [ SUM of Activity Variance on C
ritical Path]
Project Variance = [SD of Project]^2
Total Float = LS - ES
= LF - EF
Contract Incentives Formulas
--------------------------------------
Savings = Target Cost - Actual Cost
Bonus = Savings * Percentage
Contract Cost = Bonus + Fees
Total Cost = Actual Cost + Contract Cost
Class of Estimates
----------------------
Definitive +5%
Capital Cost +10-15%
Appropriation +15-25%
Feasibility +25-35%
Order of Magnitude > +35%
Project Selection
----------------------
Present Value (PV) = F V / (1+r)ⁿ
Future Value (FV) = PV x (1+r)
Net Present Value (NPV) = S (PV / (1+r)ⁿ + PV / (1+r)ⁿ + PV / (1+r)ⁿ
+ PV / (1+r)ⁿ )
Cash Flow (CF) = Cash Inflow - Cash Outflow
Discounted Cash Flow = CF x Discount Factor
ARR = S Cash Flow / No. of Years
Return on Investment (ROI) = (ARR / Investment) * 100 %
Benifit Cost Ration (BCR) = Benefits / Cost
Cost of Quality (CoQ) = ( ( Review Efforts + Test Efforts + Training
Efforts + Rework Efforts + Efforts of Prevention) / Total Efforts) x 100 %

Potrebbero piacerti anche