G e t p r e p a r e d f o r t h e P M P ® E x a m

Self Assessment Test


7 5 F r e e S a m p l e Q u e s t i o n s

“If money is your hope for independence you will never have it. The only real
security that a man will have in this world is a reserve of knowledge, experience, and
ability.”
Henry Ford
Explanations I want to skip the Feedback
explanations
Each question in this section and go Mailed September 15 2009 by Stephen H. (Canada): "The test was very helpful, and
self assessment test down to the test highlighted areas where I needed further studies – thank you."
has one best answer. right now Mailed June 27 2009 by Bill C. (USA): "I passed the PMP exam yesterday."
Mailed April 08 2009 by Mary K. Y. (USA): "This was great practice. It highlighted
Time to finish the test: 90 Minutes. some areas on which I need to focus."
Mailed August 25 2008 by Aarti S. (USA): "Your tips and practice exams were really
There is a timer in the title bar (top of
helpful and I was able to focus on areas that I was weak at and pass the exam."
most browsers).
Mailed October 10 2007 by Naji C. (Canada): "I am glad that I did your tests online,
Click the dark blue button (below) to the free 75q and the 175 one. The questions helped me pass the exam and really
reset the timer to 00:00:00. find gaps in my knowledge. By the way, you are the only one who covered the PTA
questions. I had on my exam 3 PTA related questions."

This sample test has been designed to Mailed October 10 2007 by Stefano B. (Italy): "I would like to thank you again for the
help you practicing for the current PMP® free and precious support provided by your tests. They were really close to the exam
exam—based on the PMBOK® Guide 4th and helped much me and my other 2 colleagues to pass the PMP exam with a good
score."
Edition.
Mailed July 14 2007 by Belinda C. (USA): "I did take the exam and passed it back in
It is also helpful in preparation for other May. I believe that your questions were the closest to prep for the exam."
project management exams including Mailed March 8 2007 by Pam H. (USA): "I only whish I could have found you earlier. I
PMI's CAPM® and PgMP® or CompTIA's missed this exam 3 times. I even went through #######'s Boot Camp... a good
Project+. course but something went amiss for me when I really saw the questions on the test
... I have not been studying these type of questions given to me from the Boot
The passing score (the number of right Camp."
answers to pass this preparation test) is Mailed January 8 2007 by Joseph K. (UK): "I did the test and had 54 correct answers.
75%. I then passed the exam. Your questions were a good preparation for the real thing. "
Mailed September 12 2006 by Claudia D. (USA): "I just took (and passed) the PMP
exam yesterday. Your test is the closest I have found to the real thing. I was getting
Please visit www.pmi.org and navigate to fairly high scores from other practice tests and was quite shocked yesterday by how
difficult the real exam was."
Mailed May 9 2006 by Rick M. (USA): "I teach an 8 day PMP Prep Course. I have had
over 120 of my students pass the PMP exam over the past 2 years. I have always
encouraged my students to take your exam to test their knowledge."
Mailed April 20 2006 by Walid T. (Canada): "I found some of the questions quite
challenging and requiring more than the allocated 72 seconds to answer ... the
sample test provided a good learning experience."
Mailed January 25 2006 by John C. (USA): "Your test questions are very useful and
helped me assessing where I need to do more."

Mailed August 1 2005 by Stephen L. (New Zealand): "Good questions."

to find more information about the PMP Mailed June 14 2005 by Saurabh V. (India): "The test is the most comprehensive one
exam. that I have seen so far."

Mailed August 26 2004 by David S. (UK): "I can start breathing again, score for the
exam 158/200, thanks for the confidence boost from your test questions!"
Visit the author at
- www.oliverlehmann.com (English) or Mailed June 29 2004 by Nadja V. (Finland): "I took several practice exams. Your exam
- www.oliverlehmann-training.de (German) provided the best reality check both in terms of level of difficulty of the actual PMP
exam and my score on the final exam. Thanks."
Click here for over 2,000 more prep
questions from various providers.

1 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

Mailed Jan 12 2004 by Andrea I. (Italy): "I did the test two days before the exam and
found it useful and also a good approximation of the real exam question, compared
PMI ® did not participate in the with other sample tests taken before. Moreover, the result reached was exactly the
same as in the exam (84%)."
development of this self assessment test
and has not reviewed the content. Mailed May 05 2003 by Dana P.B. (USA): "I did find the questions helpful. To the
extent that I passed the exam on my first attempt."

Click here to reset the timer and start the test

See references Marked for review


1. ________ is typically not referred to as a buffer type in Critical Chain project management.

Resource buffer

Free buffer

Feeding buffer

Project buffer

See references Marked for review


2. A company has to make a choice between two projects, because the available resources in money
and kind are not sufficient to run both at the same time. Each project would take 9 months and would
cost $250,000.

1. The first project is a process optimization which would result in a cost reduction of $120,000 per year.
This benefit would be achieved immediately after the end of the project.

2. The second project would be the development of a new product which could produce the following net
profits after the end of the project:

1. year: $ 15,000
2. year: $ 125,000
3. year: $ 220,000

Assumed is a discount rate of 5% per year. Looking at the present values of the benefits of these
projects in the first 3 years, what is true?

Both projects are equally attractive.

The first project is more attractive by app. 7%.

The second project is more attractive by app. 5%.

The first project is more attractive by app. 3%.

2 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


3. A production process has been defined as part of an industrial equipment manufacturing project. The
process is intended to produce steel bolts with a length of 20 cm. The control limits are 19.955cm and
20.045cm.

The measurements made at the end of the process yielded the following results:

20.033cm, 19.982cm, 19,995cm, 20.006cm, 19.970cm, 19.968cm,


19.963cm, 19.958cm, 19.962cm, 19.979cm, 19.959cm.

What should be done?

The process is under control. It should not be adjusted.

A special cause should be investigated, the process should be adjusted.

The control limits should be adjusted.

The measuring equipment should be recalibrated.

See references Marked for review


4. Your project management team includes two external consultants each from a different company.
You found that repeated conflicts between the two consultants already slow down project progress
and jeopardize achievement of objectives.

Which stage of team development can be difficult to overcome in such a situation?

Storming from Forming, Storming, Norming, Performing

Panic from Enthusiasm, Panic, Hope, Solution

Kickoff from Assignment, Kickoff, Training, Communicating

Frustration from Direction, Frustration, Cooperation, Collaboration

3 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


5. During a project Earned Value Analysis is performed and gives the following numbers:

EV: 523,000; PV: 623,000; AC: 643,000.

Which results are correct?

CV: +120,000; SV: +100,000

CV: +100,000; SV: +120,000

CV: -100,000; SV: -120,000

CV: -120,000; SV: -100,000

See references Marked for review


6. A project manager spent some days to create a multi-page document which he called Project charter.
The document should have been issued by the project sponsor. The sponsor found the document
outsized and asked for a condensed document.

Which of the following is not normally an element of the Project charter?


The authority level of the project manager

Detailed control account and work package descriptions

The business need that the project was undertaken to address

High-level risks

4 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


7. A document called ____________ is created by decomposing the project scope into smaller, more
manageable elements.

Scope Statement

Network Logic Diagram

Work Breakdown Structure

Requested Change

See references Marked for review


8. Which of the following tools is used to create a Risk Management Plan?

Risk planning meetings

Documentation reviews

Data precision rankings

Diagramming techniques

5 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


9. In order to speed up a project, you made a decision to fast-track a phase currently performed with
five team members and another one which was planned to begin in four weeks time with another five
team members.

Which of the following activities should you do first?

Make sure that all exit criteria of the consecutive phase have been met to ensure the flow of
communications in a team situation which is more complex by a factor of 2.
Make sure that all entry criteria of the previous phase have been met by planning and
performing a phase gate meeting to assess technical aptness.
Make sure that all exit criteria of the previous phase have been met by planning and
performing a phase gate meeting to assess technical performance.
Restructure your team and delegate tasks in order to ensure the flow of communications in a
team with the number of communication channels increased by a factor of 4.5.

See references Marked for review


10. A project manager needs a certain number of identical valve housings for a power station project.

He starts with 100 raw items which are made as metal castings. Out of this batch, 15 are found
leaking from micro-porosities in a subsequent pressure test. 6 of these housings can be recovered
by a special sealing process for raw castings.

The 91 housings are then being machined. After this process step 10 machined castings are found
leaking. 3 of these items can also be saved using another sealing process for machined castings.

The remaining 84 housings are getting mounted to the power plant pipe work. During a pressure
test after this process step it is found that 12 valves are leaking. Out of these a number of 6 valves
can be saved by replacing the sealing rings used.

Finally the project manager has 78 valves which he can use. What is true?

RTY = 0.84

RTY = 0.78

RTY = 0.91

RTY = 0.65

6 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


11. You found the following Earned Value Analysis information for a recently closed out project:

SPI = 0.7, CPI = 1.0

The project has been cancelled while it was executed. At that time the project was behind
schedule and on budget.
The project's deliverables have all been finished. The project came in behind schedule but on
budget.
The project's deliverables have all been finished. The project came in ahead of schedule but on
budget.
The project's deliverables have all been finished. The project came in on schedule but over
budget.

See references Marked for review


12. Which should be included in a Requirements management plan?

The document should trace requirements to project scope / WBS deliverables.

It should describe how requirements activities will be planned, tracked, and reported.

It should trace high-level requirements to more detailed requirements.

It should trace requirements to business needs, opportunities, goals, and objectives.

7 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


13. In a traditionally drawn decision tree, a circle represents ___________.

a chance to which no Expected Monetary Value can be assigned so that a likely pay-off can not
be shown.
a decision to which no Expected Monetary Value can be assigned so that a likely pay-off can
not be shown.
a chance to which an Expected Monetary Value may be assigned to calculate the most likely
pay-off.
a decision to which an Expected Monetary Value may be assigned to calculate the most likely
pay-off.

See references Marked for review


14. A project management team has subcontracted work to a service company. Which of the following
tools is the best choice to assure that this company will be able to meet the quality requirements of
the project?

Quality audit

Deliverable inspection

Fixed price contract

Service level agreement

8 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


15. With your team you are using judgment from subject matter experts to identify and analyze project
risks. There is a small number of experts available, but some of them have long been in a teacher-
student or manager-assistant relationship.

Which of the following techniques can ensure best that there is no dominating opinion during an
expert review?

Peer review

SWOT analysis

Delphi technique

Monetary value calculation

See references Marked for review


16. You are running a project for a customer based on a cost reimbursable contract with the following
terms:

Target costs: $ 1,000,000


Fixed fee: $ 100,000
Benefit/cost sharing: 80% / 20%
Price ceiling: $ 1,200,000

Which is the PTA (= Point of total assumption, Break point) of the project?

$1,300,000

$1,500,000

$80,000

$1,125,000

9 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


17. During execution of a project which is performed for a customer on a T&M (Time and Material)
contract base, a new project manager is taking over the assignment.

He discovers that two members assigned to the project have charged time without performing any
work for the project customer. Upon further investigation, he determines that this occurred because
there have been no other project assignments open for these employees. The customer is unaware
of these facts.

What should the project manager do?

Try to find some productive work for these staff members in the project and leave them on the
team.
The best thing is to do nothing. The customer will not realize the problem anyway.

Try to find a responsible person for the over-assignment who can be made accountable.

Take the two people off the team immediately and arrange for the refund of the excess
charges to the customer.

See references Marked for review


18. Start dates in the following network logic diagram are defined as early morning, finish dates are
evening.

If tasks are scheduled to begin at early start date, what is true?

Activity B has a free float of 10 d.

Activity B has a total float of 10 d.

Activity A has a free float of 10 d.

Activity A has a total float of 10 d.

10 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


19. Your project is executed with a globally spread virtual team. The project progress has been found to
be too slow. Which measure is most likely to immediately speed up the project?

Technical training for all team members

Daily phone conferences and detailed reporting

A team meeting at a location convenient to all team members

Collocation of team members at a suitable place

See references Marked for review


20. A project management team wants to procure some customized products which are available in
identical grade and quality from many vendors. What should be included in the procurement package
to ensure that their offers will be comparable?

A statement of work describing the needs of the project in sufficient detail to enable vendors to
make suitable proposals
A statement of work specifying attributes and metrics of the requested deliverables in detail to
allow vendors submission of bids
The approved project scope statement, the WBS which should be broken down to Work
Package level and the WBS dictionary
The risk management plan and the reports from those risk management reviews which have
been made so far

11 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


21. Which of the following becomes increasingly important in a virtual team environment?
Requirements engineering

Communication planning

Formal procurements closure

Network diagramming

See references Marked for review


22. You are assigned as the project manager to a project which is executed for a customer under FP
contract. Your customer informed you this morning that they insist on certain "refinements" of the
project scope.

You agree that the requested actions make really sense to the project, but believe that they
constitute a major change increasing the project scope. What should you do next?

Accept the request of the customer. Diligently document the additional costs and working hours
spent by yourself and the team on the implementation of the change and invoice these to the
customer at appropriate rates.
Perform Earned Value Analysis to assess the current status of the project and get all the
numbers you need to communicate the case to the Change Control Board which then will have
to make the best decision regarding the customer request.
Check the contract, the project charter, the scope statement and other documents related to
the project and the contract. Implement ADR (Alternative Dispute Resolution) procedures if the
conflict cannot be resolved otherwise.
Talk to the project sales department and find a joint solution with them how to best reject the
request considering the commercial and strategic value of the customer to the organization
you are working for.

12 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


23. A prime contractor in a customer project under CPFF contract has run into unexpected technical
problems. Fixing them will require a lot of additional work to be done.

The company made a decision to book more staff and equipment from their subcontractors in order
to adhere to the agreed timeline. The customer agreed to this decision.

What will most likely happen?

The contractor‘s indirect costs will increase and the customer‘s payment for them will increase,
too.
The contractor‘s indirect costs will increase but the customer‘s payment for them will not
increase.
The contractor‘s indirect costs will not increase but the customer‘s payment for them will.

Neither the contractor's indirect costs nor the customer‘s payment for them will increase.

See references Marked for review


24. A project management team is evaluating the causes that might contribute to unsatisfactory
performance and quality. Which of the following statements is not true?

Normal process variation is attributable to random causes and sometimes also called "white
noise".
Special causes are easier to predict and handle than random causes (also called common
causes).
Special causes are unusual events which are difficult to foresee and often produce outliers.

A process can be optimized to limit the bandwidth of variations due to random causes.

13 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


25. You are performing a project management audit in your company and find that most of the project
plans are neither consistent nor up-to-date.

Which of the following statements is not true?

Projects should never be executed without a valid, updated and working project management
plan.
The consistency of the project management plan is secondary because it is only the results that
matter.
A great deal of effort is required to develop and update a project plan, but the benefits include
less pressure on all stakeholders and a resulting product that will satisfy the requirements.
Poor planning and insufficient updating of project management plans are common reasons for
cost and time overruns.

See references Marked for review


26. You want to perform active risk acceptance. What should you do?

Create contingency reserves in resources, money and time.

Develop a plan to minimize impact in case that an identified risk occurs.

Develop a plan to minimize the probability of occurrence for identified risks.

Make additional resources available to speed up the project.

14 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


27. A project manager made 3-point estimates on a critical path and found the following results:

Assuming ±3 Sigma precision level for each estimate, what is the standard deviation of the allover
path?

App. 4.2 days

App. 5.2 days

App. 6.2 days

You can not derive the path standard deviation from the information given.

See references Marked for review


28. When do bidder conferences normally take place?

After the contract has been awarded to keep alternatives open.

After submittal of bid or proposal, but before contract award.

Prior to the submittal of a bid or proposal by the bidder.

After technical meetings with bidders to discuss contract requirements.

15 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


29. What is defined by control limits?

A measuring instrument solely used to describe process capability. The process is found
capable if the ±3 Sigma range is exceeded by not more than 0.3% of a tested sample lot.
The limits of the six Sigma area on either side of a control chart to plot measured values; data
found outside the area are out of specification and can lead to rejection of an entire batch.
The area consisting of typically three standard deviations on either side of a mean value of a
control chart to plot measured values found in statistical quality control
The area consisting of typically three standard deviations on either side of a mean value of a
control chart to plot measured values found in quality assurance

See references Marked for review


30. The Scope baseline consists of what?
Scope statement, WBS, and WBS dictionary

Cost baseline, Quality baseline and Schedule baseline

Configuration management plan and Configuration identification document

Procurement statement of work and Project scope statement

16 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


31. Activity 1 has a duration of 20 days, Activity 2 of 10 days, Activity 3 of 5 days and Activity 4 of 6
days.

What is the minimum total duration between the Milestones A and B?

36 days

37 days

39 days

42 days

See references Marked for review


32. Which tool and technique is used to Create WBS and Define activities?

Nominal group technique

Human resource assignment

Brainstorming

Decomposition

17 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


33. Which of the following statement(s) regarding whistle-blowing is/are not true?

a. It is a term used to define an employee’s decision to disclose information on unethical, immoral or


illegal actions at work to an authority figure.
b. An employee should always discuss the matter with people external to the company before following
the "chain of command" and discuss it with the immediate superior.
c. The consequences of whistle-blowing are often extreme and include possible being branded as having
bad judgment, firing, civil action and imprisonment.
d. Carefully considered whistle-blowing can lead to the end of unethical business practices.

b, c

c, d

See references Marked for review


34. Which of the following statements is not true?

Attribute sampling is the process of assessing whether results conform to specifications or not.

Prevention means keeping errors out of the process by applying actions before the process
starts changing its input.
Variables sampling means that the result is classified into one of the 3 categories:
"acceptable" - "acceptable after rework" - "rejected".
Inspection is often mainly done to keep errors out of the hands of the customer instead of as a
means of process control.

18 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


35. Which statement describes best why you should document assumptions?

Assumptions might prove to be wrong. Knowing which assumptions were incorrect allows
baseline adjustments in case of project crisis.
Assumption analysis is a valuable tool and technique to explore the validity of assumptions
during risk identification.
Assumptions limit the project management team's options for decision making because they
can not be controlled by the team.
In case of schedule or budget overruns, the documentation of assumptions supports a clear
assignment of responsibility.

See references Marked for review


36. Which is normally not regarded as an element of Cost of quality?

Prevention costs

Maintenance cost

Appraisal costs

Failure costs

19 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


37. You have recently been assigned as a project manager to a new B-O-T (Build, Operate, Transfer)
capital project. Reviewing the initial documentation you found out that it has been calculated with a
very small margin during operations of its product for the shareholders. What should you do?

As you are not responsible for lifecycle costing, you don't have to worry about operation
profits. Focus on project costs from initiation through handover.
Ensure maximum profits by buying the best and cheapest items, components and modules -
potentially from a big number of different suppliers - and integrating them.
Create a realistic plan broken down to a sufficient level of detail. Perform all risk management
processes. Ensure real-time communications with all stakeholders.
Try to get a second project manager assigned to share decision making and accountability to
shareholders with the person.

See references Marked for review


38. A project is handled by departments of an organization and expedited by a project coordinator.
Which of the following statements is most likely to be true?

The performing organization is a weak matrix.

The performing organization is doing "management by projects".

The performing organization is a strong matrix.

The performing organization is projectized.

20 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


39. You are project manager in a global project with a team consisting of people from various countries.
What can you try to prevent misunderstandings due to cross-cultural differences?

Use all communication methods available that are suitable for the team and follow up in
writing when communicating verbally. Remember that cultural and individual diversity may
help project teams solving unforeseen problems during the course of the project.
When you are about to form a team for your project, keep in mind that some cultures are
developed, others are more primitive. Some have values, some not. You should consequently
avoid choosing members from countries with cultures that are not similar to your own.
Cultural dilemmas can prevent any project from being successful. They should therefore be
smoothed or suppressed so as to make sure that they cannot disrupt project work. Your effort
should concentrate on communication that can help reach that goal.
As norms regarding communication habits differ significantly across various cultures,
communicating between people from different countries should only be done using language.
The nonverbal dimension simply bears too many risks.

See references Marked for review


40. Which statement on conflicts is true?
Conflict resolution should focus on people, not issues.

Conflict is natural and forces a search for alternatives.

Conflict should always be handled in private and not in the team.

Too much openness is a common cause of conflict.

21 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


41. A change request in a project has been rejected some weeks ago. Yesterday, the project manager
found out that it nevertheless has been implemented by the team members, who knew of the
change request, but not of the rejection.

In order to avoid such a situation, Rejected change requests should be consistently communicated to
stakeholders through which process?
Report performance

Verify scope

Perform integrated change control

Monitor and control risks

See references Marked for review


42. What is a trigger in project risk management?

An expected situation causing an unidentified risk to occur

A warning sign that a previously identified risk might be occurring or has occurred

An unexpected situation causing an identified risk to occur

An unexpected situation causing an unidentified risk to occur

22 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


43. According to the project plan, a contractor is scheduled to deliver some software components today
afternoon. A regular payment is due to be made to this contractor tomorrow.

You and your project team received a note this morning informing you that the software delivery will
be delayed by 2 weeks.

What should you do right now?

You should delay the payment also for 2 weeks.

You must immediately find a different contractor.

You should conduct a meeting with the contractor to resolve the delivery issues before making
the payment.
You should make the payment and reschedule the project plan.

See references Marked for review


44. In a software company a large number of simultaneously performed projects utilize the same groups
of human and other resources.

What is the term commonly used for this situation?

Concurrent engineering

Resource over-allocation

Resource pooling

Program management

23 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


45. What does the acronym RACI commonly stand for in project management?

Responsible, Accountable, to be Consulted, to be Informed

Remote, Attached, Connected, Integrated

Risk Analysis and Caution Initiative

Randomly Accessible Cashflow Information

See references Marked for review


46. You have used estimates made by your team members and applied the Critical path method to
compute a Network logic diagram for your project. Then you found out that it cannot be sufficiently
optimized for scarce resources and fast progress towards a given deadline. What should you do next?

Apply resource leveling heuristics to uncritical activities only.

Reduce estimates on duration and work efforts by an adequate percentage.

Apply Three-point estimation and Critical chain project management.

Remove physical constraints and replace hard logic with soft logic.

24 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


47. Liquidated damages (LDs) are contractually agreed payments in order to...
...give the contractor an incentive to meet an aggressive schedule or challenging quality
objectives.
...penalize the contractor for late completion of a project or failure to meet specifications.

...cover the customer's costs caused by late completion or failure to meet specifications by the
contractor.
...make a bid or proposal binding for the offerer while the customer has time to select among
various bidders.

See references Marked for review


48. What should not be covered by a risk management plan?
Roles and responsibilities for handling project risks

Timing of project risk management activities

The methodological approach used for risk management

Individual risks and potential responses to them

25 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


49. You are assigned as the project manager to a project which had a one-time cost variance in the past
caused by unexpected rework which has meanwhile been finished.

You perform Earned Value Analysis and find the following results:

EV: 250,000; PV: 200,000; AC 275,000

BAC is 500,000.

What is right?

EAC = 550,000

EAC = 525,000

EAC = 500,000

EAC = 425,000

See references Marked for review


50. An estimation has been made that the construction of a residential home will cost a certain amount
per square foot of living area. This is an example of what type of estimating?

Analogous estimating

Bottom-up estimating

Top-down estimating

Parametric estimating

26 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


51. What is true for prototypes?
Prototyping causes significant costs and should be avoided wherever possible.

They are tangible and allow for early feedback on requirements by stakeholders.

Prototypes are mostly developed toward the end of a design or build phase.

Prototypes increase the risk of misunderstandings between developers and users.

See references Marked for review


52. What is a constructive change?
A change request that helps improving the project and its product, service or result and is
discussed generally in a friendly style.
A direction by the buyer or an action taken by the seller that the other party considers an
undocumented change to the contract.
A field change or ad-hoc change mandated by the project customer in a public construction
project.
A change request which will lead to the re-construction of an older version of the project
performance baseline by the contractor.

27 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


53. Which of the following is generally not regarded to be a motivator according to Frederick Herzberg?

Working conditions and interpersonal relations

Responsibility for enlarged task

Interest in the task

Recognition for achievement

See references Marked for review


54. What is true for modern project management? Project managers need...

... to have a strict standing in negotiating

... to show experience in tricking business partners

... to be team players and facilitators instead of "bosses"

... to be strongly linked to local traditions

28 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


55. You are the project manager in an engineering project and have recently signed a contract with a
software vendor for the development of a complicated control solution. The software will be used to
control machinery equipment which your project team is currently developing. The contract is a
lump-sum contract. The contractor has target cost estimated which seem rather low to you. Which of
the following statements is not true for this situation?

It is the contractor's risk in this type of contract that their profit may vanish if costs have been
underestimated.
This form of contract should only be chosen when all the requirements for the building of the
product are well-known by all parties involved.
In a fixed-price contract, change requests can cause issues regarding additional time and extra
costs for the changes to be applied.
It is likely that your organization may have to assume any unexpected additional costs for the
software development.

See references Marked for review


56. A review to determine whether of project activities comply with organizational and project policies,
processes, and procedures is commonly called

Quality auditing

Inspection

Quality testing

Reject screening

29 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


57. Which of the following is true in regard to the Code of Accounts?

It allows one to easily identify the breakdown level of the item in the resource structure.

It describes the coding structure used by the performing organization to report financial
information in its general ledger.
It is the collection of unique identifiers generally assigned to WBS items.

It defines ethical behavior in the project and the responsibilities to the customer and the
profession.

See references Marked for review


58. You are the manager of your company's project management office. The company is running many
concurrent projects; most of them share a resource pool of technical staff. Understanding how
resources are utilized across projects has been found essential to overall project performance,
including cost effectiveness and profitability.

This morning you received a message that the resource pool members will be unable to perform as
planned for the next months because the overall work load has grown too high and while delays are
adding up, the morale of the staff is going down.

What should you do next?

Ensure that quantitative information for all projects is being made available in a uniform and
reliable fashion and verify that the project management methodology is adhered to. Then
consolidate the information to get an understanding of the problems related with the use of
shared resources.
Implement an enterprise project management software solution which is able to level the
human resources across the various projects and which has the capability to model resource
assignment on a percentage level thus optimizing resource utilization for the overall
organization.
Do nothing related to the described problem unless you are explicitly requested by the
organizations upper management. Supporting decision making on the level on which project
portfolio management is done, is not the project management office's business.
Evaluate project management software which supports planning and scheduling across
enterprise-wide project portfolios. Avoid managing the availability of shared enterprise
resources for the projects run by an organization because this is not the business of a project
management office.

30 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


59. You have been criticized that certain specifications in your Scope Statement do not pass the test for
SMART objectives. What are SMART objectives?

Objectives specified in far more detail than necessary for a execution of a successful project.

Easily achievable objectives which help you reducing the pressure on yourself and the team.

Objectives that should be achieved in order to attain formal recognition by both the customer
and the project sponsor.
Objectives that are described using specific, measurable, assignable, realistic and time-related
specifications.

See references Marked for review


60. You have been assigned as a project manager to a software project. While you and your team are
working on a WBS (Work breakdown structure), estimations for activity durations based on the
activity list vary significantly. Which additional documents may help you clarify this situation?

Milestone list and scope baseline.

Project schedule network diagrams and human resource plan.

Activity cost estimates and scope baseline.

Activity attributes and project scope statement.

31 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


61. You are performing Earned value technique on your project.

After budget approval, an additional and unexpected cost item has been identified, which made the
project more expensive some weeks ago. The item has meanwhile been paid by the project team,
and it is expected that for the remaining duration of the project, costs will be as budgeted.

In this case, which is the best formula to calculate EaC (Estimate at Completion)?

EaC = BaC - CV

EaC = BaC / CPI

EaC = AC + BtC / CV

You can not compute the EaC.

See references Marked for review


62. During a company event, you had the opportunity to talk to a colleague project manager. He told
you that in his current project actual costs are 15% under cumulated costs budgeted for today.

What do you think?


The information given to you by the colleague is not sufficient to assess project performance.

The project will probably be completed with total costs remaining under budget until the end.

A significant cost increase during the further course of the project will probably bring the costs
back to baseline level.
Original cost forecasting and budgeting for the project must have been poor to allow this
variance.

32 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


63. What is the meaning of a concept called the "Journey to Abilene"?

Project managers should visit their customers far more often than what is usual in order to
avoid misunderstandings and bad emotions.
International projects may have an increased need for traveling which can lead to additional
costs and troubles with time zones.
Committee decisions can have the paradox outcome, that a jointly made or approved decision
is not desired by any individual group member.
A project is a temporary endeavor undertaken to create a unique product, service or result.
Repeating it would be similar to making the same journey twice.

See references Marked for review


64. Which of the following statements describes best the relationship between project phases and the
Project life cycle?

The Project life cycle includes the time when the project is performed and the expected product
lifespan after that.
In project management, the sequence of project phases and phase gates is often referred to as
Project life cycle.
The Project life cycle is regarded as a sequence of project activities while phases are defined to
control overlapping activities.
The Project life cycle describes how iterations of project management processes are used when
a project schedule is developed.

33 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


65. Which is an appropriate order in most project situations for the development of scope-related
documents?

1. Project SOW (Statement of work),


2. Project charter,
3. Project scope management plan,
4. Project scope statement,
5. WBS (Work breakdown structure) and WBS dictionary.
1. Work breakdown structure,
2. Scope statement,
3. Project charter,
4. CSOW (Contractual statement of work),
5. Contractual Work breakdown structure
1. Feasibility study
3. Contract,
4. CWBS (Contractual work breakdown structure),
5. Scope of work descriptions,
6. PID (Project initiation document).
1. BOM (Bill of materials),
2. CAP (Control account plan),
3. Project charter
4. Change management plan,
5. Scope baseline.

See references Marked for review


66. What is the S-curve in project management?

A graph that is generated if a normal curve is integrated.

A graph that is to be integrated to generate a normal curve.

A metaphoric description of the short term uncertainties that are present in every project.

The graph that describes the typical growth of earned value during the course of the project.

34 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


67. An output of the Estimate activity resources process is a document called "Activity resource
requirements". It identifies the types and quantities of resources...
...while the term resources is limited to equipment and materials.

...required for each activity in a work package.

...while the term resources is limited to human resources.

...to be obtained solely from the performing organization.

See references Marked for review


68. What is not the purpose of Configuration control when Configuration management is applied in a
project?
Verification that the configuration identification for a configuration item is accurate, complete,
and will meet specified program needs.
Ensuring that proposed and approved changes to configuration items are fully analyzed.

Ensuring that proposed and approved changes to configuration items are fully documented.

Managing and controlling the frequently requested changes to a project by applying agreed
rules.

35 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


69. Which statement describes best the meaning of the term Cost baseline?
A cost baseline is always created by translating time-phased cost information into cost data on
activity or work-package level.
A cost baseline is an approved time-phased budget that will be used to measure and monitor
cost performance on the project.
Data to draw a cost baseline can be easily generated and updated as necessary from
information related to actual project cost.
A cost baseline is usually displayed in the form of an inverse S-curve drawn from the beginning
of the project until data date.

See references Marked for review


70. Which is not true in regard of RoI (Return on Investment) for a project?

It defines the cumulated net income from an investment at a given point in time or during a
defined period.
It includes investment, direct and indirect costs and may include allowances for capital cost,
depreciation, risk of loss, and/or inflation.
It is most commonly stated as a percentage of the investment or as a dimensionless index
figure.
It is the time when cumulated net income is equal to the investment.

36 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


71. A project sponsor requested Earned Value Data on two concurrent projects from the project
managers. Both projects are regarded as equally important and strategically beneficial and have
been finished by over 80%. He received the following information:

Project A:
PV: $1,800,000
EV: $2,300,000
AC: $2,100,000

Project B:
PV: $2,000,000
EV: $1,500,000
AC: $1,600,000

The sponsor considers to shift some resources from Project A to Project B to speed up the second
project which is currently behind schedule.

What is the most likely outcome of such a measure?

Changing team assignments during late course of a project typically increases cost efficiency.

Changing team assignments during late course of a project typically increases time efficiency.

According to the Law of diminishing returns, the consolidated Cost variance of the two projects
will decrease.
According to the Law of diminishing returns, the consolidated Cost variance of the two projects
will increase.

See references Marked for review


72. Which of the following statements describes best the relationship of quality and grade?

Low grade is always a problem; low quality may be overcome by a good rework and repair
process.
Grade is a category or rank given to entities having different functional requirements but the
same need for quality.
Both quality and grade can often be improved through intelligent measuring, testing and
examining.
Low quality is always a problem as it bears on the ability of an item to meet requirements; low
grade may sometimes be acceptable.

37 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


73. Network templates which contain only portions of a network are often referred to as

Subnetworks or fragment networks

Subprojects

Programs

WBS items

See references Marked for review


74. What is the Internal Rate of Return (IRR) of a project?

The time period needed to pay back the investment from a project when future income is
discounted.
The inherent discount rate or investment yield rate produced by the project over a pre-defined
period of time.
The rate of negative risk that can be accepted for a project without turning the Expected net
present value negative.
The expected benefit from a project’s deliverable calculated as a percentage of the original
investment over a specified time period.

38 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

See references Marked for review


75. You just created the following network logic diagram to describe the planned flow of activities for
your project which will start tomorrow:

Which potential inconsistency in the diagram should you solve right now?

Activity E is open ended ( a "dangle") in relation to the finish milestone path convergence.

Activity F is open ended in relation to the path divergence after the start milestone.

You cannot calculate a critical path when lags and/or leads are calculated in percent.

Activities E to F need another task drawn as a hammock to calculate Level Of Effort.

Reset all answers Solve Sample Test Print Sample Test

Result: 20 of 75, 26.6 %

Notes:
- After clicking the Solve Sample Test button, the correct answers will be highlighted in blue color above in the questions &
answers section.
- PMI made a decision in 2006 to not publish passing scores for the exams any more. The actual score is estimated to be between 61%
and 75%. I recommend to target 75% results or better in this and all other difficult prep tests you are taking, 82% in simple tests.

I am...
...generally interested in the PMP certification.
...on my way to pass the PMP exam.
...already certified as a PMP.
Finished? Klick here to send your feedback to me.

FREE TOOL!
Did you stumble over
More providers of free PMP questions on project
preparation questions selection and decision
tree technique?
Christelle P. from Canada mailed Oct 11 2003: Then click this link for Decision
Tree Software, which is free for
"I passed the test! Thanks for the 75 prep questions. The only way to people studying for the PMP
succeed is to write tons of practice exams!" certification exam.

So true! In 2002, I was the first provider of a major collection of free NEW group on
LinkedIn!
PMP exam prep questions. Today, you can find thousands of questions You are on the way to
on the web. become a PMP? Join the first

39 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

Below are links to more providers with more than 2,000 free prep LinkedIn group just for people like
you.
items (questions and answering options):

# of
free Level of
Provider URL Comment
test difficulty*
items
Satya Das www.techfaq360.com 200 Free digest offering for an exam
simulator. See also comments from
students
Ajith Namboothiri www.ajithn.com 208 Requires registration. Number of
questions may grow, as visitors are
invited to add further questions.
Many questions of CAPM exam
style.
CertChamp www.certchamp.com 200 Some questions have been
reported to have errors.
CertGear www.certgear.com 6 Free trial of CertGear's exam
simulator.
Certification.about.com certification.about.com 20 Questions based on Whizlabs'
Exam Simulator software trial.
EdWel Programs www.edwel.com 200 Requires registration
Head First Labs www.headfirstlabs.com 200 Online practice exam from the
authors of Head First PMP book. A
PDF file with 2MB for download.
MeasureUp www.measureup.com 7 Simulates a test environment
online similar to the original
environment.
My PMP www.mypmp.ie 90 Simulates a test environment H
online similar to the original
environment.
Oliver F. Lehmann, PMP www.oliverlehmann.com 175 PDF file (app. 1MB) for download. H
Just like the real thing: Questions
are written against the PMP
Examination Specification and
reference to a current project
management source.
www.oliverlehmann-training.de 175 German language aid for the 175 H
questions.
www.oliverlehmann.com 75 The 75 questions above, with a H
timer in the title bar.
itunes.apple.com/de/app/xzams- 30 30 free questions for Apple H
pmp-sample/id399303897?mt=8 iPhone. 400+ questions in the
commercial offer ($10)
www.oliverlehmann.com 164 CAPM Prep Questions. Not quite
the PMP exam style, but
nevertheless helpful for your
preparation.
PMConnection www.pmconnection.com 10
PMExam.com www.pmexam.com ? Order their free Daily Digest as an H
e-mail service. A great resource
with intelligent questions.
PMPQuest.com www.pmpquest.com 12
PMP Question Bank pmpbank.googlepages.com 200 Good, difficult questions. H
PM Study www.pmstudy.com 50 200 free questions after optional
registration.
PMTI www.4pmti.com 15 Registration required.
Pmzilla www.pmzilla.com 155 Registration required.
PreparePM www.preparepm.com 165 High quality questions, which H
simulate the real test very well.
ProXalt www.proxalt.com 20 Registration required.
Tutorials Point www.tutorialspoint.com 200
Voight Project Solutions www.voightps.com 500 My friend and colleague Dr. Roger H
Voight has a large body of free
questions. Many of them are also
helpful for CAPM candidates.
Test Prep Review www.testprepreview.com 15
Threon www.threon.com 13 H

40 of 41 1/31/2011 10:27 AM
Test time: 06:33:37 - Total test time: 90 Min. Testing time is over http://www.oliverlehmann.com/pmp-self-test/75-free-questions.htm

* Level of difficulty marked with H: If you achieve 75% in these tests, you should be well prepared for the real
exam. Raise the number to 82% for the other tests.

Please send an e-mail to Oliver F. Lehmann, PMP if you are another provider, if a description is not correct any
more, if you have any comments on the quality and relevance of test questions, or if one of the links appears to be
broken.

A Note to My Visitors

Thanks a lot J to all who informed me that the owners of the websites

have copied my free sample questions and re-published them with their copyright assigned L.
The second of these two even sells my work for a fee - and the work of other good colleagues too.

That people are using my work may be honorable. But: I prefer to be asked before my material is
used by others—I would probably have allowed it, as I have done so often.

I also value rightful copyright information and a reference to the author. This is how I am quoting
others or use their materials in my websites and seminar literature wherever possible.

We Germans have a term for that: Gute Kinderstube – good manners from good education by good
parents.

The 250 sample questions in this website (and the many more used in my seminars)
- match the updated exam (per July 2009),

- are written against PMI's original PMP Examination Specification,

- reference to the appropriate body of knowledge,

- have been peer-reviewed for correctness and appropriateness,

- are open for discussion and feedback - of which I receive a lot.

20 April 2006, updated 09/03/2007, 30/03/2009, 25/01/2009, Munich, Germany

Advertisment

"PMI", "PMP", PgMP", "CAPM", "PMBOK" are marks of the Project Management Institute (PMI) which are registered in the United States of
America and in other nations
PMI has not participated in the creation of this self assessment test and has not reviewed it for correctness.
This test is for self assessment only and no guaranty is given for passing the PMP®.
Some of the names of companies and their products listed and linked to on this page are marks which are registered in various
countries.