Sei sulla pagina 1di 3

NATIONAL STEEL BRI D G E A L L I A N C E STEEL BRIDGE NEWS

Simple-Made-Continuous Bridge
Cuts Costs
Cost-effective detailing was only one of the advantages of a simple-made-
continuous weathering steel girder bridge in New Mexico.

T
BY TED L. BARBER, P.E.

THE NEW MEXICO DOT HAS GREAT- stressed concrete required five girder lines, tion. The steel girders, all grade 50W, have
LY IMPROVED MULTI-SPAN, PLATE- but steel plate girders required only four a total depth of 54 in. The web is 0.472 in.,
GIRDER STEEL BRIDGES DESIGNED girder lines. and the cross sections of the top and bot-
AS SIMPLE-SPAN FOR DEAD LOADS A shallower depth decreased the earth- tom flanges are 0.866 in. by 13.78 in. and
AND CONTINUOUS FOR LIVE LOADS. work required to build the bridge ap- 0.866 in. by 17.32 in., respectively.
These designs ease fabrication and erection, proaches, as well as the amount of right-
helping to keep steel bridges competitive of-way needed for a new parallel offset Superstructure Detailing
with concrete. The simple-made-continu- alignment. It also improved the bridge aes- New detailing ensured that the top plate
ous concept cuts costs through repetitive thetics in the river area. Other bridges built connecting in-line girders at the piers would
fabrication, full-length girder erections, along the same river have vertical curves slip properly under DC1 construction load-
simplified connections, and flexible deck- that seem somewhat out of place for this ings, allowing beam-end rotation. By con-
pour sequencing. river valley. trast, on the US 70 project the contractor
The economical steel bridge design placed the deck and pier diaphragm in one
Bridge Overview incorporated an easily fabricated and con- continuous pour. Construction workers had
The bridge discussed here crosses structible bridge superstructure with no to tighten all top continuity plate connec-
the Rio Grande River on NM 187, near traditional bolted splices between piers. tion bolts before slab pour because of their
Array. This two-lane, four-girder struc- Eliminating these bolted splices avoided the location inside the concrete pier diaphragm.
ture, designed by the NMDOT, has five shoring towers required for erection. The This induced some level of stress through-
105-ft spans and a width of 34.5 ft. The design implemented constant plate thick- out the beam. The shear resistance of neo-
substructure consists of driven, filled, steel nesses and dimensions with no flange tran- prene bearing devices induced these forces,
pipe piles. Concrete curtain walls surround sitions. One-piece diaphragms, positioned which are caused by beam-end rotation un-
the piles to five feet below grade. The con- on wide spacing, also facilitated easy erec- der deck pour loadings.
struction phase started in the fall of 2004,
completing in the summer of 2005.
On an earlier project, the simple-made-
continuous concept served in a dual-design
analysis (steel vs. pre-stressed concrete
bridges) for a bridge on US 70 in southern
New Mexico. Design consultant for the US
70 bridge alternates was Parsons Brincker-
hoff, Inc. Bids by construction contractors
for these bridge alternates differed by only
0.2 percent out of a total project construc-
tion cost of $21 million. This small dif-
ferential cost tipped the decision to look
at applying the simple-made-continuous
concept to steel bridges located in similar
geographies.
The NM 187 steel bridge project in-
corporated further improvements in de-
sign and construction details. Selection of
the superstructure type depended heavily
on economic analyses of various configu-
rations of steel girders and pre-stressed
concrete beams, while limiting the depth
of the new superstructure. The prelimi- Figure 1. Dual-design analysis indicated that steel required only four girders, while concrete
nary design scenarios determined that pre- pre-stressed beams required five (for the same depth).

DECEMBER 2006 MODERN STEEL CONSTRUCTION


Figure 2. Connection plate bolts outside the pier permit tightening after
the deck pour, minimizing induced stresses.

NMDOT improved the girder connec- the connection continuity plates to con- stage transformed joints at piers to mo-
tion for the NM 187 bridge design by plac- form to beam dead-load camber at each ment connections for girder-line analysis.
ing the bolts outside the poured concrete beam end. This allowed the connection STAAD Pro also allowed factoring of loads
diaphragm at the piers (Figure 2). Bolts plate to fit up with loose bolting during and graphical presentation of the location
placed heads-up and nuts-exposed-down dead-load application. The top-plate slip- of axle loads and their position at maxima.
permitted tightening of the connection page also avoided unintended shear de- Many of today’s software programs seem to
after pouring of the deck and pier dia- flections in the steel-reinforced neoprene lack presentation of positions for the load-
phragms. After deck pours, the bolt heads bearing pads during the slab pour, as well ing on the structure. Mathcad performed
were locked into the concrete deck. Work- as any induced moment in the girders. the calculations for the steel design using
ers tightened bolts by turning nuts with Additionally, the reviewers requested a the LRFD code.
direct tension indicators from below. Final small increase in the length of the slotted
tightening came after all concrete had been hole in the continuity plates to aid erec- Fabrication and Erection
poured for the deck and pier and abutment tion tolerances. As a result, the contractor Global steel market conditions delayed
diaphragms, prior to opening for traffic. was able to erect beams and lift continuity the start of fabrication of the girders for
The design required adding reinforcing plates (with bolts) into place without any the project. The nationwide supply of steel
bars to normal deck reinforcement patterns alignment problem. Bridge erection was decreased between the time of bidding and
longitudinally over the piers. The addi- simple and straightforward. notice to proceed. The contractor asked
tional reinforcement achieved the required The design intentionally centers the for suspension of work on the contract for
negative moment capacity for the bridge’s bridge’s vertical alignment at the crest of a three months over the winter to allow for
continuous live-load function. Under live vertical curve, allowing for the uniformity delivery of the raw plate to the fabricator.
loads the continuity connection plate will of all girders and greatly simplifying the NMDOT planned this bridge for con-
be lightly stressed. The continuity plate bridge in design and detailing for construc- struction during the low-flow stage of the
connection also added redundancy in the tion. Steel girders for this bridge were de- river. It was essential to complete spans 4
event that future deck deterioration reduc- tailed for the same exact length, plate thick- and 5, the two spans over the river, before
es the effectiveness of the deck reinforce- ness, dimensioning, and camber, facilitated the water reached spring irrigation levels.
ment for negative moment capacity. by a slight adjustment to the length of end In spite of the three-month suspension of
The bearing stiffener plate on each spans. Simple horizontal steel channel dia- work, fabricated steel delivery and erec-
beam end at the piers served to develop phragms added to the bottom flange in the tion took place to complete the two river
compression for this moment connection. negative moment region over the piers spans on time. The flexibility of the simple-
A simple plate perpendicular to the web provide additional buckling resistance. made-continuous girder system permitted
and bearing stiffener braced the bearing the contractor to pour spans 4 and 5 while
plate in the compression zone. Design Firsts beams had not yet been erected on spans 1,
This type of connection also gave more The bridge represents the first in-house 2, and 3. Thus, the contractor was able to
flexibility to the bridge contractor on pour design of a steel bridge with this detail- fulfill this contact requirement.
sequences. Contractors in the state want ing and the first project to implement Economical and fast fabrication resulted
to pour entire bridges in one day. The AASHTO LRFD Bridge Design Specifica- primarily from the repetition of girder de-
500+ cubic-yard volume of concrete on tions. No commercial software packages are sign throughout the structure. Repetition
this bridge deck prevented a one-day pour. available for the simple-made-continuous in shop fabrication increased productivity
But with this design, contractors can pour steel design concept. Instead, STAAD Pro by at least 25 percent. Like-size flanges,
across spans, pier concrete diaphragms, and structural analysis software and Mathcad webs, and girder lengths provided the most
bulkhead 6.5 ft from a pier cap. performed a two-stage analysis and design advantageous price and delivery of steel
Reviewers of shop drawings made a calculation for the beam lines. For the first plate from the mill. Additional advantages
change requesting that the fabricator bend stage, all spans were simple. The second included:

MODERN STEEL CONSTRUCTION DECEMBER 2006


Figure 3. A connection plate bolts the top
flanges of the two girders that meet at a pier,
making the girders continuous for live loads.

• Detailers could develop shop drawings for Two relatively small cranes, readily showed that steel bridges can compete
one girder; all others were nearly alike. available in the state, easily erected the steel with pre-stressed concrete in a predomi-
• The fabricator cut flanges and webs using beams. Prestressed concrete beam bridges nantly concrete bridge state. This concept
only one drawing. often require much larger cranes and large will work well in other similar river and dry
• Shop fabrication necessitated only one jig mobilization costs, difficult lift configura- stream-bed crossings of significant length
for tacking and welding. tions, and more erection time. The State and requiring at least two spans. This type
• The continuity plates that spliced the of New Mexico is in the middle of a $1.5 of design is limited to maximum girder
girders together at the piers were all iden- billion road and bridge improvement bond lengths that can be hauled to the bridge
tical and could be processed full-size us- program over six years. One of the goals is location; otherwise, expensive traditional
ing CNC equipment. to facilitate smaller bonding requirements field splices are necessary.
• The girders did not require full layout so that more construction firms are able to
and assembly in runs. bid projects. Using resources within the Ted Barber is a bridge design unit supervisor
• Assembly drilling, required for conven- state are essential for this program. with the New Mexico Department of Trans-
tional bolted girder splices, was unneces- The design phase of this project started portation (NMDOT) in the Bridge Design
sary. before steel price levels increased over the Section.
With all parts alike, erection efforts in past few years. Despite these increases, cost
the field were much more efficient as well. per square foot for this bridge came in lower Owner and Designer
Big savings resulted from: than some other concrete bridges recently New Mexico Department of
• Eliminating bolted field splices between bid in the state. With a total deck area of Transportation
piers. 18,170 sq. ft, the cost of this bridge as re- Contractor
• Eliminating sandblasting of girders (the ported to the Federal Highway Administra- Reiman Corp., Cheyenne, Wyoming
bridge is not in an area exposed to view). tion was $75 per sq. ft. Prestressed concrete
Fabricator
• Specifying weathering steel, which will girder bridges of comparable square footage
Roscoe Steel & Culvert Co., Billings,
develop a rich color and form a protec- were $68 and $88 per sq. ft. each.
Montana (AISC member)
tive patina in time. This simple-made-continuous project

DECEMBER 2006 MODERN STEEL CONSTRUCTION

Potrebbero piacerti anche