Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Disclaimer
The information contained within this manual, along with the other NYISO manuals, is intended
to be used for informational purposes and is subject to change. The NYISO is not responsible for
the user’s reliance on these publications or for any erroneous or misleading material.
©
Copyright 1999-2009 New York Independent System Operator
NYISO SYSTEM PROTECTION MANUAL
Table of Contents
Table of Figures ......................................................................................................................... vi
Table of Tables .......................................................................................................................... vi
Revision History .........................................................................................................................vii
1. Reporting Transmission and Generation Protection System Operations and Protection
System Performance .......................................................................................................... 1-1
1.1 Scope ........................................................................................................................................1-1
1.2 Data Collection and Reporting ..................................................................................................1-1
1.2.1 Transmission Owner Collection Schedule..................................................................1-1
1.2.2 Generation Owner Collection Schedule .....................................................................1-1
1.3 Transmission of Data and Discussion of Results......................................................................1-1
1.3.1 Transmission Owners .................................................................................................1-2
1.3.2 Generation Owners.....................................................................................................1-2
1.4 Information Collected and Data Format ....................................................................................1-2
1.4.1 Transmission Owners .................................................................................................1-2
1.4.2 Generation Owners.....................................................................................................1-3
1.5 Data Collection ..........................................................................................................................1-3
1.5.1 Transmission Owners .................................................................................................1-3
1.5.2 Generation Owners.....................................................................................................1-3
1.6 Follow-Up Actions .....................................................................................................................1-3
1.7 Interpretations ...........................................................................................................................1-4
1.8 Information Requested by NPCC..............................................................................................1-4
1.9 References ................................................................................................................................1-4
2. Application of Disturbance Monitoring Equipment (DME) .............................................. 2-1
2.1 Definitions..................................................................................................................................2-1
2.2 Specification and Settings of DME............................................................................................2-1
2.3 Time Zone .................................................................................................................................2-1
2.4 Survey of DME Equipment........................................................................................................2-2
2.5 Sharing of DME Data ................................................................................................................2-2
2.6 Other .........................................................................................................................................2-2
2.7 References ................................................................................................................................2-2
3. System Protection Data ...................................................................................................... 3-1
3.1 Relay Characteristics ................................................................................................................3-1
3.2 Pilot Protection Systems ...........................................................................................................3-1
3.3 Clearing and Reclosing Times ..................................................................................................3-2
3.3.1 Clearing Times............................................................................................................3-2
3.3.2 Reclosing Times .........................................................................................................3-2
3.3.3 Special Protection Systems ........................................................................................3-3
3.3.4 Special Protection Systems ........................................................................................3-3
3.3.5 Other Remedial Action Systems.................................................................................3-3
3.3.6 SPS Data Submission and Updating Procedures ......................................................3-4
3.3.6.1 Facility Equipment Owner Actions.....................................................................3-4
3.3.6.2 NYISO Actions...................................................................................................3-4
3.4 Power Line Carrier Frequencies ...............................................................................................3-5
3.4.1 Introduction .................................................................................................................3-5
3.4.2 UTC PLC Task Force Contacts ..................................................................................3-5
Table of Figures
Reserved for future use.
Table of Tables
Revision History
1.1 Scope
The NYISO SPAS has been assigned the responsibility of analyzing BPS Protection System
Performance (PSP) and maintaining a record of all BPS protection system operations. This
function was initiated mainly so that the benefits of these experiences would be shared
among SPAS members.
is due. This schedule may be adjusted in some quarters due to constraints such as
conflicting meetings.
Any items that are incomplete or remaining under investigation should be documented in
the SPAS meeting minutes and action items list and addressed at subsequent SPAS
meetings until the items are closed.
Any mitigation plans should be presented to SPAS and documented in the SPAS meeting
minutes and action items list and addressed at subsequent SPAS meetings until the items
are closed.
1.7 Interpretations
Questions of interpretation should be brought for discussion at the SPAS meeting
immediately following the quarter during which the event occurred. Such discussions may
result in rules or interpretations being added to this manual or subsequent Technical
Bulletins.
1.9 References
NPCC B-21, “Guide for Monitoring of Protection System Misoperations,” July 14,
2004, or most recent version, available at the following address:
http://www.npcc.org/
NERC PRC-003-1, “Regional Procedure for Analysis of Misoperations of
Transmission and Generation Protection Systems,” or most recent version, available
at the following address:
http://www.nerc.com/
NERC PRC-004-1, “Analysis and Mitigation of Transmission and Generation
Protection System Misoperations,” or most recent version, available at the following
address:
http://www.nerc.com/
NERC PRC-016-0, “Special Protection System Misoperations,” or most recent
version, available at the following address:
http://www.nerc.com/
2. A PPLICATION OF D ISTURBANCE
M ONITORING E QUIPMENT (DME)
Disturbance Monitoring Equipment (DME) as used in this document includes, but is not
necessarily limited to, dynamic disturbance recorders, digital fault recorders, and phasor
measurement units.
The NYCA has long been a pioneer in the effective application of DME and continues to be
exemplary in its ability to effectively use DME to accomplish the three main purposes: (1) model
validation, (2) disturbance investigation, and (3) assessment of system protection performance.
The NYCA has also been an active participant in preparation of the various DME-related
documents of the IEEE, North American Electric Reliability Corporation (NERC), the Northeast
Power Coordinating Council, Inc. (NPCC), and the New York State Reliability Council
(NYSRC); several of the most important documents are listed in the section 2.7, “References,”
below. This Manual addresses only those items that are not already covered in the applicable
documents of NERC, NPCC, and NYSRC.
2.1 Definitions
DME – Disturbance Monitoring Equipment
DDR – Dynamic Disturbance Recorder
DFR – Digital Fault Recorder
PMU – Phasor Measurement Unit
NYISO – The New York Independent System Operator, an Area Reliability Coordinator
TO – Transmission Owner
GO – Generation Owner
2.6 Other
DME installed by New York TOs and GOs shall be operated and maintained in accordance
with the requirements of NPCC Criteria A-15 and NERC Standard PRC-018-1.
Consideration should be given to consultation with NYISO staff in regard to DME
locations and configuration.
2.7 References
NYSRC Rule C-R5, “Disturbance Recording”
NPCC Criteria A-15, “Disturbance Monitoring Equipment Criteria”
NERC Standard PRC-002-1, “Define and Document Disturbance Monitoring
Equipment Requirements”
NERC Standard PRC-018-1, “Disturbance Monitoring Equipment Installation and
Data Reporting”
NPCC Guideline B-25, “Guide to Time Synchronization of Substation Equipment”
NPCC Guideline B-26, “Guide for Application of Disturbance Recording
Equipment”
IEEE C37.111-1999, “IEEE Standard for Common Format for Transient Data
Exchange (COMTRADE) for Power Systems”
IEEE C37.232-2007, “IEEE Recommended Practice for Naming Time Sequence
Data Files”
relays), separate pages shall be attached. If the Facility Equipment owner is using the Power
Technologies, Inc. PSS/E program, then PSS/E input forms may be attached to the Relay
Characteristics Form.
A protection system that limits the ability to load a facility to rated Short-Term
Emergency (STE) capability
The NYISO System Protection Coordinator notifies the Facility Equipment owner SPAS
Member when one of the above situations is detected and a NYISO System Impacting
Protection Memo System report is required.
3.4.1 Introduction
Coordination of PLC frequencies within New York State is the responsibility of the NYISO
successor group to the System Protection Advisory Subcommittee (SPAS).
In order to carry out these coordination responsibilities, the NYISO participates as part of a
working group known as the Power Line Carrier Task Force, or PLC Task Force. This task
force comprises designated UTC PLC Data Base Contacts and the NYISO System
Protection Coordinator.
The PLC Task force originally collected and supplied information on New York PLC
facilities to NERC, which later turned over to UTC the responsibility of maintaining the
PLC Database.
In all these cases, the PLC Frequency Data Report form is completed and sent to the
NYISO. The instructions for forms PLC1 and PLC2, and the forms themselves, are
available on the UTC Web site at this address:
http://www.utc.org/utc/plc-forms-instructions
All the information on Form PLC2 form must be completed, and the applicable UTC
Transaction Code for this form must be specified. All transmitter information entered for
the first time shall be designated as transaction code A or P.
Add in service A
Add in proposed P
Correction C
Delete D
Kathleen Fitzpatrick
United Telecom Council
1901 Pennsylvania Ave NW #500
Washington, DC 20006
kathleen.fitzpatrick@utc.org
3.5.1 Introduction
The NYISO System and Resource Planning department Protection Coordinator shall
maintain a uniform short-circuit representation for fault analysis. The Equipment owners
shall periodically review and update their respective portions of the representation. It is
necessary for the NYISO to maintain a current short-circuit representation to ensure
availability of this data for any necessary analyses required in a system impact study in
accordance with the NYISO Transmission Expansion and Interconnection Manual
(http://www.nyiso.com/public/documents/manuals/planning.jsp?maxDisplay=20) and other
industry Standards. Voltage and dynamic stability studies for either system reliability or
operating security also need accurate fault analysis data.
The NYISO uses the ASPEN One-Liner program; however, new data or modifications to
existing data may be submitted in any of the standard data formats used by the industry
(e.g., PSS/e, CAPE, etc.).
The NYISO System and Resource Planning department Protection Coordinator shall make
the representation available to all Facility Equipment owners, other NYISO staff, or to such
contractors and consultants or regulatory agencies for purposes of conducting system
studies associated with transmission system reliability assessment.
4.1 Entities
NYISO (as Area Reliability Coordinator) – NYISO staff will initiate the request and
collect the data and compliance statements.
UFLS Entity – Generally, the New York Area UFLS Entities are the same as the New York
Area TOs; however, this term may also apply to a Transmission Operator, Distribution
Provider, and/or LSE that is required to own or operate a UFLS program.
4.2 Schedule
In order to support collection of the NPCC D-12 compliance data, NYISO staff will send an
inquiry by e-mail on or about April 1 of each year to the SPAS Participants and
representatives designated by the UFLS Entity for this purpose. This e-mail inquiry will
request data sufficient to perform analysis of compliance with the following table from D-
12:
Table 1 - UFLS Parameters for the Eastern interconnection Portion of the NPCC
Notes:
(1) Total operating time is the load-weighted average for all load to be shed within a Balancing Authority area,
with maximum deviation for any load limited to ±50 ms.
(2) Minimum UFLS relay operating time=100ms.
The e-mail inquiry will request data sufficient to perform analysis with the following
statement in D-12:
D-12, 5.4 “Generators shall not be tripped for under-frequency conditions in the
area above the curve in Figure 1, except as provided for in Sections 5.4.1 and
5.4.2.” (Figure 1 is included in D-12 following section 7.)
The e-mail inquiry will specify the UFLS Entity response time, which shall be at least 30
days.
In parallel with the activity described herein, the NYISO will also be collecting data
directly from GOs.
4.4 Format
A format for reporting compliance will be distributed with the e-mail inquiry. The
following information will be reported on this form:
Name of UFLS Entity
Date of report
Name of the individual making the report on behalf of the Entity
For Section 5.2.1 of D-12:
Previous year’s summer integrated hourly peak load
UFLS at each step, expressed as both megawatts and percentage of Entity’s peak,
including those steps provided that are beyond the NPCC-mandated steps
For Section 5.4 of D-12:
List of generators that do not conform with NPCC D-12.
For each such non-conforming generator, the generator megawatt rating, trip setting
in Hertz, and time delay in seconds.
Compensatory load shedding for each such non-conforming generator, with the
megawatts load shedding and trip setting in Hertz.
Non-conforming generators with a rating below 20 MW may be reported in groups
with other generators of the same settings.
Compensatory load shedding for generators that have been reported in groups may
also be grouped.
Overall Compliance:
A statement of compliance with NPCC D-12
4.5 Notifications
At the completion of the data collection, the NYISO will prepare an Area Compliance
Report. This report will be completed within 60 days of the initial data request, and copies
will be sent to the appropriate NPCC entity or group and the NYCA UFLS Entities. (This is
necessary as PRC-007 places the obligation on each UFLS entity to “ensure that its UFLS
program is consistent with its RRO TFLS program requirement.”)
4.6 References
NPCC D-12, “UFLS Program Requirements,” June 29, 2009, or most recent version,
available at:
http://www.npcc.org/documents/regStandards/Directories.aspx
“UFLS Implementation Plan,” June 29, 2009, available at:
http://www.npcc.org/documents/regStandards/Directories.aspx
NPCC B-7, “Automatic Underfrequency Load Shedding Program,” September 4
2008, or most recent version, available at
http://www.npcc.org/documents/regStandards/Guide.aspx
NERC Standard PRC-007-0, “Assuring Consistency with Regional UFLS Program
Requirements,” Requirement R1, available at:
http://www.nerc.com.
NYSRC Rule F-R8, “Load Shedding Allocation,” available at:
http://www.nysrc.org.
5.1 Scope
The NYISO SPAS has been assigned the responsibility of monitoring compliance with the
relay maintenance criteria set forth in NPCC directory D-3.
5.5 Reference
NPCC Regional Reliability Reference Directory 3, “Maintenance Criteria for Bulk
Power System Protection,” July 11, 2008
A.
A.
A.1. Introduction
This appendix establishes minimum guidelines to provide a uniform method of selecting
power line carrier (PLC) frequencies within the New York Control Area (NYCA).
Procedures used by the Transmission owners to notify necessary parties of PLC frequency
changes and additions and to keep the Utilities Telecommunications Council (UTC) PLC
database current can be found in the section 3.4.4 of this manual.
PLC spectrum conservation has been a major concern within the power utility business for
many years. These guidelines have been developed to conserve spectrum while staying
within industry-established frequency separation limits to minimize interference between
channels.
It is assumed that the user of this manual is familiar with the application of power line
carrier systems.
A periodic review of these guidelines may be necessary, however, as dictated by changes in
equipment technology.
Use lower frequencies on longer lines and higher frequencies on shorter lines. A
“short line” is one with an attenuation (line and coupling losses) less than 10 dB or a
physical length of approximately 20 miles or less. A “long line” is one with an
attenuation more than 10 dB or a physical length in excess of 20 miles. Use the
highest frequency possible while maintaining adequate operating margins to save the
lower frequency spectrum for use on long lines.
Avoid PLC frequencies that correspond to low multiples of λ /2 or λ /4 (half or
quarter wavelength of PLC frequencies, respectively) on short overhead lines.
Use frequencies that correspond to an odd multiple of λ /8 on overhead lines with
low attenuation.
Use narrow band equipment where speed is not a constraint.
Use power below 10 W where possible (i.e., 1-W guard, 10-W trip) to minimize
interference taking into account “bad” weather requirements (i.e., increasing noise
and attenuation) of the PLC system.
Unless otherwise noted, parallel lines not terminating on the same bus will be treated
as though they were, for PLC frequency selection purposes.
When PLC frequencies are to be applied to power cables, great care should be taken
to minimize PLC losses due to the low characteristic impedance of the cable, series
impedance mismatch at the coupling point, and standing wave reflections. This can
often be done by using lower PLC frequencies, using PLC frequencies at λ /2 or
multiples thereof, and by using extra-hi C coupling capacitors.
Although this guide identifies guidelines for PLC frequency selection, the following
additional points require consideration to ensure proper PLC system operations:
¾ Receiver Sensitivity
¾ Signal-to-Noise Ratio Requirements
¾ Receiver Selectivity
¾ Operating Margin, Including Transposition and Other Modal Loses
¾ Bad Weather Conditions
¾ Coordination with Adjacent Utilities
¾ Use of Voice Channels
¾ Line Tuners and Other Auxiliary Coupling Equipment Losses
Solid State
Tube Type Crystal Synthesized
Controlled Wide Band Narrow Band
On/Off
3 ms 15-20 dB 15 dB
(Baseband)
25-30 ms 0 dB 25 dB 500 Hz 200 Hz 5 mV
FSK Transmitter Trip 7 ms 5 dB 25 dB 1500 Hz 500 Hz 15 mV
(Baseband)
4 ms 7 dB 25 dB 3000 Hz 1000 Hz 15 mV
6 ms 5 dB 10 dB 1000 Hz 480 Hz
FSK Transmitter Trip
9 ms 0 dB 10 dB 340 Hz 170 Hz
(Audio Tones) 16 ms -3 dB 10 dB 170 Hz 85 Hz
Voice w/ Comp. 15 ms
A.5. References
Dowty RFL Industries, Communications Division. The PLC Handbook (PLC-79-1).
Boonton, NJ: Dowty RFL Industries, Inc., 1979.
General Electric Company, Power Systems Management Business Dept. PLC
Applications Guide – Protective Relaying Channels (GET-6920). Malvern, PA:
General Electric Company, 1985.
General Electric Company, Technology Center. Application Guide Relaying
Communications Channels (GET-8034). Malvern, PA: General Electric Company,
1993
IEEE: Power Systems Communications Committee. IEEE Guide for Power-Line
Carrier Applications (ANSI/IEEE Std 643-2004). New York: IEEE, 2005.
Ray, Roger E. “Channel Considerations for Power Line Carrier (RPL 83-3).” Coral
Springs, FL: Westinghouse Electric Corporation, 1983.
IEEE: PSRC H9, “Special Considerations in Applying Power Line Carrier for
Protective Relaying,” available at:
www.pes-psrc.org/
B.
B.1. Introduction
The System Protection Advisory Subcommittee (SPAS) has been collecting protection
system performance data for the Bulk Power System (BPS) for many years. In late 1988,
the Protection System Performance (PSP) Working Group was established to evaluate this
data and to evaluated the established procedure. This report format and procedure is the
result of the efforts of the working group to improve the reporting process.
B.2. Discussion
The protection system has been categorized into three areas to better define the reporting
procedure. A protection group consists of individual relays and communication packages
and their associated instrument transformers, d.c., and trip coil equipments. The protection
system is composed of a combination of protection groups, i.e., the primary and secondary
protection groups. The entire system, from the instrument transformer to the breakers, will
be referenced as a protection system. For the purpose of the PSP reporting system, a two
terminal transmission line has two protection systems, one at each end. Protection System
Performance reporting is on a per-terminal basis. Each terminal, should be reported
separately. For example, a two-terminal transmission line fault that is cleared correctly
normally will be counted as two “correct” protection system operations. Redundant
protection groups are considered to be one protection system; if any or all of the protection
groups operate correctly to clear a fault, the PSP will be recorded as one “correct”
operation.
If there is a known misoperation of a protection group that did not compromise the
performance of the protection system as a whole, then the misoperation should result in an
incorrect code.
Protection System Performance data records are necessary only for automatic operations
involving BPS facilities. A separate PSP record should be completed for each event. An
event is defined as any set of conditions, resulting in the unscheduled operation of the
protection system. Operations that occur during commissioning, before the protection
system is turned over to System Operations, should not be reported. A single PSP record
should be used to record from the initiating condition to the auto reclosing. Subsequent
relay operations should receive individual PSP records. Operations resulting from manual
or supervisory close will be considered a separate event, whether the manual or supervisory
close occurs during or after the auto reclose cycle. Additional comments describing the
event should be listed at the bottom of each report. It is important that all reports that
contain incorrect operations have sufficient comments to facilitate analysis and assessment
of preventative strategies.
A single event could cascade into additional events, such as a transformer failure due to a
through fault or a breaker failure. A new PSP report should be filed for each additional
event. A breaker failure is the failure of a breaker to open correctly. For this condition, the
PSP should be coded as incorrect because the intended breaker failed to clear the fault
(Code IBR in section B.4). The first event cascades into a second event, which is entered on
an additional report with an initiating condition entered an equipment failure. If a line
terminal trips, automatically recloses, and trips again, count two operations, but consider
the sequence to be all part of the same event.
In tabulating the year's operations, it was decided to categorize the Disturbance- and Non-
Disturbance–Initiated events separately. For this purpose, a disturbance is defined as an
unplanned event that causes an abnormal system condition or any perturbation to the
electric system.
included on the PSP report strictly for the purpose of gathering data on automatic
restoration. Although it is normally considered part of the protection system, the reclosing
relay is not necessary for clearing faults. Failure of a reclosing relay to operate shall not be
considered an incorrect operation for the purposes of filling out a PSP report. Also, breaker
trips caused by low gas or low air-pressure controls will not be reported. Breaker pole
disagreements that initiate breaker failure protection system tripping of adjacent/remote
breakers should be reported.
An entry of “U.I. ” (Under Investigation) in section B.4 indicates an event that is
unresolved. This event will not be counted until a finalized record has been submitted.
Pilot: If a line fault is cleared by a time-delayed backup relay, and this line has pilot
protection, it should be considered that the pilot group failed to operate correctly and the
protection system failed to operate in its design time. Thus, the protection system operation
should be coded “incorrect” at the slow-tripping terminal. Likewise a pilot group overtrip
will also be recorded as a single protection system “incorrect” at the tripping terminal.
These “incorrects” will be coded “ICO, ” for Incorrect Communications.
Direct Transfer Trip: If, during routine testing, an erroneous direct transfer trip signal is
sent and trips a breaker(s) at a remote station, the PSP procedure will be initiated by the
receiving end utility in conjunction with the sending end utility. Two reports will result:
The receiving end utility reports a correct protection system operation at its terminal, and
the sending end utility reports the personnel incorrect at its terminal. A transmission line
terminal that trips or fails to trip due to direct transfer trip channel noise (no fault detection
devices participating at the receiving terminal, no sending terminal participation) is to be
coded as incorrect "I-CO," at the receiving terminal.
B.4.1. Participant
CE – Consolidated Edison Company of New York, Inc.
CH – Central Hudson Gas and Electric Corporation
LI – Long Island Power Authority
NG – National Grid
NY – New York State Electric and Gas Corporation
OR – Orange and Rockland Utilities, Inc.
PA – New York Power Authority
RG – Rochester Gas and Electric Corporation
B.4.3. Date/Time
Date |M.M| |D.D| |Y.Y|
Time |H.H| |M.M|
Time should be stated in twenty-four hour format local time, i.e., EDT or EST, whichever is
in effect.
(Seconds and milliseconds will be added in the future.)
B.4.4. Event
B.4.4.1. Initiating Condition
The root cause regardless of whether the operation being described involves a power
system fault. The prefix on the field designates whether it was a power system disturbance
(D) or not (N). A full listing of the required inputs for this field can be found in the Event
Table, on page B-7.
B.4.4.3. Element/Location
The element at or on which the initiating event occurred. A full listing of the required
inputs for this field can be found in the Event Table, on page B-7. The
identification/location of this element can be included in the comments.
B.4.4.4. Circuit/Equipment
Affected BPS element or failed breaker.
B.4.4.8. Station
Location of the protection system listed in the following item.
The incorrect relay entries to replace the #’s are listed in Table B.3. Incorrect includes
failure of protection system to operate in design time.
|I.C.O| Incorrect – COmmunication (Complete Line Package and/or DTT
Package)
|I.N.L| Incorrect – Not Listed
|I.U.N| Incorrect – UNknown
|I.B.R| Incorrect – BReaker
|I.U.I| Incorrect – Under Investigation
|I.T.P| Incorrect – Test: Plan, hardware, software
|I.P.#| Incorrect – Personnel
The incorrect personnel entries to replace the #’s are listed in the Incorrect-Personnel Table
which follows.
B.4.6. Comments
Comments should be entered to describe the event.
B.4.7. Submitted By
Person responsible for submitting the record and the date completed.
EVENT TABLE
INITIATING CONDITION RESULTING CONDITION ELEMENT
OTHER GENERATOR
PROCEDURE NONE
RELAY PHASE-SHIFTER
SWITCHING POTHEAD
TREE PT
UNKNOWN REACTOR
VEHICLE STRUCTURE
WEATHER SWITCH
TRANSFORMER
UNKNOWN
Note: Add initiating condition “tower construction.”
INCORRECT-PERSONNEL TABLE
P9 OTHER OR UNKNOWN
Note: Codes IP2 and IP3 are not misoperations as defined by NPCC and NERC. The NPCC definition is contained in
document B-21, revised 09/04/2008, and the current NERC definition is contained in the NERC “Glossary of Terms
Used in Reliability Documents,” dated February 12, 2008. The NERC definition is under revision.
Note: Add P Code for Commissioning Testing In-Service Checks.
INCORRECT-RELAY TABLE
IR1 MISSING PART
IR9 OTHER
IRJ SOLID STATE RELAY COMPONENT FAILURE NOT COVERED BY SERVICE LETTER
IRK SOLID STATE RELAY COMPONENT FAILURE COVERED BY SERVICE LETTER
C.
Appendix C. Forms
Line No.
Line Name
Terminal
Base Voltage
Submitted by Date
CT Ratio
PT Ratio
Please attach RX plot with notations, or any other information necessary to describe protection systems for modeling.
Number of pages attached
Line No.
Line Name
Terminal
Base Voltage
Submitted by Date
Line No.
Line Name
Terminal
Base Voltage
Submitted by Date
IF YES, BREAKER
NO YES RECLOSING TIME*
HIGH SPEED RECLOSING*
DELAYED RECLOSING*
FIRST SHOT – Hot bus dead line
If there is no hot bus dead line reclosing at this end, i.e.,
reclosing is by sync check only, or not at all, choose NO.
* Definitions of terms are in the NPCC Bulk Power System Reclosing Guide, Document B-1, dated 03/11/2009.