Sei sulla pagina 1di 3

Tremie concrete

Methods for placing high quality concrete under water


BY W. MALISCH

Tremies can be used to place concrete


under water for caisson seals, bridge
piers, drydock walls and similar
structures.

uccessful placement of concrete under water cement plus pozzolan is 0.45.

S requires careful planning and attention to de-


tail. The concrete must flow readily into place
and consolidate under its own weight because
vibration might cause surrounding water to mix with
the in-place concrete and wash out the cement. All
Aggregate maximum size for reinforced placements
should be 3⁄4 inch, while use of 11⁄2-inch aggregate is rec-
ommended for nonreinforced placements. Rounded ag-
gregates are preferred. Fine aggregate content of 45 to 55
percent by volume of total aggregate and entrained air
methods of placing concrete under water are designed content of up to about 5 percent are generally desirable.
to prevent cement washout and the consequent forma- A slump of 6 to 9 inches is commonly used, but a
tion of weakly cemented sand and gravel pockets. slightly higher range may be needed when reinforcing
In the tremie process, concrete is placed through a cages restrict the flow or when horizontal flow over long
vertical steel pipe with an open, funnel-shaped upper distances is required. Wa t e r- reducing or water- re d u c-
end. The lower end of the tremie is kept immersed in ing/retarding admixtures are particularly beneficial in
plastic concrete so that freshly placed concrete doesn’t reducing water content to provide a cohesive yet high-
come into contact with the water. Direct visual inspec- slump concrete. The use of superplasticizers is not rec-
tion of the deposited concrete is usually impossible dur- ommended for massive placements unless slump loss
ing the placing operation, so progress of the pour must testing has shown no detrimental effects. It is extremely
be monitored by carefully observing the volume of con- important to maintain as high a slump as possible for as
crete placed and the rate of rise. long as possible so blockages don’t develop in the trem-
ie and so concrete continues to flow freely after exiting
Concrete mix proportioning the pipe.
Concrete to be placed by the tremie process must flow
readily and yet be cohesive enough not to segregate. Rel- Tremie equipment
atively rich mixtures are used (at least 600 pounds of ce- Tremie pipe diameter usually ranges from 8 to 12
mentitious material per cubic yard). Pozzolans improve inches. Smaller diameters may cause pipe blockages. For
flow characteristics and are generally used in amounts deep placements, sections of the pipe with flanged, gas-
up to about 15 percent of the cementitious material keted joints are used so upper sections can be removed
weight. The recommended maximum ratio of water to as concreting progresses.
the end seal. Concrete flows out and mounds up around
the mouth of the pipe, establishing a seal. Initial lifting of
the tremie should be done slowly to minimize distur-
bance of material surrounding the mouth of the tremie.
When using a go-devil and the wet pipe technique to
start a pour, the tremie is lifted a maximum of 6 inches to
allow water to escape. Concrete is then added slowly to
force the go-devil downward. Once the go-devil reaches
the mouth of the tremie, the tremie is lifted to allow the
go-devil to escape. The tremie shouldn’t be lifted again
until a mound is formed and a seal established.
After starting, tremies shouldn’t be lifted again until
they are embedded 3 to 5 feet. All vertical movements of
the tremie pipe must be done slowly and carefully to pre-
vent a loss of seal. If loss of seal does occur, the tremie
must be brought back to the surface, the end plate must
be replaced, and flow restarted. A go-devil must not be
Figure 1. To start a pour, the bottom of the tremie pipe is used when restarting a tremie after loss of seal. Water
sealed with an attached gasketed plate or with a wooden
pushed out by the go-devil will wash cement out of the
plug.
previously placed concrete.
End plates or plugs such as the ones shown in Figure
1 are used when a dry pipe technique is employed for Placing concrete with a tremie
starting the tremie pour. As the pipe is lowered to rest Concrete placement should be as continuous as pos-
on the bottom, water pressure seals the gasket and the sible through each tremie. Long delays in placement
pipe is kept dry. may allow concrete to stiffen and resist flow once place-
In very deep placements, buoyancy may be a prob- ment resumes. While interruptions of up to approxi-
lem when an end plate is used to seal the pipe before mately 30 minutes may allow restarting without any spe-
it’s placed in the water. Use of pipe with thicker walls or cial pro c e d u re s, longer delays must be treated by
weighted pipe can overcome buoyancy problems. Al- removing, resealing and restarting the tremie.
t e rn a t i ve l y, an open-ended pipe can be set and a go- Tremie pipes must be spaced so that the concrete
devil or traveling plug inserted to keep water from pen- doesn’t have to flow too far. Otherwise, segregation will
etrating the first concrete placed in the pipe. The plug occur and too much area on the sloping face of the flow-
must be tight enough to exclude water from the con- ing concrete will be exposed to water. This latter prob-
crete but loose enough to move under the weight of the lem results in weak layers of high water-cement-ratio
c o n c re t e. An inflated rubber ball has been used as a paste within the structure. A pipe spacing of 2 or 3 times
plug, but at depths greater than about 25 feet the ball the depth of concrete being poured is ideal (Figure 2).
may collapse and become ineffective as a seal. Because Usually the spacing will be between 15 and 35 feet but
it will regain its shape when it pops back to the surface, tremie concrete has been flowed up to 70 feet in very
the lost seal may not be noticed and poor quality con- thick pours.
crete may result. The tremie pipe must remain fixed horizontally while
concrete is flowing. Ho ri zontal movement of the pipe
Starting a tremie
placement
Tremies started using the
end plate, dry pipe technique
are filled with concrete in the
dry. To minimize segregation
caused by dropping concrete
in deep placements, a 2- or 3-
foot depth of a cement-sand
mortar mix can be placed in
the tremie first. Then even if
the regular tremie mix segre-
gates during free fall it will
remix in the mortar at the bot-
tom. After the tremie pipe is Figure 2. Tremie pipes are spaced so that concrete doesn’t have to flow too far.
full it is raised no more than 6 Typical spacing is 2 to 3 times the depth of concrete being placed.
inches off the bottom to break
will damage the surface of the concrete in place, create crete may be injected below an already set mass of con-
additional laitance and possibly lead to loss of seal. Hor- crete. This might raise the mass and cause cracking.
izontal distribution of the concrete is accomplished by
flow of the concrete after it exits the pipe or by halting Dealing with blockages
placement, moving the pipe, reestablishing the seal and Tremie blockages that occur during placement should
resuming placement. be cleared with extreme care to prevent loss of seal. The
In large placements, two methods have been used to tremie should be quickly raised 6 to 24 inches and then
distribute concrete horizontally. In the layer method, the lowered in an attempt to dislodge the blockage. The
entire area of placement is concreted simultaneously us- depth of pipe must be watched closely during all such
ing a number of tremies. Level of the concrete is kept attempts. If the blockage can’t be jarred loose, the trem-
roughly horizontal as it rises. With the advancing slope ie should be removed, cleared, resealed and restarted.
method, one portion of the concrete is brought to fin- The best way to prevent blockages from occurring is to
ished grade and then the tremies are moved to bring ad- ensure an uninterrupted supply of high-slump, flow-
jacent low areas to grade. Work normally pro g re s s e s able concrete and a continuous placing sequence.
from one end of a large placement.

Controlling discharge elevation


of the tremie pipe
Once concreting is underway, the mouth of the pipe References
should be kept buried and about 3 to 5 feet below the 1. “Guide For Measuring, Mixing, Transporting, and Placing
concrete surface. If the elevation of the tremie hopper is Concrete,” ACI 304R-85, ACI Journal, May-June 1985, pp.
248-250.
controlled by a crane, a good crane operator can feel a
loss of tension on his cables and immediately lower the 2. “Marine Structures,” Handbook of Concrete Engineering,
tremie pipe when there is a danger of losing the seal. All Second Edition, Van Nostrand Reinhold Company, New
vertical movements of the tremie pipe must be done York, 1984, pp. 713-716.
slowly and carefully to prevent loss of seal. 3. “Underwater Concrete,” HERON, Volume 19, No. 3, 1973,
One way of detecting a loss in seal is to monitor the 52 pp.
volume of concrete in place throughout the placement.
Underruns indicate a loss of seal because washed and 4. “Standard Practice for Concrete,” Engineer Manual No.
segregated aggregates will occupy a greater volume. Al- 1110-2-2000, U.S. Army Corps of Engineers, September
1985, pp. 7-14 through 7-15.
so, if the seal is lost the flow rate of concrete in the pipe
will increase noticeably. 5. “Pumping Over or Under Water,” Pumping Concrete:
Lines can be marked on the tremie pipe at conve- Techniques and Applications, Concrete Construction Publi-
nient intervals to help the crane operator determine cations, Inc., Addison, Illinois, 1985, pp. 10.1-10.4.
when the pipe needs to be raised. Periodically a weight
on a dropline can be lowered until it rests on the sur-
face of the freshly placed concrete. By observing the
position of the marks on the pipes and measuring the
distance to the top of the concrete, the operator can
judge when the pipe mouth is buried to a depth that re- PUBLICATION #C860123
quires it to be raised. Copyright © 1986, The Aberdeen Group
If a tremie pipe is left too low for too long, fresh con- All rights reserved

Potrebbero piacerti anche