DIMENSIONES METRADO

N° DE
ITEM PARTIDA UBICACIÓN DE ELEMENTO U.M.
VECES LARGO ANCHO ALTO PARCIAL TOTAL

1 ZAPATAS (fc=245 - 1/2") 9.57 m3


Z1 2 1.20 1.20 0.50 1.440
Z2 4 1.10 1.10 0.50 2.420
Z3 2 1.40 1.20 0.50 1.680
Cimiento EJE A-A / 1-3 2 1.05 0.60 0.50 0.630
Cimiento EJE C-C / 1-3 2 1.05 0.60 0.50 0.630
Cimiento EJE 1-1 / A-C 2 2.31 0.60 0.50 1.383
Cimiento EJE 3-3 / A-C 2 2.31 0.60 0.50 1.383
2 COLUMNAS (fc=245 - 1/2") 7.16 m3
C1 6 0.25 0.30 11.02 4.959
C2 2 0.25 0.40 11.02 2.204
C3 0 - - - -
2 VIGAS (fc=245 - 1/2") 3.88 m3
V1 (1-1 / 3-3) 2 8.00 0.25 0.20 0.800
V1 (A-A / C-C) 2 5.50 0.30 0.25 0.825
V2 (1-1 / 3-3) 1 8.00 0.25 0.17 0.340
V2 (A-A / C-C) 1 5.50 0.30 0.25 0.413
V3 (1-1 / 3-3) 1 8.00 0.25 0.17 0.340
V3 (A-A / C-C) 1 5.50 0.30 0.25 0.413
V4 (1-1 / 3-3) 1 8.00 0.25 0.17 0.340
V4 (A-A / C-C) 1 5.50 0.30 0.25 0.413
Incluyendo 10% de desperdicio
Item DESCRIPCION BOLSA M3 BALDES
1 CEMENTO 261.00
2 HORMIGON - -
3 ARENA GRUESA 12.00 670.00
4 PIEDRA GRANDE - -
5 PIEDRA MEDIANA - -
6 PIEDRA CHANCADA 12.00 670.00
7 AGUA 5.00 279.00