To,
All Adl. CE, Zone,
GETCO,
All SE (TR),
GETCO
In order to standardize the drawings and documents for GETCO, following points are deliberated
and finalized those may please be noted and implemented with immediate effect.
All are requested to keep those as permanent reference. Drawing/Documents may be prepared on
the basis of the same. No change in any of this format should be made without approval of
Competent Authority at Corporate Office.
(K.S.DAVE)
Chief Engineer (Project)
C.F.W.C to:
1) MD GETCO
CC to:
1) CE (TR)/(R & M) Corporate Office
GETCO -with request to prepare the respective
2) CE (LDC) Gotri formats for drawing/documents as per the
3) ACE (Tel & Testing) (R & C) standard guidelines given herein and to
Corporate office GETCO adopt the same for ISO documentation
4) SE (Civil) Corporate Office GETCO
5) SE (Project) Corporate Office GETCO
Annexure-I
Drawing ID
P- Primary
S- Secondary
Project ID
First Digit 06 for 66 kV
1 for 132 kV
2 for 220 kV
4 for 400 kV
Second digit S-for SS
L-for Line
Last three digits- Sr. No. of project
E for Electrical
C for Civil
Annexure-III
Date w.e.f.
Revision No.
TS-Technical Specification
GTP-General Technical Particulars
QR-Qualifying Requirements
FQP-Field Quality Plan
E for Electrical
C for Civil
Annexure-IV
GETCO
Released For Manufacture
Released for Construction
Released for Information