Sei sulla pagina 1di 3

ROTATING EQUIPMENT/MAINTENANCE

Controlling coupling guard leakage


Novel design eliminates curing time and lowers temperatures

K. M. WORRELL and A. O. AL KHOWAITER, Saudi Aramco, Uthmaniyah Gas Plant,


Udhailiyah, Saudi Arabia

C
oupling guard oil leakage on critical gas compressor To meet this objective, a three-piece design was created
trains can be a problem causing delays in startup after that eliminated the need for horizontal split-line gaskets. This
repairs due to sealant curing times, and a daily tiuisance design included an expansion bellows and circumferential
to operators. At Saudi Aramco's Uthmaniyah Gas Plant facility, flanges with O-rings. While the design met many of the objec-
three 25,000-hp sales gas compressors are considered critical tives, it was too heavy and still had problems with flanges due
to the plant's daily output of 2.500 MMscfd natural gas. The to sag. The second design (Fig. 2) introduced the concept of
machines were installed almost 25 years ago with a standard a telescopic sliding fit, and the expansion bellows was elimi-
split-line multistage coupling guard enclosing a diaphragm nated to reduce weight. 1 his design proved practical In terms
coupling between the gearbox and the of eliminating the split lines and using O-
compressor (Fig. 1). ring sealing throughout. However, some
This coupling guard design uses gaskets • We found the ideas flange leakage due to sag occurred at the
between the split lines and the flange faces mid-position, posing a problem as well as
to reduce oil leakage. Due to expansion presented by Michael M. pressurization of the guard. The team went
from heat and distortion over time, the Caiistrat in his book were back to the drawing board one more time
gaskets were not effective at controlling with a new approach.
011 leakage. To control leakage, a sealant particularly appropriate After researching coupling enclosure
compound was applied between the flange designs, we found that the ideas presented
faces. This added an additional curing for the design we were by Michael M. Caiistrat in his book Flex-
time that delayed return to operations by ible Couplings: Their Design Selection and
12 hours and had a negative impact on pursuing Use, were particularly appropriate for the
production of 150 MMscf of sales gas per design we were pursuing. Since the origi-
occurrence. nal design was to eliminate the require-
Uthmaniyah Gas Plant engineers made a decision to redesign ment for curing time with an oil-tight enclosure, we had failed
the coupling guards to eliminate the leakage and reduce the out- to address the need for cooling and the problem of sag.
of-service time required for sealant curing. The first step was to A third modification was added that included additional air
inquire about new coupling designs offered by the compressor flow by installing two lV4-inJ air inlets and a single 2-in. drain.
manufacturer. Review of these designs and costs associated with The turbulent flow of air inside the enclosure was critical to
those offered did not meet the expectations of the local design team, performance, which necessitated a smooth transition of the flow
so the decision was made to proceed with an in-house design. angle from the inlets to the drain. Placement of the inlets and

Collapsible

Item Assembly drawing, coupling


Existing compressor side Material Aiuminum steel
Quantity One requiied

The second design used a telescopic stiding fit.

HYDROCARBON PROCESSING FEBRUARY 200


107 129
ROTATING EQUIPMENT/MAINTENANCE

preventing any leakage from theflanges.The additional benefit


of lower temperature was an unexpected surprise.
When the compressor was shut down, we tound that we still
had a leakage problem. With no coupling rotation, no vacuum
was present and the main joint bet\vecn the two halves of the
coupling leaked due to sag. The solution proved to be a simple
design that has been used for many years to seal packing leaks. A
slip flange was Installed on one half of the joint and aflangering
was welded co the larger-diameter side of the joint. One row of
packing was installed and squeezed between the twoflanges.This
design eliminated all problems with leakage due to sag.
Just as putting a man on the moon was an act accomplished
by teams of engineers working with ideas developed and
improved upon by others, the successful design implemented
at the Uthmaniyah Gas Plant was the result of many engineers
building upon others' ideas and successes. HP

K e i t h M . W o r r e l l is the supervisor of reliabilily and techni-


cal support at Saudi Aramco's Uthmaniyah Gas Plant in Saudi
Arabia. He has been involved in maintenance engineering for 32
drain was blended into the structure to accomplish smooth flow years, with the past 15 years concentrated on reliability and condi-
without need for an oil deflector. In fact, the trailing edges of tion-based maintenance. Mr Worrell is a 1974 graduate of North
Carolina State University,
the iniet and drain acted as a deflector. This design (Fig. 3) was
built and installed In the summer of 2005. Performance exceeded
our expectations. Not only did the coupling not leak, but it also A , O. Al K h o w a i t e r is a machinery consulting engineer in the
lowered the overall coupling enclosure temperature by lOO^R We idi Aramco Consulting Services Department in Dhahran. Saudi
•I lUia. He has been involved in rotating equioment engineenng for
discovered that this design was pulling a vacuum while the cou- }8 years. Mr. Al Khowaiter is a 1987 graduate of the King Fahad
pling was rotating causing a drop in temperature and effectively University of Petroleum and Minerals, Dhahran, Saudi Arabia.

HYDROCARBON

o
PROCESSING

HPI Construction
Boxscore
The single most authoritative survey of global construction
projects now presented in separate supplement with
the February, June and October issues of Hydrocarbon
Processing. Increase your presence to this global
construction market at a time that new projects are being
added at the rate of 40 per week by advertising at the
special rate of $5,970 (gross) for a full-page, four-color ad
in one issue or $11,940 (gross) for a full-page, four-color
ad in the next three issues! A full year's coverage at only
$11,940 to a targeted circulation of the buyers/specifiers
of engineering, construction and licensing services in
the global HPI (approximately 16,000). In addition,
each advertiser will receive 25 copies of the HPI
Construction Boxscore supplement for their sales and
marketing purposes.

For more information, contact:


Mark Peters, Publisher
Hydrocarbon Processing
2 Greenway Plaza, Suite 1020, Houston, TX 77046
Tel: +1 (713) 529-4301, Fax: +1 (713) 520-4433
ma rk, pete rs@g uif pub. com

Potrebbero piacerti anche