Sei sulla pagina 1di 6

SIMULATION FOR FACILITY LAYOUT REDESIGN:

Coventry City Council: Reengineering a multi-activity depot layout


Angeliki Karagiannaki Les Oakshott
Athens University of Economics & Business University of Warwick
Dept. of Management Science & Technology Warwick Business School
47A Euelpidon Str., Athens, 11362, Greece Gibbet Hill Road, Coventry, CV4 7AL, UK
Email: akaragianaki@dmst.aueb.gr Email: les.oakshott@wbs.ac.uk

KEYWORDS organisations, though, the first response to any


Simulation, Facility Layout Problem. perceived facilities demands is to employ an
architect or an industrial engineer. However,
ABSTRACT the design skills that these specialties tender
are only one aspect in creating prudent, cost-
This paper presents an application of
effective and long-term facilities restructuring.
simulation modelling within a facility layout
Amidst this convention, organisations need a
reengineering on behalf of a services’
clear strategy that incorporates an explicit
organisation; Coventry City Council (CCC).
facilities reengineering plan.
This organisation was burdened with its
operational activities that take place at its This paper describes an experience
depot. The available parking places were not where the authors used simulation modelling
adequate to meet the fleet’s needs and, in to redesign a depot’s layout after evaluating
addition, were disproportionally dedicated to alternative viable plans and deciding on the
the operational activities. Some parts of the most valuable in terms of efficiency. It
depot were bustle with life whereas others involves work undertaken for Coventry City
were laid idle. Consequently, the poor depot Council (CCC). CCC has a depot based in
design resulted in inefficiencies in terms of Whitley, Coventry. The depot consists of two
heavy congestion at the entry-exit points, at the distinct parking sites, one for operational
resources (fuel station, waste transfersite etc.), vehicles and one for private cars. The depot
Health and Safety issues, lack of control, low has a number of diverse operational activities
space utilisation, high risk of vandalism, and interacting with each other: Street Cleansing;
untidy appearance. Therefore, the major Grounds Maintenance; Waste Services; Special
objective of this project constitutes the Needs Transport; Highways Works; Street
redesign of the depot’s layout after evaluating Lighting; Taxi Licensing. It accommodates
alternative viable plans and deciding on the about 300 operational vehicles that represent
most valuable. To address this facility layout these activities. They arrive at the depot to tip;
problem, simulation modelling was employed. to fuel, to have access to the water supply; to
Testing various risk-free scenarios, managers wash out; to be inspected; and to park.
could study the performance characteristics of
This organisation was burdened with its
the proposed layouts without affecting the real
synchronising operational activities due to
system. The recommended layout involved the
disconnected and scattered storage structures
reallocation of resources, the reorganisation of
and space constraints. The existing network of
the network of roads, the operational vehicles
the logistic activities related to the arrival,
to be parked at dedicated parking places, and
loading, and departure processes of the
explicit operating rules to be followed by the
vehicles in the depot showed no clear,
drivers.
underlying plan. Some parts of the depot were
INTRODUCTION bustle with life whereas others were laid idle.
The available parking places were not adequate
The dynamic character of today’s
to meet the fleet’s needs and, in addition, were
competitive environment forces organisations
disproportionally dedicated to the operational
to an incessant reassessment in an effort to
activities. Consequently, the poor depot design
respond. Their facilities, though, should be
resulted in inefficiencies in terms of heavy
considered as an integral part of this effort.
congestion at the entry-exit points, at the
Hence, organisations must continually
resources (fuel station, waste transfersite etc.),
revaluate their existing facilities to ensure that
Health and Safety issues, inaccessible
they are consistent with both the
resources, lack of control, low space
environment’s demands and the management’s
utilisation, overcrowded aisles, high risk of
strategic requirements. For the majority of
vandalism, and untidy appearance. Moreover, These algorithms are available as layout
the operational vehicles have not got priority software packages.
over the private ones. In fact, the depot can be • Finally, literature provides also some
viewed as a number of finite operational hybrid algorithms that represent a
vehicles arranged on the depot’s parking places combination of approaches. For instance,
and a number of resources (i.e. fuel station, Dunker et al. (2005) presented an algorithm
waste transfersite, water supply, high pressure that combines dynamic programming and
washing, and workshops). The spatial genetic search for solving a facility layout
rearrangement of these facilities (vehicles, problem.
parking places and resources) in an effective
manner is what OR people call the facility Despite their effectiveness, these
layout problem. Thus, although the facility approaches imply difficult-to-use mathematical
layout problem may arise in many contexts and formulations and in addition, require
can be solved by various approaches, in this accurately defined design objectives and
case the authors used simulation modelling to constraints. Approaches based on graphical
evaluate alternative layouts that derived from a representation were developed in order to offer
strategic facility reengineering framework. more comprehensible procedures, the
possibility of adding multidimensional factors
This paper is organised as follows. and not having accurately defined elements.
Section 2 draws upon literature from the topics • Systematic Layout Planning (SLP)
of facility layout problem and simulation represents this category (Muther, 1973).
modelling. Based on the review, a However, this approach focuses on a
methodology was developed in order to render functional way of thinking.
operational for this application (Section 3). • Thus, in order to “get away from the
Section 4 constitutes the main body of the functional mindset and meet today’s
empirical investigation. Section 5 discusses rapidly changing strategic operations
any implications. Finally, Section 6 provides needs”, the Strategic Facility Planning
the conclusions of the entire depot’s (SFP) was built on the earlier approach of
reengineering plan and suggests areas and gaps SLP (Wrennall and Lee, 1994).
for further work.
However, none of the above methods
LITERATURE REVIEW looked at the facility layout problem as a large-
Since the whole body of literature in the scale reengineering project. Thus, integrated
field of facility layout planning is extensive, facilities reengineering approaches were
this review is, therefore, selective. It deals with developed.
literature that provides an overview of different • The most effective one seems to be that of
approaches for solving the facility layout the FacPlan method proposed by Lee
problem and reveals the need to incorporate (1996).
simulation modelling within layout A step forward is that of simulation
reengineering. modelling. While it is certainly not a scientific
The facility layout problem concerns the measure, simulation models can be an
spatial and non-overlapping arrangement of extremely valuable, timely and cost-effective
numerous interrelated activities to achieve means to study the performance characteristics
some objectives. There is no single and user- of a proposed layout. By providing system-
friendly OR methodology that can ensure wide views of the impact of changes to the
provably optimal solution and good run times existing system without physically building,
and incorporate the strategic mindset. amending or interrupting the system,
simulation offers a platform to validate the
In an effort to design and evaluate effectiveness of an altered design (Senko and
alternative layouts, many optimisation Suskind, 1990). There are many contributions
approaches were proposed. focused on simulation modelling in general
• Mathematical modelling demonstrates an (Law and Kelton, 2000; Banks et al., 2001,
optimal solution but only in case of small Robinson, 2004). What is worth mentioning,
or greatly restricted problems (Foulds and though, is that there are several contributions
Robinson, 1978; Montreuil and Ratliff, dedicated solely to the application of
1989; Boswell, 1992). simulation to facility layout design. However,
• Heuristics can usually give a sufficient (but these applications are mainly dedicated to
not optimal) solution quickly in case of manufacturing systems design such as material
large-scale problems (Jaydeep et al., 2003). handling system design, manufacturing cell
design, warehouse or factory layout design
(Law et al., 1993; Heavey and Browne, 1996). Model content
Nevertheless, literature provides only a few Table 1: Model scope
applications to the facility layout problem for
Include/
services’ organisations. An example is that Component Justification
exclude
given by Lo et al. (2002). Running large-scale Flow through the depot
emergency exercises constitute a time- and Aggregation system during the day.
cost- consuming process. Thus, in order to of vehicles of The individual vehicles are
each Include represented by their density
examine the existing layout and assist in operational (meaning the type of
planning the spatial arrangement during activity operational activity) and not
emergency situations, Lo et al. used simulation directly as individual entities
modelling. Flow through the depot
system at the start and end of
METHODOLOGY Operatives Include shift
Depart from and arrive to a
The authors implemented a compound building-base
methodology that can be considered as an All resources need to be
innovative way to structure such a problem as Queues for modeled to give full statistics
Include
each resource on queues and resource
no similar case has been presented in the utilisation
literature: Allocation of
the fleet of
1. a FacPlan method that consists of an in- each Include Experimental factor
depth analysis of all the depot’s elements operational
and the design of alternative layouts (SFP activity
approach). The phases of this approach are Allocation of
Include Experimental factor
each resource
described thoroughly by Karagiannaki
Experimental factor
(2005). Include agent-based
2. simulation modelling in order to evaluate behaviours; meaning the use
the proposed layouts and attain a more Operating
of a set of rules that
efficient allocation of the resources. Include individual drivers follow (e.g.
rules
drivers usually choose the
SIMULATION MODELLING shortest queue, or they will
not join a queue if there are
Two alternative layouts were agreed to more than five vehicles in it)
be evaluated using simulation modelling. Traveling Fixed, based on the speed
Include
times limit in the depot
Conceptual Modelling Scale Include
Design of the layout based on
a 1:500 scale
Modelling objectives Visitors are represented as
Visitors Include
• Determine which proposed layout offers vehicles (not pedestrians)
the most efficient allocation of the The priority is given to the
Priorities
driver inside the island. The
operational vehicles and which operating (islands- Include
priority is given to
rules it must incorporate so that with 95% crosswalks)
pedestrians in the crosswalks
confidence: Inspection
Include
The drivers inspect their
1. the maximum queue size in each facility time vehicles before departing
Only pedestrians can walk
(exit gate, fuel station, waste transfersite, Interrelation through the two parking
weigh bridge, water supply, high pressure between the areas. Moreover, not all the
washing) is less that 6 vehicles two parking
Exclude
operatives park at the private
2. the average queuing time in fuel station, areas area. The exact number of
(operational operatives coming into the
waste transfersite, weigh bridge and exit and private) depot from the private
gate is less than 5 minutes and the average parking is not known
queuing time in water supply and high Processes
Exclude Beyond the purpose at hand
pressure washing is less than 20 minutes outside depot
3. the maximum queuing time in fuel station,
Simplification
waste transfersite, weigh bridge and exit
• Worst case scenario. The number of vehicles
gate is less than 10 minutes for 80% of
of each operational activity was the
vehicles and the maximum queuing time
maximum available. Thus, absence of
in water supply and high pressure washing
operatives -because of illnesses or vacations-
is less than 30 minutes for 80% of vehicles
and in addition, fleet deficiencies -because of
• Determine whether the agreed layout with
vehicles inspected in the workshops- was not
its operating rules allows for a potential
modelled.
10% increase in the fleet of each
• Only model the operational parking area.
operational activity without affecting the
above objectives.
• Fridays and weekends were not modelled due When the operatives park their vehicles, they
to the different shift patterns and the different follow again the pedestrians’ path and return to
number of vehicles that operate these days. the buildings.
Model Coding Verification and Validation
The computer modelling was To illustrate the concept of verification
implemented using the standard version of and validation, several forms of testing had to
SIMUL8 simulation software. The model be employed. However, because of the
layout was designed based on a 1:500 scale complexity of the depot’s system and the time
(Figure 1). Each run of the simulation model available, the authors found it inefficient to use
starts with all the vehicles parked at different some formal techniques for validating the
blocks. The blocks are based on the shift model. Therefore, they were forced to validate
patterns in order to permit the vehicles that are the model through discussion with the
parked in the back rows to depart. Thirty nine managers who have a detailed knowledge of
of these vehicles are grounds maintenance’ the system and feedback sought on whether the
vehicles (yellow vehicles), sixty two are mini model is appropriate.
buses (orange), forty are skips (green) and
FURTHER ANALYSIS
twenty six are street cleansing vehicles (blue).
None of the output statistics (maximum
queue size, average queuing time and
percentage of vehicles within the time limit) in
itself can be considered as sufficient and
necessary to lead to valid results. Each output
serves different purposes and questions. Only
by combining them will they offer an overall
understanding of the system and thus
convincing inference. In addition, it is
imperative not to forget that the simulation
models were based on the worst case scenario.
Figure 1: Print Screen of the depot’s model Therefore, based on the models’ outputs,
although some significant lengthy queues may
Based on shift patterns, the operatives
appear, this is not the case. Their size can not
depart from a building-base, follow the
be considered as strictly precise. However, it
pedestrians’ clear path (red line) in order to
can be concluded that they definitely indicate
reach the vehicles and spend some time in
problematic areas.
order to inspect and prepare the vehicles before
leaving. Then, they leave the depot (the image Regarding the first agreed layout and its
of the parking place changes to an empty first experiment (that incorporates a change in
space). The vehicles follow the network of the operating rules), the outcomes of the
roads inside the depot and deal faithfully with analysis are:
the driving regulations. This signifies that they • It appears that the fuel station and the waste
give priority to the pedestrians before any transfersite satisfy the responses that
crosswalk and the driver inside the island has determine the achievement of the objectives.
priority, as well. Vehicles return to the depot • The water supply and the high pressure
throughout the day to tip, to have access to the washing seem to operate properly as well.
water supply, to fuel and for lunch breaks. The fact that there is a significant maximum
There is no set times to these. Thus, the times queue size for the water supply is based on
used in the simulation model were based on an the worst case scenario effects. Moreover,
attempt to fit proper distributions to the data this occurs due to the rules that determine
gathered. For the fuel station, especially, a when to use this facility; meaning that all the
specific set of rules was introduced in order to sweepers have to use the water supply in the
include the behaviour of the individual drivers morning (before departing from the depot)
and thus, to model the process of fuel as close and after the lunch time. Therefore, it is
to reality as possible (agent-based behaviours). reasonable to observe a lengthy queue.
For example, drivers usually choose the • The outcomes regarding the exit gate indicate
shortest queue, or they will not join a queue if a problematic area. The maximum queue size
there are more than five vehicles in it. Finally, is 13 vehicles. However, the average queuing
the vehicles return to the depot approximately time (1.5 minute) and the percentage within
half hour before the end of shift to tip, fuel (if the time limit (100%) reveal that this lengthy
they did not manage to do so during the day), queue occurs only at peak times; in this case
wash down and complete vehicle checks.
in the morning (between 7:00 and 7:30am). benefits. The tangible outcomes can be
Also, taking into consideration that in the summarised as the decrease of any bottlenecks
current system such a queue size can be and the reduction in the queuing and
observed, the situation is not aggravating in processing times. The intangible ones can be
this proposed layout, but it does not give an considered as the aggregation of each
improvement, as well. operational activity’s vehicles, more control,
• Regarding the weigh bridge, the outputs tidier appearance, health and safety issues.
definitely indicate a bottleneck. However, the
In addition, it should be mentioned that
average queuing time (4.17 minutes) and the
although the above solution reduced the
percentage within the time limit (82.35%)
lengthy queues, some points of congestion still
reveal that this lengthy queue occurs only at
appear but only at peak times. If CCC feels
peak times (between 4:10 and 4:30). Figure 2
that the queues that still occur at peak times are
depicts the time-series of the queue size. In
not satisfactory, the authors identify three
an attempt to solve this bottleneck, the
experimental factors that can assist in giving
authors changed the operating rules
an even more efficient layout: the operating
(experiment 1). Indeed, the outcomes of
rules that the individual drivers follow; the
experiment 1 proved that the queue size has
routes that the vehicles follow inside the depot;
been decreased. Figure 3 depicts the time-
and the shift patterns of each activity. By
series of the queue size for the experiment.
combining these factors, a wide range of
Comparing the two graphs, it is obvious that
alternative solutions emerge.
the new rules resulted in smoothing the peak
time, which leads to the decrease in the Furthermore, considering an experiment
queue size. Of course, while solving the that incorporated a 10% increase in the fleet, it
traffic in the weigh bridge, the remainder should be highlighted that there are space
system was also affected; especially the fuel limitations (break-down point) that may not
station and the waste transfersite as the allow a further increase. In such a case, it is
change in the rules incorporated these recommended that CCC repeat the entire
resources. However, the results are still reengineering project; meaning to redesign and
consistent with the objectives and no other propose new layouts and implement new
problematic areas occur. simulation models. Here, it is worth
mentioning that the outcomes of the existing
simulation project can be used as benchmarks
for evaluating the efficiency of the new
layouts.
CONCLUSIONS
.05

.45
16

16

Figure 2: Time-series of the bridge queue size Regarding the simulation modelling
(Layout 1) implications of this paper, this approach can be
viewed as a powerful facility evaluation tool as
it can be employed within a facility layout
problem and thus, assist in evaluating
alternatives. The major outcomes that the
CCC’s managers may experience, but also any
.15

.55

managers that deal with a facility redesign


16

16

Figure 3: Time-series of the bridge queue size problem can be summarised as follows:
(Layout 1: Experiment 1)
9 The factors that effect the evaluation of
The first alternative layout and its the alternative layouts can be easily
improvement -that the experiment 1 identified. In this instance, these
represents- solved the bottleneck regarding the experimental factors were: the reallocation
weigh bridge. Respectively, the second of the parking places and the resources;
alternative layout and its improvement -that its the operating rules; the routes; and the
experiment represents- solved the bottleneck shift patterns.
regarding the exit gate. Based also on the fact 9 The use of simulation within layouts
there are no significant changes regarding the should be an iteration process and not be
remaining outputs, it can be assumed that the used once and thrown away. Rather, it
two layouts are supplementary. Therefore, it should be retrieved by managers on an
can be concluded that the simulation model occasional basis. Thus, the outcomes of
infers the combination of their experiments as any simulation model can be used as
the most efficient layout. This solution implies benchmarks for evaluating the efficiency
a wide range of tangible and intangible of the new layouts.
9 Simulation can incorporate agent-based Law, A.M. and Kelton, W.D. 2000. Simulation
behaviours, which play a vital role for a Modelling and Analysis, 2nd edition, McGraw-
successful model development; meaning Hill
that it includes individual behaviours. Lee, Q. 1996. Facilities & Workplace Design: An
Illustrated Guide. 1st ed. Norcross Georgia:
The literature review revealed that there Engineering & Management Press, Institute of
is no single and widely accepted technique to Industrial Engineers
provide optimal solution to a facility layout Lo, S. M., Fang, Z., Zhi, G.S. and Yuen, K. K.
2002. “A computer simulation model of
problem. Thus, the authors suggest the
emergency egress for space planners.”
combination of different approaches and Facilities, No. 20(7/8), 262-271
techniques. In this case, they implemented a Montreuil, B. and Ratliff, D. H. 1989. “Utilising Cut
compound methodology (FacPlan method and Trees as Design Skeletons for Facility Layout.”
the SFP framework it incorporates with IIE Transactions, No. 21(2), 136-143
simulation modelling) that can be considered Muther, R. 1973. Systematic Layout Planning, 2nd
as an innovative way to structure such a ed. Boston: Cahners Books
problem. Therefore, concerning any further Robinson, S. 2004. Simulation: The Practice of
work that can be employed, this paper can be Model Development and Use, Wiley
Senko, J. M. and Suskind, P. B. 1990. “Proper
seen as the launch for further examination of
Planning and Simulation Play a Major Role in
the use of simulation modelling with facility Proper warehouse Design.” Industrial
layout problems. Moreover, in order to capture Engineering, No. 22(6), 34-37
the financial aspect of the proposed layouts, a Wrennall, W. and Lee, Q. 1994. Handbook of
financial analysis could be integrated with the Commercial and Industrial Facilities
alternatives. Thus, after performing the Management. McGraw Hill
different simulation experiments, financial
AUTHOR BIOGRAPHIES
analysis could provide a significant tool to
poise the various benefits that each alternative ANGELIKI KARAGIANNAKI was born in
promises. Kozani, Greece. She holds a BSc in
Management Science and Technology from
REFERENCES
the Athens University of Economics and
Banks, J., Carson, J.S. Nelson, B.L. and Nicol, D.M. Business and an MSc in Management Science
2001. Discrete-Event System Simulation, 3rd and Operational Research from the Warwick
edition, Upper Saddle River, Prentice Hall Business School. She is currently a PhD
Boswell, S. G. 1992. “TESSA-A New Greedy student and research officer in the SCORE
Algorithm for Facilities Layout Planning.”
International Journal of Production Research,
group of the ELTRUN Research Center at
No. 30(8), 1957-1968 Athens University of Economics and Business.
Dunker, T., Radons, G. and Wesrkamper, E. 2005. Her research interests include supply chain
“Combining evolutionary computation and management, simulation and RFID technology
dynamic programming for solving a dynamic deployment. Her email address is
facility layout.” European Journal of akaragianaki@dmst.aueb.gr and her
Operational Research, No. 165(1), 55 web page can be found at
Foulds, L. R. and Robinson, D. F. 1978. “Graph http://score.eltrun.gr/groups/g_score-
Theoretic Heuristics for the Plant Layout members.html
Problem.” International Journal of Production
Research, No. 16(1), 27-37 LES OAKSHOTT was born in London,
Heavey, C. and Browne, J. 1996. “Model England and went to the University of Hull
management systems approach to where he studied Physics as a first degree and
manufacturing systems design.” International Operational Research at masters level. He then
Journal of Flexible Management Systems, No.
8(2), 103-130
worked as an OR analyst in various
Jaydeep, B. Chung-Hung, C. and Kam-Fai, W. organisations including British Rail before
2003. “FACOP: A user friendly FACility layout moving into academia. He is now a Senior
OPTimisation system.” Computers & Teaching Fellow at Warwick Business School
Operations Research, No. 30(11), 1625 where he is responsible for obtaining external
Karagiannaki, A. 2005. Simulation for Facility projects for the MSc in Management Science
Layout Redesign: Coventry City Council: and Operational Research. He is the author of
Reengineering a multi-activity depot layout, several text books including “Business
MSc Thesis, Warwick Business School, Modelling and Simulation” (1997). His email
University of Warwick
Law, A.M., Garson, J.S., Musselman, K.J. and Fox,
address is les.oakshott@wbs.ac.uk and
J.G. 1993. “Forum on crucial issues in the his web page can be found at
simulation of manufacturing systems.” http://www.wbs.ac.uk/faculty/members/les/oak
Proceedings of the Winter Simulation Conf., shott
916-922

Potrebbero piacerti anche