Georgy Borisov
Associate, Head of Real Estate
Practice, Moscow
Baker Botts LLP
.......................
FIDIC Contracts
What is FIDIC? FIDIC based construction contracts are becoming increasingly popular in
Given the vast number of various forms of con-
tracts in the construction industry worldwide, the Russian construction industry. This article attempts to clarify what FIDIC
the community has always struggled to create
certain uniform sets of documentation that standard forms are, the principles upon which the forms are based, the structure
would simplify the bidding process, be more
“user friendly”, and could be repetitively used
of the standard forms and the ways in which each standard form differs from the
for different types of construction projects. other standard forms.
FIDIC is one of many professional associations
that has been trying to achieve these goals in duration, and for projects with no need for spe- STRAIGHTFORWARD PROJECT/ Conditions of
the last several decades. cialists (sub-contractor) or an Engineer as all НЕСЛОЖНЫЙ ПРОЕКТ Contract for
нет/no
FIDIC is the Federation Internationale des the design is done by the Contractor. EMPLOYER DESIGN/ да/yes Construction /
да/yes ПРОЕКТ ЗАКАЗЧИКА Условия договора
Ingenieurs-Counseils (International Federation Construction Form of Contract (or Red строительного
of Consulting Engineers), established in 1913 Book) is used where the design is done by Fixed price – lump sum нет/no подряда
by a group of French and Swiss engineers, with (or on behalf of) the Employer; the project Short Form Little employer involvement
its headquarters in Geneva, Switzerland. It is an may require the Contractor to supply plant of Contract / No major unforeseen risks/
Фиксированная цена – CONTRACTOR DESIGN/
Сокращенный ПРОЕКТ ПОДРЯДЧИКА
internationally recognized organization repre- design and/or execute some design, and the единовременная выплата.
контракт Plant and/or high unforeseen risks/
senting over 1 million professionals in 75 coun- project is administered by an Engineer hired Минимальная вовлеченность
tries. In the past couple of years, we have expe- by the Employer. заказчика. Отсутствие существенных Производственные и/или высокие
непредвидимых рисков непредвидимые риски
rienced significant growth in interest from our In the Plant and Design-Build Contract no
clients, Russian and international developers, (Yellow Book) the Contractor is responsible да/yes
нет/no да/yes
project sponsors and construction contractors, for Plant, Building and Engineering Works, DISCUSS IN DETAIL/
in using FIDIC standard forms for construction though the Employer may have executed ПОДРОБНОЕ ОБСУЖДЕНИЕ EPC Turn-Key
Employer’s requirements with the Plant and
projects in Russia. We see the reason for that in some design. Projects / Design-Build /
Contractor, and negotiate a modified Проектирование,
acknowledgement by the industry that FIDIC EPC Turn-Key form of contract (Silver FIDIC contract/ материально- Производственное
forms are clear and coherent, all clauses are Book) provides for engineering, procurement Обязательства заказчика перед техническое проектирование/
подрядчиком и заключение обслуживание строительство
essential, the definitions are detailed and the and construction by the Contractor who is to договора FIDIC в новой редакции и строительство
structure of every standard contract is consis- deliver a fully equipped facility to the Employer «под ключ»
tent with the other FIDIC standard contracts. with tests on completion. The design is per-
More important, in our view, is that FIDIC formed by the Contractor in accordance with payment can start only after certified inter- FIDIC suggests that the Letter of Tender and
forms are fair and equitable – risk is allocated the Employer’s requirement. im payments exceed 30% of the Accepted Letter of Acceptance, documents that are part
to the party which is best able to control, bear All these different forms, in essence, are Contract Amount and the advance pay- of the tender documentation, are made a part
and deal with such risk. Every FIDIC standard about risk allocation between two parties ment must be repaid before 80% of such of the contract.
form is complete and flexible – the standard (Employer and Contractor), and are based on Accepted Contract Amount is certified. A special feature of any FIDIC contract
forms cover most needs and are readily adapt- one fundamental issue – who is responsible for In other words, the Employer (and the is that its terms and conditions consist
able to fit any requirement of the parties to it. the design of the project. The issue is not who lender) is better protected under the MDB of both General Conditions and Particular
And last, but not least, FIDIC standard forms are is doing design, but who is responsible for it. Harmonized Edition as compared to the Conditions. The General Conditions are a
recognized by the industry – they have been regular form of the Red Book. standard combination of contract provisions,
tested for an extensive period of time in many Risks and Price while the Particular Conditions are the result
jurisdictions all over the world. As you can see from the above diagram, the Composition of the Contract of negotiation between the parties and are
formula is simple – the contract price is direct- The FIDIC contract, being a full agreement designed to modify or delete some of the
The FIDIC “Rainbow” ly dependent on the risks (mostly, foreseen) between the Employer and the Contractor for a General Conditions.
There are several types of FIDIC contracts (or taken by the Contractor, with the Red Book given project, is a compilation of several com- FIDIC’s tender process suggests that
books), most bearing a dedicated color to on the lower end of the risk spectrum for the ponents, which, taken together, form the con- the Employer include the chosen standard
allow for easier identification and operation Contractor for the lesser consideration, and the tractual arrangement of the parties. A FIDIC FIDIC contract and the proposed Particular
of each form: Silver Book requiring the Contractor to accept contract consists of: Conditions in the tender documentation
Short Form of Contract (Green Book), all the project’s risks. Contract Agreement package with or without the possibility
Construction (Red Book), Letter of Tender for the Contractor to negotiate the terms
Plant and Design-Build (Yellow Book), MDB Harmonized Edition of Red Book Letter of Acceptance of the Particular Conditions, depending on
EPC Turn-Key Projects (Silver Book), FIDIC has been successful in introduc- Conditions of Contract the terms of the tender. In either event, it
Employer-Consultant form of contract ing its standards to international lenders. Specification is the Particular Conditions which reflect
(White Book), A group of international banks (MDBs, or Drawings the specificity of the project on the con-
Dredging and Reclamation Work (no color) multilateral development banks) led by Schedules tractual level. Accordingly, contractors
and Tendering Procedure (Blue Book). The World Bank and which also includes Dispute Adjudication Agreement should exercise maximum care when
Below we will briefly speak about the first the EBRD, Nordic Bank of Development, As utilization of a FIDIC form is very often reviewing and negotiating the Particular
four forms, i.e. Green, Red, Yellow and Silver Inter-American Development Bank, Black the result of a FIDIC based tender process, Conditions.
Books, as these are of most relevance to a gen- Sea Trade and Development Bank, Asian
eral construction project. Development Bank, African Development
In addition to the logic shown in the diagram Bank and Islamic Bank for Development),
shown here, the factors influencing the choice have made the special edition of the FIDIC Silver Book /
of form of the contract are: Value/Complexity; Red Book a part of their standard bidding Серебряная
Yellow книга
Design Responsibility; Need for Variations; Risk document. In other words, international Book /
Рынок/ Red Book /
Allocation; Work Type; Payment; Administration; lenders prefer (and sometimes insist) that Желтая
market Красная
книга
Risk / Риск
and Involvement of the Engineer. the construction projects they finance uti- Книга
lize the Red Book Harmonized Edition.
What are the basic differences? The special features of this edition of
Short Form Contract (Green Book) is used for the Red Book are: an Engineer has less
simple or repetitive work or for works of short authority; and deduction of the advance Price / Цена
119