Logical Framework Guide

Similar terms used


Goal Overall objective, Development objective, Long-term objective
Project purpose Short-term objective, Specific objective
Outputs Results, Immediate objectives, Intermediate results
Activities Actions
Assumptions Risks, Development hypothesis
Objectively verifiable indicators Targets, performance indicators, variables
Means of verification Sources of verification, Means of assessment, Sources of information

Narrative Summary Verifiable Indicators Means of Verification Important Assumptions


What are the quantitative ways
What sources of (Goal to Supergoal):
of measuring, or qualitative
information exists, or can What external factors are
Goal: ways of judging, whether these
be provided cost- necessary for sustaining
broad objectives are being
effectively? objectives in the long run?
achieved? (estimated time)
What are the quantitative What sources of (Purpose to Goal):
measures or qualitative information exists or can be What conditions external to the
evidence by which provided cost-effectively? project are necessary if
Purpose:
achievement and distribution Does provision for achievements of the project’s
of impacts and benefits can be collection need to be made purpose is to contribute to
judged (estimated time) under inputs-outputs? reaching the project goal?
Outputs: (Output of Purpose):
Indicate each of the What are the factors not within
What kind and quantity of
outputs that are to the control of the project which,
outputs, and by when will they What sources of
be produced by the if not present, are liable to
be produced? (quantity, information?
project in order to restrict progress from outputs to
quality, time)
achieve project achievements of project
purpose purpose?
(Activity to Output):
Recommended VI’s are 1) What external factors must be
Activities:
included against all activities. there to obtain planned outputs
Indicate each of the
This is essential for projects What are sources of on schedule?
activities that must
reporting and monitoring information? 2) What kind of decisions or
be done in order to
against the Logical actions outside the control of the
get the outputs.
Framework. project are necessary to start the
project?

‘Logic of the Framework’


Objective tree to Logical Framework