Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
It is contended that the scale of some in-house software projects (and the
potential impact of project failure on an organization’s operating capa-
bilities and reputation) is such that the progress of those projects warrants
the concentrated attention of senior managers (and possibly, the Board).
The article utilizes a case study to illustrate how the adoption of key
proposals outlined in the business information systems and software
engineering literatures for the management of these projects may not
necessarily be effective. This work augments Walker and Oliver (2005),
which examined the options when accounting for software expenditure
and recommended expensing for consistent treatment. This article then
reviews the ‘information needs’ of senior managers, and presents a set of
six reporting templates to facilitate the effective monitoring of progress
of software projects (including post-migration expenditure on system
enhancements and maintenance, and efforts to capture planned benefits).
In some circumstances, the scale and risks associated with software develop-
ment projects warrant oversight of these projects by the Board, possibly
through the establishment of specialist ‘IT governance’ subcommittees.
Accordingly, a model charter for an IT governance committee is presented
in an appendix.
Key words: IT corporate governance; Management reporting; Model charter;
Reporting templates; Software development.
43
© 2006 Accounting Foundation, The University of Sydney
ABACUS
44
© 2006 Accounting Foundation, The University of Sydney
SOFTWARE DEVELOPMENT REPORTING TO MANAGERS
Table 1
Align project to The strategic plan should clearly McFarlan et al. (1983);
the organization’s define business strategic priorities Boynton et al. (1992);
strategy The information systems strategy Galliers (1995);
should plan for future changes in Henderson et al., (1996);
information systems and technology Moskowitz and Kern (2003)
Comprehensive assessment of potential
solutions is undertaken to avoid
overlooking viable alternatives
Predetermine the A business case is prepared to Seward (1975); Buss (1983);
criteria for support the initiative/project using Berger (1988); Sassone (1988);
assessment tangible and intangible benefits Boehm (1989); Ould (1990);
including formal cost-benefit analyses Hochstrasser and Griffith (1991);
Financial methods (e.g., pay-back Mirani and Leederer (1993);
period choice of discount rates/internal Hares and Royle (1994);
rate of return; sensitivity analysis) are Hogbin and Thomas (1994);
stipulated with agreed thresholds and Barua et al. (1995); Neuman (1995);
calculation criteria Ballantine et al. (1996);
Risks are assessed and unacceptable Braithwaite (1996);
risks are mitigated Whiting et al., (1996);
Ballantine and Stray (1998);
Yetton (1997); Fitzgerald (1998);
Remenyi (1999); Devaraj
and Kohli (2002);
Li and Johnson (2002)
Apply multiple A feasibility study is used to establish Brooks (1975); Lay (1985);
controls over viability of the preferred solution Youll (1990);
expenditure and A testing regime is established to Coleman and Jamieson (1991);
product quality discover defects Farbey et al. (1992);
Commissioning is regimented to ensure Willcocks and Lester (1993a, 1993b);
systematic preparation Rowsell-Jones (1995);
Remenyi et al. (2000);
Seddon et al. (2001)
Management A systematic review occurs for all Turner (1980); Capper (1988);
reviews are subsequent proposals (variations) for Lincoln (1988);
conducted to changes to the scope of projects, and Abdel-Hamid and Madnick (1990);
improve project changes in projected costs and planned Kumar (1990);
outcomes delivery dates Lincoln and Shorrock (1990);
Project records are selectively included Farbey et al. (1993);
in the internal audit program Mirani and Lederer (1993);
Project documentation is subject to Norris (1996); Peters (1996);
verification Ward et al. (1996); Murphy (2002)
A post-implementation assessment
is conducted of all major projects
45
© 2006 Accounting Foundation, The University of Sydney
ABACUS
Devaraj and Kohli, 2002). The Board can be informed about these matters in a
variety of ways: formal reports, presentations from vendors or IT staff, and feed-
back from key stakeholders. In the business information systems literature, con-
tributions that have considered formal reporting arrangements have primarily
focused on reports dealing with efficiency of effort (see, e.g., Hochstrasser and
Griffith, 1991; Hogbin and Thomas, 1994; Gardner, 2000; ISACA, 2000) rather
than whether the investment of resources is in accordance with prior budgetary
allocations, or likely to secure promised benefits or (more generally) be effective
in meeting strategic objectives.
The following hypothetical case study describes a software development project
undertaken by an organization that had adopted many of the ‘best practices’ sum-
marized above. It is a composite based on the authors’ observations of major IT
projects in around a dozen different organizations (though, following the approach
of Drucker, 1974, the facts are disguised to avoid identification of the firms
involved). The case describes a software development project that experienced
major difficulties, but which after considerable effort (and expense) may well have
been regarded as technically successful. The case study concerns the acquisition
and development of software. It features a hybrid approach (‘buy best of breed’ and
‘build as bespoke’), reflecting the common contemporary practice of enhancing
off-the-shelf packages (Meyers and Oberndorf, 2001). The case study draws on
that reported in a previous work dealing with the accounting treatment of soft-
ware development expenditure (Walker and Oliver, 2005, esp. pp. 72–3), but has
been amplified to place greater emphasis on the steps taken to ‘manage’ that
expenditure, to ensure oversight of software development activities and assessments
of risk in this area, and to highlight the information provided to senior managers
and the Board during the course of the project. The additional case material provided
here is shown in italics.
46
© 2006 Accounting Foundation, The University of Sydney
SOFTWARE DEVELOPMENT REPORTING TO MANAGERS
47
© 2006 Accounting Foundation, The University of Sydney
ABACUS
work requests for modifications of the existing software had led to excessive
staffing in this area, mainly through the employment of casual systems analysts
and programmers. The initial feasibility study suggested that the new software
could enable a reduction in staff numbers of around eighty-five (including seventy
contractors to the IT Department).
The project formally commenced in January 2001 under direction of a Software
Development Manager with financial sector experience hired on a twelve-month
contract. The Steering Committee recognized that its in-house capabilities to modify
an off-the-shelf package were limited. It was deemed desirable to have day-to-day
responsibility for the project assumed by a manager with experience in the industry
and familiarity with stakeholder expectations.
Software functionality modifications to meet the needs of the firm’s clients were
completed during 2001, in accordance with the project schedule, at a cost of $8.3
million. The involvement by the Software Development Manager of in-house ‘users’
in acceptance testing identified a range of programming defects associated with
computations and the user interface. Despite schedule pressures, these defects
were rectified prior to the software being put into production.
Data conversion was completed at the cost of $100,000. This comprised check-
ing of transactions and balances in the old system and uploading checked balances
into the new system. A number of urgent enhancements were authorized when it
was recognized that the new system required full transaction detail from legacy
systems to allow correct computations. This led to additional, unbudgeted costs,
including testing, of $600,000. Although minor problems were identified as fixes
requiring action, none were ‘day 1’ problems. Despite the additional work, the new
system was commissioned as scheduled on 2 January 2002, and the project was
then under budget by $1 million.
Such was the extent of the modifications to the licensed software that $100,000
was paid to a specialist technical documentation contractor to prepare on-line
manuals for operators. This was unbudgeted.
After the first end-of-month run (January 2002), ‘day 2’ problems emerged. As
a consequence, the project committee agreed that two transaction-specific modules
were to be rewritten and re-tested. When eventually put into production on 30 May,
the additional work had cost $1.5 million. In addition, both modules required new
computation and reporting subsystems as well as additional (and expensive) out-
put testing of the entire system at an additional cost of $750,000. Some records
which were in error remained quarantined because the new programs failed to
process them correctly. Additional programming costing $500,000 was required to
handle the exceptional conditions required by the quarantined accounts. These
additional expenditures were authorized by the IT Manager either as within delegations,
as acceptable spending of the remaining surplus from the original budget, or a com-
bination of both. Although this work was completed by the reporting deadline of
30 June, account balances were unable to be reconciled by finance staff. At nights
and weekends during July, checks were made of all records to ensure accuracy
(cost $50,000) and each of the modules for valid computations (cost $50,000). This
confirmed further computation errors were still present in the rewritten modules
48
© 2006 Accounting Foundation, The University of Sydney
SOFTWARE DEVELOPMENT REPORTING TO MANAGERS
but also revealed that some incorrect record details had been transferred unchecked
to the new system.
Advice to the Board from the Steering Committee emphasized the project was
within budget; however, business units outside IT had incurred unbudgeted costs.
The value of the current approach was reiterated in the context of the IT Strategy
and the feasibility study. A memo from the Software Development Manager in sup-
port of the project warned that ‘disruption or delay would jeopardize the likelihood
of substantially reducing the number of contractors engaged on software develop-
ment’. On 30 June 2002 Board approval was given for Finserv to enter into a fixed
price contract for $4 million over two years to resolve outstanding enhancement
requests.
Subsequently, Finance staff calculated that $500,000 in staff time had been spent
in reconciling account balances. They estimated an additional $500,000 using
casuals would be spent in correcting errors now incorporated in individual record
balances that had been quarantined.
In March 2003 the firm’s major clients required additional modifications to the
software to accommodate changes in legislation and to offer a wider range of
choices to the client’s customers. These modifications would necessitate total
rewriting of one module of the software, at a cost of $1 million. At the same time,
the software vendor indicated that it had commenced work on its new generation
financial services suite that it expected would be released in around eighteen
months, and gave notice that the existing software package would no longer be
supported after two years.
In 2004, two years after migration, the mandatory post-implementation review of
the new system was conducted. It was found that IT staff and contractor numbers had
only reduced by fifteen (many fewer than the seventy forecast). This was primarily
because, on advice from the Software Development Manager, the Project Steering
Committee had agreed to extend the contracts of fifty consultants to complete addi-
tional development. This included a backlog of approximately one hundred change
requests, all sought by operational staff to improve the efficiency of their activities.
Additionally, there were ten small projects intended to eliminate the need for manual
work-arounds and tasks to handle exceptional circumstances. Further, there were
six separate small projects aimed at enhancing Finserv’s internet capability and sys-
tem security. The scale of all of these additional projects was below the threshold
for referral to the Board since each had an estimated average duration of four days
(twenty-three developer-months). In the Finance Department, account balances
were being reconciled monthly and any errors identified in clients’ accounts were
being corrected within thirty days. Clients reported that, despite initial teething
problems, they were now very satisfied with the new system.
INTERPRETATION
49
© 2006 Accounting Foundation, The University of Sydney
ABACUS
1. Support decisions to approve the staged advance of the project from feasibility
assessment, development, migration, implementation, termination and post-
implementation (Seward, 1975; Lay, 1985; Coleman and Jameison, 1991; Farbey
et al., 1992; Whitten, 2000);
2. Provide assurance that the project is within acceptable bounds of budget, quality
and schedule (Balachandra and Raelin, 1980; Turner, 1980; Pinto and Slevin,
1987; Archibald, 1992; Buttrick, 2000); and
3. Support subjective assessments of benefits realization (Mirani and Lederer, 1993;
Norris, 1996; Peters, 1996; Ward et al., 1996; Devaraj and Kohli, 2002; Murphy, 2002).
The case study illustrates several types of information or reports that senior
managers and the Board could have utilized to avoid ‘surprises’ and, possibly,
take actions that would have lowered costs or achieved a better return on the
investment in new software. Shortcomings in reporting were intertwined with
shortcomings in the governance arrangements operating within the organization.
50
© 2006 Accounting Foundation, The University of Sydney
SOFTWARE DEVELOPMENT REPORTING TO MANAGERS
budgeted costs in past periods, then senior managers and the Board would have
become aware of delays in the project and the considerable resources (both within
the IT Department and elsewhere in the organization) that were being expended.
The reporting of estimates of progress to be achieved in the next period would
provide the basis for closer scrutiny and, possibly, remedial actions being under-
taken in a timely fashion.
Some administrative arrangements were unintentionally dysfunctional. The
Board had ensured that a Steering Committee was to oversee the project, approve
the budget and staffing, and review planned delivery dates and all proposed
changes to the scope of projects. It had endorsed the IT Manager’s recommenda-
tion that programmers and business analysts be engaged on short-term contracts,
with the intention of realizing benefits quickly through reductions in staff num-
bers. In fact, this arrangement may have created incentives for staff to delay the
completion of tasks so that their contracts were renewed—thus adding to overall
costs. Whatever the source of cost-overruns, the committee was not required to
report its actions to the Board, so that the extent of the cost-overruns was not
immediately appreciated. The post-implementation recommendation to obtain
further consulting assistance for implementation is likely to reduce the level of
reporting without necessarily addressing the root causes of the problems.
51
© 2006 Accounting Foundation, The University of Sydney
ABACUS
6
Unexpected increases in product prices, labour costs and currency fluctuations may lead to expenditure
in excess of budget. An alternative to incorporating a budget allowance for contingencies is to allow
variances in expenditure on specified line items (e.g., + 10 per cent) before requiring further approval.
52
© 2006 Accounting Foundation, The University of Sydney
SOFTWARE DEVELOPMENT REPORTING TO MANAGERS
Overall Assessment
The case illustrates how it is not sufficient to have proactive senior managers and
Board setting policies covering the criteria for approval of capital projects and their
administration, to ensure that an organization will systematically assess the organiza-
tional implications of project proposals before undertaking financial commitments.
While Finserv’s senior managers and the Board had utilized a host of traditional
tools (such as cost-benefit analysis, budgets and feasibility studies) and standard
approaches (such as formal delegations of responsibilities), it had done so without
utilizing them appropriately, and without fully integrating management of the project
with the overall governance arrangements operating within the organization. The
Board was left uninformed about critical decisions which led to cost escalations, and
was not in a position to monitor adequately a project that was consuming significant
resources. While technically the project might eventually have been a success, delays
and cost-overruns meant that projected net benefits were less than originally forecast.
It is granted that some of the shortcomings in reporting and governance
arrangements generally illustrated here are not peculiar to software development
projects, and could equally occur in other industries. Yet the prevalence of ‘failed’
or disappointing projects7 suggests that there is a case for routine upstream reporting
to senior managers and the Board about a range of aspects of non-routine
expenditure on information systems.
7
For statistics from a number of surveys see http://www.it-cortex.com/Stat_Failure_Rate.htm.
53
© 2006 Accounting Foundation, The University of Sydney
ABACUS
1. A financial report (Table 2a) showing costs to date, projected total costs and
projected total benefits. The financial report should be centred on a Work
Breakdown Structure. Since the Work Breakdown Structure is completed as
part of project planning, effort spent on unlisted tasks will require explanation.
There is clear evidence that projects that are ‘managed’ without this detail are
likely to fail (Charette, 1989; Chapman and Ward, 1997; Devaux, 1999).
2. A non-financial measures of progress report (Table 2b), presenting a selection of
key indicators for tracking progress of software development projects. With
regard to change requests, senior managers would expect prompt finalization.
Some requests and rejections may be contentious and these would be registered
in the ‘conflict’ section. Consistent with Kaplan and Norton (1996), the report
contains lead indicators of project completion so it is forward looking.
54
© 2006 Accounting Foundation, The University of Sydney
TABLE 2
Note 1: Reporting detail will be provided by project and within project by defined module or requirement.
Note 1: Reports should include a short explanation and description of proposed remedial action.
Baseline schedule Latest authorized adjusted Initial projected Latest revised projected Actual
© 2006 Accounting Foundation, The University of Sydney
TABLE 2
(continued)
Risk Risk Key Key Project Risk element Risk response Key Recommendation
ref description business business deliverable decision
date event User Useability Accept Mitigate Transfer Avoid date
acceptance
ABACUS
(f) Benefits realization schedule
56
proposed to next
Implementation
implementation
Date benefit is
period budget
to start being
Adjustment
responsible
Method of
Feasibility
obtaining
Variance
Manager
Forecast
estimate
estimate
estimate
variance
realized
Type of
Reason
savings
benefit
benefit
Initial
Post
for
Note 1 Note 2 Note 3 Note 4 Note 5 Note 6 Note 7
Notes: 1. Possible categories include: revenue gain; savings achieved or outgoings avoided; appreciation of asset.
2. E.g., reduction in staff positions; reduction in overtime; reduction in casual/temporary assistance; procurement efficiencies; one-off revenue increase;
bring forward receipt of revenue; increases in recurrent revenue; one-off cost savings; postpone outgoings; reduced recurrent costs.
3. Estimate from business unit provided as part of business case.
4. Estimate from feasibility study.
5. Estimate prior to implementation.
6. Actual identified during post-implementation review.
7. Difference between post-implementation assessment and initial estimate.
SOFTWARE DEVELOPMENT REPORTING TO MANAGERS
3. A milestone report (Table 2c) showing baseline, adjusted and estimated com-
pletion dates (with actual completion date to be noted for later reference). The
milestone report records each authorized adjustment to the proposed comple-
tion date, so the impact of these decisions can be distinguished from lack of
progress. In addition the milestone report requires an initial projection which
is then regularly updated to provide senior managers with information that
indicates the likelihood of the project running over time.
4. An unfavourable events report (Table 2d) should be articulated with the routine
milestone report, to explain poor progress. Where the unfavourable events
report lists problems overlooked in prior reports on non-financial measures
and estimates of milestones, senior managers are then in a position to question
the assumptions relied upon in the former.
5. A risk report (Table 2e) aims to present senior managers with an evaluation of
risks, proposed responses, and deadlines for determining the choice of a course
of action (recognizing that there is a range of acceptable risk responses [Standards
Australia, 2004]). Risk is an unavoidable aspect of information technology. At
the outset the risks considered include the opportunity cost of not proceeding
and the relative merits of different options under consideration. Once a project
is authorized, risks are associated with the continued availability of IT skills,
availability of suitable human resources, and the schedule. Where a past risk
report overlooked unfavourable events, senior managers may wish to consider
the way it was prepared and hold staff accountable.
6. A benefits realization schedule (Table 2f) identifies who is responsible for the
realization of benefits (generally, managers of business units). Project delays
and cost overruns may affect the quantum of benefits available. This form of
report may influence both the point at which benefits begin to be captured and
the effort dedicated to their realization.
Use of these six reporting formats should provide senior managers and the
Board with early warning signals about difficulties in software projects. Senior
managers may then be in a position to initiate corrective actions.
Introducing additional reporting formats runs the risk of imposing costly and
burdensome tasks to staff responsible for software development projects. However,
if the reporting formats were agreed and established from the outset of projects
as the critical senior management deliverables, the cost of maintaining records
and providing up-to-date reports would be minimal since they would be part of
the formal reporting regime. Consequently senior managers and Boards could
reasonably expect these reports to be available ‘on call’.
57
© 2006 Accounting Foundation, The University of Sydney
ABACUS
involvement is appropriate when projects are initially proposed is not contentious. But
the literature has not emphasized continuing involvement.
Continuous reporting is warranted, if for no other reason than to establish a
discipline on business units and IT departments. While judgments about the need
for Board involvement will depend upon the circumstances of individual firms
and the industries within which they operate, the case for Board involvement seems
particularly compelling if any of the following are present:
• a history of cost overruns and project failure in the business unit or the com-
pany as a whole;
• the authorized or proposed expenditure is material;
• the software is highly complex;
• deficiencies in the software under development will have adverse effects on the
firm’s trading capabilities or reputation.
For some organizations, the issues may warrant concentrated Board attention
through the establishment of an IT Governance Committee—a practice that appears
common in many public sector organizations, and has recently been advocated by
a range of groups, commentators and professional advisers8 (though often without
a detailed analysis of the charter of such a committee). In this connection, it has been
suggested that a Board dominated by directors who regard information systems
and technology as a support tool will be inclined to relegate their supervisory role
to middle managers, thus missing opportunities seized by their competitors (Carr,
2003). An Appendix to this article provides a suggested ‘charter’ which (following
Walker, 2004, in respect of Audit Committees) is structured so as to distinguish
objectives, membership, responsibilities, authorities and procedures.
A theme of this article is that improved outcomes may be achievable if an
organization establishes monitoring arrangements and accountability mechanisms
extending upstream to senior managers and the Board. The Board, for its part, has
a responsibility to ensure that governance arrangements are established to safeguard
a firm’s resources. It is contended that the scale of many software development projects
is so significant that governance arrangements should extend to ensure systematic
upstream reporting on both financial and non-financial factors regarding the initial
plans, budgets and subsequent progress of software development projects. Examples
of such large projects would include integration of existing applications, application
migrations as part of infrastructure revitalization, substantial application enhance-
ment of existing capability or delivery, and outright core application replacement.
references
Abdel-Hamid, T. K., and S. E. Madnick, ‘The Elusive Silver Lining: How We Fail to Learn From Soft-
ware Development Failures’, Sloan Management Review, Fall 1990.
8
See, for example, IT Governance Institute, 2003; Hoffman, 2004, provides a summary of opinion and
of recent surveys of the use of IT governance committees. One of these surveys noted that of 200
CFOs and IT executives surveyed in North America and Europe, less than 20 per cent of respond-
ents had set up corporate or IT governance committees with formal membership and charters.
58
© 2006 Accounting Foundation, The University of Sydney
SOFTWARE DEVELOPMENT REPORTING TO MANAGERS
Archibald, R. D., Managing High-Technology Programs and Projects, 2nd ed., John Wiley, 1992.
ASX Corporate Governance Council, Principles of Good Corporate Governance and Best Practice
Recommendations, March 2003.
Balachandra, R., and J. A. Raelin, ‘How to Decide When to Abandon a Project’, Research-Technology
Management, Vol. 23, No. 4, 1980.
Ballantine, J. A., R. D. Galliers and S. J. Stray, ‘Information Systems/Technology Evaluation Prac-
tices: Evidence from U.K. Organisations’, Journal of Information Technology, Vol. 11, No. 2,
1996.
Ballantine, J., and S. Stray, ‘Financial Appraisal and the IS/IT Investment Decision Making Process’,
Journal of Information Technology, Vol. 13, No. 1, 1998.
Barua, A., C. H. Kriebel and T. Mukhopadhayay, ‘Information Technology and Business Value: An
Empirical Investigation’, Information Systems Research, Vol. 6, No. 1, 1995.
Berger, P., ‘Selecting Enterprise-Level Measures of IT Value’, in P. Berger, J. G. Kobielus and D. E.
Sutherland (eds), Measuring Business Value of Information Technologies: Useful, Innovative
Approaches for Management, International Centre for Information Technologies, ICIT Press,
1988.
Boehm, B., Tutorial: Software Risk Management, IEEE, 1989.
Boynton, A. C., G. C. Jacobs and R. W. Zmud, ‘Whose Responsibility is IT Management?’ Sloan
Management Review, Vol. 33, No. 4, 1992.
Braithwaite, T., The Power of IT: Maximising Your Technology Investments, ASQC Quality Press,
1996.
Brooks, F., The Mythical Man-Month: Essays on Software Engineering, Addison-Wesley, 1975.
Buss, M. D. J., ‘How to Rank Computer Projects’, Harvard Business Review, Vol. 61, No. 1, 1983.
Buttrick, R., The Project Workout: A Toolkit for Reaping the Rewards From all Your Business
Projects, 2nd ed., Financial Times/Prentice-Hall, 2000.
Capper, L., ‘Post-Implementation Assessment of Information Systems Applications: Notes From Personal
Experiences’, in N. Bjorn-Andersen and G. B. Davis (eds), Information Systems Assessment:
Issues and Challenges, Elsevier, 1988.
Carr, N. G., ‘IT Doesn’t Matter’, Harvard Business Review, Vol. 81, No. 5, 2003.
Chapman, C., and S. Ward, Project Risk Management: Processes, Techniques and Insights, John Wiley,
1997.
Charette, R. N., Software Engineering Risk Analysis and Management, McGraw-Hill, 1989.
Coleman, T., and M. Jameison, Information Systems: Evaluating Tangible Benefits at the Feasibility
Stage of a Project Appraisal, unpublished report, City University Business School, London,
1991.
Devaraj, S., and R. Kohli, The IT Payoff: Measuring the Business Value of Information Technology
Benefits, Prentice-Hall, 2002.
Devaux, S. A., Total Project Control: A Manager’s Guide to Integrated Project Planning, Measuring
and Tracking, John Wiley, 1999.
Drucker, P., Management: Tasks, Responsibilities, Practices, Harper and Row, 1974.
Farbey, B., F. Land and D. Targett, ‘Evaluating Investments in IT’, Journal of Information Technology,
Vol. 7, No. 2, 1992.
——, IT Investment: A Study of Methods and Practices, Butterworth-Heinemann, 1993.
Fitzgerald, G., ‘Evaluating Information Systems Projects: A Multidimensional Approach’, Journal of
Information Technology, Vol. 13, No. 1, 1998.
Flyvbjerg, B., M. S. Holm and S. Buhl, ‘Underestimating Costs in Public Works Projects—Error or
Lie?’, Journal of the American Planning Association, Vol. 68, No. 3, 2002.
Galliers, R. D., ‘Rethinking IT Evaluation in the Context of Business Systems Strategy’, in B. Farbey,
D. Targett and F. Land (eds), Hard Money—Soft Outcomes: Evaluating and Managing the IT
Investment, Alfred Waller, 1995.
Gardner, C., The Valuation of Information Technology, John Wiley, 2000.
59
© 2006 Accounting Foundation, The University of Sydney
ABACUS
Grindley, K., Managing I.T. at Board Level, 2nd ed., Pitman, 1995.
Hares, J., and D. Royle, Measuring the Value of Information Technology, John Wiley, 1994.
Healy, P., Project Management: Getting the Job Done on Time and in [sic] Budget, Butterworth-
Heinemann, 1999.
Henderson, J. C., N. Venkatraman and S. Oldach, ‘Aligning Business and IT Strategies’, in J. Luftman
(ed.), Competing in the Information Age: Strategic Alignment in Practice, Oxford University
Press, 1996.
Hochstrasser, B., and C. Griffith, Controlling IT Investments: Strategy and Management, Butterworth
& Heinemann, 1991.
Hoffman, T., ‘IT Governance is on the Hot Seat’, Computerworld, July 2004.
Hogbin, G., and D. V. Thomas, Investing in Information Technology: Managing the Decision-Making
Process, McGraw-Hill, 1994.
IEEE, Glossary of Software Engineering Terminology, IEEE Standard 610.12-1990.
IT Governance Institute, Board Briefing on IT Governance, 2nd ed., 2003.
Information Systems Audit and Control Association [ISACA], ‘COBIT Control Objectives’, 3rd ed.,
2000. <Downloaded from www.isaca.org, 23 November 2002>
Jones, C., Estimating Software Costs, McGraw-Hill, 1998.
Kaplan, R. S., and D. P. Norton, The Balanced Scorecard: Translating Strategy Into Action, Harvard
Business School Press, 1996.
Kit, E., Software Testing in the Real World: Improving the Process, ACM Books, 1995.
KPMG Peat Marwick (Australia), Toolkit for the Company Director, 1994.
Kumar, K., ‘Post Implementation Evaluation of Computer Based Systems—Current Practices’,
Communications of the ACM, Vol. 33, No. 2, 1990.
Lay, P. M., ‘Beware the Cost/Benefit Model for IS Project Evaluation’, Journal of Systems Manage-
ment, June 1985.
Li, X., and J. D. Johnson, ‘Evaluate IT Investment Opportunities Using Real Options Theory’,
Information Resource Management Journal, July–September, Vol. 15, No. 3, 2002.
Lincoln, T., ‘Retrospective Appraisal of Information Technology Using SESAME’, in N. Bjørn-Andersen
and G. B. Davis (eds), Information Systems Assessment: Issues and Challenges, North Holland,
1988.
Lincoln, T., and D. Shorrock, ‘Cost-Justifying Current Use of Information Technology’, in T. Lincoln
(ed.), Managing Information Systems for Profit, John Wiley, 1990.
London Stock Exchange, Corporate Governance: A Practical Guide, 2004.
McFarlan, W. F., J. L. McKenney and P. Pyburn, ‘The Information Archipelago—Plotting a Course’,
Harvard Business Review, Vol. 61, No. 1, 1983.
Maines, L. A., ‘Judgment and Decision-Making Research in Financial Accounting: A Review and
Analysis’, in R. H. Ashton and A. H. Ashton (eds), Judgment and Decision-Making Research in
Accounting and Auditing, Cambridge University Press, 1995.
Marciniak, J. J., and D. J. Reifer, Software Acquisition Management: Managing the Acquisition of
Custom Software Systems, John Wiley, 1990.
Meyers, B. C., and P. Oberndorf, Managing Software Acquisition: Open Systems and COTS Products,
Addison-Wesley, 2001.
Mirani, R., and A. L. Lederer, ‘Making Promises: The Key Benefits of Proposed Information Systems’,
Journal of Systems Management, Vol. 44, No. 10, 1993.
Moskowitz, K., and H. Kern, Managing IT as an Investment: Partnering for Success, Prentice-Hall
PTR, 2003.
Murphy, T., Achieving Business Value From Technology: A Practical Guide for Today’s Executive,
John Wiley, 2002.
Myers, G. J., The Art of Testing, John Wiley, 1979.
Neuman, P. G., Computer Related Risks, ACM Press, 1995.
60
© 2006 Accounting Foundation, The University of Sydney
SOFTWARE DEVELOPMENT REPORTING TO MANAGERS
APPENDIX A
GLOSSARY
61
© 2006 Accounting Foundation, The University of Sydney
ABACUS
62
© 2006 Accounting Foundation, The University of Sydney
SOFTWARE DEVELOPMENT REPORTING TO MANAGERS
APPENDIX B
OBJECTIVES
MEMBERSHIP
Members shall be appointed by the Board for a limited period and shall not auto-
matically be re-appointed. The Board may engage outside experts to strengthen
the committee (either as members or advisers).
AUTHORITIES
RESPONSIBILITIES
Generally
To ensure that management has clearly articulated plans for the entity’s existing
and proposed investments in IT (including architecture plans, infrastructure
acquisition and maintenance plans, software acquisition and development
plans, prioritization criteria and security over access, documentation of processes
and data).
63
© 2006 Accounting Foundation, The University of Sydney
ABACUS
Performance Responsibilities
To review or develop key performance indicators relating to the application of IT
within the entity.
To commission post-implementation evaluation reviews of completed projects
including the annual test of the disaster recovery plan.
To annually assess the Committee’s own performance and review its charter.
PROCEDURES
Attendance
All directors who are not members of the IT Governance Committee shall have
the right to attend meetings.
64
© 2006 Accounting Foundation, The University of Sydney
SOFTWARE DEVELOPMENT REPORTING TO MANAGERS
Meetings
The Committee’s secretary shall propose a schedule of IT Governance Committee
meetings to ensure that all of the Committee’s responsibilities are addressed dur-
ing the financial year.
Meetings may be called by the chair of the Committee, or at the request of the
chair of the Board.
The Board shall appoint an executive to act as secretary to the Committee. The
secretary shall (in conjunction with the chair) be responsible for:
• drawing up the agenda, supported by documentation, and circulating that
material to Committee members prior to each meeting; and
• preparing draft minutes of the meetings of the IT Governance Committee, and
circulating minutes to members of the Committee and the Board.
The secretary shall provide draft minutes of meetings and provide them for
review by the chair of the Committee within ten working days.
Minutes shall be accompanied by an ‘action plan’ detailing matters that require
attention and the responsible officer, as the result of the Committee’s deliberations.
The Board shall be provided with minutes of IT Governance Committee meet-
ings at its next meeting (and oral reports of any meetings for which minutes have
yet to be prepared).
Submissions
Business units may make submissions to the Committee.
65
© 2006 Accounting Foundation, The University of Sydney