Sei sulla pagina 1di 24

U

'F
iI
Ra iIways

9
Earthworks and drainage 2513

25.1 Earthworks and drainage 25.1.2.2 Rock cuttings


British Railways has indicated safe slopes for rock cuttings and
The contours of the territory to be crossed by a railway are
angles of repose for rock embankments in a chart reproduced as
obviouslv decisive as to its average gradient but they are also the
Table 3 in BS 6031. If steep cuttings in rock are essential, then it
background to fixing the maximum permissible gradient within
is necessary to apply engineering geology concepts to assess
the limits of tractive and braking adhesion. The lower the
joint sets in relation to the direction of slope. Rock anchors,
difference between average gradient and maximum gradient the
rock bolts and sprayed concrete may be used to assure stability
greater is the practicable train load and the lesser are the
before considering the use of mass-retaining walls. Chalk and
deviations from constant-speed running. The minimum curva-
certain other soft rocks are susceptible to weathering and frost
ture to be used also determines the differences between the line
action and may be protected by vegetation cover.
speed limit and local speed restrictions. Long curves of small
radius on heavy gradients may involve derailment hazards for
very long and heavy trains, arising from braking or tractive 25.1.2.3 Soil cultings
effort surges along the train. Both maximum gradient and
Where the slopes are in noncohesive sands and gravels, the
minimum curvature have a large effect on the earthworks cost of
angle of repose is the limiting gradient (with a maximum value
constructing a railway and, because of this, the ideal of con-
of I : I). Usually, the gradient is shallower than this due to the
stant-speed running is often subject to heavy qualification. This
presence of finer layers in the soil system or a silt or clay matrix
is particularly the case in mountainous country.
around the gravel. The non-cohesive soils tend to be self-
Railway alignment needs to be planned to give a volume draining but erosion can occur when water springs part way up
balance between excavation in cuttings and tipping in embank- the slope. At such locations a non-woven geotextile filter can be
ments, subject to the material excavated being suitable for
placed and covered with uniform coarse stone (away from the
tipping to form embankments and subject to minimizing the sun’s rays) which will hold the fabric in place.
haul of the excavated soil. Recourse to borrow pits for embank- Drainage measures should take the form of preventing water
ments and spoil hauls for cuttings should be minimized. reaching the slope and of removing it from the slope. Unlined
The route may also be affected by other considerations which ditches behind the crest of the slope increase the hazard.
may be economic, environmental or technical. These would Drainage trenches, whether behind or below the crest, should be
become apparent in a full site investigation, where such matters
designed to intercept water and have impermeable membranes
as previous mining activity, underground services, effect on below them and on the downfill face to prevent water once
neighbouring structures, nature of the groundwater table and collected from re-entering the soil. Modem counterfort or
watercourses would be taken into account. Guidance is avail-
buttress drains differ greatly from the original open forms. Like
able in relevant Codes of Practice, such as BS 6031 and BS 5930.
all drains they should be lined with a geotextile layer to prevent
(See also Chapters 9, 1 I and 17.) erosion behind and fouling within them. The top I or 2 m
should be composed of impermeable material, either compacted
25.1.1 Site investigation clay fill or a system of stone and plastics membrane to prevent
\ surface water reaching deep into the ground, where it could
This will vary according to the extent of the problem. At the
cause internal pore water pressure at likely slip surfaces.
outset, a preliminary study may give adequate information to
In some cases, there is a mantle of more permeable silt or sand
specify the route corridor from geological maps and memoirs, overlying the older clay and, if possible, a lateral interceptor
topographical maps and aerial photographs. Earth satellite
drain should be placed about 20 m behind the crest to prevent
imagery with interpretation of selective wavebands by special-
the fast seepage of water.
ists in remote sensing can indicate important features. Water
In addition to the above rotational slides, translational slides
table conditions may vary throughout the year from those
obtaining at the time of exploration. can occur, usually as a shallow mass moving on a planar
surface. They can take the form of slab or block slides, wedge
For more localized investigation, the type of equipment
failures, debris slides and flow slides. These possibilities are
(augers, percussion and rotary tools, penetration heads, loading assessed in the site investigation. Mires are formed as peat is laid
plates, pumps), instruments (piezometers, inclinometer tubes,
down in a specific sequence with variations in soil content,
seismometers, resistivity meters, gravimeters, etc.) must be
dimensions of fibre (roots, trees, etc.) and extent of humifica-
chosen according to conditions. Relevant disturbed or undis-
tion. Peats reduce greatly in volume under the effects of loading
turbed samples should be procured for testing. According to the
and drainage. In making cuttings in a peat system, quite
type of ground, the construction and the design philosophy
applied, it may be necessary to carry out full-scale site testing substantial waterflow can occur and a filter is advised to deal
with long-term monitoring of instruments. with fine particles otherwise carried from the slope.
In all cases of cuttings, other engineering works at ground
level should be considered. Urban or industrial construction
25.1.2 General involves roads which act as catchments to deliver water to local
drainage systems and also water services: if these are defective
In the past, railways have been maintained over poor ground,
and near the slope, water can flow to increase pore pressure and
with inadequate trackbed materials with a high input of labour
precipitate a slip. Similarly, surcharging, especially if accompa-
time and at slow or moderate train speeds. Although the
following concepts may be used in modifying old railways, the nied by dynamic loads from construction plant or the placing of
storage containers, can seriously reduce the factor of safety.
basic approach is to obtain a minimum maintenance high-speed
Steep rock faces, chalk cliffs, and boulder-strewn hill slopes
railway accepting normal freight traffic on conventional
sleepers. may present rockfall or chalkfall problems which may need
special watchmen, signalling provisions, special fence, apron or
tunnel protection.
25.1.2.1 Cutting slopes
Slopes in natural ground may be constructed at safe angles 25.1.2.4 Embankments
according to the properties of the soil. The nature of the natural soil to receive the embankment must
.
2514 Railways
be investigated. If it is too weak to receive the embankment Drainage. The control of water in the trackbed is a major
loading at the rate of placing likely to be used by the contractor, factor in designing the construction layers in relation to the type
failure could occur. A total stress analysis is applicable for this. of subgrade soil as discussed above. Soils such as sands and
The conventional technique is to place berms as counterweights gravels which may be drained fairly easily do not present a great
at the position of heave. A modem alternative is the use of problem unless there is an artesian head in this case, there can
reinforcing geotextiles or meshes (usually of plastics) to resist be a slow upward migration of fine or medium sand under track
tensile forces. The fabric is laid directly on the ground and vibration combined with water flow, and a geotextile is neces-
covered with a granular layer at least 200 mm thick; this acts as sary to hold down this sand. Cohesive soils cannot be drained
a filter and permits construction plant to move easily over the easily and the installation of a channel or pipe will only reduce
site without sinking into the underlying soft soil. Further fabric the pore water pressure to invert level in its immediate vicinity.
or mesh is laid at higher levels, the number and spacing of layers It is not practical to attempt to remove water from clay in this
depending upon the engineering properties of the specialist type way as such a large number of drains would be required. If
of material chosen. water arrives through precipitation or by flow from adjacent
areas, then a relatively small amount is sufficient to produce
Slope angles. Embankments may be formed at angles varying deleterious changes in pore pressure and so it is practical to
from ratios of 1 : 1 horizontal to vertical for crushed rock and provide drains to intercept and remove this free water. Most of
gravels to 2.5: 1 or even shallower for clays and silts. The slope the water in cohesive soil is held in capillary suction.
angles depend both on the material and rainfall. For modem The relationship between the moisture content of cohesive
railways, peat should not be used as fill material. soil and the water table is complex, depending upon the over
The surfaces of slopes should be protected from erosion. This consolidation ratio (OCR) of the soil. Weathering reduces the
may occur naturally as vegetation is established, followed by a OCR effect at the surface.
protective topsoil. If surface erosion is a problem, various One object in designing the system of drains and track is to
systems are available, such as spraying with a seed mulch, produce a maintenance-free system or one needing minimal
turving, placing filter fabrics held down by gravel layers or using attention. Channel drains are readily accessible for cleaning and
a honeycomb mesh to hold seeded compost in place. deal with rainwater, they can be laid at very slight gradients and
can deliver at catchpits to deeper pipe camers if necessary.
Rockfalls. Vertical or sloping rock faces may erode or topple Many pipe drains act both as collectors and carriers, allowing
to cause rocks of various sizes to fall towards the running line. water to enter at open joints or through perforations. The
Although vegetation may help by bonding superficially, protec- various forms of pipe are glazed earthenware, galvanized corru-
tion must involve coping with the energy of rockfall and gated steel, pitch fibre and, now coming more into use because
removing the debris regularly. If space is available, one or two of ease of handling, plain or perforated PVC pipe. Geotextiles
berms are constructed between the base of the slope and the are of great use in static drainage conditions and most railways
railway to collect scree. For some faces, a plastic geomesh is report satisfactory results using commercially available filtering
adequate. non-woven fabric. For normal purposes, a fully heat-bonded
geotextile with a surface density in the range 100 to 200g/m2 is
Reinforced earth. The dimensions of embankments and of acceptable; needle-punched geotextiles should be of slightly
gravity-retaining structures can be reduced by the inclusion of heavier grade. Fabrics placed in quasi-static conditions near the
various strengthening meshes, fabrics, strips and rods of metal, track should be of heavier grade up to 350g/m*, or more if
glass fibre or plastics. The tensile resistance of these elements is needle-punched. Such a geotextile would be placed in the sixfoot
applied to the adjacent granular soil to produce a composite of a double track line after one track had been cleaned or
system permitting the construction of vertical faces in the fill. blanketed. This would prevent slurry from the dirty adjacent
These external faces are protected by facing elements usually of track flowing across.
concrete, resulting in a structure which is economic and which A modern standard design for a side drain is a trench lined
can accommodate settlement. The various qualities of creep, with geotextile with a perforated pipe drain running along its
longevity of reinforcement, corrosion, etc. are still the subject of base; above and around the pipe is placed uniform stone such as
study but many such structures exist throughout the world, ballast, with the top of the geotextile lapped over the stone
including railway environments. There are none so far beneath a about 200 mm below the surface: more stone on the geotextile
high-speed running line and, in this particular case, such systems protects it from disturbance and from the effect of the ultra-
can be installed up to a horizontal distance of 5 m from the violet rays of the sun. As perforated drains can release as well as
running line. collect water, possibly at susceptible locations, it is often the
practice to place a polyethylene film to line the trench.
Trackbed designs. The thickness of subsleeper construction
(trackbed) is a function of number and size of axle loadings and
of the subgrade soil. Modern railways assess the subgrade soil in 25.2 Ballast
one of two approaches: ( I ) the classification of the soil accord-
ing to its physical properties and taking account of the water Ballast, the material around and below the sleeper, is placed to
table; or (2) correlating some measured strength or modulus of provide support and lateral resistance to the sleeper. It permits
the subgrade with an empirical design chart. The thickness of adjustment of level and alignment as required and, if this is done
the trackbed may also depend upon its component layers to manually, the maximum size of particles should be about
protect against frost, water and particle movement. In very 50 mm. Ballast should be free-draining, mainly of single size, of
frost-prone areas, such as Central Europe, the thickness of cubical shape but, above all, durable so that there is negligible
ballast for frost protection exceeds that which might be required volume change under track loading. The wet attrition value
for prevention of bearing capacity failure. (WAV) gives the best correlation, with minimum maintenance
The thickness of ballast (all dimensions are below bottom of requirements over the long term and this is determined by the
sleeper) is a minimum of 200 mm to permit tamping machines to test described in BS 812: 1951. clause 27, which specifies the
operate. Although new ballast injection machines would permit exact size and type of sample to be used. If particles of different
this to be reduced, a high-speed or high-axle-load railway would size from the 50 to 37.5 mm required in the test are used, then a
require 300 to 500 mm thickness for minimum maintenance. different WAV is obtained. The WAV should not exceed 4% for
Ballast 2515

good ballast and it is possible to obtain stone with a WAV down nominal 20mm size between the ballast bed and the sleeper,
to 1%. It is rare for synthetic stone, such as slag, to have which is lifted to insert the stone. There is now a track-levelling
adequate wet attrition properties and they may generally be machine, electronically controlled, which evaluates cant and
grouped with most limestones as being unsuitable to be in level from an advancing inclinometer trolley and places the
contact with the sleeper. Hardness is difficult to define in exact quantity of stone by pneumatic injection to obtain proper
relation to other tests but, if the ultrasonic pulse velocity of the level. As stone more than 50 mm below the sleeper is not moved
homogeneous mineral is 6000 m/s or greater, the stone will be and brought with its dirty matrix up to bottom sleeper level, as
suitable. In severe climates, a freezing and thawing test may be with a tamper, the likelihood of pumping track is somewhat
applicable. lessened; the beneficial effect of high-quality small stone is not
The dimensions should conform by weight to the values reduced by mixing with existing worn stone and there is less
shown in Table 25.1; and the 1.18 mm limit effectively minimizes attrition of the base of the sleeper.
the amount of dust present.
Table 25.1 25.2.1 Track profile
Under traffic, rail level, as measured by accurate optical or
Square mesh
inclinometer-based machines, shows a profile which is repeated
sieve Yo topass even after many successive tamping and loading cycles. This is
related to the care with which the original trackbed layers were
63 100 installed. When the subgrade is prepared initially, and as
50 100-97 subsequent layers of blanket and ballast are placed and com-
28 20-0 pacted, it is necessary to provide extra sighting instruments on
14 2 4 compaction and grading plant so that there are no short
1.18 0.3-0 variations in level. This can be successfullydone by using a laser
system aimed at the surface a fixed distance ahead and which
The stone should have a maximum flakiness index of 50%. causes the equipment to compensate for deviation from the
For elongation qualities, not more than 2% by weight of required level by moving its instrumented blade up or down.
particles should have a dimension exceeding 75 mm. The ends of the sleepers need to be boxed-in with shoulder
The effect of many tamping cycles is to break up ballast ballast to a minimum width of I50 mm for any tracks, 200 to
particles; stone as hard as possible is required to accommodate 250 mm for running lines carrying moderate-speed, moderate-
this. When a sleeper is tamped, a horizontal load - the major axle-load traffic, 300mm minimum for welded track on the
principal stress - is applied to the ballast, causing it to deform straight and 350 mm for welded track on curves. Generally,
vertically and lift the sleeper. The minor principal stress is there is little advantage in extending shoulder ballasting beyond
vertical with the subsequent arrangement of stone particles in 300 to 350 mm. In the last decade or so, the practice of raising
the least favourable position to support track loading, even the shoulder ballast in a slope from about top of sleeper level at
though the rail level is now correct. The maximum rate of rail the rail to about top of rail level at the shoulder edge has become
settlement occurs after tamping, which reduces as the stone common on European railways. This practice not only increases
packs down under traffic, with the major principal stress becom- the lateral stability of the track but provides a useful reserve of
ing vertical. The trackbed becomes more stable under vertical boxing ballast which can be temporarily utilized to make good
loading and the best relevelling procedure is the manual or the boxing ballast when the track is tamped. The angle of the
mechanical placing of measured quantities of small stones of shoulder should be about 55'.

3307
~~

- I d
3307
(Min. dimension) (Min. dimension)

Pandrol rail. fastening

915
c

' \ Approved sand


\
1000-gauge
polythene sheet
I
where required Pipe drain

Figure 25.1 Components and formation for continuous welded


rail (CWR) track (dimensions in millimetres)
2516 Railways

25.3 Sleepers and to in-track service trials in order to prove the efficacy of new
steel sleeper designs.
Many of the older steel sleeper designs gave average service
25.3.1 Timber sleepers and sleeper spacing lives of over 50 years before failing through cracking in, or
The traditional track support since the early days of railways adjacent to, the rail seat area. Generally, these cracks propa-
has been the timber sleeper, but now prestressed concrete gated from rail fastener holes or slots or from discontinuities in
sleepers are in use in many countries. In some countries the the rail seat area. Abrasive wear and/or corrosion in this area
baseplated timber sleeper is already more expensive to install also contributed ultimately to sleeper failure. The steel sleeper
than a baseplateless prestressed concrete sleeper. design features, and especially those associated with the rail
In Britain, the sleepers and point and crossing timbers have fastener mountings, together with the accumulated gross traffic
traditionally been of softwood, chiefly douglas fir from Canada, tonnage carried, are the most important factors determining
Maritime pine from southwest France and Corsica, and Baltic steel sleeper life. Recently improved steel sleeper designs have
redwood from Poland and Russia. Homegrown fir sleepers have given due cognizance to these influences.
been used when they have been available. In continental Eur- It is commonplace to recondition old steel sleepers which
ope, beech and oak sleepers have been widely used. All soft- have already given a 30- to 50-year ‘first life’, by welding-on
wood sleepers, and most hardwood sleepers that,can be impreg- suitably designed reconditioning plates. If required, the recondi-
nated, are pressure creosoted by the Bethell or Ruping processes tioning plates used may permit a change in rail fastener type or
before being baseplated. The harder softwood sleepers such as rail section to be made for the further ‘second life’ of the steel
douglas fir or scots fir and hardwood sleepers need to be incised sleeper. When damaged in service, e.g. by derailments, steel
prior to creosoting. Four to 14 litres of creosote per sleeper is a sleepers can readily be repaired by pressing and/or welding.
normal absorption, according to species. In Canada, the US and Steel sleepers do not burn or suffer from exposure to dry heat.
South America a mixture of mineral oil and creosote is used. In tropical climates their immunity to insect or fungoidal
A timber sleeper may have a first or running line life of damage is extremely beneficial.
between 6 and 50 years with an average of about 20 years Loss of metal section through corrosion is usually surpris-
according to traffic loading, weather exposure, the nature and ingly low, but there may be a few very special sites subject to
incidence of the indigenous vegetative and insect enemies of severe corrosion, where the use of steel sleepers would be
timber, the presence or absence of baseplates, the nature of the inadvisable. Under-design of the rail seat, or inadequate sup-
fastenings, the quality of the ballast and its maintenance, the port thereof, can greatly increase the localized corrosion and
species of timber and, significantly, the rate at which it has fatigue damage in this generally highly stressed area, and due
grown. allowances have been made in modern designs.
The British softwood timber sleeper is 250 x 125 x 2600 mm Steel sleepers pack neatly into bundles and thus simplify all
with switch and crossing timbers of 300 x I50 mm section. In handling and transport operations and greatly reduce these
Europe, hardwood sleepers mainly of oak or beech are used costs. The relatively low mass and convenient and uniform
with a depth of 160 mm. Sleeper spacing in Britain is 700 mm shape of steel sleepers is of benefit in both mechanical and
with 650mm on curves or on timber sleepered continuous manual handling.
welded rail (CWR). In countries other than Britain, timber The use of steel sleepers provides good resistance to lateral
sleeper spacings of 600 mm are common with some as close as and longitudinal movement of the track and gives high consist-
550 mm in heavy-axle situations. ency of gauge,,both at installation and during subsequent
The sleeper spacing applied represents a compromise between service. The achievement of good alignment is necessary when
overall sleeper cost and the lessened frequency of maintenance steel sleepers are initially installed and when retamping after a
attention and reduced rail bending stress which results there- brief ‘running in’ period. The additional care and attention at
from. In addition, a decrease in sleeper spacing may be appro- this early stage generally results in a reduced need for subse-
priate where the formation is weak or where it is not practicable quent maintenance, realignment and retamping. Some of the
to increase the total track construction depth by increasing the older steel sleeper designs were difficult to install and adjust, but
depth of ballast. Since also increasing the density of sleepering modern designs are now relatively easy to install and to use for
increases both the lateral and vertical resistances to buckling ‘spot replacements’.
movements of the track, it is general practice to reduce sleeper The inverted trough shape and its entrapment of tamped-up
spacing when laying track intended to carry long welded rails. ballast provides many benefits. The natural resistance of the
Where the rail formation is regularly subjected to frost heave ballast is more.effectively utilized by steel sleepers, and ballast
distortions, there may be a case for deliberately choosing a depth may be decreased by 75 to IOOmm as compared with
rather weak rail with complementary close sleeper spacing in wood or concrete sleepers. This can be of distinct advantage in
order to allow the track to accommodate itself to a frost heave tunnels with limited clearances and ballast depth. Where stan-
contour without imposing undue bending stresses in the rails. dard ballast depth is retained, the additional load-spreading
effect of steel sleepers and their ballast-filled inverted trough,
may enable sleeper spacing to be slightly increased. Also, the
inverted trough shape has the in-built benefit that any enforced
movement of the sleeper increases the entrapped ballast density
25.3.2 Steel sleepers and its resistance to further sleeper movement, in comparison
Steel sleepers are widely used in India, Africa, South America, with the solid shape of wood and concrete sleepers where
Asia and in parts of Europe. Steel shortages during and eventually a ‘break-free’ point is reached.
following the Second World War, and the increased use of Steel sleepers are similar to concrete in their tendency to
concrete, impeded the further development of steel sleepers until degrade soft ballast more rapidly than wooden sleepers. Hence,
about the mid 1970s. Since then, there has been a considerable the use of a hard stone is preferred for steel sleepers. Neverthe-
amount of research done in Australia, Europe, Japan and less, many old steel sleepers have given long and satisfactory
Britain to evolve improved steel sleeper designs. Computer- service utilizing a gravel-type ballast.
based design techniques, e.g. finite element analysis, and Insulating pads, fastener shoes and/or washers must be
modern stress measuring and analysis techniques have been incorporated in the steel sleepers designed for lines using track
applied to both full-scale laboratory loading and fatigue testing circuit signalling. In most cases the insulating components used
sleepert an
aBickmtical to tlpase d with ImRmutC skpxs. Modem Spacing in British track is usually 700 or 6fioaun, although
p w IfmteIhb hove improd the deariat becuicy of thnn 600 mm spacing is used in sevcre curves.
insulating components and the track circuits, but &e high In the past 15 ycan, collcrctt sleepem have gaimd wider
ebctrical conductivity of steel sleepers requires special attention internationalaaxptance for several d,
to their design and maintenance.
The mass of individual steel Saecpers is usually mid-way (1) and M e r fteiBht &le loads
between that of wood and cmwcte, and may be considered a stronger trrd;.
dissdvant.ge with nspact to resietpnCe to the mticalbuckling (2) Hfgh rpbolu intcnsivc track use d t a t e
of continuously welded rail track. However. the e n t
ram d d frequency of maintenance cycles.
ballast in the inverted trough of steel sleepers and their general (3) IacrecuKd use of mechanized track-laying and ;renewal
shape @articularly the n t w c ~designs) greatly imxeaseJ the equipment has overcqnae the ditxculty of hamuing heavy
‘dfective in-track mass’ of s t t e l - q track. msleepm.
Most rail fastener types can be accommodated ia steel sleeper (4) Softwood sleepm are oftea unable to withstand the stresses
designs, and thm arc only isolated fastener systems which in modern main-line track and goodquality hardwood is
cannot be economicallyincorporated in stcd rlspcr dcaips. increasingly expensive and dillidt to obtain.
(5) With modern fastenin@, d y a r c s i i t pad is required
between the rail and sleeper thereby elimimting expensive
base plates.
It is generally predictedtla pstresssd concreteskaprrs will
253.3 cormeteskepers have an average life of 40 to 56 years. Some of the earlier designs
The first experiments with reinforced concmetc slccpsrs were of concrete sleepers have been removed from the track due to
ma& over 100 yean ago. concrate is attradivlely resistant to premature failure of the fastenings *Ugh the canatc re-
decay, insect attack and fire, but it is brittle, and reinforad mains structurally sound. Since 1964, British Rail h.llc uscd the
concrete skcpcrs would not withstand the im- loads in main Pandrol fastening in which tbe IeSs m b l e components can be
line track.A solution dtveloped in Frana in the 19-a~ to renewed (Figure 25.3). gC high speeds (over 110 kmb) wheel
use pairs o f r d n f o r a d coMntc blocks connected by stad tie and rail d p a d&ct.tans~~usc hi#t.ftrcsscs in concrete
bars.This twin-block sleeptr ooatinucsin use notably in Fr~mcc, sleepm which, ifallowcd to paoja can causecracking in the
Spain and North Africa but is of declining importance world- rail seat area of sleepers. Rcstrrssed sleepers with such cracks
wide. can remain scnkeabk, providing tkc’cause of high stress is
Undcr the pr*unues of timber shomges during the Second promptly deta3ed a d naiwas lluxsqp
World War, a satisfactory mnobloaPr congett atceper was The brit& MtWC Of-COmrcte somlhwa gives cause for
M o p e d in Britain in 1943 using the then & techaiqw of concern in derailment dam&&.Jn practics, the enhanced stabi-
pretensiowl, pnsrneecd conmtc. This has led to I major lity of
-oc tf+JLrsrk*rs UK incideace Qfderail-
industry in Britain (over 30 million pretensidned coecrcte m a t s and their Scvcrity is r d & d by modcrn fastmine whkb
hold dl during i k d h ~ ~ Wel
tl-
fil
~ .ledbpllast crib
provide protection to the concreteand derpihmnt damage to the
slovakia, Iraq,Japm, South Africa, Australin, Canada and the track is not a Signiscant probkm with monoblock concrete
US). sleepers. Twinblock sleepers, however, perform badly as the tie
In Britain and most of the other count& pretensionad bar% relatively easily bent causing severe gauge narrowing.
comrcte skcpcrs arc made by the 1o.g-line method in which the Whilst concrete is a smhiconductor, adequate insulation for
tendons arc fully bonded. This gives good distribution and track circuitscan be obtained simply and cheaply by incorporat-
control of prestress. Post-tmsioned sleepers were developed in ing insulating components into thc htcning.
West Germany in the 1950s and have found limited favour (in Concrete skcpen can be cast into a concrete slab to provide
West Germany, Italy, Spain and Mexico). ballastkss track but it is advisable to use sbcpas with projecting
t British Rail standard sleeper designated F27BS. reinforcement to ensure permanent cone@m to the in situ
is lrith*9.3 m q smn-wire strands (Figure 25.2). concrete. In dry locations, cspccialk,tumW undu sensitive
It is 2.5&4m kmg, 2 0 3 G - h under the rail, 264 mm wide at buildings where structure-borne m t i o v is ob;jectionabk,
thc bap and weighs
S t
m b gq rVQ oin 3 kg. For more arduous conditions, a
m .1psbeenintrodUad,prcrtrrsrcdwith
cight strands in thc sarke concrete envelope aS the FzHR(:
attenuation can be achiev
(w$hOut p j d u g reinfo
mg into the slab.
- -- .
Recently the F40. a 2.480 m long sleeper,has keen dev&ped to R a e n s i O d concrete bepmsjbve bocn in PIG in && asill
fpcilit.te Single-linemchaaizad track renewal withiathe tigat switch and croadng bearers &we U m d y 197or. UIb was
British Rail structw gauge. The base width is imxeapad to inhibited by the praaia of drilling the coMxctc to locate rail
285mmtomaintainthebeaMgareaandthedepthis2OOrmn fastenings, but manufactunrs have now dcvctoped methods of
under the rail which mves the same weight as the F27BS. cartina fasteninss into the beareW. and incrcaainn use is ~ t i ~ i -
2518 Railways

Figure 25.3 Types of rail fastening: (a) spring spike, (b) Pandrol
fastening, (c) K fastening, (d) square-section cut spikes, (e) FIST
fastening
1.4rnrn
rnrn
rnrn

W12.7 rnrn

0U.
Fastenings 2519

Rail f a s m w Wded into two catcg~&: dimct and


indire& : k ak further divided i@ elastic a&i rigid. Direct
fastenhpare those which fastea tbe raildircctlyltothesleeper,
and ingimt arc those which *f the rail to 0 chair M
bgseplatc. which SS f a s t e d to them^^^^ scpantd$.
Botb types of fastenings may-be either e W or rigid,
dcpedhg on whether a spring element is incorpara- and also
on whether they am adjustable or self-ftfdiontng.
-q- * c$ spike was theoriginal f W ursd
for flat bohom raB & b e 25.3), but in E& ifis'% longer
used except in sidings and light, p$rrow-&augc railways. In
North America, however, and on &ne&anlbuilt railways in
various parts of the wor~ci,it is still ins&nd on lines
carrying axk loads of up to 35 t. Resiliept fonus o w b u t spike
have, howcwr, been used extensively outside Qqda and the
US,p a r t i d a d y in Europe.
The cut spike has a number of disadvantagcs whiah have lqi
to the dedine in its use by European railways. $be majsr
disadvantages are: (1) short sleeper life due to spike I;illing a@
baseplate cutting (2) the need for high slecperins density (ia
America timber
normal); (3) the
with h c a v y - d
spike is a simple and robust system'wjiiahh i:ItJclfwcl)to rapid
pioneer developments, but it is poorly suited toafgtr
welded rail. q m i a l l y in countries where temperatures vary
between extremes of heat and cold. It'is alro d lit& use in

used with baseplatts, their performance is improved and this


OPD be fmplarcdrfsmth&wim dit&daubmio,sgkkavm
.rallolJEc~*~~mtol(h,sl~>Ilris~drrqolt$l
psrotiet to ftb8aeplab&aQI&arledr-f-
OE-< ' 'I' ' : ''
, ;,,I.V I ~ ~ , j . r < ~ , a
~ ~ ~ i a g e d ~ ~ w ~ d r ~ ~ p
8 pOdk1- On ths!dkS# t-w
allows the rail to float ' k d : . 3 & t I m & m ~ ~ ~
resisting rail creep and rail expansion due to temperature

timbarsleeper (bottom)

*U to w emm&iod'h#JbPll * . M c * f i
~ l r g ~ * * ~ ~ W ' 8 l h b b / ~ ~

Pandrol fastening, particularly for continuously welded rail.


tries,e.g. Belgium, only two are u s a t B & c d u n y p ~ g ~ The importance of the fastening in welded-rail track being able
& m O O 1 l l l l P P d l l ) r q d m t ~ . hwrnbrof to m a n
iw Ah GQ%qpu?a..
s @ i l & i p 6 . B a r c n k m b a w d o g r d w h c a ~ ~ ~ i J s k fuadlmental$hCfhc_St&dl@ 0 t h e h M d h ~ . I U Q L C
rillar*h ~ I I @ & c ~ ,r ~- . '8, significance if the ballast condition is below.-s I.
The clamping force generated by the rail M gmw&
able to resist any tmdency for thc rail ta creep throu&,w
fasteniw but n&,+ much,gb to all* the rail b push &t
slaesgs thmughthe ballast section. A nominalclip pnwsure of
betwecn&.4 and 2 $per rail is pncrally &icient ta@eve *.
It is inprtant tbpt any self.;4maionin@ip is de@pedto
a larged@ection u $ y fitted -sition @ order to-ize t h
effects of inanufaduing t o w on c#p. rail pad, insulatclr,
. foot/ For exam#c. a clip with 6 mm of
rail clip &xming. an&rail
~ ~ ? h a f i t P ~ f Q ~ W i t h 3 I W
2511 0 Railways

of wear or tolerances, whereas with 12 mm of deflection, the toe


load loss will be only 25%. The ability to ensure positive and
accurate track gauge retention is also an important feature of a
rail fastening.
Resilient rail fastenings are now used in the harshest of
operating conditions, such as heavy haul and high-speed pas-
senger services, and particular attention is being devoted to
improving the. ability of fastening assemblies to attenuate the
transmission of dynamic forces from rail to sleeper. This is
proving to be of particular importance in the case of fastenings
used with concrete sleepers in high-speed passenger operations.
Considerable effort is being focused on improving rail pad
characteristics.
A further area of development in rail fastenings is the need for 2.75
-1
mechanical installation in those areas of the world where track
labour costs are relatively high, and machines are now available
to drive some of the more widely-used fastening types.

25.5 Rails +I

The flat bottom, or Vignole, rail is now an almost universal


=
I-

standard so that the obsolescent bull head rail of past British


practice need not be developed here.
Generally, rail sections or weights are derived from progres-
sive experience, not because of analytical difficulties but because A1
2.75
of inadequate quantified knowledge. of what conditions of
loading and support actually occur.
A simple rough guide to appropriate rail weight in kilograms 49 t 1
per metre is to multiply the axle load in tonnes by 2. However, it
is necessary to make allowance for a speed factor and the Figure 25.6 Sections of British Rail types 110A and 11 3A and
following formula given by Schramm does this: fishplate (all dimensions in millimetres)

10 600
Rail weight in kilograms per metre = 156 - -
(Aa + 67) (25.1) The present standard in Britain is the 56.5 kg/m (BS I13A) rail,
adapted from the earlier British standard 109 Ib/yd rail and its
where A =static axle load in tonnes and a = the speed factor. successor BS I IOA section. Until relatively recently in Europe
The speed factor is still under critical review but it can be the standard section was the UIC 54 kg/m rail, but currently an
evaluated by three equations which are widely accepted for increasing proportion of main line track is being constructed
practical use: using UIC 60 kg/m section. In the USSR main line, heavy duty
tracks incorporate 75 kg/m rail sections.
a=I+(V/30000) up to 1 0 km/h (25.2)
Table 25.2 relates to a representative sleeper spacing of
a = I +(4.5V/lW)-(I.SV/lO’) up to 140km/h (25.3) 630mm. If the spacing is wider than this, and until recently
British practice utilized a sleeper spacing of 750 mm, the stress
due to bending moment may be up to 9% greater, but in any
a = I . I8 + (0.706 V/IO’) over 140 km/h (25.4) case the occurrence of three loose sleepers can put up rail
bending stress by 100% as can a heavy wheel flat at 30 km/h. At
From the above expressions, Table 25.2 has been produced. The rail ends a 12 mm dipped joint can, with an unsprung mass of
figures give an indication of appropriate weights within f 15%. the order of 20% of the static load at a speed of 160 km/h, create
British Standard specifications include rails from 25 to a dynamic increment of load equal to the static load. Since the
56.5 kg/m; in Europe rails up to 60 kg/m are used and up to great majority of rail breaks occur at rail ends it can be stated
70 kg/m in the US. that the rail weight selected must take into account the unsprung
masses on the heavier axles and also the state of maintenance of
joints which can be realized.
Table 26.2 Approximate rail weights, in kilograms per metre The weight of rail chosen has an influence on the shear
loading of the subsoil. According to Eisenmann increasing the
Static Speed rail weight from 48 to 68 kg/m diminishes shear stress by 20%.
axle (kmfi) As rail weights increase, the breadth of the rail foot increases
weight so that changing to a heavier-weight rail will generally involve
(1) 50 100 140 160 200 changing the baseplates or, where cast-in inserts are used,
respacing the inserts, unless the new rail is limited to new
IS 28 34 36 37 39 sleepers. Similarly, the administration of permanent way stocks
20 36 42 44 46 49 is simplified, and the tied-up capital reduced, if the range of rail
25 44 50 52 54 58 sections in use is limited.
30 50 56 59 61 65
35 57 61 65 67 10 The subsurface Hertzian stresses arising from wheel to rail
contact must be very carefully considered, in view of their
Rails 25/11
Table 25.3

Country Max. axle load Rail section Max. speed Rail steel grade used
(0 (kg/ml Straight track Curves

Britain 26 56.4 200 Normal Wear-resist.


Europe 22.5 60 200 Wear-resist. Premium
us 28 68 120-1 30 Wear-resist. Premium

relationship with wheel load, wheel size and tensile strength of steel surface hardens rapidly in service under stress and impact,
the rail steel. The Hertzian contact stresses are directly related to and develops high wear resistance. However, it is expensive,
the square root of the wheel load and inversely related to the needs great care in machining to avoid the risk of fatigue crack
square root of the wheel radius. The nominal shape of the rail initiation and can only be welded to similar steel by normal rail
head and wheel tread profiles and the progressive wear of these welding techniques. Its higher thermal coefficient of linear
two profiles in service. also influence the actual wheel-rail expansion also produces manufacturing problems and service
contact area and, hence, the Hertzian contact stresses. The use limitations, but rolled austenitic manganese rails have been
maximum level of the Hertzian contact stress normally occurs a successfully welded and used in the relatively constant tempera-
few millimetres below the contacting surfaces, and shelling and ture conditions of underground railways.
similar subsurface fatigue failures can develop if the shear stress Experimental work continues in the evaluation of more exotic
in this contact zone exceeds about 50% of the ultimate tensile and expensive rail steel chemistries for special applications, e.g.
strength of the rail steel. Under conditions of excessive stressing, bainitic steels.
complete collapse of the rail head can occur.
The principal rail specifications in international use are BSI I Rail joints are either suspended or supported. Joints are also
of the British Standards Institution, UIC 860-0 of the Union square, i.e. opposite each other, or staggered by up to half the
Internationale des Chemins de Fer (UIC) and the Munual of the rail length. In some administrations, rail joints are square on the
American Railway Engineering Association (AREA). A norm straight and staggered on the curves. Rail and fishplate sections
for railway rails (IS0 5003) has also been published by the need to be considered together in selecting a rail section, since if
International Standards Organization (ISO). the ratio of the f, of the fishplate is much below 25% of the fr.,
The most commonly used rail steels are defined in the above of the rail, broken fishplates and battered rail ends are likely to
standard specifications and can be classified as follows: have a high incidence.
( I ) Normal grades, typically of 680N/mm2 minimum UTS as
per BS 1 I normal grade and UIC 860-0 grade 70.
(2) Wear resisting grades, typically of 880 N/mm2 minimum
25.5.1 Rail failures
UTS as per BS 1I wear resisting grades A and B, UIC 860 It is necessary in any railway system that a record should be kept
grades 90A and 90B, AREA standard carbon grade. of all cracked and broken rails removed from the track. In
(3) Premium high strength grade, typically of 1080 N/mm2 addition, the cause of failure must be noted in order to monitor
minimum UTS. any specific problems which may be developing. This is camed
out with the use of a standard reporting form which gives details
The premium high-strength rail grades are still the subject of of track and conditions as well as the type of defect. This
much research and development, and are briefly referred to in information is fed into a computer and frequent monitoring of
only one specification - AREA. the data gives any developing trends.
These premium grade rails are produced either by the use of Whilst this latter information gives details of rails removed, it
alloy steels, generally about I % chromium and in some cases does not give any indication of those defects remaining in the
with micro-alloying additions of vanadium, molybdenum or track under observation. This information comes from the
niobium, or by the heat treatment of wear-resisting grade rails, normal regular examination of the track which is carried out by
e.g. BS wear resisting grade A. UIC 860 grade 90A, or AREA means of an ultrasonic rail flaw detection train and also by
standard carbon grade. The heat treatment may consist of either hand-held ultrasonic rail flaw detectors used by pedestrian
full section hardening or localized head hardening only. operators.
The rail steel grade selected for a particular track is dependent The ultrasonic test train is normally a self-propelled unit
on various factors including track design, traffic and operating consisting of two vehicles. It operates at speeds up to 30 km/h
conditions, standards of maintenance and economic factors, etc. and uses a series of probes which are applied to the rail head
Table 25.3 illustrates the different optimum strategies selected either in the form of sliding probes or wheel probes. The data
by different railroads. It is common practice to utilize a higher- from these probes are partially reduced by an on-board com-
strength, more wear-resistant. rail steel grade in tight curves, puter and the resulting information is stored on magnetic tape
and a less expensive grade in straight track. for subsequent off-line analysis. The defects detected by this
Broad recommendations for the selection of rail steel grade system are sent to the appropriate maintenance engineers for
based on track curvature and traffic intensity are outlined in action depending on the type of defect.
UIC Code 721-R. In addition to the train, hand-held ultrasonic units are used to
A special grade of rail steel utilized throughout the world, carry out work in areas not covered by the test train and also to
albeit in relatively small quantities, is austenitic manganese steel examine, in greater detail, defects which have been picked up by
(12-16% Mn) which is usually used in heavily trafficked tur- the test train but which require more detailed study. In addition,
nouts, switches and crossings. Many crossing vees (frogs) are the hand units are also used for monitoring defects which are
produced as austenitic manganese castings. Rolled austenitic allowed to remain in track until such time as they can be
manganese rails are produced in Britain in relatively small repaired or removed.
quantities being used in the fabrication of turnouts and S and C Ultrasonic testing of rails is carried out at a frequency
work, and occasionally in curved track. Austenitic manganese determined by the types and speeds of traffic carried. It ranges
I 25112 Railways
from 6 months to alternate years for some of -the lightly used
~ ~ _ _

Maximum cant:
branch lines. on curved track I50 mm
In addition to this routine testing, other specialized tests are at station platforms I10 mm
carried out by both the test train and the hand operators which maximum cant gradient I in 400
include gauge measurement, crack size estimation in special deficiency on plain line, CWR I10 mm
cases and weld testing.
deficiency on plain line, jointed track 90 mm
deficiency on switches and crossings welded
into CWR
25.6 Curved track on through line I10 mm
on turnout 90 mm
The main curves of the railway are nominally of constant radius, with negative cant on turnout 90 mm
i.e. circular curves; curves made up of two or more circular at switch toes 125 mm
curves of different radii curving in the same direction are called deficiency on switches and crossings in
compound curves. Straights are generally and desirably con- jointed track .
nected to circular curves by transition curves of progressively on through line 90 mm
vaqing radii; and adjoining circular curves of different radii are on turnout 90 mm
commonly joined together in a similar way if the difference of with negative cant on turnout 90 mm
radii exceeds about 10%. Two adjoining circular curves curving at switch toes 125 mm
in opposite directions comprise a reverse curve, and here, Maximum rate of change of cant
whatever the radius, the presence of connecting transitions is on plain line 55 mm/s
relatively more important than with circular or compound on switches and crossings 55 mm/s
curves. Maximum rate of change of cant deficiency
For practical purposes the cubic parabola y = k x 3 gives a on plain line 55 mm/s
uniform change of curvature between tangent point on the on switches and crossings 55 mm/s
straight and tangent point on the curve, or between the tangent Maximum rate of change of cant deficiency
points of two curves, and is the most used form of transition on plain line 55 mm/s
curve. The versines, measured on half-chord overlapping chords on switches and crossings (inclined design) 55 mm/s
along the transition, change with linear uniformity from zero to on switches and crossings (vertical design) 80 mm/s
R although it is usual to smooth out the rate of increase and
decrease at the start and end of the transition by putting on
about one-sixth of the rate of the first versine at the zero station (2) The proximity of permanent speed restrictions, junctions,
and reduce the increment at the final transition station to about stopping places, etc.
five-sixths of the half-chord rate of increase. Versines are (3) Track gradients which may cause a reduction in the speed of
conveniently measured in millimetres. freight or slow-moving passenger trains without having an
The geometrical relation between a circular curve and a appreciable effect on the speed of fast trains.
transition curve tangenting on to both the straight and the (4) The relative importance of the various types of traffic.
circular curve involves the moving inwards along a diameter
normal to the straight of the circular curve by an amount termed Generally, where fast and slow trains run on the same lines,
the ‘shift’. The transition curve bisects the shift at its midpoint an intermediate speed is selected to fix the cant. In this situation
measured along the straight tangent line and the offset from that it may exceptionally be necessary to limit the cant and therefore
line to the tangent point of the transition and circular curve is 4 the maximum speed to prevent surface damage to the low rail by
times the shift or 8 times the offset at the mid-transition point. It heavy axles on slow-moving freight trains.
follows that where no transition exists or where it is insufficient Each line of a double line should be separately assessed. In
in length the institution or extension of a transition can be done exposed locations subject to high winds it may be desirable to
only by sharpening the radius of the circular curve concerned or limit cant to below the 150 mm maximum.
moving the tangent straight away from the curve, though this Normally, cant or cant deficiency is uniformly gained or lost
may be worthwhile since any transition is better than none. within the length of a transition curve or, where there is no
The length of a transition curve is determined primarily by transition curve, as may occur in switches and crossings, over
what is judged to be an acceptable rate of change of cant or cant the length of the virtual transition, which for practical purposes
deficiency. For standard gauge plain track a desirable rate may is taken as the shortest distance between the centres of bogies of
be 35mm/s, with a maximum of, say, 55mm/s to secure coaching stock using the line. If the desired cant cannot be put
passenger comfort. In switches and crossings a rate as high as on within this length observing a maximum cant gradient of I in
80 mm/s may be applied but a good standard of switch and lead 400,the cant loss or gain is continued on to the circular curve.
design is desirable for this rate of loss or gain of cant or cant The 1 in 400 cant gradient mentioned relates to axle twist
deficiency. derailment possibilities, especially where four-wheeled vehicles
Some limiting cant and cant deficiency values observed in are concerned.
British practice on a 1.432m gauge are listed at top right. The maximum permissible speed on circular curves appropri-
ate to the determination of permanent speed restrictions may,
Wherever space permits, curve design should be based on the for standard gauge railways, be obtained from the following
desirable rate of change of cant or deficiency of 35 mm/s. expressions:
The amount of cant applied to a track depends upon con-
sideration of the following factors: Equilibrium (or theoretical) cant= E= 11.82(Vef/R)mm
Equilibrium speed = Ve=0.29J(RE) km/h
( I ) The line speed limit, i.e. the maximum speed at which traffic
is allowed to run on a line or branch or section of a line or Maximum speed = Vm = 0.29JR (E+ D ) km/h
branch. This limit is usually fixed with reference to the value
and distribution of permanent speed restrictions on the line where R = radius in metres, E=cant, which may be either actual
or branch, or section thereof, involved. cant or equilibrium cant but in practice the difference is not
Curved track 25/13

likely to be significant, though the distinction has to be kept in metres. Thus, what is described in American practice as a 10"
mind in certain circumstances, and D = maximum allowable curve would be described in Europe as a curve of 175 m radius.
cant deficiency in millimetres. Main railway curves are initially set out by theodolite gener-
ally on the basis that equal chords are subtended by equal angles
Desirable lengths of transition curves can be derived from the but informal setting out by an offset from a tangent followed by
greater of the two values obtained from: the use of overlapping chords of convenient length using the
versine appropriate to the radius can give a degree of accuracy
Length= L = 0.0075EVm m sufficient for less important curves. A selection of curve formu-
or L=O.O075DVmm lae covering most calculations for the design or setting out of
railway circular curves is set out in Table 25.4.
where E=cant in millimetres, D=deficiency of cant in milli- It is desirable to keep rail joints more or less square, or at a
metres and Vm= maximum permissible speed in kilometres per constant stagger where this is preferred, on curves by inserting
hour. short rails in the inner rail of curved track. The difference in rail
length, D, for standard gauge and for 18.3 m rails is given by
If space is limited, the length of the transition may be reduced to D =.(27.45/radius in metres) m. Alternatively, the approximate
two-thirds L subject to a minimum cant or cant deficiency difference in length can be obtained from the formula D = 3 ver-
gradient of I in 400. sine. It is normal to take a standard range of short rails from the
On compound curves to be traversed at a uniform speed, the makers and for 18.3 m rails, these are 18.25, 18.20 and 18.15 m.
desirable length is obtained from the greater of the two follow- The precise alignment of curves is vital to a smooth ride,
ing expressions: stability of the track geometry and minimizing track wear.
There are several alternative methods of adjusting railway
L = 0.0075(E, - EJVm m or curves as a maintenance operation but all are based on versine
L=0.0075(0, - D3Vm m measurements and relate, either to a smoothing or averaging
approach, in which the differences between a limited number of
where E, and D, are the cant and cant deficiency conditions for adjacent versines are adjusted to give a fairly uniform rate of
one curve and E, and D, are the similar values for the other change in transitions or to a fairly uniform value on circular
curve. curves; or to a design lining approach in which the whole of the
Similarly, on reverse curves the transition lengths are given versines of a curve are adjusted as one revision operation to give
by: a precise rate of increase or decrease in transitions and a strictly
uniform value on the circular curve portion, as far as clearances
L = 0.0075(EI+ E,) Vm m or from structures, etc. will permit. It is generally convenient to use
L=0.0075(D,+DJVmm smoothing or local adjustment techniques after a curve has been
aligned on a design basis. It is also normal practice to set
It should be noted that in using the above formulae the markers or monuments or pegs in or beside the tracks when
constants used have reference to a standard gauge, to an design lining is carried out.
assumed height of the centre of gravity of vehicles of about Curve realignment can be based on manual measurement of
1.5m and a subjective passenger comfort assessment of the versines or with less accuracy on the versine measurements of a
tolerable rate of change of cant or cant deficiency. To this extent track geometry recording car or of a track lining machine.
the values are arbitrary rather than absolute and refer to The side and interbody clearances shown on the diagram
standard gauge. Further qualifications are that the springing of contained in the Department's Requirements (see Figure 25.15)
vehicles may be such as to produce excessive lean under cant relate to straight track and may need to be augmented on curved
deficiency running to encroach significantly on side clearances track for end throw or centre throw of vehicles, which are
or to diminish passenger comfort, whilst if the centre of gravity generally of the same magnitude.
of a vehicle is higher or lower than that assumed the maximum
permissible speed is affected in inverse ratio, so that certain Centre throw= C=Bz/8R
vehicles may be permitted to run at a higher speed than other
vehicles. End throw=E=(Lz- EZ)/8R
The versine or middle ordinate of a chord on to a curve is
proportional to the curvature and is the basis of all railway where E = wheelbase or bogie centres, L = length of vehicle, and
curve alignment, checking and adjqstment. Its value as deter- R = radius.
mined from triangular analysis is given b y
To this increase of effective body width on curved track must be
2R={(C/2),/V)+ V (25.5) added a further allowance due to the tilting of the vehicle to the
low side on canted track. In Britain, the loss of side clearance at
where R = radius of a curve, C = length of chord on which the the vehicle cornice is about 2.25 times the actual cant.
versine is measured, and V= the versine, but since the value of V It is general practice slightly to widen the track on very sharp
is very small in relation to R in railway situations, the final V of curves to allow all vehicles, especially locomotives with long
the expression may be disregarded so that for both field rigid wheelbases, to pass round such curves without straining
measurements and calculation purposes: the track. The normal British practice is:
Curves over 200 m radius widened to 1435 gauge
V=C/8R (25.6) 200 10 I10 m radius widened to 1439 gauge
I10 to 70 m radius widened to 1451 gauge
In Britain and on the Continent, railway curvature is usually
described by the length of the radius measured in metres. The Appropriate values of gauge widening for a given track radius
American practice is to describe a curve by the angle subtended depend o n free play of wheelsets, .length of half wheel flange
at the centre of the curve by a chord of 30.48 m. For railway below rail level and rigid wheelbase of the critical vehicle.
work it is sufficient in transposing degree units into radius units In 'the UK it is the Department of Transport's enjoined
to divide 1746 by the degree of the curve to give the radius in practice to install check rails on curves of 200 m or less radius.
25114 Railways
Table 26.4 Curve formulae

Given Sought Formula Given Sought Formula

E. M C c = Z M J i ( E + M)/(E- M)} T, a M M = Tcot (a/2)vers (a/2)


E, R C C = 2RJ{E(2R+ E)}/( R + E) D R R= 50/sin ( 0 / 2 )
E, T C C=2T(T’- E’)/(T’+ E’) C, E R O = RI+ R 2 { ( 4 E ? - C ) / 8 E ) - ( R C / 4 ) - ( C E / 8 )
E. a C C = 2E {sin(u/2)}/{exsec (a/2)} C. M R R= {(M + (C/2)’)/2M
M. T C O=C- 2TC+4M2C+8M’T C, a R R= C/2 sin ( 4 2 )
M. R C C=2J{M(2R- M)} E, a R R = E/ex sec (a/2)
M,a C c=2Mcot (44) M. E R R= EM/(E- M)
R. T C C = 2 TR/J( T‘ + R ’) M..a R R = M/vers ( 4 2 )
R. a C C = 2R sin (42) T, C R R=CT/J{(ZT+ C)(2T- C)}
T. a C C = 2Tcos (a/2) T, E R R={(T+ E)(T-E)}/2E
R D sin ( D / 2 ) = 50/R T. M R O= R’- R’(M2+T’)/2M+ RT’- MT’/2
a, L D D= 100a/L approx. T, a R R= Tcot (a/2)
C. M E E=M(C+4M’)/(C-4Mz) C. E T O=2T1- T’C- 2TE’- CE’
C.a E E= C{ex sec (u/2)}/2sin (a/2) C. M T T=C(Cz+4M’)/2(C’-4Mz)
M.a E E= M/cos ( 4 2 ) C.a T T = C/(2 cos(a/2)}
R. C E E= R’/J((R+ C/2)(R- C/2)} E, a T T= Ecot(a/4)
R, M E E= R M / ( R - M) M. E T T=EJi(E+ M)@- M))
R. T E E= J(T’+ R’) - R M.a T T= M(tan (a/2)}/{vers(a/2)}
R. a E E= R ex sec (a/2) R. C T T= CR/2J{(R+C/2)(R- C/2)}
T. C E E= T J ( ( 2 T - C)/(2T+C)} R. E T T=J{E(ZR+ E)}
T, M E O = E’+ E’M- ET’+ MT’ R. M T T= RJ{M(ZR-M)J/(R-M)
T, a E E= Ttan(a/4) R. a T T= R tan (a/2)
R. a E E= R( I -cos (a/2)/cos (a/2) D. L a a= DL/l00 approx.
a, D L L = 100a/D approx. M.C a tan (a/4) = 2M/C
C. E M 0 = M’ + M’E + (MC’/4) - (C’E/4) M. E a cos (a/2)= M/E
C.a M M = (C/2)tan (a/4) R. C a sin (a/2)=C/2R
E, a M M = E cos (a/2) R. E a ex sec (a/2)= E/R
R. C M M = R - J { ( R+ C/2)(R- C/2)) R. M a vers (a/2)= M / R
R. E M M= RE/(R+E) R. T a tan (a/2)= T / R
R. T M M= R - ( Rz/J(T’ + R’)} T, C a cos (a/2)= C/2T
R. a M M = R vers (a/2) T, E a tan (a/4)= E/T
T, C M M = ( C / W V T - C)/(2T+C)) R. a L L= 0.017 453 292 5Ra
T, E M M=E(T’-E’)/(T’+ E’)

D= k g m O f CUNC M = Mid-ordinate Nore: ex ICE A = = A - I - ( I -cos A)/cos A andvcrs A = I -cos A


R - Radius
i= Ext. -
angle antral angle
L* Length of C U N ~
T=Tangent
C= Long chord
E = External distance

Check rails_are also sometimes installed in Britain on flatter to the temperature at which the rails were fastened to the
curves to diminish side cutting of the high rail or as a protection sleepers. If, as is usual, the rails are fastened down on installa-
against inadvertance or mishap at the bottom of a gradient. tion within a prescribed narrow temperature range situated at or
Wide flangeway check rails or guard rails may also be installed a little above the mean of the annual rail temperature range in a
to protect bridge supports or girders against being struck by normal or stress-free condition, then the amount of tension in
derailed vehicles. In the UK this provision is a Department of winter and compression in summer is limited to what is judged
Transport Requirement. to give an optimum compromise between a cold season hazard
of broken rails and a hot season hazard of track buckles.
The installation and maintenance of welded rail track need
25.7 Welded track more technical insight and attention than ordinary track. The
lateral strength of the track depends upon three main elements:
About two-thirds of the on-track maintenance work put into ( I ) the f, of the two rails; (2) the framework stiffness of the
jointed permanent way is at or adjoining the rail joints and the assembled rails and sleepers as developed by the fastenings; and
great majority of rail failures occur at or near fishplated joints. (3) the frictional loading of the ballast on the sides, ends and
For these and other reasons the tendency today is to use long bottoms of the sleepers. The resistance of the track to vertical
welded or continuously welded rails. buckling, which generally occurs in combination with, or as a
This procedure entails the elastic containment of the longitu- trigger to, lateral buckling, is determined mainly by the total
dinal expansion and contraction stresses arising in the rails as a weight of the track, and in this context concrete through-type
consequence of variation in the rail temperature with reference sleepers show a considerable advantage. In a fully-ballasted
25.8.1 sn#chLs
The ha4 of a switch is the point from whi& it is fme to move.
Eprly switch dcaigns had a loose heel fenned by a &-tight
fishplated joint but this type is now M d y 4ortdnidc of
sidings. It is now the gmcnd practice for tha-heddthc switch to
be formed by abhckhstwtea
switChdPndS iswellbddndthe
heel. The length of the switch planing* r8t bead of tbc rail
variesbetweenabout ldand I I mandnnwt&wayaduhistra-
pnscribed limits (21 to 2 7 T for the UK). In th& way it is oiom have a range oftwub eight Stsndardpitcbes to meet the
possible to lay welded track all the year round. The pull requirad requirements of short leads in depots pad various spqeds of
to &tend a 56kg/m rail is of the order of 1.6tyC. The tensots -on the runninglines.
have a Capacity of about 70 t. originally,ordinoryorstraightp~~switch~was
universally applied but during the last few duxdescurvcd
planing, in which the switch rail is bent strrtially wkiW being
planed on ode sidc of= head, has becomr, general. In $his way
t h c c u r w ~ g t 4 u o u g hthe lead i s o a * l i a Q t d t e ~ s w i t c h
tip. A merit practice is to apply a larger radius to t h e m of
the switch t&n is applied to the switch beyond tbeslaofthe
planingto gin a more robust switch tip a r i t l r ~ h i t c ~ t m g k .

258.2
Crossings are described by the angle at tbe crowing nose. In
wntincntd Jkope it is common to state this in &qpew but over
the Englisb-#paking world the angle is usually deoaibal as 1 in
N. Howerer, the an& of a crowing cxprclcrod &? 1 in N varies
slightly d i n g to tbe mepnUing convention adopted. Thus if
1 in 8 is druined by measuring 8 units plogll@cccntr&s for I
unit of s;rpaetrical spread normal to t8s ElALtrclina (antreline
Illtpsun).&en measuring 8 units along 0110 leg of the we for a
spradof 1 unit measured at right angles btbat kg((ri0btangle
m a n n c ) give~ 1 in 7969. whilst if8 unita islacasuad along
Figun 264 Hydraulic rail sressec This h..a M t pu(l md each leg to@= a spread of 1 unit the croaaingd&wiU be I in
380-rnrn stroke. For pus hi^ action, the rail clamps are turned 8.016 (isoccelts measure). It is therefore ncccsmy for any
through 180'. (Courtesy:Pennaquip Co. Ltd) railway to have t specific mode of mcamingcrossin@w k h is
known to (111-lying manufacturers of q. or to state
tsaangkmdegras.
Welded rails are not normalfy laid in Europe in curves with a In the UK l b d diamond crorsiags am limited by Minirtry
lesser radius than 600m.Long wIdcd rails arc made up by ilash requiremssltto be not flatter than 1 in 7.5. In m n h t a l Europe
butt welding of atandard rail hgths into welded rails of MO to 1 in 10isthepmallimit.Whmalinecraringflattcrtb.nthe
400m kngthin depot and wcldcdinto continuouswd&d rails allowed limit is F , the points of the diamond crossings
by Thermit WeMS, except in t6C USRwherc a mqortabk arc consteudcd as slachcs and have to beset to suit tha train
flash butt welder is appIicd to join raib in the tract. movematdesired.
It is normal practia in Britain and Fmnce to install sliding There ia no official &nit on the angle of -on croahgs but
switchesat the ends of long welded rails but in t h m a n y this is 1 in 28 is a b thcflattcst an& at which thecrosoingwgthas
not done, reliance being placed on very 1&n fastening of the sufficient robustness. Crossings arc either made up from rails or
welded raih wtam they connect with jointed traclr. arc cast in 12 to 14% steel. Butlt-up crossings have
The advantages of wdded track include an extension of rail the inhmnt limitationsof boltcd a s s e m b h and of rcQGlltyears
lives by about a ttu.d,a reduction of on-track maintenance by it has becomegeneral practicein the UKtondd thevrtrsction
about half, a dramatic reduction of rail b r c a b d L and Huck4askn the wings. In general. it is Pefmsd p d to
running spccds, less damage to the formation, increased sleeper have cast amsings for high-speed or heavily worked l h s rising
lives, i m p r 0 w ; d ride comfort, a duction oftnction energy of built-up d g s for kss exacting duty. It is also prcfarcd to
up to 5%. and a reductionin train noise. IneEect. welded rails. usccastcrossingsforanglcstlattcrthanabout 1 in20.InthcW
~ W ~ s l a p e r s a n d a d f - t s o p i a n i f-arc
ae it is common practice for the nose section of the crossing to be. a
awnplsmentruytoeach oteer inextkadiogthe life and redil&lg manganese casting to which ordinary rail section wine are
t8e long-team overall cost of permanent way. attached to form what is known as a rail bound cast crossing.
alignment and *I

*-

c ,-

Figure 26.11 Sectin of slab track laid in tunnel (to increase provided by the introdudioaor removal of hcight-adjuaing
haadroom for alactrifiition, and to reduce maintenance costs) pads located under basepates mounted on the units.
25/18 Railways

Although these systems place a greater need on period demanding is the dntenance task.The stiffnessof the rail, the
maintenance than do the more cmtia\rour forms of slab track, shper spacing end the depth of ballast BW important f&ors
the d s e and lower c mt of adjwthg the track f&wing major af&aling the cost of maintenance.
of the slab mon than aompensafcfor thje extm dfort The evolution of the aatomatic levelling lining and tamping
m certainlocafisesi Ia streh locations, w h e the stabiiity of slab ma&nein t ~ 1 9 6 o s ( F i g n p c 2 5 . 1 2 ) c h a n g a d t h e ~ p a ~ e r n
track& nequiradtdlow Mgh-sped twffk: or themre isf'ieduced of track maintenance. The original manual method of maintan-
d s a m but ~ ~ ~
where id a &tang powitbility of si@&ant ance, using beater picks, was to drive individual pieces of ballast
movamsd of the back, e.g. as a tosdr df mawWpake, this under the s l w tb &ain the nquircd rail kvtE aM1 hnness of
fonn of dab e& cowtruction 'hgM<rnnyadvsablgca over sapport. A iater&ve?oopnent, pimeemd in France, was to jack
0 t h the skeper and spread small stone chlppings over the bearing
Ertirnateo of the limit of speed at which tzaiRs can MI on a m . This system wes known as meilwtFcd &owl pucking
conventional tracks vary between about 250 and 400km/& The
h i t s tltat u ~ p l e e e don speeds dftraigsby sleb m c k arelargely
teoSe dmcuracyof m c ~ ~ u n min l ~ to detba ratd mrect
c lor&r
(Msp) and was efitrtlmly SUOOOSSN in producing gmd track
a l k u g b expensive in labour.
A ncsnt development has been the laachaeizationhf this
.
m i s a l i pt~ the coastrbchn stpga. K the call for higher process using a machine known as a 'Stoneblower'. This
speeds continues to be made, it may oaly be pwibie to meet it d i n e automrrtically mcamm the voids under the s h p e ~ ~
by *g Ltabtrack. and, using pophisticatad ekottonic controls, pneumatically in-
Similarly, if the need to provide sinuous riailwpy mutes jects the coned quantity of stone to ptoduce the amect
through highly congested areas continues, the use of slab track longitadinal. vuticrl track profila, k prototype machine using
should allow &is tb Ire b e using the &ea&amount d spacc and this process has recently boen can91matd (Figure 2'5.13). Deve-
w&i~thebast o~ls&&int on &ain speeds. lopment work on this prinapk has shown that track maintained
bythissystarn on~de~orcllssac.appto.im~lyonsquaner of
the nte of traek maiMeined by eonvmtional mnphg. Very
25.10 Track maintenance and renewal cansidora~srrviagr am the&- possible in maintenance costs
by u s i g this new tececkwque.
Gencdy, the p k r the strength and iahennt stability of the otker -inn, llsGd in &tion with tamping end stone-
design of tlsb track canstructian and its foundation, the km blowing are ballast-regulating machines for positioning ballast
Track maintenance and mwwd 25kl9

shortw.veabcNppIlolu
* ot;U)to180mfrcqucncywithadeptb

hundred. Recxnt rcsclvch has highlightad t k &&porWn& of


maintaining the CO& wheel-rail interaction involving both
- 1

F@uro28.13 Roeotype ’Stdneblower‘ fa pecking ard a l i i


track. (Courreqc Plasser (G6) Ltd)
Railway structures 25/21
Stations should be constructed to be as fire resistant as Overline bridges and elevated roads alongside railways must
practicable and extinguishing equipment provided for dealing be provided with parapets complying with Department of
with fires in station premises. Transport Technical Memorandum (Bridges) No. BE 5 . These
parapets are intended to protect pedestrians and/or to contain
errant vehicles and prevent them from falling on to the railway;
they may also be required to be solid, to prevent splash, reduce
25.11.3 Bridges and viaducts noise or screen railway electrification equipment.
Bridges and viaducts may be constructed in steel, concrete For bridges carrying roads, such as motorways, from which
(reinforced or prestressed), brickwork or masonry. The use of pedestrians, animals and pedal cycles are excluded by order, the
other materials such as light alloys will be considered on their minimum height of parapet above the adjoining paved surface
merits, but cast iron must not be used in any portion of the must be 1.250m. The lower 600 mm of the parapet should have
structure of a bridge carrying a railway except when subject to a mesh or solid infill panel, which may be mounted outside any
direct compression only. Structural timber is usually restricted longitudinal members.
to light overline bridges. For bridges carrying all-purpose roads and footbridges, the
New and reconstructed bridges must be built to provide at parapet is to have a traffic face which is smooth and without
least the mandatory clearances to the kinematic envelope (des- hand- or footholds. The minimum height of parapet above the
cribed below) as illustrated in Figure 25.15. For British Rail, adjoining paved surface must be 1.500m. For bridges used
this requirement gives a standard structure gauge 4.640 mm frequently by equestrians, the height must be at least 1.800m.
high (above rail level) and 2.340mm clear laterally from the If a bridge over a railway which is electrified on the overhead
centreline of the nearest track (when the latter is straight; system has a parapet with a plinth on its outer face, access must
additional lateral clearance is necessary alongside curved be denied to that plinth. Any parapet more than 100 mm thick is
tracks). to be surmounted by a ‘steeple-shaped’ coping (i.e. with steep
Underline bridges must be provided with robust kerbs as part sides meeting at the top at an acute angle).
of the bridge structure and extending to a height of at least At locations where the likelihood of vehicle impact with the
305 mm above rail level to contain the wheels of any derailed parapet and consequential damage resulting from its penetra-
vehicle. Such bridges must provide for a safe lineside walkway, tion outweigh the hazards resulting from the containment and
with a substantial parapet or railing not less than 1.250m in redirection of errant vehicles within the traffic scheme, ‘high
height above the walkway (unless the main girders themselves containment’ parapets must be provided.
provide a sufficient parapet). On bridges and viaducts which are Pipelines carrying liquids or gases over the railway must be
longer than 40 m or where visibility of approaching trains is incorporated in a bridge constructed for another purpose or be
limited, it may be necessary to incorporate recesses in the supported by a purpose-designed beam or service bridge. Such a
parapet design to afford the refuges described below. bridge should preferably span the railway without intermediate
Bridges and other structures built over or immediately adjac- supports. Consideration may be given to a free-standing design
ent to railway lines must be protected against the consequences of pipe crossing only in the case of low-pressure water mains or
of their supports being struck by railway vehicles in the event of similar pipes conveying non-hazardous materials.
a derailment. Such supports should be located as far from the The design loadings and other criteria for both underline and
tracks as practicable. If they can be kept 4.5 m or more clear of overline bridges are generally as set out in BS 5400. The major
the nearest rail, there will normally be no requirement to design railway undertakings in Britain require underline bridges to be
for impact forces. Where this clearance cannot be achieved, the designed and constructed by their own staff or under their direct
supports must be designed with a degree of robustness and control.
continuity to minimize the etTects of contact by a derailed Where bridges are to be constructed under or over existing
vehicle and to withstand nominal impact forces. railways, special techniques are usually necessary to minimize
Clearance between kinematic
envelope and railway operational
Standard structure gauge\
1 I structures above cantrail level.
Normal - 250. Minimum - 1GQ.
On railways with existing or
’proposed overhead electrification
the requirements for electrical
. clearance, where
these are greater,
shall apply

Nearest
isolated Recess for signal wires and cables if required
length but excluding masts carrying This space to be kept clear as far
overhead line equipment on electrified -. as possible of permanent obstructions
railways.
J
Nearest face of all other structures Standard dimension between structures
-
including masts carrying overhead line for double line standard gauge railway
equipment on electrified railways.

Figure 25.15 Department of Transport -standard structure gauge


and kinematic load g a u g e
25/22 Railways
the interruption to the normal operation of such railways; the 25.1 1.5 Refuges
requirements of these techniques may significantly influence not
Refuges are to be provided in all tunnels and also on long
only the temporary works but also the design of the permanent
bridges and viaducts and where the railway is enclosed by
works. It is usually more economic to ensure that work adjacent
lineside structures unless lateral clearances over a continuous
to running lines, particularly excavation, is located sufficiently length of 40 m or more are such that staff can stand in safety
far away from them to avoid the necessity for the imposition of during the passage of trains. Similarly, on embankments and in
speed restrictions on railway traffic. The design and construc- cuttings, wherever lineside clearances over a length of 40 m or
tion of all bridges and viaducts should also be such as to
more do not give safe standing room, refuge spaces are to be
minimize future maintenance on grounds of both economy and
provided. The criteria as to what clearance allows men to stand
avoidance of interference with railway traffic. Provision should
at the lineside in safety are defined as 830mm from the
be made to ensure that all parts of bridges are accessible for
kinematic envelope at its widest point for train speeds of up to
regular inspection and maintenance and that all exposed steel
160km/h and 1.700m for train speeds between 161 and 200
can be painted. Underline bridges should be designed to carry
km/h.
normal ballasted track.
Refuges and refuge spaces should be located on both sides of
the line at a spacing not exceeding 40 m, staggered to give an
effective spacing of 20 m or less. Refuges must be at least 2 m
high, 1.400 m wide and 700 mm deep, with their floors substan-
tially at the level of the adjacent lineside walkway. Handholds,
25.1 1.4 Clearances to assist men in keeping their balance during the passage of a
The structural and electrical clearances (to be provided on new train, are to be provided in refuges and also elsewhere if lateral
lines and on existing railways where new structures are built or clearances only marginally exceed the criteria specified in the
existing structures are modified or where clearances are other- previous paragraph.
wise altered) are specified in the revised part of the above-
mentioned Department of Transport Requirements published
in 1977.
Structural clearances are related to the ‘kinematic envelope’ 25.12 Inspection and maintenance of
of the stock which will use the line and are illustrated in Figure structures
25.14 in respect of lines carrying trains at speeds up to 200 km/h;
that figure is based for the purpose of illustration on the In the interests of safety and economy, it is essential to have up
kinematic envelope applicable to British Rail vehicles. to-date and reliable information as to the current condition of
The kinematic envelope is derived from the static load gauge all railway structures and to carry out any necessary repairs or
as follows: ( I ) the maximum permitted cross-sectional dimen- renewals in due time.
sions of vehicles and their loads when at rest and located The key to proper maintenance, therefore, lies in a system of
centrally on straight and level track; (2) the static load gauge regular routine and methodical examination by suitably trained
must be enlarged to allow for the maximum possible displace- and experienced staff in order to provide the responsible main-
ment of the vehicles when at rest or in motion, with respect to tenance engineer with well-founded records, for each structure,
the rails, taking account of their suspension characteristics and as to: ( I ) its condition; (2) its current fitness for its intended
making allowance for maximum permitted tolerances in the purpose; (3) its rate of deterioration; and (4) the urgency for
manufacture and maintenance of the vehicles, including wear; remedial action.
and (3) the resultant kinematic load gauge must then be further It is common practice to legislate for superficial examinations,
enlarged to take account of the maximum permitted tolerances undertaken at intervals of about I year, and less frequent
in gauge, alignment, top- and cross-level of track including the detailed examinations, in which every element of the structure is
effects of wear. The kinematic envelope so derived thus contains carefully and thoroughly inspected at close range and the extent
the full cross-section of vehicles and their loads under any of any deterioration quantified. The frequency of detailed
permissible condition of operation and maintenance of both examinations will depend upon the nature, age and condition of
vehicles and of track. It does not, however, allow for the end- the structure, but the interval between such examinations
throw and centre-throw of vehicles on curved track, and addi- should rarely exceed 6 years unless there are special problems or
tional allowance for these must be made as appropriate. unjustifiably high costs in providing adequate access; in the
Electrical clearances are dependent upon the nominal voltage latter event, decisions as to the action to be taken following an
of the overhead conductor system and upon whether the cate- examination should have particular regard to the length of time
gory of clearance is to be normal, reduced or special reduced. likely to elapse before the next one. Additional special examina-
They must include provision for tolerances in the installation tions may be necessary after flooding, damage from impact, fire
and maintenance of the overhead equipment and of the track or vandalism and similar eventualities.
limiting values of the vertical clearance for normal, reduced and Proper examination depends upon adequate safe access to all
special reduced clearance conditions between the underside of a parts of a structure. Suitable provision should have been made
structure and the kinematic load gauge shown diagrammatically for this in the initial design by providing removable panels,
in Figure 25.15 (for 25 kV a.c.). Also shown are the corre- walkways, fixing points for ladders or safety lines and by
sponding clearances between the undersides of structures and avoiding the creation of inaccessible spaces. Where the latter has
the designed rail level, based on the normal British Rail static not been done, some ‘opening-out’ should be undertaken, at
load gauge. It will be noted that the standard structure gauge on least on a sampling basis. Recourse to expensive scaffolding may
British Rail allows for overhead electrification at voltages up to often be avoided by the use of mobile inspection platforms.
25 kV, albeit with ‘close tolerances’; the vertical distance from Examiners must compile full written reports of detailed
rail level to the undersides of structures should ideally be examinations. To facilitate this, most railway undertakings use
increased to 4.780m if this can be achieved with reasonable specially devised forms, which act as a checklist and encourage
economy, and further increased where a bridge is adjacent to a clear, concise and comprehensive coverage. Sketches or photo-
level crossing, over which the overhead equipment has to be graphs are valuable for illustrating defects. Reports must record
raised to give 5.600 m clearance over road levels. defects in quantitative form, e.g. the loss of section (or the
Bibliography 25/23

amount of section remaining), the extent of any displacement, these languages are used at UIC and ORE meetings, French
the magnitude of any movement, the width, length and orien- being the primary procedural tongue.
tation of cracks, the extent of hollow-sounding brickwork, the Another European body which makes a significant contribu-
depth of perished mortar or the degree of water percolation. tion to railway technical literature in its periodical bulletins, is
Where appropriate, 'tell tales' and plumbing/levelling points the International Railway Congress Association (IRCA) whose
should be established and readings from them recorded. In some administration is in Brussels.
cases, more sophisticated techniques of investigation may be The principal technical railway co-ordinating organization in
called for. The objective should be to ensure that the mainten- the US is the American Railway Engineering Association
ance engineer has readily available data as to the nature, rate (AREA) of Chicago which issues a periodical journal covering
and extent of the development of any defect, i.e. the way in minutes of meetings, reports of special committees and recom-
which deterioration is occurring over a period of time by mendations for specifications and technical procedures. The
comparing a succession of reports. Thus, he is assisted in AREA also sponsors research and development projects which
diagnosing the cause of trouble and guided in his judgement as are mainly progressed by the Association of American Rail-
to the urgency for remedial action. roads (AAR) at its Research Centre at Chicago. The Pan
Financial constraints may well limit the number of structures American Railway Congress is a similar but less developed
which can receive maintenance attention in any year, and it is organization covering the countries of South America. Much
therefore necessary to establish some kind of priority rating valuable railway research and development work is done in
system for defects, to ensure that available resources are dir- Japan and the English version of the monthly Journal of the
ected where the need is most urgent. This may well involve some Permanent Way Society of Japan, founded in 1958 in Tokyo,
assessment of the residual strength of members. Calculations provides a comprehensive contemporary reflection of this work.
and possibly instrumental tests may be necessary to determine Important permanent way research centres also exist in
critical stresses; these should be based on the nature and Prague, Moscow, Belgrade and Johannesburg but the results of
magnitude of the loads actually having to be sustained and their activities are normally limited to domestic distribution.
should have regard to the current condition of members, The chief technical and development railway work carried out in
allowing for loss of original section, distortion and similar the UK is associated with the Research and Development
defects. Centre at Derby which has a considerable international repu-
The nature, extent and timing of any repair will vary widely tation. Its reports are generally limited to internal circulation
depending on the circumstances applicable in individual cases. within the British Railways Board but most of its railway
Decisions hereon must rely heavily on the informed judgement research projects are reported through papers and articles for
of the experienced maintenance engineer. For repairs to be the British engineering institutions, chiefly the Institution of
effective, it is essential that the cause of the defect is correctly Civil Engineers, the Institution of Electrical Engineers, the
diagnosed and that that cause, rather than its results, is properly Institution of Mechanical Engineers, and the technical press. It
dealt with. Desirably, this should be done before serious defects also accepts commissions for research from-outside the British
develop, by preventive maintenance of a stitch-in-time nature, Railways Board.
e.g. painting of metalwork and timber, pointing of brickwork The national railways of the UK, Canada, France, Germany
and masonry and sealing points of water percolation. and Japan are also associated with sponsored railway consul-
It is also a matter of professional judgement to determine tancy organizations which, whilst primarily concerned with the
when repairs are no longer economic and reconstruction is techniques of railway organization, also offer technical advice to
justified. clients.
Contemporary railway civil engineering practice and develop-
ments in the UK and elsewhere are more to be found in papers
presented to the railway division of the Institution of Civil
25.13 Research, development and Engineers and to the Permanent Way Institution, in the bulle-
international collaboration tins and journals of ORE, IRC. and the AREA and in the
railway technical press of the UK, France, Germany and
T h e principal railway co-ordinating body in Europe is the UIC America, rather than in the few standard textbooks on railway
(Union Internationale des Chemins de Fer) whose headquarters engineering which are necessarily less up to date.
is in Paris. Its primary purpose is the encouragement and
development of standard railway policies and practices through-
out Europe. It has a permanent secretariat but it works through Bibliography
committees covering the activities of most railway departments.
Twenty-six nations are constituent members. Berridge, P. S. A. (1969) The girder bridge. Maxwell.
Its technical research co-ordinating arm is ORE (Office for Eisenmann, J. (1969) 'St!ess distribution in the pe'manent way due to
Research and Experiments) which has its office at Utrecht. The heavy axleloads and high speeds.' American Railway Engineering
UIC issues specifications, standards, and recommendations for Association Proceedings.
Fastenrath, F. (1981) Railroad trark - theory and prarrice. New York.
railway practice to which railway administrations are expected
Heeler, C. L. (1979) British Railway Track. Permanent Way
or encouraged to adhere. The ORE is represented on all Institution, London.
technical committees of UIC and issues reports made by work- Prud'homme and Bentot (1969) 'The stability of tracks laid with long
ing parties or by specially commissioned persons of academic or welded rails', International Railway Congress Association Bullerin
professional distinction to member administrations of UIC. (July 1969).
The field and laboratory work of ORE is assigned to member Schramm, G. (1961) Permanenr way rerhnique and eronomy.
administrations or to universities or technical schools; such Darmstadt.
work is usually progressed by an appropriate working party Turton, F. (1972) Railway bridge maintenance. Hutchinson, London.
Department of Transport (1983) Bridge inspection guide. HMSO,
composed of delegates from member administrations serviced
London.
by a technical secretary from ORE. Distinguished men from Department of Transport (1982) 'Design of highway bridge parapets'.
industry and universities are sometimes co-opted to serve on Technical memorandum (bridges) No. BE 5. HMSO, London.
specific working parties; UIC and ORE reports are normally Institution of Civil Engineers (1984) Proreedings ofronference on work
issued simultaneously in English, French and German, and rerhnologyfor the next derade at University of Nottingham.
25/24 Railways
Permanent Way Institution. Journals and reports of proceedings, list of BS 882:I983
papers and authors 1884-1976. ‘Specification for aggregates from natural sources for concrete.’
Ruild.oy Construction and Operution: Requirements .for Pussenger Lines BS 913:1973
and Recommendotions.for good.^ Lines (I 963 reprint). HMSO, ‘Wood preservation by means of pressure creosoting.’
London. BS 1377:1975
Ruiluuy construction und operurion: structural ond ekcrricul cleoronces ‘Methods of test for soil for civil engineering purposes.’
(1977).HMSO, London. BS 2589:I955 ( 1984)
Roiluwy Construction ond Operorion: Level Crossings ( 198I ). HMSO, ’Railway track spanners.‘
London. BS 4521: Part I 1971: Part I I 1975:Part 111 1974 Part IV 1975
Railwuy engineering and moinfenance encyrlopaerlia. Simmons ‘Turnouts using flat bottom rails.’
Boardman, US. BS 4978:1975 (Amended 1984)
Research and Development Division. British Rail and Association of ‘Timber grades for structural use.’
American Railroads ( I 98I ) Proceedings 0fro~ferennc.eon roil BS 5268:1984
rerlinology at University of Nottingham. ‘Code of practice for the structural use of timber.’
BS 5400:1978 Parts I to 10
British standards ‘Steel. concrete and composite bridges.‘
BS I1:1978 (Amended 1984) BS 5493:1977(Amended 1984)
‘Specification for railway rails.’ ‘Code of practice for protective coating of iron and steel structures
BS 47:1959 (Amended 1979) against corrosion.’
‘Steel fishplates for bullhead and flat bottom railway rails.’ BS 59301981
BS 64:1946 (Amended 1960) ‘Code of practice for site investigations’
‘Steel fishbolts and nuts for railway rails.’ BS 6031:1981 (Amended 1983)
BS 144:1973 (Amended 1974) ’Code of practice for earthworks.’
‘Coal tar creosote for the preservation of timber.’ EIS 81 10:1985:Parts I to Ill
BS 500:1956 (Amended 1976) ’The structural use of concrete.’
‘Steel railway sleepers for flat bottom rails.’ CP 2004:1972 (Amended 1975)
BS 751:1959(Amended 1976) ‘Foundations.‘
‘Steel bearing plates for Rat bottom railway rails.’

Potrebbero piacerti anche