Sei sulla pagina 1di 4

Vapor barriers

under concrete slabs


Should the concrete be placed directly on the vapor barrier?

By Bruce A. Suprenant

any architects and engineers re- used to protect floor coverings or Vapor barrier performance
M quire the use of a vapor barrier
under concrete slabs. Even though the
electronic equipment that might be
damaged from moisture moving up-
Vapor barriers effectively minimize
water inflow, but some water vapor
use of a vapor barrier might be com- ward through the concrete slab. Re- may still pass through them. The Port-
mon, the specified location of the va- cently, vapor barriers have also been land Cement Association (PCA) con-
por barrier varies. Some specifiers re- used to minimize the infiltration of ducted moisture migration tests in
quire a sand layer or a crushed base radon. which concrete slabs were placed di-
over the vapor barrier. Others insist The American Concrete Institute’s rectly on a wet clay subgrade (Ref. 2).
that the vapor barrier be placed direct- (ACI) Committee 302 “Guide for Tests were run with and without a va-
ly under the slab. Specifiers must care- Concrete Floor and Slab Construc- por barrier and with and without a
fully consider the effect of the location tion” suggests that a vapor barrier may gravel layer that served as a capillary
of the vapor barrier on the perfor- not be necessary where no drainage or break. Vapor barriers used were 4-mil
mance of the concrete slab. soil problems exist and in arid regions polyethylene and 55-pound roofing
where irrigation and heavy sprinkling felt.
Why use vapor barriers? are not done (Ref. 1). However, some As Figure 1 shows, using a vapor
Vapor barriers are traditionally specifiers always use a vapor barrier barrier, with or without a gravel layer,
specified to minimize moisture in- because it is inexpensive to install at lowered the amount of water passing
flow through concrete that’s in con- the time of construction and moisture through the slab from below. After 2
tact with water or water vapor from problems are difficult to correct after months of testing concrete with a wa-
a high water table. Vapor barriers are construction. ter-cement ratio of 0.70, moisture in-
flow through the slab with no vapor
barrier was about three times higher
than inflow through the slab with a va-
por barrier.
Figure 1 also shows that a granular
capillary break reduces the water in-
flow even without a vapor barrier.
However, the vapor barrier applied
over a granular layer greatly reduced
the moisture movement through the
concrete slab from the water below.

Vapor barrier properties and


installation methods
Polyethylene sheeting is the most
common vapor barrier material. A 4-
to 6-mil-thick polyethylene sheet is
typically placed on a compacted sub-
grade or on a sand layer spread over
Figure 1. A vapor barrier is effective in preventing water inflow from the ground- the subgrade.
water through the concrete slab. Using a vapor barrier in combination with a gran- Some specifiers prefer thicker
ular capillary break provides the greatest resistance to water inflow. polyethylene sheeting, especially if the
barrier will be placed in contact with a
crushed stone base. Others recom-
mend using sheet membranes or as-
phalt core board. The thicker, stronger
materials resist punctures better during
construction. They also allow less wa-
ter vapor to pass. Regardless of the
sheeting thickness, vapor barrier joints
should be airtight with proper laps to
help prevent water vapor movement.
ACI 302 recommends using a 3-
inch-thick sand layer over the vapor
barrier before concrete is placed.
However, some architects and engi-
neers suggest using a 1⁄2- to 1-inch
sand layer since even if compacted,
the 3-inch sand layer can be easily
displaced during concrete placement.
Then the sand may mix with the con-
crete or the slab thickness may vary.
Both result in a weaker slab. Also, a
thick sand layer may lead to pumping
at the joints when the slab is subject-
ed to forklift traffic.
Still other architects and engineers
prefer placing a crushed stone layer
over a 50-mil-thick polyethylene
sheeting that won’t be punctured by
the stone. The crushed stone is not
easily displaced during concrete
placement, can support construction
equipment for compaction, and elim-
inates any pumping at the joints. Ad-
ditionally, a thin layer of sand is usu-
ally used on top of the crushed base
to minimize subgrade drag between
the crushed stone and the concrete
slab.
Although ACI 302 recommends
putting a sand layer on the vapor barri- Figure 2. Concrete slabs placed over polyethylene cracked, while slabs placed
er, some specifiers require placing over a sand base didn’t crack. Details of the test slab program show three differ-
concrete directly on the vapor barrier. ent base conditions as well as four curing conditions on each of the bases for
each slab. Three different concrete mixes are described on the right.
When this is done, however, finishers
may purposely punch holes in the va-
por barrier to reduce bleedwater rise concrete slab reduces subgrade fric- mum frictional restraint stress of only
and allow the slab to set quicker. If it’s tion. Reducing friction between the 13 psi at the center of a pavement with
important that the vapor barrier not be slab and subgrade allows more shrink- contraction joints on 20-foot centers
punctured, onsite inspection will be age contraction to occur. As more (Ref. 7). For short slabs, the investiga-
necessary. If the vapor barrier is used movement occurs, fewer cracks should tor recommended designing for curl-
only to reduce subgrade friction, form. ing stresses and ignoring the restraint
punching holes in the vapor barrier Studies have shown, however, that of shrinkage contraction.
may be permitted (Ref. 3). subgrade friction doesn’t have much
influence on movement of short slabs Vapor barrier effects
Vapor barrier effect caused by changes in slab temperature on concrete properties
on subgrade friction or moisture content (Ref. 5, 6, and 7). Vapor barriers can affect the behav-
Some engineers believe that placing One investigator calculated a maxi- ior of the concrete slab and signifi-
the vapor barrier in contact with the
cantly influence finishing time, crack- cant for these high water-cement con- Vapor barrier effects
ing, and strength. Both the engineer crete mixes than they would have been on slab curling
and contractor need to understand how for concrete mixes with a low water- ACI 302 indicates that placing con-
concrete properties are affected by the cement ratio and slump. crete in direct contact with a vapor
vapor barrier. Strength. Nicholson also cored the barrier increases slab curling (Ref. 1).
Finishing time. Placing concrete concrete placed over polyethylene Since the bottom of the slab loses no
directly on a vapor barrier increases sheeting, a 3-inch sand layer, and a 3- moisture and the top dries rapidly,
the amount of bleedwater that rises to inch sand-cement layer. Concrete shrinkage at the slab surface pulls the
the top surface. Because of this, it also placed over a sand bed was more than edges upward. Placing the concrete on
increases the waiting time needed be- 30% stronger than concrete cast on the a sand layer is expected to help reduce
tween bull floating and further finish- polyethylene (Ref. 9). curling by minimizing the difference
ing. Finishers must wait for the bleed- Interestingly, one PCA publication in moisture content between the top
water to disappear before troweling. suggests that less water should be used and bottom of the slab.
If the finishers are too eager and in concrete that will be placed directly A sand layer may also reduce curl-
start to work while the bleedwater is over a vapor barrier (Ref. 10). The ing caused by localized moisture con-
still visible, surface defects are likely theory is that placing concrete on a tent differences beneath a slab. In a
to occur. Thus placing concrete direct- granular layer lowers the water-ce- study of pavement warping, moisture
ly on a vapor barrier increases finish- ment ratio, thereby increasing concrete measurements of the subgrade soil
ing time and the possibility of surface strength. Since the vapor barrier pre- showed that a free-draining granular
defects. ACI 302 also says that a va- vents this water loss, the water-cement layer helped to distribute water more
por barrier directly under a concrete ratio should be adjusted downward at uniformly below the slab so that dif-
slab aggravates plastic shrinkage the time of batching to provide the ferences in moisture content weren’t
cracking (Ref. 1). same equivalent strength as concrete as great (Ref. 4). Although there was a
The PCA tests did show that when a on a sand layer. greater total slab uplift caused by
concrete slab was placed directly over For the high-water-cement-ratio swelling soils, differential uplift was
a vapor barrier, instead of over a sand concretes tested by Nicholson, the smaller.
layer, water flow from the concrete sand bed would be an obvious benefit.
was greater at early ages (Ref. 2). The The difference in strength between Should the vapor barrier be
researchers believed this was due to concrete placed directly on a vapor in contact with the concrete?
more evaporation of the mix water. barrier versus a sand layer, like the Because concrete properties and fin-
When vapor barriers were not used, difference in cracking, should be less ishing methods probably have a greater
some mix water could be lost to the significant at lower water-cement ra- effect on concrete performance than the
subgrade below, thus reducing the tios. vapor barrier, it is not surprising that ar-
amount of mix water evaporation mea- Blumer believes that a sand layer chitects, engineers, and contractors dis-
sured at the top surface. decreases concrete strength by remov- agree on the correct location of the va-
Cracking. Nicholson studied ef- ing water from the concrete that is por barrier. Some have seen good slab
fects of vapor barriers on cracking be- necessary for proper curing (Ref. 11). performance and some have seen poor
havior by placing concrete over Because of this, Blumer says the vapor results when concrete was placed di-
polyethylene sheeting, a 3-inch sand barrier should be placed in contact rectly on a vapor barrier.
layer with no vapor barrier, and a 3- with the slab, just as polyethylene I believe that the location of the va-
inch sand-cement layer with no vapor sheets are used on top of the slab, to por barrier for interior concrete proba-
barrier (Ref. 8). The results, shown in minimize water loss and promote ce- bly doesn’t matter if a high-quality
Figure 2, were dramatic. There was ment hydration. concrete with a low water content and
extensive cracking in the slabs placed If the water-cement ratio is at least water-cement ratio is used and it’s fin-
on polyethylene and little cracking in 0.42, there’s enough water in the con- ished correctly. Under these condi-
the slabs placed over sand or cement- crete to fully hydrate all of the cement tions, the concrete performance will be
treated sand. Nicholson attributed the (Ref. 12). If the concrete was placed the same regardless of whether the
reduction in cracking to absorption of with a water-cement ratio lower than concrete and vapor barrier are separat-
concrete mix water by the sand base. 0.42, then the loss of water to the sand ed by a sand layer.
It’s interesting to note that the con- layer might be important. However, For concretes with high water con-
crete mixes used in the study varied in most commercial slab-on-grade con- tents and high water-cement ratios,
water-cement ratio from 0.7 to 0.8 and cretes are placed with a water-cement placing the concrete over an aggregate
had a slump from 8 to 9 inches. The ratio of 0.45 to 0.55. Also, the amount layer is beneficial. It speeds up finish-
dramatic reduction in cracking and the of water lost to the sand layer depends ing, increases strength, and reduces
water loss from the concrete into the on whether the sand is wet or dry. the possibility of finishing defects and
sand base were probably more signifi- curling.
8. Leo P. Nicholson, “How to Minimize
References Cracking and Increase Strength of
1. ACI Committee 302, “Guide for Slabs on Grade,” Concrete Construc-
Concrete Floor and Slab Construc- tion, September 1981.
tion,” ACI 302.1R-89, American Con- 9. Richard H. Campbell, Wendell Hard-
crete Institute, P.O. Box 19150, Red- ing, Edward Misenhimer, Leo P.
ford Station, Detroit, MI 48219. Nicholson, and Jack Sisk, “Job Condi-
2. H. W. Brewer, “Moisture Migration— tions Affect Cracking and Strength of
Concrete Slab-on-ground Construc- Concrete In-place,” ACI Journal,
tion,” Bulletin D89, Portland Cement American Concrete Institute, January
Association, 5420 Old Orchard Rd., 1976.
Skokie, IL 60077, 1965. 10. Ralph E. Spears, Concrete Floors
3. Robert F. Ytterberg, “Shrinkage and on Ground, Portland Cement Associa-
Curling of Slabs on Grade,” Part 3 of tion, 1978.
3, Concrete International, American 11. H. Maynard Blumer, “New Justifi-
Concrete Institute, June 1987. cations in an Old Debate: Specifying
4. W. H. Roor, Chairman, “Report of Vapor Barriers Under Slabs-on-
Committee on Warping of Concrete Grade,” The Construction Specifier,
Pavements,” Proceedings Highway Construction Specifications Institute,
Research Board, National Research 601 Madison St., Alexandria, VA
Council, 2101 Constitution Ave., NW, 22314, February 1990.
Washington, DC 20418, V. 25, 1945. 12. Sidney Mindess and J. Francis
5. A. G. Timms, “Evaluating Subgrade Young, Concrete, Prentice-Hall, New
Friction-reducing Mediums for Rigid York, 1981.
Pavements,” Highway Research
Record No. 60, Highway Research
Board, National Research Council, Bruce A. Suprenant is a consulting en-
1963. gineer, an associate professor at the
6. Bengt F. Friberg, “Frictional Resis- University of Colorado in Boulder,
tance under Concrete Pavements and and a contributing editor for Concrete
Restraint Stresses in Long Reinforced Construction.
Slabs,” Proceedings Highway Re-
search Board, National Research
Council, V. 33, 1954.
7. Shigeyoshi Nagataki, “Shrinkage
and Shrinkage Restraints in Concrete
Pavements,” Journal of the Structural
Division, ST 7, American Society of PUBLICATION #C920292
Civil Engineers, 345 E. 47th Ave., New Copyright © 1992, The Aberdeen Group
York, NY 10017, July 1970. All rights reserved

Potrebbero piacerti anche