Sei sulla pagina 1di 25

HSE STANDARD

MODULE 05
EXCAVATION

BSP-02-Standard-1643

THIS DOCUMENT CONTAINS


ONE
MODULE IN A SET
COMPRISING
HSE STANDARDS
FOR THE
BRUNEI SHELL COMPANIES

Revision Approved: SCO/4


2.1 Document Author: SCO/4x
BSP – Excavation Module 05

Document Control
DOCUMENT TYPE DOCUMENT OWNER SECURITY CLASSIFICATION
Standards SCO/4
DOCUMENT REFERENCE AUTHOR APPROVED BY
BSP-02-Standard-1643 SCO/4x SCO/4
KEY WORDS

Revision Record
REV REVISION DESCRIPTION DATE
2.1 Incorporating TSM/12 recommendations April 2003

Distribution Control
Distribution of this document is controlled by the Document Owner. The distribution is as follows:
-

Notice and Warning


Copyright , Brunei Shell Petroleum Company Sendirian Berhad
This document is the property of Brunei Shell Petroleum Sendirian Berhad (BSP), Seria 7082, Negara
Brunei Darussalam. Circulation is restricted to BSP and its designated associates, contractors and
consultants. It must not be copied or used for any other purpose other than which it is supplied,
without the expressed written authority of BSP.
Except where provided for purposes of contractual requirements, BSP disclaims any responsibility or
liability for any use or misuse of the document by any person and makes no warranty as to the
accuracy or suitability of the information to any third party. Any misuse of the document is
redressable by BSP.

Excavation - Rev 2.1 Page 2 of 25


BSP – Excavation Module 05

Contents Page

CHAPTER 1 RESPONSIBILITIES........................................................................... 5
1.1 Excavation Supervisor ............................................................................................................................... 5

1.2 Worksite Supervisor .................................................................................................................................. 5

CHAPTER 2 REQUIREMENTS ............................................................................... 6


2.1 General Requirements ............................................................................................................................... 6
2.1.1 Definitions............................................................................................................................................. 6
2.1.2 Shallow Excavations ............................................................................................................................. 6
2.1.3 Unsupported Excavations ..................................................................................................................... 6
2.1.4 Deep Excavations.................................................................................................................................. 7
2.1.5 Deep Foundations ................................................................................................................................. 7
2.1.6 Mechanical Digging.............................................................................................................................. 7
2.1.7 Headings and Tunnels........................................................................................................................... 7

2.2 Preparation and Permit Requirements.................................................................................................... 9

2.3 Support System Design Requirements..................................................................................................... 9

2.4 Written Excavation Plan ........................................................................................................................... 9


2.4.1 General Considerations......................................................................................................................... 9
2.4.2 Preparation .......................................................................................................................................... 10
2.4.3 Work Planning .................................................................................................................................... 10

2.5 Identification of Underground Services................................................................................................. 10


2.5.1 Prior to Start of Work ......................................................................................................................... 10
2.5.2 Cable Avoidance Tool ........................................................................................................................ 11

2.6 Pilot Trenching ......................................................................................................................................... 11


2.6.1 Requirements for Pilot Trenches ........................................................................................................ 11
2.6.3 Pilot Trenching – Method B (see Figure 4)....................................................................................... 12

2.7 Disposal of Spoil and Backfilling ............................................................................................................ 13


2.7.1 Disposal of Soil ................................................................................................................................... 13
2.7.2 Backfilling........................................................................................................................................... 13

2.8 Gas Testing................................................................................................................................................ 13

2.9 Ventilation ................................................................................................................................................. 14

2.10 Lighting.................................................................................................................................................. 14

2.11 Water Removal ..................................................................................................................................... 14


2.11.1 Rainwater and Surface Water.......................................................................................................... 14
2.11.2 Ground Water .................................................................................................................................. 14

2.12 Access and Barriers .............................................................................................................................. 15


2.12.1 Access .............................................................................................................................................. 15
2.12.2 Gangways and Bridges.................................................................................................................... 15
2.12.3 Barriers ............................................................................................................................................ 16

2.13 Checklists ............................................................................................................................................... 16

CHAPTER 3 PRECAUTIONS ................................................................................ 17


3.1 General Precautions................................................................................................................................. 17

Excavation - Rev 2.1 Page 3 of 25


BSP – Excavation Module 05

3.2 Failure Modes ........................................................................................................................................... 17


3.2.1 Soft Clay.............................................................................................................................................. 17
3.2.2 Stiff Clay ............................................................................................................................................. 17
3.2.3 Rock..................................................................................................................................................... 17

3.3 Support Systems ....................................................................................................................................... 18


3.3.1 Supports Designed and Specified On-site .......................................................................................... 18
3.3.2 Supports Designed by Specialist Designers ....................................................................................... 18

3.4 Access ......................................................................................................................................................... 18

3.5 Barriers...................................................................................................................................................... 18

3.6 Means of Escape ....................................................................................................................................... 18

3.7 Discovery of a Suspicious Object............................................................................................................ 18

REFERENCES ........................................................................................................... 20
Appendix 1 - Ground Conditions and Slopes ...................................................................................................... 21

Appendix 2 - Checklist for Excavation Plan........................................................................................................ 23

Appendix 3 - Checklist Prior to Start of Work ................................................................................................... 24

Appendix 4 - Checklist Whilst Work is in Progress ........................................................................................... 25

This module is one of a series produced by the Brunei Shell Companies (BSC), which represent
minimum acceptable HSE standards for a wide variety of operations. Individual operating procedures
and/or task specifications should reflect these minimum standards and should be consulted, where
appropriate, prior to start of work.
Comment and feedback from users of this module is encouraged, in order that the series may be
updated as appropriate to reflect current requirements.
For details of the current revision status of all modules, a summary of intermediate updates published
since the last issue, and information on how to comment on this module, please refer to the last
edition of Module 00, HSE Standards Master Index, which is republished at regular intervals.
This document is unregistered and copies are available from the Company Representative.

Excavation - Rev 2.1 Page 4 of 25


BSP – Excavation Module 05

CHAPTER 1 RESPONSIBILITIES

The Process Owner of this module is SCO/4 (PPA/3, POP/2, SFE/21, EOP/1, TSM/22)

1.1 Excavation Supervisor


The Supervisor with responsibility for the excavation shall ensure that:
- no excavation is carried out in an area without the prior knowledge and approval of the
Asset Holder.
- a written plan is prepared and submitted for BSC approval for all excavations which exceed
1.5 metres in depth.
- all worksite supervisors are properly trained in the relevant permit to work and safety
requirements for each proposed excavation.All possible steps have been taken to identify all
underground services in the vicinity of the intended excavation and precautions taken to
prevent damage to them.
- TSM, as the Technical Authority on positioning and mapping issues, are continuously
updating the Asset Holder’s map database from B2B surveys and as-builts and wish all
excavation crews to be aware of hidden hazards.
- TSM/221 will provide on request a colour 1:500 scale Permit To Work Map showing all
known services in the intended excavation site. PTW applications will not be authorised if
an out-of-date PTW Map is submitted. PTW Maps display a three-month expiry date and
TSM require all PTW signatories to refuse (in the interest of safety) all Maps that have
expired.
- PTW Map requests must be made in person to enable TSM/22 personnel to create a map of
the exact location of the intended excavation. TSM/22 personnel will not entertain request
made via e-mail or telephone.
- Any services not identified on the PTW Map that are found during the excavation must be
notified to the Geomatics Department for inclusion in updates to the Map Database. If the
reason for excavation is to lay a new line, it is the Asset Holder's responsibility to request
positioning services from TSM/1 or provide accurate as-laid plans that can be incorporated
in the TSM Map Database. The excavation site cannot be closed until this data is obtained.
Failure of the Asset Holder to provide this data will be reviewed on its next PTW Map
application and PTW authorisation.
- a system of review and control is established to ensure that the safety requirements of
excavation activities are reviewed on a regular basis.

1.2 Worksite Supervisor


Prior to commencing excavation works on any BSC asset, it is the responsibility of the worksite
supervisor to ensure that:
- a permit to work, supported by an excavation certificate, has been obtained before work
commences and that permit conditions are observed.
- all personnel wear the correct personal protective equipment at all times whilst undertaking
the work.
- all persons are properly supervised at all times whilst the work is taking place.
- the excavation is adequately protected against possible collapse.
- the excavation is properly protected, having proper regard to location, depth and public
accessibility.
- the safety aspects of the excavation work are properly addressed, and that any written
excavation plan is properly followed.

Excavation - Rev 2.1 Page 5 of 25


BSP – Excavation Module 05

CHAPTER 2 REQUIREMENTS

2.1 General Requirements

2.1.1 Definitions
An “excavation” is any operation which lowers or disturbs the existing ground level to a depth greater
than 0.3 metres. Examples of activities which are considered to be excavation works include excavation
of trenches or ditches, insertion of spikes, piling, use of crane outriggers on soft soil, or other similar
activities. Normal gardening is not considered to be excavation.
A “shallow excavation” is any excavation which lowers the existing ground level to a depth of less than
1.5 metres.
An “unsupported excavation” is an excavation where the sides of the work are battered (i.e. sloped or
raked) away from the bottom of the excavation to ground level, without support.
A “deep excavation” is any excavation which lowers the existing ground level to a depth of 1.5 metres or
more.
A “supported excavation” is an excavation where the sides of the work are supported by timber, steel,
concrete or other materials.
Hand digging” means excavation using spades and other hand tools, but does not include use of spikes,
pickaxes and the like, unless specifically permitted in writing.
Mechanical digging” means use of excavators, breakers, or any similar power assisted tools.
The "total working area" is the area which is used to get the work done, i.e. the location of the trenching,
the planned area where spoil is stockpiled and the area where heavy equipment travels.
"Dewatering" is the removal of water from the water table by means of a mechanical pumping unit in
order to minimise water in the excavation / soil."

2.1.2 Shallow Excavations


Unless unusual conditions are encountered, e.g. loose sand or the like, a shallow trench may usually be
excavated without being battered or supported (see Figure 1).

2.1.3 Unsupported Excavations


Unsupported excavations shall only be allowed:
- where the excavation depth does not exceed 1.5 metres,
- where the characteristics of the ground are known and
- when the behaviour of the soil can be accurately predicted.

Excavation - Rev 2.1 Page 6 of 25


BSP – Excavation Module 05

Figure 1 - Shallow Excavations: Trench Depth of 1.5m Maximum

The maximum angle of batter permitted, in optimum conditions for any unsupported excavation,
shall be 45 degrees from the horizontal.
Appendix 1 gives a set of guidelines for the estimation of ground conditions and relevant slope angles.
Dewatering is necessary if the water table is less than 0.5m from the bottom of the intended maximum
dept of the excavation (i.e <1.7m depth). A dewatering plan is to be submitted to the relevant Site
Supervisor for approval in these case.

2.1.4 Deep Excavations


All deep excavations shall be either battered, benched or shored (see Figures 2 and 5). A written
excavation plan and sketch must be prepared for all excavations greater than 1.5 metres in depth (see
Section 2.4). For excavations intended to be greater than 3 metres deep, the written excavation plan
must be approved by the BSC Project Engineer.

2.1.5 Deep Foundations


It is highly likely that dewatering will be necessary for deep foundations. Deep dewatering may have a
significant impact on the surrounding environment, e.g. subsidence of roads, buildings, pipelines. etc.

2.1.6 Mechanical Digging


Mechanical digging is not permitted unless the area to be excavated has been checked by use of a cable
locating tool and pilot trenches have been dug (see Sections 2.5 and 2.6).
The location of any encountered services shall be clearly marked with a red peg and the type of service
(cable or pipe) identified. A record, usually a drawing, shall be made showing the exact location of
encountered services and shall be submitted to the relevant Site Supervisor. Only after he is satisfied
that all necessary precautions have been taken shall mechanical digging proceed.
All mechanical digging equipment shall be suitable for the area classification of the plant and comply with
permit requirements.

2.1.7 Headings and Tunnels


Prior to commencement of the work, the contractor shall be provided with all available soil investigation
reports. Requirements for any additional soil investigation should be clearly specified in the contract.

Excavation - Rev 2.1 Page 7 of 25


BSP – Excavation Module 05

In addition to requiring an excavation plan, the following shall be detailed for all headings and tunnelling:
- the potential hazards which may be encountered.
- the specification and quality of materials.
- the excavation techniques which will be used.
- the level of workmanship which will be required.
- the level of supervision which will be required.
A detailed design shall be included for the full length of the heading or tunnel.
A competent civil engineer shall design the excavation plan for:
- any heading or tunnel which exceeds 2 metres in height or width, and
- any heading which is to be cut into rock.

Figure 2 - Trench Depth between 1.5 m and 3.0 m without Shoring

Excavation - Rev 2.1 Page 8 of 25


BSP – Excavation Module 05

2.2 Preparation and Permit Requirements


All excavation work on behalf of the Company involving disturbance of the ground, in buildings or
workshops and on demolition sites shall be carried out under a work permit issued in accordance with HSE
Standard Module 03- Permit To Work Procedure or the BLNG Permit To Work Manual, as appropriate.
No excavation may be carried out without the knowledge and approval of the Asset Holder or his
authorised representative.

2.3 Support System Design Requirements


The use of supports which are designed and specified on-site shall only be allowed for:
1. Double sided, narrow trench support, not exceeding 6 metres in depth in non-water bearing ground.
2. Shallow pits or shafts, not exceeding 6 metres in depth, in non-water bearing ground.
3. Where water problems have been eliminated by other means, and the limitations in 1) and 2) above
have not been exceeded.
All support requirements which do not fall within the specifications laid out above shall be specially
designed. This includes excavation adjacent to sectional foundations where standard excavation is not
possible.
Specialist advice shall be sought if there are any doubts as to the safety and sufficiency of any support
system which has been designed and specified on-site.
All support systems shall be designed to the Company approved standards (see Section 4 - References).

2.4 Written Excavation Plan


A written excavation plan must be prepared for all excavations intended to be greater than 1.5 metres
deep. This must be approved by the relevant Site Supervisor prior to application for any Permit to Work.
For excavations intended to be greater than 3 metres deep, the Site Supervisor should consult with and
gain written approval for the excavation plan from the Company Design Engineer or Senior Construction
Engineer.

2.4.1 General Considerations


The excavation plan and attached sketches should show that consideration has been given to the
following:
- purpose and proposed depth of the excavation.
- the location and nature of underground services.
- predicted nature of the ground to be excavated.
- expected presence or absence of water in the ground.
- potential for water to run into the excavation from the surface.
- support system design.
- stages at which timbering or sheet piling shall be placed in the excavation as work proceeds.
- presence of loose ‘pockets’ in what is otherwise firm, stable ground.
- nearness of any buildings or roads and the weight of traffic.
- whether any other important work is to be carried out adjacent to the proposed excavation.
- whether any materials are likely to be stacked nearby.
- stages of the excavation which are to be dug by machine or by hand tool.
- amount of room which will be needed for raising and lowering material in the course of work.
- whether the sides of the proposed excavation can be splayed to allow more freedom and make
wedging easier, the period that the excavation will be open, the maximun allowable trench length
and the weather that may be expected.
- whether the timbering or sheet piling can be removed safely as the backfilling proceeds.
- access to and egress from the excavation.
- emergency evacuation of the excavation.
- requirements for a gas testing programme.

Excavation - Rev 2.1 Page 9 of 25


BSP – Excavation Module 05

- arrangements for temporary site shelters at long-duration excavations in open areas.


The intended installation or removal of sheet piling can cause significant vibrations and thus affect
sensitive computer equipment. Information on the intended use of sheetpiling shall be submitted to
SCO/4 or LEN/6 Civil Section, as appropriate, for approval prior to commerncement of the work.

2.4.2 Preparation
The excavation plan shall show that checks have been made to locate:
- electric cables (including overhead cables if a mechanical excavator is to be used).
- gas, water and oil pipes.
- telephone, TV and radio cables.
- storm water, sewage and other underground transportation systems.
- the proximity of any foundations which may be affected by the excavation.
- roots of trees.
The excavation plan shall detail the relevant requirements to deal with the above obstructions in a safe
manner.

2.4.3 Work Planning


The excavation plan shall specify:
- permit and excavation certificate requirements.
- detailed description of the work to be done.
- duration of the excavation work and the period for which the excavation will be open.
- details of mechanical excavation areas.
- types of machinery to be used.
- details of hand digging areas.
- amount of materials (timber, sheet piling etc.).
- air and gas monitoring equipment.
- ventilation requirements and breathing equipment.
- methods of removal of water from the excavation.
- ladders.
- safety barriers, warning signs and fluorescent tape.
- fire extinguishers and first aid requirments.
- access points, gangways and bridges.
- lighting equipment.
- pumps and compressors.
- disposal of excavated soil/waste and transportation of sand for top-up trenches, including numbers
and types of vehicle required, and the route they will use to and from the excavation site.
- emergency arrangements.
The excavation plan shall show that cheeks have been made to ensure that the persons who will be
responsible for supervising the work at site are competent to do so.

2.5 Identification of Underground Services

2.5.1 Prior to Start of Work


The presence of any underground services is to be established prior to commencement of any
excavation works by taking the following steps:
- Examine Intergraph plots of underground services.
- The total working area shall be checked on underground service plans (held by TSM ,) and shall be
scanned using a Company -approved cable avoidance tool to ascertain the presence of electrical
cables and underground services.
- Obtain the necessary work permits, supported by the excavation certificate.

Excavation - Rev 2.1 Page 10 of 25


BSP – Excavation Module 05

2.5.2 Cable Avoidance Tool


Where mechanical digging is to be used, the use of a cable avoidance tool or similar, to identify possible
buried services, is mandatory.
- The use of mechanical diggers or graders or any other mechanical means for the removal of topsoil
or grass and vegetation, prior to digging pilot trenches, is strictly forbidden.
- Use of the cable locator shall be restricted to trained persons only.
- Underground services identified shall be marked with posts specifying the types and size of
services.
- Scanning shall not be limited to the trench width, but shall include any additional areas used for
drain points, battering, benching etc..
- Where the excavation is to be greater than 1 metre width, scan at both sides of the proposed
excavation, and at every 5 metres across the trench.

2.6 Pilot Trenching

2.6.1 Requirements for Pilot Trenches


Prior to use of mechanical digging, pilot trenches shall be dug in order to locate any underground
services.
Note that pilot trenching may not be required if there is clear indication that the presence of underground
services could be extremely unlikely e.g. in virgin jungle locations.
- Pilot trenches shall always be dug by hand in maximum depth steps of 1.5 metres, relative to the
adjacent ground level.
- The cable avoidance tool shall be used in conjunction with pilot trenching in order to locate
underground services. If any are detected, their whole length within the proposed excavation shall
be exposed by hand digging.
- Pilot trenching shall be carried out in accordance with either Method A or Method B described on the
following pages.
The proposed routeing for pilot trenching shall be the resposibility of the BSC Site Supervisor.

Excavation - Rev 2.1 Page 11 of 25


BSP – Excavation Module 05

Figure 3 - Pilot Trenching prior to Mechanical Excavation

2.6.3 Pilot Trenching – Method B (see Figure 4)


- Request up to date drawings of underground services in the vicinity of the proposed trench.
- Use a pipe or cable location tool to scan the proposed trench.
- Excavate longitudinal pilot trench by hand along the middle of the proposed trench to either the required
depth plus 0.3 metres, or to a maximum depth of 1.5 metres.
- Excavate transverse pilot trenches by hand every 5 metres, to the full width of the proposed excavation
and to the same depth as the main pilot trench.
- Repeat the scanning of the trench with the pipe or cable location tool.
- Mechanical excavation of the areas between the hand dug pilot trenches but not exceeding the proposed
maximum width of the trench may now proceed to a maximum depth of 1.2 meters below original ground
level.
- Where the proposed depth of the mechanical excavation exceeds 1.2 metres, further pilot trenching by
hand in maximum depth steps of 1.5 metres to a maximum depth of 3.0 metres must be repeated,
following the general methods above, prior to further mechanical excavation.
Note: It is suggested that Method B becomes uneconomic where the transverse pilot trench width exceeds 7
metres.

Excavation - Rev 2.1 Page 12 of 25


BSP – Excavation Module 05

Figure 4 - Pilot Trenching prior to Mechanical Excavation

2.7 Disposal of Spoil and Backfilling

2.7.1 Disposal of Soil


Unshored excavations:
Spoil may be disposed of along the sides of the excavation, provided that the distance to the edge of the
nearest portion of the spoil heap is not less than the final excavation depth (see Figure 1).
Shored excavations:
Spoil may be disposed of along the sides of the excavation, provided that the distance to the edge of the
nearest portion of the spoil heap is greater than 1 metre (see Figure 5).

2.7.2 Backfilling
Where backfilling using wheeled or tracked vehicles is to take place, or the excavation is in an area
where it is forseeable that vehicles may attempt to approach close to the excavation, stop boards should
be fitted at a distance of 1.2 metres from the excavation (see Figure 1).

2.8 Gas Testing


A gas testing programme shall be devised and maintained in circumstances where:
- work must be suspended if oxygen content is greater than 21%.
- there is a potential for oxygen deficient atmospheres to occur. Work must be suspended in
atmospheres where the oxygen content is 20% or less.
- the excavation takes place in ground which is known or suspected to be contaminated with oil or other
potentially flammable materials to such a degree that a flammable atmosphere may occur. Work must
be suspended if a Lower Flammable Limit (LFL) of 1% is exceeded.
- depending on the nature of the excavation and the location of supporting equipment, there is a
potential for a build up of toxic gases such as Carbon Monoxide (emitted from internal combustion
engines) or Hydrogen Sulphide (produced as a by-product of bacterial decay). Work must be
suspended if half of the Occupational Exposure Standard (O.E.S) or the Short Term Exposure Limit
(S.T.E.L.) for the toxic gas is reached (as specified in current edition of U.K. HSE “Guidance Note
EH40”).
The gas testing programme shall form part of the excavation plan.

Excavation - Rev 2.1 Page 13 of 25


BSP – Excavation Module 05

In circumstances where a hazardous atmosphere is found to exist, the work shall be suspended and the
excavation shall be treated as a “Confined Space” (see HSE Standard Module 07 - Confined Spaces).

2.9 Ventilation
In conjunction with the gas testing programme, excavations which have a potential for:
- oxygen deficient atmospheres,
- the build up of flammable gas mixtures or
- the build up of toxic gases to occur shall be artificially ventilated by means of air scoops or electric
blowers.
In general, internal combustion engines should not be used inside excavations, except on a short term
basis such as compaction machines for backfilling. Where internal combustion engines are used near the
edge of an excavation, care shall be taken to ensure that the exhaust fumes are directed away from the
excavation.
All electrically operated blower must be classified for the hazardous area in which they are to be used.

2.10 Lighting
Consideration should be given to illuminating excavations during the hours of darkness, especially where
excavations are outside the Company operating areas and to which the public may have access.
When work is in progress during the hours of darkness, or in deep excavations, shafts and tunnels,
sufficient lighting shall be provided to allow work to progress safely. Such lighting shall be suitable for the
environment in which it will be used.

2.11 Water Removal

2.11.1 Rainwater and Surface Water


Wherever surface ditches, streams etc. are incapable of draining off excess water, trenches shall be
constructed to carry the water away from the excavation.
The trenches shall be designed to cope with the maximum rainfall which may be expected whilst the
excavation is in progress. If unexpectedly high rainfall occurs during excavation operations, water
removal by manual or mechanical means shall be carried out.

2.11.2 Ground Water


Where the presence of ground water may create difficult working conditions or may endanger the
stability of the sides and/or floor of the excavation, the excavation shall be:
- surrounded by interlocking steel sheeting, an in-situ concrete diaphragm or a grout curtain to
prevent the water from entering the excavation, or,
- a ground de-watering programme shall be used to keep excavations clear of water whilst work
proceeds or to reduce the loads which bear on the earthworks support materials.
The ground de-watering programme shall be either by drainage, or by installing well-points around the
site and pumping out the water to lower the ground water table to below that of the excavation (see
Figures 1 and 2)
Before a ground de-watering programme is instigated, expert advice may need to be taken to establish:
- the feasibility of such a programme in the ground conditions pertaining to the excavation, and,
- that, as a result of de-watering no fine materials will be drawn from under adjacent structures with
consequent risk of settlement.

Excavation - Rev 2.1 Page 14 of 25


BSP – Excavation Module 05

Figure 5 - Trench Depth less than 3.0m with Shoring

2.12 Access and Barriers

2.12.1 Access
Access to all excavations shall be controlled and restricted to the minimum number of personnel required
for the performance of the work.
A safe means of access to and egress from the excavation shall be provided for personnel and
machinery.
Reflective or illuminated barriers shall be considered where the ambient lighting is inadequate. This is
mandatory in public areas and places with a high volume of pedestrian traffic.

2.12.2 Gangways and Bridges


Personnel Access
Safe means of access shall be provided where personnel are required to cross excavations. Any
gangway provided should be suitable for the intended task, and where the span or materials used
warrant it, should be approved by competent engineers as suitable for the intended task.
Where personnel may fall 2 metres or more, gangways shall:
- be fitted with guardrails and toeboards, and,
- be at least 0.46m wide for personnel access and 0.6m wide for personnel and materials access.
Material and Vehicular Access
Bridges shall be installed where plant and vehicles are required to cross excavations. All bridges shall be
specifically designed and constructed by competent engineers to ensure:
- the safety of drivers, vehicles and loads, and,

- that the edges of the excavation are not damaged or excessively loaded.
All bridges shall be clearly signposted to indicate the maximum permissible loads. Flashing lights shall
be installed on bridges that are to remain "swithed-on" at night.

Excavation - Rev 2.1 Page 15 of 25


BSP – Excavation Module 05

The construction of temporary bridges across excavations by the use of simple steel plates, scaffold
boards etc. is prohibited.

2.12.3 Barriers
All excavations, irrespective of the depth, shall be suitably barriered to restrict access by personnel not
associated with the excavation activities.
Barriers and stop blocks shall be erected at a suitable distance from the excavation to prevent:
- personnel or vehicular traffic from damaging the excavation and,
- accidental access to the excavation of personnel and equipment.
Additionally, the edges of all excavations, where personnel may fall more than 2 metres shall be
protected by rigid barriers or, alternatively, excavations shall be securely covered.
Non-rigid barriers may be used in areas where access for persons and transport is not required. The
materials used shall give an obvious warning by being immediately apparent and brightly coloured.
Wherever barriers are set back from the edge of the excavation, all access to the excavation shall be
confined to proper paths and roads and materials should not be stacked in the space between the
barriers and the edge of the excavation.

2.13 Checklists
The following checklists are contained in the appendices of this document:
Appendix 2 is a checklist to be followed at the design stage of an excavation plan.
Appendix 3 is a checklist to be followed prior to the commencement of excavation work.
Appendix 4 is a checklist to be followed on a regular basis whilst work is in progress.

Excavation - Rev 2.1 Page 16 of 25


BSP – Excavation Module 05

CHAPTER 3 PRECAUTIONS

3.1 General Precautions


Ensure that:
- the written excavation plan is followed at all times.
- the correct personal protective equipment is being worn.
- barriers are in place and are of an adequate construction.
- stops for lorries and dumpers are in place to prevent them falling into the trench.
- signs and warning lights are adequate for the purpose.
- tipping areas are clear.
- foot bridges and vehicle bridges are in a safe condition, supported and with rails in place.
- debris boards are in place.
- safe access and egress is maintained.
- the ground and water table is as assumed for the excavation plan.
- pumping operations do not remove fine particles from the soil and weaken the structure.
- wedges are secure on timbering and sheet piling and supports are safe during any compaction
operations.
- exhausts are positioned clear of the trench or excavation.
- trench sides are clear of hazards.
- the ground is not deteriorating during the work.
- proper slinging arrangements have been made for the removal of debris.
- visibility and lighting is adequate.
- the edges of the excavation are clear of soil and debris for a distance equivalent to the excavation
depth, or 1.0 metres in the case of shored excavations.
- work is suspended if an underground service is damaged. Broken cables and burst pipes must be
reported to the Asset Holder as soon as possible to obtain isolations and repairs. All incidents must
be reported in accordance with HSE Standard Module 30 - Incident Reporting and Investigation
Procedure.
Ensure that in deep trenches, pits or shafts, tests for oxygen deficiency, flammable gases and toxic gases
are carried out at least once per day, before work commences, and when work has stopped for 1 hour or
longer.

3.2 Failure Modes


In shallow and unsupported excavations ensure that the type of ground being excavated is not liable to the
failures which may occur in relatively shallow excavations.

3.2.1 Soft Clay


Ensure that unsupported or battered excavations in soft clays do not fail due to “rotation”.

3.2.2 Stiff Clay


Ensure that unsupported or battered excavations in stiff clays do not fail due to:
- the relief of lateral restraint which allows the top of the excavation to swell inwards, and/or,
- by rain or other surface water penetrating fissures at the surface and softening the clay (earth falls
are more frequent in wet weather).

3.2.3 Rock
Ensure that the rock being excavated in unsupported or battered rock excavations are not separated into
bedding planes, cleavage planes or fissures which form planes of weakness along which the rock may
slide.
Ensure that all loose rocks hanging to the excavation face are removed as the digging proceeds.

Excavation - Rev 2.1 Page 17 of 25


BSP – Excavation Module 05

Large volumes of heavy rock can move short distances very rapidly. Ensure that rock excavations are
supported, even for shallow excavations, if there is any doubt over the integrity of the rock face.

3.3 Support Systems

3.3.1 Supports Designed and Specified On-site


Where excavation supports are designed and specified on-site, ensure that:
- proper account has been taken of the ground conditions when deciding the method of support,
- the method of support complies with recognised good practice in all details.
Where proprietary systems are used, ensure that the installation is strictly in accordance with the
manufacturer’s instructions.
Ensure that the system of work to be adopted is explained in detail to all of the persons engaged in
placing or removing supports, and others who will be working in the excavation.
If practicable, the system of work should be illustrated with drawings or sketches, or with suitable
proprietary literature, together with checklists. Ensure that the method of work and instructions and
sketches provided are strictly adhered to.

3.3.2 Supports Designed by Specialist Designers


The instructions laid down by the specialist designers should be followed at all times whilst the
excavation is in progress.

3.4 Access
Ensure that safe means of access to and egress from excavations is provided and maintained throughout
the duration of the excavation.
Ensure that there is an easy means of escape in the event of an emergency.
Ensure that access to and from ladders is on firm ground and that the ladders are:
- placed in the supported part of the excavation.
- effectively secured, near to the top, to prevent slipping sideways, by lashing either to adjacent support
material or to stakes driven firmly into the ground for the purpose.

3.5 Barriers
Ensure that barriers are erected as soon as practicable after excavation commences. (Barriers may be
omitted, or moveable barriers may be placed, at specific points to allow access of personnel or the
movement of plant, equipment and materials.)
Ensure that:
- barriers or stop-blocks are fitted at all locations where cranes, dumpers, lorries, tippers etc.
manoeuvre close to the edge of the excavation.
- the edges of the excavation are protected from damage during vehicle manoeuvres.

3.6 Means of Escape


Ensure that the means of escape and rescue are provided and maintained throughout the duration of the
excavation activities.
Ensure that all personnel are instructed in the escape and rescue procedures which should be followed in
the event of an emergency.

3.7 Discovery of a Suspicious Object


On discovery of a suspicious object believed to be an explosive device, e.g. unexploded bomb, the
following action shall be taken immediately:
1. Stay clear - do not touch or try to move the object.
2. Notify FSE on telephone extensions 3269/4329 and VSL on 2999.

Excavation - Rev 2.1 Page 18 of 25


BSP – Excavation Module 05

3. Evacuate all personnel from the area following the normal evacuation procedure. Set up road barriers
if required. For an object up to 1.0 metre in length, an area with a radius of 100 metres from the
object should be evacuated. An area with a radius of 250 metres should be cleared for larger objects.
4. Using poles and flutter tape, set up a cordon round the evacuated area then notify management of the
action taken.
5. Prevent access to the cordonned-off area until FSE or the police arrive.
6. If the object is discovered in or near a company installation, all the services in the area shall be
isolated to minimise the effect of possible ruptures to pipelines and vessels. The decision to close in
hydrocarbon facilities shall be made at AU’s division head level.

Excavation - Rev 2.1 Page 19 of 25


BSP – Excavation Module 05

REFERENCES

BS-CP 2004 Code of Practice for Foundations


BS 4074 Specification for Metal Props and Struts
BS 5930 Code of Practice for Site Investigations
BS 6031 Code of Practice for Earthworks

U.K. Construction Industry Research and Information Association (CIRIA):


Technical Note 95 Proprietary Trench Support Systems
Report 97 Trenching Practice

U.K. Timber Research and Development Association:


Sizing of Timber Supports

U.K. HSE:
Guidance Booklet HS(G)47 – Avoiding Danger from Underground Services
Guidance Notes EH 40 – Toxic and Hazardous Substances

Excavation - Rev 2.1 Page 20 of 25


BSP – Excavation Module 05

Appendix 1 - Ground Conditions and Slopes


SAFE TEMPORARY
GROUND TYPE FIELD TESTS AND DESCRIPTIONS SLOPES
(See Notes)
(DEGREES FROM
HORIZONTAL)
GRANULAR 1. Particles visible BOULDERS (> 200mm) 35/45 (6) 30/40 (6)
2. Sand feels gritty COBBLES (60-200mm) 35/45 (6) 30/35 (6)
3. Visually assess proportions GRAVEL SAND (02-60mm) 30/40 10/30
of Boulders/Cobbles/Sand (0.06-2mm)
30/35 10/30
COHESIVE 1. Particles not visible SILT (0.002-0.06mm) 20/40 5/20
2. When damp silt and fine
sand are shaken in the hand,
water appears on the surface
3. Soft clay is easily moulded
by fingers CLAY (5) Trench Depth 1.2-3m 3.6m
4. Firm clay is moulded by Soft Clay 30/45 20/30 10/20
strong finger pressure
5. Stiff clay is indented by Firm Clay 35/45 30/40 20/25
strong finger pressure
6. Fissure clay should be
examined for its structure Stiff Clay 40/45 35/45 25/35
See (6) & (7)
1. Rotten or rotting vegetable PEAT (black, Soft non-fibrous 10/20 5/10
matter grey or brown
clayey or sandy)
2. Smell of decay
Firm non-fibrous 15/25 10/15
3. Fibrous or non-fibrous
Firm fibrous 35/40 (6) 20/25 (6)
4. ‘Soft’, ‘Firm’ or ‘Stiff’
Stiff fibrous 35/45 (6) (7) 25/35 (6) (7)
FILL 1. All types of man-placed As main soil According to According to
material type (eg clay, category above category above
sand, gravel
2. Note constituents including
etc.)
unnatural inclusions
ROCK 1. Mass stronger than the As appropriate Check Check orientation of
above soil types to the orientation of planes
predominant planes
2. Important to note
constituents and
cementation, structure and
characteristics
orientation (fissures, joints,
bedding, layers etc.)
3. Closely joined rock may act
as “granular” and weak
weathered rock as “clay”
GROUNDWATER 1. Levels of water encountered Full description See Note 1 (d) See Note 1 (d)
necessary
2. Rate of entry
3. Standing level
4. Flood conditions

THE SUGGESTED SLOPE ANGLES ARE FOR GUIDANCE PURPOSES ONLY – SEE NOTES.

Excavation - Rev 2.1 Page 21 of 25


BSP – Excavation Module 05

NOTES ON GROUND CONDITIONS:


1. These are GUIDE figures to slopes based on and subject to:
a) Temporary conditions (i.e. generally 1 to 14 days).
b) Field safety and experience.
c) A safety limit of 45 degrees (but see Note 6 below).
d) Water seepage can cause washout and undermining.

2. Dry’ site: minor or no seepage from excavated faces. Minor or no surface run off.

3. Wet’ site: submerged or widespread seepage from excavated faces.

4. The behaviour of soils is influenced by the grading, particle size, shape and density. In mixed soils
the maximum grain size of the smallest 15 percent by weight of the grading tends to characterise
the soil.
5. Normally consolidated clays are usually stronger within a few metres of ground level due to
desiccation. However, the clay crust is fissured for the same reason (note the fissures may not be
visible) and is seldom more than 4 metres deep.
Due to the fissuring, the face becomes unstable and lumps fall into the excavation. In deeper
excavations there is a risk of toe failure due to underlying softer clay. The suggested slopes are
intended to avoid danger to workers from these risks and are offered as a guide only.
6. Flatter or steeper slopes may be applicable or required subject to the evidence on:
a) Incipient (structural) failure planes
b) Safety precautions against small or large falling fragments

Excavation - Rev 2.1 Page 22 of 25


BSP – Excavation Module 05

Appendix 2 - Checklist for Excavation Plan


The following information will be required in order to determine the method of excavation and the need
for support. In addition, in the case of trench work in particular, what has to go into the trench or
excavation will be important. The handling of such items may well affect the form of support that can
be used. The answers to the following questions need to be considered before any decisions can be
taken.
1. What are the soil types and groundwater conditions?

2. Is there any knowledge of work carried out previously in the area?

3. Is the excavation adjacent to existing structures or roads?

4. Are there any obstructions to the line of the excavation? (e.g. public utility mains or cables, sewers,
industrial mains, overhead cables, or limited clearance on the line of the excavation which may
restrict choice of excavating equipment?

5. Has the condition of adjacent buildings been recorded? (e.g. cracks etc.)

6 Is there any risk of surface flooding whilst the work is being carried out? Is flooding from services
possible?

7. Is the excavation within the Company operating area, or are special precautions necessary to
protect the public?

8. If the excavation is a pipe trench, what are the maximum depths to be supported? What size and
length of pipe have to be handled? Can pipes be tested in short lengths or does the specification
require testing of greater lengths?

9. In the case of wide excavations, what will be the implications of the support system to the
permanent work – and vice-versa?

10.What surcharge loads are likely to arise?

11.Will the support method involve vibration? Will it affect the stability of the excavation and/or
adjacent buildings?

12.Is it possible to formulate a safe excavation plan with the information available, or will other
information be required?

13.Are there sufficient supports?

14. Is there a dewatering and alarm system?

Excavation - Rev 2.1 Page 23 of 25


BSP – Excavation Module 05

Appendix 3 - Checklist Prior to Start of Work


1. Is the person directly supervising the work, fully experienced and competent in the support of
excavations?

2. Have all services been located and proved as to position?

3. Are the necessary drawings or sketches (where on-site developed support designs are to be used)
available? Have the operatives been properly briefed and instructed as to what is required of them?

4. Are all materials necessary available on site and in accordance with the drawings/sketches?

5. Has all machinery to be used in the excavation been certified as fit for use and is it suitable for the
work it will be undertaking?

6. What arrangements are required with regard to site security (especially for those sites where
members of the public may enter the area)?

7. Is there adequate working space for the proposed plant and equipment to be used?

8. Is there adequate room for spoil heaps and are they positioned more than 1.5 metres from the edge
of the excavation?

9. Will bridges or gangways be needed? If so, are the materials and equipment ready?

10.Are there sufficient ladders available for access to and from the excavation?

11.Will lighting be required?

12.Is all the appropriate personal protective equipment available for personnel?

13.Are all personnel competent to carry out this type of excavation without additional training and/or
supervision?

14. Has the Excavation Permit bear approval ?

Excavation - Rev 2.1 Page 24 of 25


BSP – Excavation Module 05

Appendix 4 - Checklist Whilst Work is in Progress


The following list covers only the main points which need to be checked when inspections and
examinations are being carried out whilst work is in progress.
1. Is access to and from the work face sufficient and secure from danger?
2. Are all working faces secure, wedges tight and support material free from damage?

3. Is there any sign of movement or deflection in the support system?

4. Is the soil condition as predicted? If not, what action should be taken?

5. Are the spoil heaps being properly maintained and positioned more than 1.5 metres from the edge
of the excavation?

6. Are pipes, bricks and other materials kept well clear from the edge of the excavation so that there is
no risk of them falling into the excavation due to accidental dislodgment?

7. Is all plant and machinery kept well clear from the edge of the excavation so that there is no risk of
vibration damaging the support?

8. Are the drawings/sketches being properly followed in installing the support? (Particularly the
spacing of walings and struts.)

9. Are the walings and struts, or proprietary equipment, supported against falling downward – by
hangers, puncheons, lip blocks etc.?

10.Is there any risk of flammable or toxic gases entering the excavation?

11.Is there any risk of an oxygen deficient atmosphere occurring inside the excavation?

12.Has the risk of flooding been properly assessed?

13.Is resuscitation equipment, and a person trained in its use, available?

14.Have all personnel been instructed in the evacuation procedure for the excavation, and the correct
rescue procedure to follow, if someone is overcome by toxic or asphyxiating gases.

15.Have all support materials been checked before installation in the excavation? In particular are the
correct pins provided in the trench struts?

16.Is the work adequately barriered off? Have all the relevant safety signs been posted at entry/exit
points? Is the work adequately barriered or covered and lit at night? Are watchmen needed?

17.Are personnel wearing the proper personal protective equipment? Are any other items of PPE
required?

18.In pits, shafts and tunnels, in particular, is adequate lighting provided? Is the temporary lighting
system safe and free from damage?

19.Are gangways and bridges properly designed and constructed and in a good state of repair? Are
they the correct width? Do they have the correct guardrails and toeboards?

20.Where backfilling is required are stop blocks fitted?

21.Is the support withdrawal part of the excavation plan still feasible? Are the persons carrying out
the support withdrawal competent to carry out the work and have they been properly instructed?

22.Where pumping is taking place, is a proper check being kept to ensure that fine material is not
being withdrawn from behind the support system?

23.Are the operatives all working in a safe and competent manner?

24.Is the excavation plan being followed? Is it working or does it require some amendment so that the
task can be performed more safely? Do you require expert assistance in any of the tasks which are
being performed?

25.DOES THE SITE HAVE THE PROPER ONGOING SUPERVISION WHICH IS ESSENTIAL TO
MAINTAIN A SAFE PLACE OF WORK?

Excavation - Rev 2.1 Page 25 of 25

Potrebbero piacerti anche