Sembawang Engineers & Constructors Pte Ltd

460 Alexandra Road, #27-01 PSA Building Singapore 119963


T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone

CONSTRUCTION OF REINFORCED CONCRETE (RC) WORKS AT


CASINO – METHOD OF B2M SLAB & BEAM CONSTRUCTION

Rev Date Description Prepared Checked Approved


# By By By
A

Upul C Chee H L Dennis K


Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone

CONTENTS
1. Scope of work

2. Construction Casting Sequence for B2M Beam & Slab

3. Construction of B2M

4. PE Calculation

5. Concrete Work

6. Project organization

7. Health & Safety Risks and Control

8. Access / Egress

9. Lighting

10. Hazardous Materials & Substances

11. Waste Management

12. Equipment & Machinery

13. Special Control Measures

14. Addendum-Additional UPVC Pipes for grouting of top-down column head.

Appendix I : PE Calculation
Appendix ii ; Risk Assessment
Appendix iii Lifting
Appendix iv Lighting
Appendix v Typical Construction Joint

Page 1 of 2
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
1. SCOPE Of WORK
Construction of R/C slab and walls at B2M level for Marina Bay Sands North Podium
Casino comprising as such;

1) Install rebar work

2) Install formwork.

3) Casting of Concrete.

2. Construction Casting Sequence for B2M Beam & Slab

Casting Estimate Volume


Remark
Sequence (m3)

1 300

2 300

3 250

4 250

5 300

6 350

7 350

8 250

9 150

10 500

11 550

12 250
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone

Lay out for casting Sequence- Beams


Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone

2 4

3
1

5 6

Lay out for casting Sequence- Topping-up slab


Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone

3. Construction of B2M

3.1 Construction of RC Beam with PC T Beam or PC Slab

1) Issue of Bar Bend Schedule.(Order cut&bend re-bar from Natseel.)

2) Receive cut & bend bar and check deliver order.

3) Set up reference grid line and reference level by Surveyor(With reference


to the Grid Line Setting-out plan Dwg noAED308_DD_TC_PJW_0901 E).

4) Laying lean concrete.(Concrete G20)

5) Fabricated formwork for the side of beam piece by piece on site.

6) Set up detailed set out beam as per to the approved shop drawing.

7) Laying 12mm plywood at the top of lean concrete set out column as per
drawing.

8) Put up starter bar and coupler (E-Splice for top-down & Dextra for D-Wall
joint)of column.
Starter bar & Coupler

12mm plywood

Plywood form
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone

9) Install the beam bars layer by layer.

10) Install Starter bar system [or coupler system/ Styrofoam] will be
embedded for following slab & beam at Construction Joint (for vertical
element)

11) Install hi-rib for construction joint.

12) Close fabricated formwork on the following,

12mm Plywood

13) Dismantle formwork and patch the hole of tied rod using non-shrink grout.

14) Install T beam or hollow core by other.

15) Lay re-bar or BRC (as per to the approved drawing) and cast concrete
topping.
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
3.2 Construction of RC Beam with RC Slab

1) Issue Bar Bend Schedule. (Cut & Bend re-bar order form Natsteel)

2) Receive cut & bend bar and check deliver order.

3) Set up reference grid line and reference level by Surveyor(With reference to


the grid line setting-out plan Dwg.no. AED308_DD_TC_PJW_0901 E).

4) Laying lean concrete (Concrete G20).

5) Fabricated formwork for the side of beam piece by piece on site.

6) Set up detailed set out beam as per to the approved shop drawing.

7) Laying 12mm plywood at the top of lean concrete set out column as drawing.

8) Put starter bar and coupler (E-Splice for top-down & Dextra for D-Wall
joint)of column into plywood and plyform.

Starter bar & Coupler

12mm plywood

Plyfoam provided
by sembawang.
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
9) Install the beam bars layer by layer.

10) Install Starter bar system [or coupler system/ Styrofoam] will be embedded
for following slab & beam at Construction Joint (for vertical element)

11) Install hi-rib for construction joint.

12) Close fabricated formwork on the following,

13) Dismantle formwork and patch the hole of tied rod using non-shrink grout.

14) Install T beam or hollow core by other.

15) Lay re-bar or BRC (as per to the approved drawing) and cast concrete
topping.
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
3.3 Construction of Permanent R/C Capping Beam :
1) As-built survey to be done before access.

2) As-built survey report to be submitted and any remedial work to be done


by D-wall contractor if necessary.

3) Safety facility to be erected before any construction activity

4) Excavation of ground for capping beam formation to a approved slope and


the excavated soil to be stocked for backfilling.

5) Demarcation to the Diaphragm wall surface to verify cut-off level.

6) Hacking and removal of debris from constructed D-wall.

7) Straightening of starter bar from D-wall.

8) Setting out of capping beam profile.

9) Fabricate capping beam reinforcement[1st 12 m length section]

10) Beam / Slab location and level to be marked onto capping beam
reinforcement rebar

11) Starter bar installation using coupler (Dextra for D-Wall joint) to be done

12) Formwork erection for capping beam.

13) Cast capping beam by direct discharge from concrete truck either by
concrete bucket using mobile crane whichever workable.

14) Curing will be done after placing concrete to capping beam.

15) Proceed with fabrication of capping beam reinforcement for next 12 length
section.

16) Dismantle formwork for cast capping beam.

17) Formwork erection for capping beam.


Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
18) Cast capping beam by direct discharge from concrete truck either by
concrete bucket using mobile crane whichever workable

19) Procedure for following section to be repeated

12mm Plywood

16) Dismantle formwork and patch the hole of tied rod using no-shrink grout.

17) Backfill and compact soil( by other sub-con)

18) Lay lean concrete

19) Laying 12mm plywood at the top of lean concrete.

20) Tie rebar layer by layer.

21) Cast concrete for RC slab.


Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
4. PE CALCULATION

Appendix i

5. CONCRETE WORK

1) Zone Plan for Casino as per attached plan under item no.2.

2) Boom Concrete Pumps are to use in casino zone.

3) 4 to 6 workers to carry out the hose of each boom concrete pump. 2 to 4


vibrators are to be allocated to each casting area. 2 to 4 concreters are to
level concrete. If any area required to power float, 4 to 6 concreters are to
level concrete, and 2 nos. power float machine are to be allocated to each
casting area.

4) RC wall are to be cast by 200mm to 400mm layer by layer. More than


600mm thk RC slab are to be cast by layer by layer.

5) Vibrators shall be qualified or training workers.

6) Before big areas for slab & beam casting, site manager or supervisor shall
orally talk workers casting arrangement.

7) After casting, curing concrete.

Apply approved curing compound to concrete slab, wall or column surface


right after striking formwork.(Curing compound submitted under different
submission)

8) Post concrete inspection.


Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone

1. Project Organization

SEC-Project Director
Ng Seng Yoong

SEC-DY Project CEC-Project Director


Director Dennis Khoo Li Yun Zhang

SEC-Project Manager
Chee Heng Leong

SEC-Construction Project Manager Head Office


Manager Julian Ding Fu Li Gang Supporting

SEC-Site Engineer
Rayan / Gan Kok

SEC-Site Supervisor/s

Zone 1 Zone 2 Safety Supervisor Purchaser


Ji Hai Bing Xu Zheng Wen Chew Van Yin Cao Jin

Supervisor Supervisor Scaffolding Supervisor Labour Affairs


Formwork Formwork Li Yun Chao Tang Xuan
Concreting Concreting
Re-Bar/BBS Re-Bar/BBS

Worker Team Worker Team Formwork Supervisor Scaffolding Design


Li Yunchao Wen Jianbing

Page 1 of 2
ov8 9,4

ildingand
Bu Constructionf,uth
ority

I
t,

having satisfie,lthereguirementsuf ttrecoursaof st'!y was


;I awardcdthe
/{1i\
otilllP :

'
, .,; .1",1,1
D E P U ' fv C H t e r E R E C U t , i V e O F F t c E R
. I tnda*rlryfu,,&pnfitl
' hti blingaad Avtlyrvy
torrnt:rl,ftoll.
:
:.-''-

rfir
/{*41^1"_
*
n"'t-
fenilicrn\l$.f'SCdlitmg6' S D N t C Tl V
, IA r { ^ c E R
Corvyvcrlvn
M*rr.y ftrlri rg lt *innt
i
2 [)+cornb*v2004 tI
7 1 r r , , . ' , i , ; l ' . i , r , , , i , . .1 , , j 1 , ,.;, 1 . , , . r i
' t,l

'I

:
9NIUSTINISNS
Cg3 z c 6 z 9 l z gx v d T 9 2 T zt 0 0 z l 0 / 9 0
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone

7. Health & Safety risks and controls


All related workers will be briefed on work method statement and risk
assessment before start work.

a) Risk assessment of RC work in respect to overall scope of works -


Appendix ii

b) Lifting Plan – Appendix iii

8. Access / Egress
i. Working platform of at least 500mm in width (or 2 standard planks) shall
be provided and secured.
ii. Proper step ladders shall be provided for any ingress and egress.
iii. All workers working at height greater than 2 meter shall wear full body
harness secured to proper anchorage points and working at heights should
adhere to the Permit-to-Work at Heights requirements as well.
iv. Working platform to provide pipe handrail at 1.1m upper & 500mm lower.

9. Lighting
Maintaining sufficient and suitable lighting, whether natural or artificial, at
locations in which persons are at work is important. Sembawang will provide
400 to 1000volt flood light on the decking in various locations and also we
will provide mobile generator with spotlights to the work site for localized
illumination for night work.
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
Additional spotlight will be reserved in the event that any of the used lights
break down. Once the utilization of reserved lights in place, the damaged
ones shall be sent for servicing and repair as soon as possible.
The general Lighting plan are attached in Appendix iv

10. Hazardous materials & substances

No hazardous material and substances are used.

11. Waste Management


1) Excess concrete will be sent back to batching plant
2) Rubbish bin will be allocated in specified location
3) Recycling materials & refuse will be stored separately
4) Construction waste will be disposed by licensed waste collector
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
12. Equipment & Machinery
1) Mobile Crane, Crawler Crane for shifting rebars, formwork etc.
2) Broom Pump.
3) Air Compressor.
4) Concrete bucket.
5) Diesel Engine.
6) Concrete Vibrator (YAMA - S'pore) c/w Hose/Shaft/Twin Claw Assy.
7) Bending Machine W/Diesel Engine with 4 Pcs of Bending Nuts & Starter.
8) Cutting Machine W/Diesel Engine with 4 Pcs of Bending Nuts & Starter.
9) Oxygen Acetylene Gas Cylinder & Cutter.
10) Drill-Impact Drill Bosch GSB16-RE.
11) Circular Saw (C9 HITACHI).
12) "Hilti" TE56 combi hammers.
13) "Hilti" TE706-AVR breaker.
(Necessary certificates/Permits to be submitted prior to start work)
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone

13. Special control measures


1) Approval of permit-to work for tower crane lifting operation as well as
working at height will be submitted and approved before start work.
2) The following general control measures against safety, Environment and
Quality shall be required for our scope of work

• Proper PPE must be worn at all time.

• Toolbox meeting will be arranged for every morning before start of


work.

• Regular maintenance is carried out to the tools and equipment in


accordance to manufactures recommendation to ensure that they are in
good and safe working condition.

• All workers are taught and trained with basic safety knowledge by
using proper personnel protective equipment while working.

• Only trained and certified operators are allowed to operate the crane.
All the area will be kept tidy and proper rubbish bin will be provided.

• Supervisor’s inspection will be carried out at every stages and the


quality of work will be assured on each stages.
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone

Appendix i
PE Calculation
l
tI
wRxt^€fir:fglr4H
WR" CONSUI T NTS
203Henderson rd, #04-03,Hendersonindustrialpark
Singapore159546
Tel:(65)627
27071 Fa><:(65)62787071Email:wrxconsultants@wx.com.sg

PROJECT:
PROPOSEDERECTIONOF TIIE MARINA BAY SANDS
INTEGRATEDRESORTAT BAYFRONT AVENUE

SIDE FORMWORKDESIGN
FOR 3.2mx1.3m(D)
BEAM

Contractor: CEC ENGfNEERING Pte Ltd

28 APR. 2008
Wru(CONSULTANTS
DESIGNCALCULATION PageNo:

CheckedBy: WRX Date: 28lAbr/08

l.Godesof Practlce
CP23 :2000 FormWork
BS5950:2000 StructuralUseof Steelworkin Building
SSCPT: StructuralUseof Timber
BS6399 DesignLoadingfor Buildings
2. Uslng groupB commondgrade Timber
. Allowable
flexurestress: 12.41Nlmm2
Allowableshearstress: 1.17N/mm2
Allowablecompression stress: 10.00N/mm2
Modulusof elasticity: 11700N/mm2
Plywood:Allowablebendingstress: 12.41Nlmm2
Modulus,E : 7000N/mm2
3. Steelgrade5275
Modulusof elasticity: 206000N/mm2
4. Deslgnedloadlngs:
a. Liveload(dudng =
concreting) 1.50kN/m2
b. Selfweightof formwork=
0.40kN/m2
c. Wetconcretedensig = 25 kN/m3
5. DeslgnData
3200mm
GaseI
Max.Lateral
Pressurc f{= 1.30m
Baseon CP23:2000,cl 3.4.3- horizontalloads:

Themax.lateralpressureexertedby the plasticconcreteshatlbe the smallerof following:

a)Pmaxl= p/toox [ct J R + C 2 K . / ( H - C l J R ) l o r


= ph/100
b) Pmax2
j,%
wrlj
11=( 36I (28+rc712= 0.67 nuts
Cl= 1.00 C2= 0.30
3875
GAPS
H= 1.30m R= 1.00m/hr

l= 0.60m 2500kg/m3

Pm4<1= 27.7 kNlm2

Pmafl,= 15.0 kN/m2


WRX CONSULTANTS
DESIGNCALCULATION PageNo:

marinasands Structure:
LJJ Date: 28lAprl08 CheckedBy: WRX Date:_,,!![pgr08

So,Themax.lateralpressureto the formworkis 15.0kN/m2

Thisforcewill betransferto the sideform.

Themax.design
load 15.0
Total 15.0kN/m2

Plvwood Desiqn 18 mm thk.

Spacingof runners, s = 200 mm


Assumecontinuous span,
Modulus,Z= 54000mm3
Mmax= 0.24kNm
Max.Reaction = 3.90kN
CheckBending:
fbc = 4.44 Nlmm2<Limit: 12.41N/mm2 OK
CheckDeflection:
6l= 0.09 mm < Limit: 3.00mm OK
i.e. Plywoodis adequate

Runner I
Spacingof runners,s = 200 mm

(Section
Runners: to detail) 25 75 depth
SPan= 0.650m
Load/runner = 3.00kN/m
, Modulus,Z = 15410mm3
Mmax= 0.16kNm
Max.shearforce= 1.2kN

l= 1 5 4 1 0m m 3
[= 1360mm2
l= 520000mm4

CheckBending:
fbc = 10.28N/mm2 12.4N/mm2 OK
CheckShear:
ShearStress= 0.90N/mm2 1.17N/mm2 OK
CheckDeflection:
6l = 1 . 1 5m m 2.60mm OK

Beam:
Using RHS
2nos. 50x100x2.3mm @clc 650 mm
SPan= 1 . 5 0m
=
Load/runner 14.63kN
" Design= =
1.4DL+1.6LL 22.82kN
Mmax = 4.63kNm
Max.shearforce= 1 1 . 4k N
fl= 50 mm ry= 2'1 cm
II
WRXCONSULTANTS
I
I
i
DESIGNCALCULATION PageNo:
I

Date: 28/Apr/08
p= 100mm
l= 2.3 mm

Forcoldformsect. b=B-St= 38.5mm


d=D-St= 82 mm

b/t= 16.7
d/t= 35.7
Sectionclass1
Sx= 21 cm3
h= 17.0cm3
fi= 6.55cm2
l= 84.8cm4
momentcapacity: 1.2py7t= 11.22 4.63 kNm OK
FY*Sx= 11.55 4.63 kNm OK
Shear 144.1kN> 11.4 kN OK
Deflection:g =(5n4+2n2+1 =
)pL3/3g4n3Et 3.08mm U270= 5.56 OK
DESIGN OFTIEROD
TENSITE FORCEOFTIE ROD F = 14.625KN
TENSILE FORCEOFTtEROD(fsctor) 1.5F = 11.938KN
use R15steeltie rod
tensile -safetyload(asperlabtestreport)
capacity P 90 KN oK!

Deslgnof LateralBraclng
50xl00 mmlocaltimbercompression capacity: v 50.0 kN
2.5Yoof vertlcalload F 2.6 kN/m
Forcealongthebracing F1 3.7 kN/m
Spacingof LateralBracing 13600mm
say s 1500mm 'oKl
deslgnbasebolt on formwork bottom
max.shearon bolt =1.5F12 10.97 kN/m

Provideconcretenail O3.7
baseon testingreport
Shearcapacityperbolt % 12.33kN
requiredspacingof nail c 1686 mm
. say 500 mm oKt
designbaseconnectlonof lateralbracing
max.shearon bolt =1.6F1x0.707 4.16 kN/m
Provideconcretenail O3.7
Shearcapacityperbolt % 12.33kN
requiredspacingof nail c 2965 mm
say 500 mm oKl
use50x100timberto supportthe lateralbracing
max.pointloaddueto compressof eachbracing f= 4.16 kN

ffi
ma)<.moment M= 0.693 kNm
sec'tion
modulus Z= 62070 mm3
bendingstress Py= 11.17N/mm2 oKl
shearstress v= 0.34 KN oKl

fir@S
l-
$;i
'F rg.
; f!.
g fri
: tEl
Frl
J
F
=
ts *a
-z
I
xa
a z
t o.
^e o E
a<
=F t5
o EE r
x
- o
J

Q -
=t
, 9
- g _fi
g=
F
J z Zg
--f
F
x
€E
5F
z6 q^
J
8
z
HF -
H+
sR
-,2
>=
H*-
g ^
J
-z E ==
>tH
.E E5 o g.t
H
-
^Fs
=Jo
*
E *!E t
E =gE 4
E FgE
q *
g er6 -
-
'-
g E F
a: F: qJ
F
-
F EF
,5e E Eg
E =Fs
F
68*RB
5H€€E
F
'llo E
4 =
a
!
z,l =l
Hl
FI
lr)l
El.cS
()l
e F(d o
! al
=
x 3l EEa =
=lsii=i
oo o ,,{ tl
!t
!<l J
&l
^l q Edq
I -l E =l F=9-q3
Elqd*==
!g
=l
EI
,9 * rrl =E8*E
''I = I
0
9a c
F
E
E

g
=l
<l
I

=l=;5si
-l SHSFE
@
e.Jl : N
I
r'rl E
><t o.t =
.!
t-il >-l =
-! FI
D ! ,a
'I
!tt
.{ . t
' '.!
zl
x\J-\
t?\ b*<
crrCI
\? q,E
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone

Appendix ii
Risk Assessment
RISK ASSESSMENT FORM
Company: CEC Engineering Pte Ltd Work Title: Marina Bay Sands North Podiun Casino Zone
Process/ Location: Marina Bay Sands Tower 2 Conducted by: Li Yun Zhang-DGM, Fu Li Gang-PM,Xu Zheng Wen-SM,Ji Hai P
Approved by: Cai Wei Xin, General Manager, 26/05/08 (Names, designations) (Date)
(Name, designation)(Date)
Reviewed by Sembawang: Chau T.G. - Safety Manager Last Review Date: 2/5/2008 Next Review Date:
(Names, Designations)( Date) Upul Chandrasiri - CM

1. Hazard Identification 2. Risk Evaluation 3. Risk Control


1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d

Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app

1 Sub-sturcture

Falling into unbarricaded


1.1 Base slab construction
excavated pit
Injury to worker Cordon off the excavated pit 3 2 LR Provide the warning sign 3 2 LR Site S

Soil collapse from insufficient Injury to worker /


1.2 Base slab construction
shoring/slope protection
Cordon off the danger area 3 2 LR Provide the warning sign 3 2 LR Site S
damage to resources

If any one found any place exist


outbreak of dengue
water ponding, please report to site
1.3 Base slab construction Stagnant water in excavated pit fever / malaria / Do housekeeping daily 2 4 MR spuervisor and then supervisor 2 3 LR Site S
mosquito
must report to Main Contractor.

Disposal of waste debris /


1.4 Base slab construction
concrete waste
Pollution increased Do housekeeping daily 3 2 LR View by site supervisor 3 2 LR Site S

Ear injury by the Remind workers & give workers


Cleaning before cast Ear injury
caution
2 4 MR Wear proper ear plug 2 3 LR Site S
voice of machine
1.5 concrete by air
compressor Remind workers & give workers
Eyes injury Can cause eyes injury
caution
2 4 MR Wear proper protective goggles 2 3 LR Site S
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d

Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app

2 Rebar Installation
Falling of materials due to Use only tested gears with valid Supervisor /Lifting supervisor / Lifting
failure of lifting gears
Injury / Death
certs.
4 2 MR Rigger must check before use
4 2 MR
Site S
Delivery of materials
to working area by Falling of materials due to Deploy qualified rigger Lifting
improper rigging
Injury / Death
signalman for lifting
4 4 HR Rigger must rigging properly 4 3 MR
2.1 lorry crane and Site S
hositing material to Use cargo net to wrap while
working area Falling of materials due to Supervisor /Lifting supervisor / Lifting
breaking of pallets
Injury / Death hoisting loose materials like 4 4 HR Rigger must check before use
4 3 MR
Site S
rings or bar chairs.

Hand injury during Wear hand glove/Use 3m long Lifting


Loading/Unloading
tag line
2 4 MR Only rigger to do 2 3 LR
lifting operation Site S
Hoisting rebar by
2.2 mobile crane/tower Use only tested gears with valid
Worker can be
crane certs, and Lifting Supervisor, Supervisor /Lifting supervisor / Lifting
Falling Object injured by falling
signal men, riggers must attend
4 4 HR Rigger must check before use
4 3 MR
Site S
rebar
during lifting proceeding.

Workers’ fingers may


be injured by bars or Give workers caution when
Injury workers fingers Provide safety hand glove 3 4 MR conduct tool box meeting.
3 3 MR Site S
bend and cutter
machine

To use rod to make


Give workers caution when
2.3 To cut & bend rebar Injury workers fingers way for suspended Provide safety hand glove 3 4 MR conduct tool box meeting.
3 3 MR Site S
top & bottom rebar

Workers’ feet may be


Provide safety shoes, and signal
injured by bars when
Bars falling Wear & use PPE 3 4 MR man shall provide signal to crane 2 3 LR Site S
they hang up bars if
operator.
very heavy

Complete working platform to be


check whether eligible. Workers
Provide proper working and must wear & anchor safety belt or
Falling of persons during Safety
installation of rebars
Injury / Death walking platform of at least 4 4 HR safety harness. Above 4m height 4 3 MR
Site S
500mm wide. Scaffolds to be erected by qualified
2.4 Fixing rebar at height and approved scaffolding
contractors.

Hand injuries during


To use rod to make way for All steel bender must wear hand Safety
installation of rebars eg. for Injury
suspended top & bottom rebar
3 4 MR glove
2 4 MR
Site S
column
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d

Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app

Tie rebar on slab or Leg injury in void between Leg injury during Safety
2.5
bars
Wear & use PPE 3 4 MR Give workers caution 3 4 MR
beam walk on top of bars Site S

Placing rebar on Follow load chart indicated on Safety


2.6 Over loading Platform give way
platform
3 4 MR Spread load evenly on platform 3 4 MR
platform Site S

Serious injury or Anchor bolt fully insert, use Follow safe work procedure & Safety
Fixing rebar for wall Fall from height
safety PPE
4 4 HR provide proper working platform
4 3 MR
death Site S
2.7 or column on working
platform Serious injury or Install toe board, barricade the To clear loose materials on the Safety
Falling Object
area right below
3 4 MR platform
3 4 MR
death Site S
Hand injury during Cordon off the work area & Safety
2.8 Making rebar cage Fall down/ Hand injury Wear & use PPE 3 4 MR provide the warning sign
3 4 MR
lifting operation Site S

Use only tested gears with valid


Serious injury or
Hoisting rebar cage Rebar cage fall down Cage certs, and Lifting Supervisor, Supervisor /Lifting supervisor / Safety
2.9
give way
death by falling bars
signal men, riggers must attend
4 4 HR Rigger must check before use
4 3 MR
and installation Site S
cage
during lifting proceeding.

Provide flash back arrestors both Safety


Fire hazard Injury / Death
at cylinder outlet and torch inlet.
4 2 MR Safety supervisor must check 4 2 MR
Site S
Use oxygen and
2.10 Provide fire extinguishers at the Safety
acetylene to cut rebar Fire hazard Injury / Death 4 2 MR Apply Hot Work Permit 4 2 MR
location of hotwork Site S
Injury to eyes during gas Wear protective goggles while Safety
cutting works
Injury / Death
cutting.
4 2 MR Safety supervisor must check 4 2 MR
Site S

Use only tested gears with valid


Falling of materials due to certs, and Lifting Supervisor, Supervisor /Lifting supervisor / Safety
failure of lifting gears
Injury / Death
signal men, riggers must attend
4 4 HR Rigger must check before use
4 3 MR
Lifting of Column / Site S
2.11 Wall cage during lifting proceeding.
reinforcement Bars
Falling of materials due to Deploy qualified rigger Safety
improper rigging
Injury / Death
signalman for lifting
4 4 HR Rigger must rigging properly 4 3 MR
Site S
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d

Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app

Hands caught between base To use wood / rod to align


Explain and conduct tool box Safety
slab starter bars & column Injury / Death column reinofrcement bars into 4 3 MR meeting.
4 3 MR
Site S
reinforcement bars base slab starter bars

To check & ensure all


interconnecting rebars between
Collapse of column base slab & column reforcement Safety
reinforcement
Injury / Death
are securely & adequately tied
4 3 MR Safety supervisor must check 4 3 MR
Site S
up - further reinforcement by
welding if needed
Alignment /
2.12 Installation of Column
Reinforcement Bars To secure tension wire ( 4 lines )
at equal distance around
Collapse of column Safety
reinforcement
Injury / Death column reinforement 4 3 MR Safety supervisor must check 4 3 MR
Site S
circumference at interval height
10m & 6m respectively .

To check & ensure verticality of


Collapse of column column reforcement prior to Safety
reinforcement
Injury / Death
removed of lifting gear which
4 3 MR Safety supervisor must check 4 3 MR
Site S
suspend the column

To use full body hardness


attached to lifeline to remove
Explain and conduct tool box Safety
Falling of persons Injury / Death lifting gear ( the lifeline shall be 4 3 MR meeting / Give workers caution
4 3 MR
Removal of lifting Site S
tied to the column reinforcement
2.13 gear from column prior to lifting of column )
reinforcement

To remove lifeline using access Explain and conduct tool box Safety
Falling of persons Injury / Death
scaffold
4 3 MR meeting / Give workers caution
4 3 MR
Site S

Serious injury or Anchor bolt fully insert, use Follow safe work procedure & Safety
Fixing rebar for wall Fall from height
safety PPE
4 3 MR provide proper working platform
4 3 MR
death Site S
2.14 or column on working
Serious injury or Install toe board, barricade the To clear loose materials on the Safety
platform Falling Object 4 3 MR 4 3 MR
death area right below platform Site S
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d

Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app

3 Conventional Formwork

Falling of materials due to Use only tested gears with valid Supervisor /Lifting supervisor /
failure of lifting gears
Injury / Death
certs.
4 3 MR Rigger must check before use
4 3 MR Lifting
Delivery of materials
to working area by
Falling of materials due to Deploy qualified rigger Supervisor /Lifting supervisor /
3.1 lorry crane and
improper rigging
Injury / Death
signalman for lifting
4 3 MR Rigger must check before use
4 3 MR Lifting
hositing material to
working area
Use cargo nets to wrap while
Falling of materials due to Supervisor /Lifting supervisor /
breaking of pallets
Injury / Death hoisting loose materials like 4 3 MR Rigger must check before use
4 3 MR Lifting
bricks.
erection of the Cordon off the work area & Fo
3.2 Poor floor condition Scaffolds may topple Provide solid floor condition 4 3 MR provide the warning sign
4 3 MR
scaffold frames Sup

Serious injury or Do not leave objects at edge of Cordon off the work area below & Fo
Falling Object
platform
4 4 HR provide the warning sign
4 4 HR
Installation of beam & death Sup
3.3
slab soffit formwork
Serious injury or Conduct safe work procedure
Fall from height Wear & use PPE 4 4 HR before start work
4 4 HR Safety
death
The wire not to lest lying on the
Serious cuts from saw
Electrocution & hand injury LEW inspection 3 3 MR platform & Check electrical wire 3 3 MR Safety
blade
before use.

when electrical tools return to


store, storeman must check whether
Hand injuries during drilling Serious cuts from saw Safety guard for the disc cutters safety guard at electrical tool and
and cutting to be in place all the time
3 5 HR electrical tool can properly work. 3 3 MR Site
blade
3.4 Use of electrical tools Carpenters must wear cotton gloves
while doing drilling works.

Use industrial sockets for


extension. Not to use multiple
Electrocution & Electrical Serious injury or To use industrial plugs and
tripping sockets only.
4 3 MR socket adapters. Electrical tools to 4 3 MR Safety
death
be checked periodically by a
qualified electrical worker.
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d

Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app

Do not stack materials at the edge


Injury or death by of working platform /area.Provide
Falling Object loose materials falling Cordon off the area below 4 4 HR toe boards to a height of at least 4 4 HR Safety
from height 90mm around the working
platform. Provide the warning sign

Provide enough working platform.


Serious body injury
Fall from height Anchor the safety belt properly 4 4 HR All dismantled workers must stand 4 3 MR Safety
or death
on 600mm wide working platform.
Erection and
3.5 dismantling of Form Provide proper working and
work Falling of persons while doing Serious body injury
the formwork
walking platform of at least 4 4 HR Anchor the safety belt properly 4 3 MR Safety
or death
500mm wide.
Falling of persons while doing Serious injury or Provide scaffold access by All person must use proper
the formwork qualified erectors.
4 4 HR working access
4 3 MR Safety
death

Before erect formwork scaffold,


Engineer / Supervisor must check.
Failure / Collapsing of Serious injury or Formwork to be designed by a En
formwork PE according to BCA regulation
5 2 MR Inspection by the formwork safety 5 2 MR
death Sup
supervisor concerned during
installation and removal.

Unwanted materials & It may cause fire & Inspection daily, and establish Fo
3.6 Fire hazard & tripping hazards Do housekeeping daily 4 3 MR emergency access.
4 3 MR
materials trip. Sup
Danger of mishandling Injury to worker or Inform neighbors before use Fo
3.7 Use of explosive tools
accident
Only qualified worker to do 4 3 MR explosive tools
4 3 MR
death Sup
Loose of waste
limber/plywood
Pollution increased Do housekeeping daily 4 3 MR Inspection daily 4 3 MR Site S
Formwork materials
3.8
cleaning Cordon off the formwork materials Fo
Loose of protruding nails Injury to worker Do housekeeping daily 3 3 MR location
3 3 MR
Sup
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d

Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app

4 System formwork / metal formwork

Lifting of system Ensure materials are correctly &


Falling / Slipping of metal Supervisor /Lifting supervisor /
4.1 formwork / metal
formwork components
Injury / Death adequately secured prior to 4 3 MR Rigger must check before use
4 3 MR R
formwork components lifting

Use only tested gears with valid


certs, and Lifting Supervisor, signal
men, riggers must attend during
Falling / Slipping of metal Deploy qualified & trained Site M
formwork components
Injury / Death
rigger signalman
4 4 HR lifting proceeding. Use taglines to 4 3 MR
Sup
hold materials to prevent knocking.
Use cargo nets to hold loose
materials while hoisting
Lifting of system
4.2 formwork / metal
formwork components Ensure direct eye to eye contact
between signalman & crane
Falling / Slipping of metal Avoid lifting at contested area / Signalm
formwork components
Injury / Death
poor visibility
4 3 MR operator. To use walkie talkie to 4 3 MR
op
improve communication between
signalman & crane operator

Do not stand beneath metal Sup


Falling / Slipping of metal Lifting supervisor / Signal man/
formwork components
Injury / Death formwork components during 4 4 HR Rigger must check before use
4 3 MR signalm
lifting crane

Lifting supervisor / Rigger must


Lifting of system
check before use. Cordon off the Fo
4.3 formwork / metal Failure of lifting gear Injury / Death Use tested lifting gears. 4 3 MR work area & provide the warning
4 3 MR
Sup
formwork components
sign
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d

Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app

Falling of pcorner panel,


bracket , lower bracket , toe
bracket , tie bolt , anchor bolt ,
Do not abandon metal formwork Provide adequate manpower to
tension bolt, turn buckle, panel Fo
, channel , ladder , bracing ,
Injury components at unstable positions 4 4 HR hold components. Secure all 4 3 MR
Sup
/ locations components are correctly
support , column , cross &
rectangular tube , stabiliser
..etc

Inspection by the formwork safety


Form work to be designed by Site M
Formwork failure Injury
Professional Engineer.
4 4 HR supervisor during installation and 4 3 MR
Sup
removal.

Safety belt / full body hardness


Railing , mid-rail , toe boards and
must be provided , worn and Site M
Falling from height Injury / Death
anchored at firm point while
4 3 MR proper stairs are to be provided and 4 3 MR
Sup
Installation / safely secured .
working at height .
4.3 dismantle of metal
formwork components
Provide proper working and
Falling of persons while doing Worker must wear and anchor
the formwork
Injury / Death
safety belt
4 3 MR walking platform of at least 500mm 4 3 MR Sup
wide.

Daily housekeeping to be Do not store metal formwork


Tripping of persons Injury
performed
4 4 HR components haphazardly
4 3 MR Sup

Do not place hands / legs or


Caught between metal Provide adequate manpower &
formwork components
Injury between metal formwork 4 3 MR equipment to hold components
4 3 MR Sup
components

Do not place hands / legs or


Cut by metal formwork
components
Injury Wear leather gloves. 4 3 MR between metal formwork 4 3 MR Sup
components
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d

Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app

Ensure electrical cables are not


submerged under water. Wear
Ensure damaged cables and leather gloves. Earthing to be done
Electric shock while welding Injury / Death
electrode holders are not used.
4 4 HR for machine. Supervisor must
4 3 MR Sup
check before use and apply hot
Welding of metal work permit
4.4
formwork components
Welders to wear proper face Supervisor may sure welders to
Eye injury while welding Injury
shield while welding
4 3 MR wear proper face
4 3 MR Sup

Do not run welding cables over Ensure welding cables are properly
Tripping of persons Injury / Death long distance across equipments 4 3 MR hung and house keeping at the 4 3 MR Sup
, ..etc working area.

Flash back arrestors fixed at Supervisor must check before use


Back flow of gas with fire. Explosion /Injury
torch end and cylinder end.
4 3 MR and apply hot work permit
4 3 MR Safety

Daily check of gas hoses .Ensure Supervisor must check before use
Gas Leakage. Injury
fire extinguishers are provided.
4 3 MR and apply hot work permit
4 3 MR Safety

Welders to wear proper eye


Cutting of steel plates Supervisor must check before use
4.5 Eye injury while welding Injury goggle while performing gas 4 3 MR and apply hot work permit
4 3 MR Safety
using of gas. cutting

Burns on hand or body


Proper Personnel Protective Supervisor must check before use
working while handling steel Heat burns/ injury
Equipment (Gloves) to be used.
4 3 MR and apply hot work permit
4 3 MR Safety
plates.

Supervisor must check before use


Fire sparks Injury to eyes. Safety goggles to be worn 4 3 MR and apply hot work permit
4 3 MR Safety

To lift up and install Workers may be Lifting


System column formwork Inform the workers working Provide qualified signal man and
4.6 system column
falling
injured by system
carefully
4 3 MR rigger, check up lifting appliance
4 3 MR Fo
formwork column fwk falling sup

To erect formwork Fo
Workers may be Check scaffold proper or barricade
4.7 scaffold or work at Workers fall from height Safe work procedures, Wear PPE 4 3 MR the edge of building
4 3 MR supervi
injured from falls
edge of building sup
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d

Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app

5 Wall or Column formwork


Hand, feet, head
Signalman to give instruction
5.1 Delivering Materials Falling Object injury during lifting Wear & use PPE 4 3 MR during hoisting
4 3 MR Lifting
operation
Worker can be
Moving Components
5.2 Falling Object injured by falling Wear & use PPE 4 3 MR Give workers caution 4 3 MR Fwk S
to Assembly Point
components
Worker can be
5.3 Fixing Components Falling Object injured by falling Wear & use PPE 4 3 MR Give workers caution 4 3 MR Fwk S
components
Worker can be
Hoisting Anchor To hoist anchor plates in a box or
5.4 Falling Object injured by falling Follow SWP 4 3 MR bucket
4 3 MR Lifting
Plates
anchor plates
Can cause hand/body Provide proper access & working Fo
Fall from height Wear & use PPE 4 3 MR platform
4 3 MR
Installing Anchor injury sup
5.5
Plates into the walls Worker below can be Don't leave loose material at Area below the work to be
Falling Object
height
4 3 MR cordoned off
4 3 MR Safety
injured
Brackets or hand
Fo
Falling Object tools can fall on Wear & use PPE 4 3 MR Provide nylon rope to secure it 4 3 MR
Fixing the Brackets/ sup
5.6 workers
Alignment of holes
Can cause moderate Provide proper access & working Fo
Fall from height Use PPE and Secured cat ladder 4 3 MR platform
4 3 MR
body injury sup
Fall from height Climb form Serious injury or Anchor bolt fully insert, use Follow safe work procedure & Fo
Fixing the system give way safety PPE
4 3 MR provide proper working platform
4 3 MR
death sup
5.7 formwork unit on the
wall Serious injury or Install toe board, barricade the To clear loose materials on the
Falling Object
area right below
4 3 MR platform
4 3 MR Safety
death

Transferring rail Serious injury or Not allow person stand on the


Fall from height Anchor safety belt 4 3 MR platform
4 2 MR Safety
brackets from lower death
5.8
platform to upper Serious injury or Install toe board, barricade the Do not leave loose material at Fo
platform Falling Object
area right below
4 3 MR height
4 3 MR
death sup

Removing infill Serious injury or Fo


Fall from height Use PPE 4 3 MR Warning sign 4 3 MR
platform deck/ death sup
5.9
connected parts Serious injury or Install toe board, barricade the Do not leave loose material at Fo
between units
Falling Object
area right below
4 3 MR height
4 3 MR
death sup
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d

Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app

Fall from height Leg or hand injury Use PPE and Secured cat ladder 4 3 MR Give workers caution 4 3 MR Safety
2 to 3 persons to manually Fo
Transferring hydraulic Unsafe work practice Back injury
transfer
3 3 MR Give workers caution 2 3 LR
sup
5.10 pullers and power
pack Falling power pack
Area below the work to be Fo
Falling Object can cause serious Safe work procedure 4 3 MR cordoned off
4 3 MR
sup
injury or death

Falling Hyd Hose can Secure the Hyd Hose to the hand Area below the work to be Fo
Falling Object
rail or other fames
4 3 MR cordoned off
4 3 MR
cause serious injury sup
Installing and fixing
5.11
hydraulic hoses Spilled oil can cause
Fo
Environment slip or fall on the Safe work procedure 4 3 MR Clean spilled oil immediately 4 3 MR
sup
platform
Shifting, transfering, Serious injury or Fo
Fall from height Use PPE 4 3 MR Warning sign 4 3 MR
installing small death sup
5.12
componets on the Serious injury or Install toe board, barricade the Do not leave loose material at Fo
systemform
Falling Object
area right below
4 3 MR height
4 3 MR
death sup
The wire not to lest lying on the Fo
Electrical Harzard Electrocution
platform
4 3 MR Check electrical wire before use. 4 3 MR
sup
Self-Climbing
5.13 operation/ Hoisting by Serious injury or Conduct safe work procedure
Fall from height Anchor the safety belt properly 4 3 MR before jumping up
4 3 MR Safety
tower crane death

Serious injury or Barricade the area below & Tools, unused material to cleared
Falling Object
provide the warning sign
4 3 MR on working platform
4 3 MR Safety
death

Serious injury or Follow safe work procedure &


Fall from height Anchor the safety belt properly 4 3 MR provide proper working platform
4 3 MR Safety
Dismentling the death
5.14
system formwork
Serious injury or
Falling Object Cordon off the area below 4 3 MR Provide the warning sign 4 3 MR Safety
death
Serious injury or Workers to wear PPE, Safe work To use check list and method of
Fall from height
procedure
4 3 MR statements
4 3 MR Safety
Closing and dismantle death
5.15
formwork Serious injury or To use check list and method of
Falling Object Barricade the area below 4 3 MR statements
4 3 MR Safety
death
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d

Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app

Access to platform Worker can fall from Wear & use PPE, baricade, Provide safety net at the bottom of Fo
5.16 Fall from height
provide handrail
4 3 MR platform
4 3 MR
panel to panel opening sup

Storage of material on Serious injury or Evenly distribute material/ Remove Fo


5.17 Falling Object/ Form give way Make adequte storage area 4 3 MR unwanted material
4 3 MR
platform death sup

6 Casting Concrete

Ear injury by the voice of Give workers caution. Prepare


machine
Ear injury Wear proper ear plug 3 4 MR medical box and frist aid on site
2 3 LR Site S
Cleaning before cast
6.1 concrete by air
compressor
Give workers caution. Prepare
Can cause eyes injury Eyes injury Wear proper protective goggles 3 4 MR medical box and frist aid on site
2 3 LR Site S

Breaking of pipe joints while Injury & Property Deploy trained personnel for the
casting jointing the pipes.
4 3 MR Give workers caution 4 3 MR Site S
damage

Outriggers of the concrete pump to


Casting concrete using be fully extended and should rest
6.2
pumps Deploy trained personnel for on a firm & level ground. Provide
Injury & Property
Toppling of concrete pump
pump operation.
4 3 MR steel plates / timber logs to support 4 3 MR Site S
damage
the outriggers. To ensure parking
space enough

Body injury during


Loading/Unloading Wear hand glove 4 3 MR Only rigger to do 4 3 MR Lifting
Hoisting concrete bin lifting operation
6.3 by mobile crane/tower Worker can be
crane Signalman to give instruction
Falling Object injured by falling Wear & use PPE 4 3 MR during hoisting
4 3 MR Lifting
concrete bin
Fall down from working Serious injury or
platform
Wear & use PPE 4 4 HR Provide barricade for platform 4 3 MR Site S
Casting concrete for death
6.4
wall or column Worker can be
Falling Object Use slanting board for concrete 4 3 MR Cordon off the work area below 4 3 MR Site S
injured

Persons hit by aggregates Eye injury Wear protective goggles. 3 3 MR Give workers caution 2 3 LR Site S
Using vibrators for
6.5
concrete packing
Splashing of concrete mortar Eye injury Wear protective goggles. 3 3 MR Give workers caution 2 3 LR Site S
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d

Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app

Provide sufficient lighting during


Hit by concrete bucket Body injury Wear & use PPE 3 3 MR night casting
3 3 MR Site S

Provide rubber hand glove or


skin disease, rubefaction Body injury Wear & use PPE 3 3 MR arrange another worker
3 3 MR Site S
Casting concrete for
6.6
top slab Concrete splash into eyes Eyes injury Wear & use PPE 3 3 MR Wear proper protective goggles 3 3 MR Site S

Serious injury or Provide barricade for the working


Fall from height Wear & use PPE 4 3 MR area
4 3 MR Safety
death
Worker can be
Falling Object Use slanting board for concrete 4 4 HR Cordon off the work area below 4 3 MR Site S
injured
Workers' skin may be Provide rubber hand glove or
6.7 To cast concrete Skin disease, rubefaction Wear & use PPE 4 3 MR arrange another worker
4 3 MR Safety
disease
Formwork collapse during Injury to worker, Erect formwork according to Formwork was inspected before Fo
concreting PE's design
4 3 MR cast & weekly
4 3 MR
delay of work Sup
6.8 Casting concrete
Noise emission from concrete
pump/vibrator
Ear injury Wear proper ear plug 4 3 MR Give workers caution 4 3 MR Site S

Excess concrete / concrete Depletion/consumed Control concrete quantity before


6.9 Disposal concrete
waste finish casting
4 3 MR Give workers caution 4 3 MR Site S
of resources

Depletion/consumed Switch off the water after


6.10 Cleaning concrete Water consumed
cleaning
4 3 MR Give workers caution 4 3 MR Site S
of resources
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d

Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app

7 Power float

Deploy qualified rigger signalman


Loading / unloading for lifting work.Use taglines to
7.1 Falling of power trowel Injury/Death. Use tested lifting gears. 4 3 MR hold the trowel to prevent knocking 4 3 MR Site S
of power trowel
over men / materials.

Ensure fire extinguishers are


provided. Do not smoke while
Injury / Death /
7.2 Fuel top up of trowel Fire / explosion hazard Do not top fuel at hot work area 4 3 MR topping up fuel. Shut down power 4 3 MR Site S
Property damage
trowel & allow to cool down before
topping up fuel

To wear eye goggles while Do not apply hardener when it is


Hardner flown into eyes Eye Injury
applying hardener
3 3 MR windy
3 2 LR Site S
Application of Flaot
7.3 To use lifeline & anchor fall
Hardener
Falling from height Injury/Death. To wear and anchor safety belt 4 3 MR arrestor. To barricade the open 4 1 LR Site S
edges
Do not let engine run when Turn off engine when trowel is not
Hit by trowel Injury
unattended
4 3 MR in use
4 3 MR Site S

Operation of power Do not place hand / foot near


7.4
trowel trowel blade operation. Do not
Cut by trowel blade Injury To provide guard for blading 4 3 MR make adjustment to trowel during
4 3 MR Safety
operation

Stop engine before changing


Changing of trowel Do not make adjustment to
7.5 Cut by trowel blade Injury
trowel during operation
4 3 MR blades. Only competent person 4 3 MR Safety
baldes
shall change the blades
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d

Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app

8 Working with Explosive Powered Tools

explosive powered tools must keep


by store. Before gave explosive
Only certified & trained
powered tools, store man must
Body hit by fasteners Injury/Death. pesonnel shall operate explosive 4 3 MR check whether receiptor owned 4 3 MR Safety
powered tools ( EPT )
opereation cert. Satefy supervisor
must check before use

Check wall conditions if suitable Site supervisor must make sure


Body hit by fasteners Injury/Death.
for fastener driving
4 3 MR wall conditions.
4 3 MR Site S
Opereator must make sure and give
Maintain a safe clearance
other workers warning. If other
distance of 10m in length , beath
Working with Body hit by fasteners Injury/Death. 4 3 MR workers don't want to leave, 4 3 MR Site S
& height during operation of
8.1 Explosive Powered opereator must report to site
EPT
Tools supervisor.
Body hit by fasteners Injury/Death. Barricade EPT operation area 4 3 MR supervisor must make sure. 4 3 MR Site S

supervisor must make sure. To


wear hand glove. To wear eye
protection / facemask. Use only
Unauthorised operation of EPT -
approved EPT. Servicing / repair
Body hit by fasteners Injury/Death. EPT must be kept in safe place 4 3 MR by manufacturer only. To send EPT 4 3 MR Site S
when not in use
to manufacturer / authorised
supplier for periodic maintainence
& inspection
Legend:

S - Severity of damage, injury, etc.


L - Likelihood (chances or possibility of occurrence)
R - Final ranking (see below matrix)

*Low Risk - Define as acceptable risk i.e. No additional controls are required. Continue monitoring to ensure that controls in place are
maintained and effective.

*Medium Risk - Define as tolerable risk i.e. risk shall be accepted subject to demonstration that the level of risk is as low as reasonable.

*High Risk - Define as undesirable risk i.e. risk shall only be accepted if further risk reduction is not practicable.

*Extreme High Risk - Define as intolerable risk i.e. risk shall be reduced by whatever means possible. If it is not possible to reduce the risk,
work has to res to remain prohibited.

Likelihood of Occurrence
Potential Consequence (Severity) 1 2 3 4 5
Happens Happens
Similar incident Similar incident Incident has several times several times
not known in occurred in the occurred in our per year in per year in
Rating People Environment Assets Reputation the industry industry company company location

Slight Slight

1 injury Slight effect damage Slight impact Low Risk Low Risk Low Risk Low Risk Low Risk
Minor Minor

2 injury Minor effect damage Limited impact Low Risk Low Risk Low Risk Medium Risk Medium Risk
Major Localised Localised
Considerable
3 injury effect damage impact Low Risk Low Risk Medium Risk Medium Risk High Risk

4 Single fatality Major effect Major damage Major national Low Risk Medium Risk Medium Risk High Risk High Risk
Multiple Extensive Major Extreme High
5 fatalities Massive effect damage international Low Risk Medium Risk High Risk High Risk Risk
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone

Appendix iii
Lifting
Lifting Equipment

(a) Tower Crane –As per attached plan

(b) 80T Crawer crane-Necessary documents such as lifing capacity,parking location,LM &
LG cert., Training Cert. etc to be submitted prior to the operation.

(c) Mobile Crane- Necessary documents such as lifing capacity,parking location,LM & LG
cert., Training
Cert. etc to be
submitted prior to the
operation.
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone

Appendix iv
Lighting
GENERAL LIGHTING PLAN - CASINO B2M
Legend : -
Location of 400 V to 1000 V Flood Light
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone

Appendix v
Formwork joint

Page 2 of 2