Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
CONTENTS
1. Scope of work
3. Construction of B2M
4. PE Calculation
5. Concrete Work
6. Project organization
8. Access / Egress
9. Lighting
Appendix I : PE Calculation
Appendix ii ; Risk Assessment
Appendix iii Lifting
Appendix iv Lighting
Appendix v Typical Construction Joint
Page 1 of 2
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
1. SCOPE Of WORK
Construction of R/C slab and walls at B2M level for Marina Bay Sands North Podium
Casino comprising as such;
2) Install formwork.
3) Casting of Concrete.
1 300
2 300
3 250
4 250
5 300
6 350
7 350
8 250
9 150
10 500
11 550
12 250
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
2 4
3
1
5 6
3. Construction of B2M
6) Set up detailed set out beam as per to the approved shop drawing.
7) Laying 12mm plywood at the top of lean concrete set out column as per
drawing.
8) Put up starter bar and coupler (E-Splice for top-down & Dextra for D-Wall
joint)of column.
Starter bar & Coupler
12mm plywood
Plywood form
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
10) Install Starter bar system [or coupler system/ Styrofoam] will be
embedded for following slab & beam at Construction Joint (for vertical
element)
12mm Plywood
13) Dismantle formwork and patch the hole of tied rod using non-shrink grout.
15) Lay re-bar or BRC (as per to the approved drawing) and cast concrete
topping.
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
3.2 Construction of RC Beam with RC Slab
1) Issue Bar Bend Schedule. (Cut & Bend re-bar order form Natsteel)
6) Set up detailed set out beam as per to the approved shop drawing.
7) Laying 12mm plywood at the top of lean concrete set out column as drawing.
8) Put starter bar and coupler (E-Splice for top-down & Dextra for D-Wall
joint)of column into plywood and plyform.
12mm plywood
Plyfoam provided
by sembawang.
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
9) Install the beam bars layer by layer.
10) Install Starter bar system [or coupler system/ Styrofoam] will be embedded
for following slab & beam at Construction Joint (for vertical element)
13) Dismantle formwork and patch the hole of tied rod using non-shrink grout.
15) Lay re-bar or BRC (as per to the approved drawing) and cast concrete
topping.
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
3.3 Construction of Permanent R/C Capping Beam :
1) As-built survey to be done before access.
10) Beam / Slab location and level to be marked onto capping beam
reinforcement rebar
11) Starter bar installation using coupler (Dextra for D-Wall joint) to be done
13) Cast capping beam by direct discharge from concrete truck either by
concrete bucket using mobile crane whichever workable.
15) Proceed with fabrication of capping beam reinforcement for next 12 length
section.
12mm Plywood
16) Dismantle formwork and patch the hole of tied rod using no-shrink grout.
Appendix i
5. CONCRETE WORK
1) Zone Plan for Casino as per attached plan under item no.2.
6) Before big areas for slab & beam casting, site manager or supervisor shall
orally talk workers casting arrangement.
1. Project Organization
SEC-Project Director
Ng Seng Yoong
SEC-Project Manager
Chee Heng Leong
SEC-Site Engineer
Rayan / Gan Kok
SEC-Site Supervisor/s
Page 1 of 2
ov8 9,4
ildingand
Bu Constructionf,uth
ority
I
t,
'
, .,; .1",1,1
D E P U ' fv C H t e r E R E C U t , i V e O F F t c E R
. I tnda*rlryfu,,&pnfitl
' hti blingaad Avtlyrvy
torrnt:rl,ftoll.
:
:.-''-
rfir
/{*41^1"_
*
n"'t-
fenilicrn\l$.f'SCdlitmg6' S D N t C Tl V
, IA r { ^ c E R
Corvyvcrlvn
M*rr.y ftrlri rg lt *innt
i
2 [)+cornb*v2004 tI
7 1 r r , , . ' , i , ; l ' . i , r , , , i , . .1 , , j 1 , ,.;, 1 . , , . r i
' t,l
'I
:
9NIUSTINISNS
Cg3 z c 6 z 9 l z gx v d T 9 2 T zt 0 0 z l 0 / 9 0
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
8. Access / Egress
i. Working platform of at least 500mm in width (or 2 standard planks) shall
be provided and secured.
ii. Proper step ladders shall be provided for any ingress and egress.
iii. All workers working at height greater than 2 meter shall wear full body
harness secured to proper anchorage points and working at heights should
adhere to the Permit-to-Work at Heights requirements as well.
iv. Working platform to provide pipe handrail at 1.1m upper & 500mm lower.
9. Lighting
Maintaining sufficient and suitable lighting, whether natural or artificial, at
locations in which persons are at work is important. Sembawang will provide
400 to 1000volt flood light on the decking in various locations and also we
will provide mobile generator with spotlights to the work site for localized
illumination for night work.
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
Additional spotlight will be reserved in the event that any of the used lights
break down. Once the utilization of reserved lights in place, the damaged
ones shall be sent for servicing and repair as soon as possible.
The general Lighting plan are attached in Appendix iv
• All workers are taught and trained with basic safety knowledge by
using proper personnel protective equipment while working.
• Only trained and certified operators are allowed to operate the crane.
All the area will be kept tidy and proper rubbish bin will be provided.
Appendix i
PE Calculation
l
tI
wRxt^€fir:fglr4H
WR" CONSUI T NTS
203Henderson rd, #04-03,Hendersonindustrialpark
Singapore159546
Tel:(65)627
27071 Fa><:(65)62787071Email:wrxconsultants@wx.com.sg
PROJECT:
PROPOSEDERECTIONOF TIIE MARINA BAY SANDS
INTEGRATEDRESORTAT BAYFRONT AVENUE
SIDE FORMWORKDESIGN
FOR 3.2mx1.3m(D)
BEAM
28 APR. 2008
Wru(CONSULTANTS
DESIGNCALCULATION PageNo:
l.Godesof Practlce
CP23 :2000 FormWork
BS5950:2000 StructuralUseof Steelworkin Building
SSCPT: StructuralUseof Timber
BS6399 DesignLoadingfor Buildings
2. Uslng groupB commondgrade Timber
. Allowable
flexurestress: 12.41Nlmm2
Allowableshearstress: 1.17N/mm2
Allowablecompression stress: 10.00N/mm2
Modulusof elasticity: 11700N/mm2
Plywood:Allowablebendingstress: 12.41Nlmm2
Modulus,E : 7000N/mm2
3. Steelgrade5275
Modulusof elasticity: 206000N/mm2
4. Deslgnedloadlngs:
a. Liveload(dudng =
concreting) 1.50kN/m2
b. Selfweightof formwork=
0.40kN/m2
c. Wetconcretedensig = 25 kN/m3
5. DeslgnData
3200mm
GaseI
Max.Lateral
Pressurc f{= 1.30m
Baseon CP23:2000,cl 3.4.3- horizontalloads:
l= 0.60m 2500kg/m3
marinasands Structure:
LJJ Date: 28lAprl08 CheckedBy: WRX Date:_,,!![pgr08
Themax.design
load 15.0
Total 15.0kN/m2
Runner I
Spacingof runners,s = 200 mm
(Section
Runners: to detail) 25 75 depth
SPan= 0.650m
Load/runner = 3.00kN/m
, Modulus,Z = 15410mm3
Mmax= 0.16kNm
Max.shearforce= 1.2kN
l= 1 5 4 1 0m m 3
[= 1360mm2
l= 520000mm4
CheckBending:
fbc = 10.28N/mm2 12.4N/mm2 OK
CheckShear:
ShearStress= 0.90N/mm2 1.17N/mm2 OK
CheckDeflection:
6l = 1 . 1 5m m 2.60mm OK
Beam:
Using RHS
2nos. 50x100x2.3mm @clc 650 mm
SPan= 1 . 5 0m
=
Load/runner 14.63kN
" Design= =
1.4DL+1.6LL 22.82kN
Mmax = 4.63kNm
Max.shearforce= 1 1 . 4k N
fl= 50 mm ry= 2'1 cm
II
WRXCONSULTANTS
I
I
i
DESIGNCALCULATION PageNo:
I
Date: 28/Apr/08
p= 100mm
l= 2.3 mm
b/t= 16.7
d/t= 35.7
Sectionclass1
Sx= 21 cm3
h= 17.0cm3
fi= 6.55cm2
l= 84.8cm4
momentcapacity: 1.2py7t= 11.22 4.63 kNm OK
FY*Sx= 11.55 4.63 kNm OK
Shear 144.1kN> 11.4 kN OK
Deflection:g =(5n4+2n2+1 =
)pL3/3g4n3Et 3.08mm U270= 5.56 OK
DESIGN OFTIEROD
TENSITE FORCEOFTIE ROD F = 14.625KN
TENSILE FORCEOFTtEROD(fsctor) 1.5F = 11.938KN
use R15steeltie rod
tensile -safetyload(asperlabtestreport)
capacity P 90 KN oK!
Deslgnof LateralBraclng
50xl00 mmlocaltimbercompression capacity: v 50.0 kN
2.5Yoof vertlcalload F 2.6 kN/m
Forcealongthebracing F1 3.7 kN/m
Spacingof LateralBracing 13600mm
say s 1500mm 'oKl
deslgnbasebolt on formwork bottom
max.shearon bolt =1.5F12 10.97 kN/m
Provideconcretenail O3.7
baseon testingreport
Shearcapacityperbolt % 12.33kN
requiredspacingof nail c 1686 mm
. say 500 mm oKt
designbaseconnectlonof lateralbracing
max.shearon bolt =1.6F1x0.707 4.16 kN/m
Provideconcretenail O3.7
Shearcapacityperbolt % 12.33kN
requiredspacingof nail c 2965 mm
say 500 mm oKl
use50x100timberto supportthe lateralbracing
max.pointloaddueto compressof eachbracing f= 4.16 kN
ffi
ma)<.moment M= 0.693 kNm
sec'tion
modulus Z= 62070 mm3
bendingstress Py= 11.17N/mm2 oKl
shearstress v= 0.34 KN oKl
fir@S
l-
$;i
'F rg.
; f!.
g fri
: tEl
Frl
J
F
=
ts *a
-z
I
xa
a z
t o.
^e o E
a<
=F t5
o EE r
x
- o
J
Q -
=t
, 9
- g _fi
g=
F
J z Zg
--f
F
x
€E
5F
z6 q^
J
8
z
HF -
H+
sR
-,2
>=
H*-
g ^
J
-z E ==
>tH
.E E5 o g.t
H
-
^Fs
=Jo
*
E *!E t
E =gE 4
E FgE
q *
g er6 -
-
'-
g E F
a: F: qJ
F
-
F EF
,5e E Eg
E =Fs
F
68*RB
5H€€E
F
'llo E
4 =
a
!
z,l =l
Hl
FI
lr)l
El.cS
()l
e F(d o
! al
=
x 3l EEa =
=lsii=i
oo o ,,{ tl
!t
!<l J
&l
^l q Edq
I -l E =l F=9-q3
Elqd*==
!g
=l
EI
,9 * rrl =E8*E
''I = I
0
9a c
F
E
E
g
=l
<l
I
=l=;5si
-l SHSFE
@
e.Jl : N
I
r'rl E
><t o.t =
.!
t-il >-l =
-! FI
D ! ,a
'I
!tt
.{ . t
' '.!
zl
x\J-\
t?\ b*<
crrCI
\? q,E
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
Appendix ii
Risk Assessment
RISK ASSESSMENT FORM
Company: CEC Engineering Pte Ltd Work Title: Marina Bay Sands North Podiun Casino Zone
Process/ Location: Marina Bay Sands Tower 2 Conducted by: Li Yun Zhang-DGM, Fu Li Gang-PM,Xu Zheng Wen-SM,Ji Hai P
Approved by: Cai Wei Xin, General Manager, 26/05/08 (Names, designations) (Date)
(Name, designation)(Date)
Reviewed by Sembawang: Chau T.G. - Safety Manager Last Review Date: 2/5/2008 Next Review Date:
(Names, Designations)( Date) Upul Chandrasiri - CM
Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app
1 Sub-sturcture
Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app
2 Rebar Installation
Falling of materials due to Use only tested gears with valid Supervisor /Lifting supervisor / Lifting
failure of lifting gears
Injury / Death
certs.
4 2 MR Rigger must check before use
4 2 MR
Site S
Delivery of materials
to working area by Falling of materials due to Deploy qualified rigger Lifting
improper rigging
Injury / Death
signalman for lifting
4 4 HR Rigger must rigging properly 4 3 MR
2.1 lorry crane and Site S
hositing material to Use cargo net to wrap while
working area Falling of materials due to Supervisor /Lifting supervisor / Lifting
breaking of pallets
Injury / Death hoisting loose materials like 4 4 HR Rigger must check before use
4 3 MR
Site S
rings or bar chairs.
Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app
Tie rebar on slab or Leg injury in void between Leg injury during Safety
2.5
bars
Wear & use PPE 3 4 MR Give workers caution 3 4 MR
beam walk on top of bars Site S
Serious injury or Anchor bolt fully insert, use Follow safe work procedure & Safety
Fixing rebar for wall Fall from height
safety PPE
4 4 HR provide proper working platform
4 3 MR
death Site S
2.7 or column on working
platform Serious injury or Install toe board, barricade the To clear loose materials on the Safety
Falling Object
area right below
3 4 MR platform
3 4 MR
death Site S
Hand injury during Cordon off the work area & Safety
2.8 Making rebar cage Fall down/ Hand injury Wear & use PPE 3 4 MR provide the warning sign
3 4 MR
lifting operation Site S
Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app
To remove lifeline using access Explain and conduct tool box Safety
Falling of persons Injury / Death
scaffold
4 3 MR meeting / Give workers caution
4 3 MR
Site S
Serious injury or Anchor bolt fully insert, use Follow safe work procedure & Safety
Fixing rebar for wall Fall from height
safety PPE
4 3 MR provide proper working platform
4 3 MR
death Site S
2.14 or column on working
Serious injury or Install toe board, barricade the To clear loose materials on the Safety
platform Falling Object 4 3 MR 4 3 MR
death area right below platform Site S
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d
Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app
3 Conventional Formwork
Falling of materials due to Use only tested gears with valid Supervisor /Lifting supervisor /
failure of lifting gears
Injury / Death
certs.
4 3 MR Rigger must check before use
4 3 MR Lifting
Delivery of materials
to working area by
Falling of materials due to Deploy qualified rigger Supervisor /Lifting supervisor /
3.1 lorry crane and
improper rigging
Injury / Death
signalman for lifting
4 3 MR Rigger must check before use
4 3 MR Lifting
hositing material to
working area
Use cargo nets to wrap while
Falling of materials due to Supervisor /Lifting supervisor /
breaking of pallets
Injury / Death hoisting loose materials like 4 3 MR Rigger must check before use
4 3 MR Lifting
bricks.
erection of the Cordon off the work area & Fo
3.2 Poor floor condition Scaffolds may topple Provide solid floor condition 4 3 MR provide the warning sign
4 3 MR
scaffold frames Sup
Serious injury or Do not leave objects at edge of Cordon off the work area below & Fo
Falling Object
platform
4 4 HR provide the warning sign
4 4 HR
Installation of beam & death Sup
3.3
slab soffit formwork
Serious injury or Conduct safe work procedure
Fall from height Wear & use PPE 4 4 HR before start work
4 4 HR Safety
death
The wire not to lest lying on the
Serious cuts from saw
Electrocution & hand injury LEW inspection 3 3 MR platform & Check electrical wire 3 3 MR Safety
blade
before use.
Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app
Unwanted materials & It may cause fire & Inspection daily, and establish Fo
3.6 Fire hazard & tripping hazards Do housekeeping daily 4 3 MR emergency access.
4 3 MR
materials trip. Sup
Danger of mishandling Injury to worker or Inform neighbors before use Fo
3.7 Use of explosive tools
accident
Only qualified worker to do 4 3 MR explosive tools
4 3 MR
death Sup
Loose of waste
limber/plywood
Pollution increased Do housekeeping daily 4 3 MR Inspection daily 4 3 MR Site S
Formwork materials
3.8
cleaning Cordon off the formwork materials Fo
Loose of protruding nails Injury to worker Do housekeeping daily 3 3 MR location
3 3 MR
Sup
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d
Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app
Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app
Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app
Do not run welding cables over Ensure welding cables are properly
Tripping of persons Injury / Death long distance across equipments 4 3 MR hung and house keeping at the 4 3 MR Sup
, ..etc working area.
Daily check of gas hoses .Ensure Supervisor must check before use
Gas Leakage. Injury
fire extinguishers are provided.
4 3 MR and apply hot work permit
4 3 MR Safety
To erect formwork Fo
Workers may be Check scaffold proper or barricade
4.7 scaffold or work at Workers fall from height Safe work procedures, Wear PPE 4 3 MR the edge of building
4 3 MR supervi
injured from falls
edge of building sup
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d
Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app
Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app
Fall from height Leg or hand injury Use PPE and Secured cat ladder 4 3 MR Give workers caution 4 3 MR Safety
2 to 3 persons to manually Fo
Transferring hydraulic Unsafe work practice Back injury
transfer
3 3 MR Give workers caution 2 3 LR
sup
5.10 pullers and power
pack Falling power pack
Area below the work to be Fo
Falling Object can cause serious Safe work procedure 4 3 MR cordoned off
4 3 MR
sup
injury or death
Falling Hyd Hose can Secure the Hyd Hose to the hand Area below the work to be Fo
Falling Object
rail or other fames
4 3 MR cordoned off
4 3 MR
cause serious injury sup
Installing and fixing
5.11
hydraulic hoses Spilled oil can cause
Fo
Environment slip or fall on the Safe work procedure 4 3 MR Clean spilled oil immediately 4 3 MR
sup
platform
Shifting, transfering, Serious injury or Fo
Fall from height Use PPE 4 3 MR Warning sign 4 3 MR
installing small death sup
5.12
componets on the Serious injury or Install toe board, barricade the Do not leave loose material at Fo
systemform
Falling Object
area right below
4 3 MR height
4 3 MR
death sup
The wire not to lest lying on the Fo
Electrical Harzard Electrocution
platform
4 3 MR Check electrical wire before use. 4 3 MR
sup
Self-Climbing
5.13 operation/ Hoisting by Serious injury or Conduct safe work procedure
Fall from height Anchor the safety belt properly 4 3 MR before jumping up
4 3 MR Safety
tower crane death
Serious injury or Barricade the area below & Tools, unused material to cleared
Falling Object
provide the warning sign
4 3 MR on working platform
4 3 MR Safety
death
Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app
Access to platform Worker can fall from Wear & use PPE, baricade, Provide safety net at the bottom of Fo
5.16 Fall from height
provide handrail
4 3 MR platform
4 3 MR
panel to panel opening sup
6 Casting Concrete
Breaking of pipe joints while Injury & Property Deploy trained personnel for the
casting jointing the pipes.
4 3 MR Give workers caution 4 3 MR Site S
damage
Persons hit by aggregates Eye injury Wear protective goggles. 3 3 MR Give workers caution 2 3 LR Site S
Using vibrators for
6.5
concrete packing
Splashing of concrete mortar Eye injury Wear protective goggles. 3 3 MR Give workers caution 2 3 LR Site S
1. Hazard Identification 2. Risk Evaluation 3. Risk Control
1a 1b 1c 1d 2a 2b 2c 2d 3a 3b 3c 3d
Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app
Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app
7 Power float
Residual Risk
Initial Risk Index Res
Possible Accident/ Ill Index
Pers
No. Work Activity Hazard Health & Persons-at- Existing Risk Control (if any) Additional Risk Control
timesc
Risk
S L R S L R app
*Low Risk - Define as acceptable risk i.e. No additional controls are required. Continue monitoring to ensure that controls in place are
maintained and effective.
*Medium Risk - Define as tolerable risk i.e. risk shall be accepted subject to demonstration that the level of risk is as low as reasonable.
*High Risk - Define as undesirable risk i.e. risk shall only be accepted if further risk reduction is not practicable.
*Extreme High Risk - Define as intolerable risk i.e. risk shall be reduced by whatever means possible. If it is not possible to reduce the risk,
work has to res to remain prohibited.
Likelihood of Occurrence
Potential Consequence (Severity) 1 2 3 4 5
Happens Happens
Similar incident Similar incident Incident has several times several times
not known in occurred in the occurred in our per year in per year in
Rating People Environment Assets Reputation the industry industry company company location
Slight Slight
1 injury Slight effect damage Slight impact Low Risk Low Risk Low Risk Low Risk Low Risk
Minor Minor
2 injury Minor effect damage Limited impact Low Risk Low Risk Low Risk Medium Risk Medium Risk
Major Localised Localised
Considerable
3 injury effect damage impact Low Risk Low Risk Medium Risk Medium Risk High Risk
4 Single fatality Major effect Major damage Major national Low Risk Medium Risk Medium Risk High Risk High Risk
Multiple Extensive Major Extreme High
5 fatalities Massive effect damage international Low Risk Medium Risk High Risk High Risk Risk
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
Appendix iii
Lifting
Lifting Equipment
(b) 80T Crawer crane-Necessary documents such as lifing capacity,parking location,LM &
LG cert., Training Cert. etc to be submitted prior to the operation.
(c) Mobile Crane- Necessary documents such as lifing capacity,parking location,LM & LG
cert., Training
Cert. etc to be
submitted prior to the
operation.
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
Appendix iv
Lighting
GENERAL LIGHTING PLAN - CASINO B2M
Legend : -
Location of 400 V to 1000 V Flood Light
Sembawang Engineers & Constructors Pte Ltd
460 Alexandra Road, #27-01 PSA Building Singapore 119963
T +65 6305 8788 F +65 6305 8568
www.sembawangenc.com
Marina Bay Sands - North Podium - Casino Zone
Appendix v
Formwork joint
Page 2 of 2