FABRICATION YARD
1.0. PURPOSE
2.0. SCOPE
3.0. DEFINITIONS
5.0 RESPONSIBILITIES
6.0 PROCEDURE
7.0 APPENDIX
NIPPON STEEL BATAM PAGE 2 of 6 29-03-21
FABRICATION YARD
1.0. PURPOSE
The purpose of this document is to develop the fabrication yard's material take off
(Bulk MTO) in standardize format.
2.0. SCOPE
This scope of this document covers only the electrical, instrumentation, piping and
mechanical disciplines in doing (Bulk) material take off for each specific required
tasks.
3.0. DEFINITIONS
5.0. RESPONSIBILITIES
The following personnel are responsible for the making of all outfitting engineering
material take off (Bulk MTO):
POSITIONS RESPONSIBILITIES
Outfitting Engineering In-charge Carefully check and ensure that all the re-
quired materials are captured and as per
project specifications and requirements. As
well, to ensure that market availability and
the delivery can go along with project target
schedule.
Check and ensure that reasonable quantity
of pad stock or contingency is sufficient to
cover up future losses, damages; and for
the unanticipated additional work.
NIPPON STEEL BATAM PAGE 4 of 6 29-03-21
FABRICATION YARD
POSITIONS RESPONSIBILITIES
Lead P / M Engineer A joint effort, to define & provide sufficient,
Assistant P / M Engineer and correct materials to complete specific
tasks during bid stage and when the project
is awarded.
Outfitting Engineering In-charge Carefully check and ensure that all the re-
quired materials are captured and as per
project specifications and requirements. As
well, to ensure that their market availability
and the delivery time can go along with
project target schedule.
Check and ensure that reasonable quantity
of pad stock or contingency is sufficient to
cover up future losses, damages; and for
the unanticipated additional work.
6.0. PROCEDURE
5.1. Prior to generating bulk MTO, the assigned / designated Lead Engineer
for its specific project will study all the possibilities for making all the
required and necessary materials as per the Clients' issued
documents.
NIPPON STEEL BATAM PAGE 5 of 6 29-03-21
FABRICATION YARD
5.2. To ensure that all Clients' issued AFC drawings and project
specifications are received. Advise the Outfitting Engineering Manager,
if there is any outstanding AFC drawing; specifications and other
necessary documents.
5.4. The Lead Discipline Engineer may check and monitor from time to
time, to ensure that MTO exercise is carried continuously, until it is
completed prior to the target completion schedule.
5.5. Internally issue the MTO list to the Outfitting in-charge for in-house
checking and review.
5.6. To ensure that all the materials shown on the list are as per the
relevant project specification; as per AFC plan drawing; as per
contractual obligation and are sufficient to complete the scope of work.
Additional cross-examination is given to the MTO group, by questioning
on how, where, what they have considered with respect to scope limit,
detail of scope and materials requirements.
After checking and review, including the contingency quantity, the MTO
list will be ready for requisition. Accordingly, material requisition may
be raised for further procurement process.
5.7 The standard MTO list is shown on the appendix, This is to be used for
all Outfitting Engineering (Bulk MTO) exercise. However, for bid
activities, Summary Bid (Bulk) MTO form is to used.
NIPPON STEEL BATAM PAGE 6 of 6 29-03-21
FABRICATION YARD
6. APPENDIX