NEC

PROVISIONAL ACCEPTANCE TEST


PROCEDURE (PAT)
OF
PASOLINK NEO/I (1+0)
32E1 + 2LAN INTERFACE CARD

P/J

NOV-08
NEC Corporation
Contents

1- Visual Inspection

2- Meter Reading

3- AGC Voltage Check

4- Order Wire Fuction Check

5- Loopback Check

6- Link BER Test

7-Frequency Interference Test

8-Test Data Sheet


ON-SITE TEST PROCEDURE

ITEM NO. TEST ITEM DESCRIPTION


1 VISUAL CHECK
TEST PURPOSE
1. Visual Inspection

SPECIFICATION
Satisfactory

TEST PROCEDURE

1-Composition
Checking the components used in unit and rack.
With serial number of Antenna, ODU and IDU.
2-Structure
Checking the finishing and fittng manner.

3-Wiring
Checking the termination condition and fitting manner.
ON-SITE TEST PROCEDURE

ITEM NO. TEST ITEM DESCRIPTION


2 METER READING
TEST PURPOSE
Confirm the TX Power by LCT
Confirm the RX Level by LCT
Confirm Primary ODU power supply by PC on ODU
SPECIFICATION
TX Power : Designed Value (dBm)
RX Level : Designed Value (dBm) +∫-3dB
Depends on the cable length between the IDU and ODU (PS for ODU -32 to -60 VDC)
TEST SET UP

TEST PROCEDURE

1- Connect the PC to the LCT port on the IDU using USB Cable.

2- Enter Login Name "Admin", enter Admin password "12345678"


and press the "login button.

3- Click 'Metering' button in LCT Menu.

4- The Value of Metering items are displayed.

5- Confirms the Value of TX Power and RX Level.

6- Confirm the value of Power supply voltage.

7- Verify the above specifications for each item.


ON-SITE TEST PROCEDURE

ITEM NO. TEST ITEM DESCRIPTION


3 AGC VOLTAGE CHECK
TEST PURPOSE
Measure the AGC Voltage

SPECIFICATION
satisfactory

TEST SET UP

TEST PROCEDURE

1- Connect LCT and select Maitenance, then select Maitenance1

2- Slect Maitenance mode as "ON".

3- Slect Antenna Alignment mode as "ON".

4- At each station, remove the cap from the RX LEV MON connector on the ODU

5- At each station, Connect cables to RX LEV MON connector using F-type plug
And either end of cable connect to digital voltmeter.

6- Measured the Voltage on the digital voltmeter.

7- Check the voltage depending on the indication of receiving level on LCT.

8- Remove the cable from the RX LEV MON connector on ODU and set
the cap for this connector
ON-SITE TEST PROCEDURE

ITEM NO. TEST ITEM DESCRIPTION


4 ORDER WIRE FUNCTION CHECK
TEST PURPOSE
Verify the Order Wire Function of each link

SPECIFICATION
Satisfactory

TEST SET UP

TEST PROCEDURE

1- Connect the Headset to "EOW" jack on the front panel of the


IDU of both end.

2- Press "CALL" button on the IDU.


Requirement at opposite the buzzer on the IDU is activated.

3- Check that the orderwise telephone talking with both end


can be communicate by using Headsets.
ON-SITE TEST PROCEDURE

ITEM NO. TEST ITEM DESCRIPTION


5 LOOP BACK CHECK
TEST PURPOSE
Confirm the operation of Loop Back Mode.

SPECIFICATION IF Loop Back


Main CH Loopback (Near End)
Main CH Loopback (Far End)
TEST SET UP

TEST PROCEDURE

1- Connect the PC to the LCT port on the IDU using USB cable.

2- Click on maintenance1 menu, and set the maintenance mode "ON"

3- Click on IF Loopback ( ) button in maintenance1 menu.and set to "ON"

4- Confirm the Value field and succeedingthe process

5- Click on the setting button “Off” of the IF Loopback ( ) and


click on the “Set” button,

6- For Main CH Loopbacl (Near End), Click on the “Select” button and click on
the setting button “On” of the required CH#(s) to be loop back and click on
the “SET” button,

7- Confirm the Value field and succeedingthe process

8- Click on the setting button “Off” of the Main CH Loopback (Near End ) and
click on the “Set” button,
9- For Main CH Loopbacl Far End), Click on the “Select” button and click on
the setting button “On” of the required CH#(s) to be loop back and click on
the “SET” button,

10- Confirm the Value field and succeedingthe process

11- Click on the setting button “Off” of the Main CH Loopback (Far End ) and
click on the “Set” button,
ON-SITE TEST PROCEDURE

ITEM NO. TEST ITEM DESCRIPTION


6 LINK BER TEST
TEST PURPOSE
Verify the BER Characteristics of each link

SPECIFICATION
1 Hour errors check
Satisfied to 1 x 10⁻⁹ or less

TEST SET UP
Station A Station B

TEST PROCEDURE

1- Setup the link as above figure.

2- Click on maintenance1 menu, and set the maintenance mode "ON"

3- A Station A, Connect PC with PNMTj application and


Run the PNMTj application.

4- Apply Main CH Loopback (Far End) for selected CHs

5- Measure BER in one hour and confirm on the PNMTj display that
BER satisfies below requirement :
Requirement : 1x10e-9 or less

6- Set Main CH Loopback (Far End) for selected CHs in "OFF" mode.

7- Click on maintenance1 menu, and set the maintenance mode "OFF"


ON-SITE TEST PROCEDURE

ITEM NO. TEST ITEM DESCRIPTION


7 Frequency Interference Test
TEST PURPOSE
To Verify the Frequency interference if any

SPECIFICATION
RX level interference at sites OK/Not OK

TEST SET UP
Station A Station B

TEST PROCEDURE

1- Setup the link as above figure.

2- At Transmitting station B switch of the IDU.

3- At Station A Connect the PC and run LCT/Pnmtj application.

4- At station A measure the RX level through metering and confirm if


the RX singal is of acceptable limit.

5- Repeat the process for opposite station also.


NEC

PROVISIONAL ACCEPTANCE TEST


PROCEDURE (PAT)
OF
PASOLINK NEO/I (1+0)
32E1 + 2LAN INTERFACE CARD

P/J

NOV-08
NEC Corporation
Vendor: NEC DATE
CUSTOMER : IDEA CELLULAR LIMITED.
ON-SITE TEST STATION NAME :
DATE SHEETS STATION No. :
SYSTEM
CONFIGURATION TX FREQUENCY :___________________MHz (H/L)
(1+0)___GHZ-___QAM RX FREQUENCY :___________________MHz

NO. TEST ITEM SPECIFACTION RESULT


1 Visual Inspection ___________
1.1 Composition Satisfactory ___________
1.2 Structure Satisfactory ___________
1.3 Wiring Satisfactory ___________
2 Meter Reading* ___________
2.1 TX Power TX PWR ____dBm _______dBm
Calculated RX
2.2 RX Level (___dBm)+/3dBm _______dBm
3 AGC Voltage Check Satisfactory ___________
4 Order Wire Function Check Satisfactory ___________
5 Loop back Check Satisfactory ___________
6 Link BER Test Satisfactory ___________
7 Frequency Interference Test OK/Not OK _______dBm

NOTE : *This is the monitored reading by PC

Customer Remarks :

DATA TAKEN BY DATE


APPROVED BY DATE
WITNESSED BY DATE
ANNEXURE
SITE DETAILS:
NO. ITEM DATA
1 Azimuth

2 Cable Length

3 IF Cable Type

4 Antenna dia./Sr.No.

5 Antenna Type

6 Antenna Gain

7 Polarisation

8 Ant Heigh from ground.

9 Earth Resistance

10 Earth Cable from Equipment to Earth Bar

11 External Alarm Cabling

12 Grounding of ODU

13 Any Ext interface, if interfaced

14 Protected/Non-Protected Configuration

15 Antenna Mounting Pole Length

16 Antenna Mounting Pole diameter

Table-1: Equipment Details

Equipment Sr No.
ODU 1

ODU 2 (for 1+1 Configuration)

IDU (1+0/1+1)
Table-2: Installation Checks

Check Item Specification Result


Equipment Mounting on rack OK/NOT OF

Frame grounding of Equipment OK/NOT OF

Fiber/PCM Cable wiring/routing OK/NOT OF

Fiber/PCM Cable Connection OK/NOT OF

IF Cable wiring/routing OK/NOT OF

IF Cable Connection OK/NOT OF

Labeling of IF & Fiber/PCM cables OK/NOT OF

MCB Rating OK/NOT OF

MCB Connection OK/NOT OF

MCB Labeling OK/NOT OF

Antenna Labeling OK/NOT OF

Customer Remarks:

Customer Representative Name: DATE: SIGN:

NEC Representative Name: DATE: SIGN:

Services Provider Representative DATE: SIGN:


Name: