Sei sulla pagina 1di 4

Mechanical system

Air conditioning system

 VRF system for game zone and cinema


 Check out door unit work properly
 Check indoor unit work properly
 Test hand over must be done again
 Heat pumps for hot water generation
 Cold water inlet pipes are not properly insulated
 Check valves not insulated for dual pump system
 Heat pump condenser fins are damaged/misaligned
 Hot water line needs insulation
 Test and handover must be done again
 Cold room at basement
 Test and handover
 Outdoor unit holds much amount of ice/should be checked
 Split AC for projector and server room
 Outdoor units can be covered by perforated board
(for aesthetics valve)
 Drainage system should be permanent with piping
(not it is with bucket)
 Test hand over

Ventilation

 Car parking ventilation


 Obstacles around cc fan
 Kitchen ventilation
 Roof kitchen hood needs grease filter and oil cap
 Electric connection not done yet(for roof kitchen fan)
 Fake celling should be done for 10th floor kitchen fan
 Toilet ventilation
 All fans should work throughout the day
 Staircase pressurization system
 Not functional
 Fan is not connected to fire alarm and unitary power source
 Relief damper are not installed properly
 Projector ventilation duct can be connected with galvanized duct
 Gym ventilation, game zone ventilation, screen ventilation, steam and sauna ventilation, projector
ventilation, shower room ventilation
 All fans
 Supply fans need proper filter and must be cleaned weekly
 Exposed fans can be covered by perforated board
 All fans should be tested and handover again
Mechanical system 2

 Firefighting system
 Diesel pups lacks batteries
 Each fire hydrant hose and sprinklers should be tested
 System should be tested and handover again
 Fire extinguisher
 Expired dates passed
 Positon of extinguishers should be discussed
 Light
 Communicate with installers for any problem
 Gym, game zone, soft play mechanical equipments
 Tightening of bolts
 Delt machine mechanical problem
 Arm curl unbalance problem
 Pec deck
 Leg extension arm length
 Leg extension pin damage
 Leg press
 Total adjustment
 Abdominal crunch spring problem
 Trade male
 Generator room
 Permanent fuel filling system should be done
(Backward filling)
 Window cleaner light
 Prepare pulley system for the cable

Electrical system

 Kitchen equipments
 Show case refrigerant, deep freezer capacitor not functional
 Pizza making plate should be changed
 Laundry equipments
 Some washing machine and driers are not functional
 Check and test all laundry machines
 Fire alarm system
 Check integration with staircase and firefighting system
 Test all points
 Window cleaner light
 Test all cleaners
 Electric cables
 Most cables of the building are not properly wired
 High tension transfer cables
 Automatic transfer switch cables
 Roof communication cables
 Cables at electrical boards
 Electrical boards
 Some boards are damaged(not lockable)
 Wiring inside the boards is poor
 Electronics
 Cinema equipments
 Projector
 Screen must be checked
 Sound system
 Game equipments
 UPS battery problem
 Check and maintain game equipments
 Sound system should be checked- (speaker-leather toy)
- (hop top/tab-climbing hall)
 Gym equipments
 Check and maintain gym equipments
 Car parking gate and exit system
 Check and test the system
 Lighting+ floor head lights and exit lights
 Screen, Tv
 UPS room
 Kwh recording card for rental shops
 Sanitary system
 Water tankers
 Check leakage
 Hot and cold water lines
Check leakage
 Insulation for hot water pipe line
 Correction work for heat pump line
 Split AC drainage system is temporary
 Check each gate valve and hoses at each toilet
 Check firefighting pipe lines, sprinklers must be tested again
 Sink+ WC+ shower+ hand washes+ soap box should be checked and maintaine
 Civil works
 Water proofing
 Walls+ paints+ gypsum board+ materials are damaged with the problem of
water proofing in most places
 Wall+ window+ door+ lockers
 Some windows are broken
 Some locker keys are damaged
 Some doors are not functional and some with locking problem
 Emergency exit is not functional- doors must be connected to exit stair
 Floor
 Pu+ CARPET PROBLEM AT CINIMA
 Chair+ table
 Some tables and chairs are damaged
 Some VIP cinema chairs need electrical maintenance
 Front VIP cinema chairs are blocked by rail
 Rail at cinema has light reflection
 Others
 Hand rails should be installed at heat pump roof area
 Some RHS and welding points need anti rust and paint
 False celling and perforated board is necessary for exposed fans and split AC
outdoor units
 Car parking speed brake needs maintenance
 2nd floor kitchen floor drain has bad smell
 2nd floor kitchen cinema kitchen sun reflection

Potrebbero piacerti anche