Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Future NAP
Position
AML (Actual Measured Loss) of the Feeder lines from CO must be secured first prior to actual build
LCP and NAP pole-mount closure positions are fixed and installed facing road side
Provide 30m maintenance loop on feeder side, NO loop on succeeding LCPs and NAPs
Maintenance loop should be placed on PLDT poles only, NEVER on Meralco poles
For future or expansion NAPs, PROVIDE 5m loop at the identified locations where they will be installed
REMOVE messenger wire of expansion loop
PLACE expansion loop on the side of the future NAP facing the central office; same for future LCPs
SECURE the expansion loop with 3 cable ties and electrical tape, separated 120° apart
Cable Tie
INSTALL LCP and NAP 1 to 2 feet below center bolt of C1 pole clamp; DO NOT install on
poles with transformer C1
MINIMUM clearance between LCP/NAP to ground is 12 ft
For NAPs:
INSTALL two (2) bridle rings on both sides and one (1) at the bottom 1’ - 2’ Guy Grip
PLACE the bottom bridle ring 5” to 6” directly under the drop cable ports
ROUTE the 24F Figure 8 FOC opposite the drop cable ports side of the NAP going
to the main cable ports. C2
DO NOT route on the same side where the drop cables are, so as not to
disturb the drops.
NO bridle rings required at LCP positions Bridle Ring
Drop
DO NOT route the 24F Figure 8 FOC through the bridle ring
Cable
Bridle rings are DEDICATED for drop cable use only
USE cable tie for added support
To 24F Figure 8 FOC on the guy grip
To secure the stub cable to the pole
Once cable ties are installed, cut any excess 24F Figure 8
5” - 6” FOC
side.
Double
With RTA issue, limited space and with constraints on the pole or NAP
adjacent poles
USE double NAP (2 splitters/NAP), INSTALLED facing road side.
≥ 12ft
PROVIDE 2 additional SS buckles on the SS Straps (1 buckle/strap) that secures the LCP on the pole
SECURE the LCP cable stub to the 2 additional SS buckles with yellow tie cable.
Yellow Tie
Additional Cable
SS Buckle
LCP Cable
Stub
24F
FOC
SS
Strap Exposed Stainless
messenger Steel
wire Strap
To GRD
Ground
Rod
Clamp
Ground
Rod
WRAP the 24F Figure 8 FOC with a ½ HDPE pipe, to protect and insulate it from electrical contacts
Length of HDPE pipe should be 16”
SECURE both ends of the HDPE pipe with electrical tape
18” x ½”
Power Line HDPE pipe
24F Fig 8
FOC
Traditional
Fiber Optic
Cable
24F Figure 8
Semi-Dry Fiber
Optic Cable
8 core x 3 buffer
Figure 8
Fiber Optic
Cable
(for Aerial)
Sub-feeder
If insertion point is underground, USE Traditional FOC
If insertion point is aerial, USE Figure 8 FOC
Distribution: LCP-to-NAP, USE Figure-8 FOC
Traditional
Fiber Optic
Cable
24F Figure 8
Semi-Dry Fiber
Optic Cable
8 core x 3 buffer
Figure 8
Fiber Optic
Cable
(for Aerial)
LCP NAP
MKT
MKT LP1
LP1 NP1
Bi-Directional Optical Insertion Loss & Optical Insertion Loss Measurement using Optical Loss Test Set (OLTS)