Sei sulla pagina 1di 24

27 September 2016

CONSTRUCTION METHOD: POLE-MOUNT LCP & NAP

Loop for Future NAP


w/ Cable Tie

Future NAP
Position

 AML (Actual Measured Loss) of the Feeder lines from CO must be secured first prior to actual build
 LCP and NAP pole-mount closure positions are fixed and installed facing road side
 Provide 30m maintenance loop on feeder side, NO loop on succeeding LCPs and NAPs
 Maintenance loop should be placed on PLDT poles only, NEVER on Meralco poles
 For future or expansion NAPs, PROVIDE 5m loop at the identified locations where they will be installed
 REMOVE messenger wire of expansion loop
 PLACE expansion loop on the side of the future NAP facing the central office; same for future LCPs
 SECURE the expansion loop with 3 cable ties and electrical tape, separated 120° apart

TECHNICAL STANDARDS DIVISION


LCP / NAP

Cable Tie
 INSTALL LCP and NAP 1 to 2 feet below center bolt of C1 pole clamp; DO NOT install on
poles with transformer C1
 MINIMUM clearance between LCP/NAP to ground is 12 ft
 For NAPs:
 INSTALL two (2) bridle rings on both sides and one (1) at the bottom 1’ - 2’ Guy Grip
 PLACE the bottom bridle ring 5” to 6” directly under the drop cable ports
 ROUTE the 24F Figure 8 FOC opposite the drop cable ports side of the NAP going
to the main cable ports. C2
 DO NOT route on the same side where the drop cables are, so as not to
disturb the drops.
 NO bridle rings required at LCP positions Bridle Ring
Drop
 DO NOT route the 24F Figure 8 FOC through the bridle ring
Cable
 Bridle rings are DEDICATED for drop cable use only
 USE cable tie for added support
 To 24F Figure 8 FOC on the guy grip
 To secure the stub cable to the pole
 Once cable ties are installed, cut any excess 24F Figure 8
5” - 6” FOC

TECHNICAL STANDARDS DIVISION


GUY GRIP

 For Fig. 8 24F/48F/72F FOC, USE 1/7” Guy Grip

 For Fig. 8 144F/216F, USE 3/16” Guy Grip

TECHNICAL STANDARDS DIVISION


GUY GRIP

TECHNICAL STANDARDS DIVISION


DOUBLE NAP (2-SPLITTERS / NAP)
 For Greenfield Areas
 NO double NAP allowed
 With no RTA issue
 If Eng’g design requires > 8 NAP ports, USE 2 NAPs (1 splitter /
NAP), INSTALLED side-by-side on the pole facing road side. ≥ 12ft

 If with limited space or with constraints on the pole to


accommodate 2 NAPs, USE adjacent poles (1 NAP/pole).
≥ 12ft

 With RTA issue


 If Eng’g design requires > 8 NAP ports, USE 2 NAPs (1 splitter /
NAP), INSTALLED on adjacent poles (1 NAP / pole) facing road ≥ 12ft

side.

TECHNICAL STANDARDS DIVISION


DOUBLE NAP (2-SPLITTERS / NAP)

 For Brownfield Areas


 With no RTA issue and available space
 If Eng’g design requires > 8 NAP ports, USE 2 NAPs (1 splitter /
NAP), INSTALLED side-by-side on the pole facing road side. ≥ 12ft

Double
 With RTA issue, limited space and with constraints on the pole or NAP
adjacent poles
 USE double NAP (2 splitters/NAP), INSTALLED facing road side.
≥ 12ft

TECHNICAL STANDARDS DIVISION


LCP CABLE STUB

 PROVIDE 2 additional SS buckles on the SS Straps (1 buckle/strap) that secures the LCP on the pole
 SECURE the LCP cable stub to the 2 additional SS buckles with yellow tie cable.

Yellow Tie
Additional Cable
SS Buckle

LCP Cable
Stub

TECHNICAL STANDARDS DIVISION


GROUNDING OF FIGURE 8 FOC
 Ground messenger wire of Figure 8 FOC every end of aerial NAP and every LCP position
 Route messenger wire for grounding on the side of the LCP facing the central office
 KEEP insulation of messenger wire (DO NOT strip or remove cable sheath)
 EXTEND and CONNECT messenger wire directly to ground (ground rod)
 SECURE messenger wire to the pole with three (3) stainless steel strap

Messenger Yellow Tie


Wire Messenger
Cable
Wire

24F
FOC
SS
Strap Exposed Stainless
messenger Steel
wire Strap
To GRD
Ground
Rod
Clamp

Ground
Rod

TECHNICAL STANDARDS DIVISION


HOOKS WITH NUT ON POLE WITH NAP
 INSTALL hooks with nut together with pole clamps on every pole where NAP is installed and
for future location of NAPs
 INSTALL two (2) hooks, one (1) facing left and the other facing the right side of the street
 For end poles with NAP, meaning poles installed at dead-ends or road-ends
 INSTALL only one (1) hook and should be installed facing the open section of the
street

TECHNICAL STANDARDS DIVISION


24F FIGURE 8 FOC PROTECTION WHEN CROSSING ELECTRICAL CABLES

 WRAP the 24F Figure 8 FOC with a ½ HDPE pipe, to protect and insulate it from electrical contacts
 Length of HDPE pipe should be 16”
 SECURE both ends of the HDPE pipe with electrical tape

18” x ½”
Power Line HDPE pipe

24F Fig 8
FOC

TECHNICAL STANDARDS DIVISION


ODN DESIGN
(for UG)

Traditional
Fiber Optic
Cable

24F Figure 8
Semi-Dry Fiber
Optic Cable
8 core x 3 buffer

Figure 8
Fiber Optic
Cable
(for Aerial)

 Sub-feeder
 If insertion point is underground, USE Traditional FOC
 If insertion point is aerial, USE Figure 8 FOC
 Distribution: LCP-to-NAP, USE Figure-8 FOC

TECHNICAL STANDARDS DIVISION


ODN DESIGN
(for UG)

Traditional
Fiber Optic
Cable

24F Figure 8
Semi-Dry Fiber
Optic Cable
8 core x 3 buffer

Figure 8
Fiber Optic
Cable
(for Aerial)

 For all constructions, INSTALL Splice Closure before 1st LCP


 Splice closure should be located at main road, or
 Outside (before entry) the subdivision or village

TECHNICAL STANDARDS DIVISION


ODN DESIGN

TECHNICAL STANDARDS DIVISION


FIBER ASSIGNMENTS OF LCPS/NAPS USING 24-FIBER CABLE (8-CORE / 3-BUFFER)

TECHNICAL STANDARDS DIVISION


FIBER ASSIGNMENTS OF LCPS/NAPS USING 24-FIBER CABLE (8-CORE / 3-BUFFER)

TECHNICAL STANDARDS DIVISION


LCP DETAILS

TECHNICAL STANDARDS DIVISION


NAP DETAILS

TECHNICAL STANDARDS DIVISION


LCP / NAP NAMING CONVENTION

 For stenciling to LCP and NAP

LCP NAP

MKT
MKT LP1
LP1 NP1

MKT - Town/Municipality/City Code


LP1 - LCP Number (Sequential Numbering per Town)
NP1 - NAP Number homing LP1 (Sequential Numbering)

TECHNICAL STANDARDS DIVISION


LCP / NAP / FDC STENCILING

 USE Town/City/Municipality 3-letter code used by CSOZ


 FONT: Bold Arial; FONT SIZE: 100 (equal to 1”)
 Stencil shall be vertical and left-aligned
 Spacing shall be 0.375 in. (equal to 0.95 cm.)
 USE quick dry epoxy enamel spray paint
 BLACK on light colored background
 WHITE on dark colored background

FiberHome Fibercom Fujikura Tyco Fiberhome FDC

TECHNICAL STANDARDS DIVISION


ODN ACCEPTANCE

 Acceptance Test Protocol


 Checklist, End-to-End Test Forms, As-Built Plans, OLT PON Port Assignments,
LCP/NAP Keys
 Acceptance Test Protocol should be complete and ready prior to start of any
acceptance activity
 NO acceptance activities shall commence if above required documents are incomplete
 PM, as head of the Acceptance Committee, shall make sure;
 Completeness of the Acceptance Test Protocol
 All necessary materials and equipment needed before start of actual activities
are available
 Acceptance Committee shall compose of the following;
 PM
 End-user (Zone and FxATOp)
 Contractor
 WRITE all remarks and comments in the Acceptance Test Protocol.
 After completion of the acceptance activities, the Acceptance Test Protocol shall be
signed-off by the members of the Acceptance Committee.
 PM to furnish the Acceptance Committee with a copy of the signed ATP after
confirming completeness of the document.

TECHNICAL STANDARDS DIVISION


SECTIONALIZED ACCEPTANCE TESTING (PRE-TEST)

 Bi-Directional Optical Insertion Loss & Optical Insertion Loss Measurement using Optical Loss Test Set (OLTS)

TECHNICAL STANDARDS DIVISION


SERVICE ACTIVATION TESTING (ACCEPTANCE TESTING)

 Power Level Testing at Subscriber Side using Power Meter


 Repair Margin = 1 dB
 Keep records of all splicing and repair done on the link

TECHNICAL STANDARDS DIVISION

Potrebbero piacerti anche