TASKS ON HAND WITH PRIORITY

Sr.No Work Description Priority

3 Air consumption balance A

7 Drum filling pump A

9 Air comp.power A

13 MSGL CAL.CHECK A

18 N2 consumption & mass bal. B

19 Cooling water COC fixing A

25 Breathing air comp.review A

27 Sulphur lifting device A

28 Project cost update A

36 Minimise pollution during E2BB filling. A

44 Final P&ID - Ipbr in E2BB stream. A


45 Finalisation of hopper arrangement for benzle peroxide. A
Finalisation of hopper arrangement for sulpher in Srbr2
46 A
buffer.
58 Rotameter offer checking A

87 Table for AODD - Pressure Vs.Flow A

88 Update common vent scrubber proposal A


89 Selection & installation of polishing filter for IPBr A

91 Breathing air comp.proposal A

Inform Ele.Team about rotary valve -location/cable/push


92 A
button.

97 Indenting of HAZOP eq. A


98 Finalization of cartridge filter for IPBr & it's installation A
TASKS ON HAND WITH PRIORITY

First Person
Target Date Remarks
Responsible

Completed, the air consumption by CV is to be verified by


Brijesh Completed
Mr. Nilesh Talsaniya. Follow-up taken on 08.11.2019

Completed, finalised as per MOC test and reference


Brijesh Completed patents to use SS-316 Centrifugal Pumps available with us
for drum filling of E2BB & 1-3 BCP
Completed, VFD power saving cost compared and
Brijesh Completed
finalised to procure AC with VFD for ETP
Latest revision sent by GMM is validated and circulated to
Brijesh Completed
all for approval

Brijesh Completed Sheet prepared on 13.11.2019, to be reviewed by Amit Sir

Work Under Progress, to be discussed with Amit Sir and


Brijesh 23.11.2019 JSG . Discussed on 15.10.2019 and details given by Amit
Sir are under monitoring
Finalised after meeting with Shri MVP to procure air
Brijesh Completed
cooled breathing air compressor
To be discussed with JSG and Amit Sir regarding
BJ
requirement
Brijesh Completed Completed, Project Cost updated on 05.11.2019
To be discussed with HGD for manometer fitting in blower
Brijesh Completed
suction line
BH Completed Work Under Progress
BH Completed Hopper Arrangement Finalised

BH Completed Hopper Arrangement Finalised

Brijesh Completed Offer checked for all the three rotameters


Completed on
Brijesh Draft prepared, to be validated
18.11.2019
HB Completed Proposal prepared, review pending
HB Work Under Progress

Proposal Draft prepared, compressor, dryer and receiver


Brijesh Completed
location finalised, costing and drawings input is pending

informed to Marubhai regarding rotary valve and details of


Brijesh Completed electrical motor, location also shown in plant for cable
laying and push button
Brijesh Completed Indenting is done, Indent No: 378
BJ Completed Work Under Progress