Sei sulla pagina 1di 44

Olympic Delivery Authority

The Big Build: Completion


Milestones to 27 July 2011

July 2010

DWT2XV2dX[S*
3^\_[TcX^]
Over the past three years the Olympic Delivery
Authority (ODA) has set out in advance the
milestones it has planned to achieve for different
In April 2007 the Olympic Delivery Authority
phases of the project.
(ODA) set out 10 major milestones that it
planned to achieve by the Closing Ceremony
The first 10 milestones – known as ‘Demolish, Dig,
of the Beijing 2008 Games.
Design’ – focused on preparing the site for the main
construction
These of the
milestones willvenues and
provide theinfrastructure
foundations for the
London
for 2012 Olympic
the delivery and Paralympic
of the venues Games,
and infrastructure
ofand
the the legacy
London beyond
2012 2012.
Olympic and Paralympic
Games and the legacy beyond.
The second 10 were the first phase of construction –
The delivery of these milestones on time and
‘The Big Build: Foundations’. They focused on putting
within budget will be underpinned by five
in place the foundations of the main venues and
priority themes: design and accessibility,
infrastructure in the Olympic Park. These were followed
equality and inclusion, health and safety,
by the next phase – ‘The Big Build: Structures’.
legacy and sustainability.
AtAllthe
these
endmilestones have
of 2007 the ODA now
is been delivered.
on track
toThe
hit project remains on track and within budget.
its milestones.
This document sets out 10 new milestones that the
This publication sets out these 10 milestones
ODA plans to achieve by 27 July 2011 – a date
and the progress made by the end of 2007.
one year from the Opening Ceremony of the
London 2012 Olympic Games.

The construction of the venues and infrastructure for the London 2012 Games is funded by the National Lottery
through the Olympic Lottery Distributor, the Department for Culture, Media and Sport, the Mayor of London and
the London Development Agency.

On the cover: a view from inside the Olympic Stadium


3^]cT]cb
Foreword Page 5

Aerial view of the Olympic Park, June 2010 Page 6

Part one: Previous milestones Page 8


Milestones to the Beijing 2008 Games – Demolish, Dig, Design
Milestones to 27 July 2009 – The Big Build: Foundations
Milestones to 27 July 2010 – The Big Build: Structures

Part two: Milestones to 27 July 2011 Page 11


Milestone 01: Construction of the Olympic Stadium will be complete Page 12
and the venue ready to be handed over.

Milestone 02: Construction of the Aquatics Centre will be complete Page 14


and the venue ready to be handed over.

Milestone 03: Construction of the Velodrome will be complete and Page 16


the venue ready to be handed over.

Milestone 04: Construction of the International Broadcast Centre/ Page 18


Main Press Centre (IBC/MPC) will be complete and ready for
occupation by the Olympic Broadcasting Service and the
London 2012 Organising Committee.

Milestone 05: Construction of the Handball and Basketball Arenas Page 20


will be complete and the venues ready to be handed over.

Milestone 06: Construction of the Lee Valley White Water Centre Page 22
will be complete and the venue handed over to Lee Valley Regional
Park Authority.

Milestone 07: Construction work on Eton Manor and Royal Artillery Page 24
Barracks will be underway and on track to be completed as planned
in spring 2012.

Milestone 08: The external structure of the Olympic Village will Page 26
be finished with the internal fit out complete in most of the blocks.

Milestone 09: Construction of all permanent bridges will be complete. Page 28


All utilities will be operational. Landscaping will be well advanced
across the Park.

Milestone 10: Construction work at Stratford Regional Station will Page 32


be complete, with Londoners already benefiting from hundreds
of millions of pounds of additional investment across London’s
transport system.

Priority themes Page 36


Design and accessibility; Employment and skills; Equality and
inclusion; Health, safety and security; Legacy; Sustainability

The Big Build: Completion – Olympic Delivery Authority 3


Workers finish cladding the northern face of the Energy Centre
6^aTf^aS
27 July 2010 marks two years to go to the Opening Ceremony of the
London 2012 Olympic Games. Over the past 12 months, the Olympic Park
has changed dramatically. With the structures of the main sporting venues
complete, you can now get a real feel for the layout of the Park and the
compact nature of the site.

We would like to pay tribute to our world-class contractors and workforce


who have, once again, helped us to hit all our milestones. There have been
many challenges over the past year – not least the very difficult winter – but
they have risen to them all.

We are now entering our final year of the ‘big build’ – the construction of
John Armitt
the main venues and infrastructure on the Park – and we are setting ourselves
Chairman
10 challenging completion milestones for the coming year.
Olympic Delivery Authority
As an organisation, the Olympic Delivery Authority said in 2006 that it
would complete the main construction work by summer 2011, so the major
venues are ready to be handed over. We are on track to do this, but we
are not complacent: this remains the most challenging phase of the project.
Health and safety must remain our highest priority.

We are doing all this in what is obviously a difficult economic environment.


Our programme is helping to create thousands of jobs up and down the
country, as well as filling order books for UK plc.

As the Games get closer, the eyes of the world will increasingly turn to
London. As the venues are completed, people will see for themselves
the exciting stage for the Games in 2012 and the lasting legacy for
David Higgins London and the UK that will be left as a result.
Chief Executive
Olympic Delivery Authority

After the ‘big build’

Although the main venues and infrastructure are on track to be completed


a year before the London 2012 Games, there will still be some limited work
on the Olympic Park in the final year, as was always planned.

For example, the Olympic Village has always had a later completion date
in autumn 2011.

With the main construction finished across the site, we will be able to open
up and begin work on the fringes of the Park. For example, the site of the
warm-up track in the south of the Park is currently the location of a logistics
hub and concrete batching plant. Eton Manor in the north of the Park will
be completed in spring 2012.

In the final year, works will also be underway on some of the temporary
facilities, including the Water Polo Arena, located next to the Aquatics Centre,
An artist’s impression of the inside of the the catering facilities in the International Broadcast Centre/Main Press Centre,
Water Polo Arena during the Games and the Shooting venue in Woolwich Arsenal.

The Big Build: Completion – Olympic Delivery Authority 5


?[h\_XR@PaZeT]dTb

05

04

03

02

01

6 The Big Build: Completion – Olympic Delivery Authority


06

07

08

09

Key to venues
An aerial view of the Olympic Park
looking from south to north, June 2010.

01 Olympic Stadium
02 Energy Centre and
Primary Substation
03 Handball Arena
04 International Broadcast
Centre/Main Press Centre
05 Velodrome
06 Basketball Arena
07 Olympic Village
08 Stratford City shopping centre
09 Aquatics Centre

The Big Build: Completion – Olympic Delivery Authority 7


@aTeX^db\X[Tbc^]Tb
Milestones to the Beijing
2008 Games
demolish, dig, design

Milestone 01 Milestone 02 Milestone 03 Milestone 04


The majority of With the tunnels The main The installation
the Olympic Park and cabling temporary roads of new water
will be cleared complete, the and bridges will and energy
and cleaned. power for the have been built, systems that
Olympic Park giving access to will serve the
will be set a safe and secure Olympic Park
to switch construction site during and after
underground. for the ‘big build’. the London 2012
Read more about the 10 milestones Games will
to the Beijing 2008 Games in have started.
‘demolish, dig, design’. This
can be downloaded from the
London 2012 website at:
www.london2012.com/milestones

Milestone 05 Milestone 06 Milestone 07 Milestone 08 Milestone 09 Milestone 10


The regeneration The transport Construction will Construction Contracts will The development
of the waterways enhancements have started on on the Olympic have been let of the Legacy
will have started, that will open the bridge that Village will and designs Masterplan
improving the up east London will take people have started. agreed for the Framework (LMF)
environment and and support the over the Aquatics ‘big four’ venues for the Olympic
access for the London 2012 Centre to the in the Olympic Park will be well
‘big build’. Games will have Olympic Stadium. Park – and at advanced.
started, with Building work on venues outside
many complete. the Stadium will London work
be about to begin. on site will
have started.

8 The Big Build: Completion – Olympic Delivery Authority


Milestones to 27 July 2009
the big build: foundations

Milestone 01 Milestone 02 Milestone 03 Milestone 04


Almost all of the Seven bridges The new Primary The foundations
Olympic Park will be structurally Substation at Kings of the Olympic
will have been complete, 10 Yard will be Stadium will be
cleared and further bridges substantially complete. Work
cleaned. The and underpasses complete, with the on the upper
overhead pylons will be under new equipment also seating structure
will have been construction and in place to transmit and roof will
Read more about the 10 milestones removed and the the building of permanent power be underway.
to 27 July 2009 in ‘the big build: erection of the the permanent to the Olympic Park
new perimeter roads will have from the wider
foundations’. This can be
security fence started. The national network.
downloaded from the
will be underway. refurbishment of The construction
London 2012 website at:
the waterways in of the new Energy
www.london2012.com/milestones the Olympic Park Centre will be
will be complete. well underway.

Milestone 05 Milestone 06 Milestone 07 Milestone 08 Milestone 09 Milestone 10


The foundations Work will have Contracts will Building work Significant Outside of
of the Aquatics started on the have been let, will be underway progress will London the
Centre will have foundations of designs agreed on the majority have been made ODA works at
been completed the Velodrome and work will of the Olympic on the transport Weymouth and
with work on and International be about to Village plots. projects that Portland will have
the building’s Broadcast start on the are increasing been completed
structure well Centre/Main Handball Arena. capacity to and ready for
underway. Press Centre. The design of support the use. Construction
the Basketball Games. Of the work will have
Arena will have 25 underway, also started on
been agreed, 13 will be the Lee Valley
and the process nearing White Water
of appointing completion. Centre.
construction
contractors will
be underway.

The Big Build: Completion – Olympic Delivery Authority 9


Milestones to 27 July 2010
the big build: structures

Milestone 01 Milestone 02 Milestone 03 Milestone 04


The structure The Aquatics The Velodrome The structure of
of the Olympic Centre’s structure and the International
Stadium including permanent roof will be Broadcast Centre
the roof will be structure and complete, with and multi-storey
complete. The roof will be work about to car park will
first seats will be complete and all start on installing be finished,
fitted and work three swimming the timber track. with roof and
Read more about the 10 milestones on the field pools will be wall cladding
to 27 July 2010 in ‘the big build: of play about dug out. well underway.
structures’. This can be downloaded to start. The Main Press
from the London 2012 website at: Centre’s structure
www.london2012.com/milestones will be nearing
completion.

Milestone 05 Milestone 06 Milestone 07 Milestone 08 Milestone 09 Milestone 10


The Handball The majority All works will More than half of The Energy All major transport
Arena and of the Olympic be complete at the new bridges Centre, Primary improvements will
Basketball Arena Village homes the Eton Dorney and underpasses Substation, main be in progress
structures will will be structurally Rowing venue. will be complete sewer and deep or complete, and
be in place with finished and The new lake and and parts of the sewer pumping the next level of
internal works internal works competition courses Olympic Park station will all detailed planning
underway. will have started. at Lee Valley White Loop Road be operational. for transport
Building work All the major Water Centre will in operation. operations during
will have begun infrastructure be finished with the Planting will the Games will
on the new Eton needed to facilities building have begun The Energy have been
Manor sporting support the almost complete. A across the Park. Centre will now completed.
facilities. development planning application be operational
will be complete. will have been in autumn 2010,
submitted for the and will be
Shooting facilities commissioned
at the Royal in line with
Artillery Barracks. requirements for
heating across
the Olympic Park.

10 The Big Build: Completion – Olympic Delivery Authority


=X[Tbc^]Tbc^"':d[h" !!
DWT2XV2dX[S*3^\_[TcX^]

The Big Build: Completion – Olympic Delivery Authority 11


Milestone 01

BPXbX]VcWTQPa
By 27 July 2011: Construction On the evening of 27 July 2012, the for the cabling needed for the
of the Olympic Stadium will Olympic Stadium will be a burst of ceremonies, Olympic Broadcasting
sound, light and energy, when the Service and timing equipment.
be complete and the venue
Opening Ceremony marks the start The ground is now being prepared
ready to be handed over. of the London 2012 Games. and flattened in readiness for the
first layer of surfacing for the athletics
Throughout the Games, the Stadium track. The final track surface will
will be at the heart of the action, be laid in summer 2011, when the
hosting the Olympic and Paralympic environmental conditions will be
Athletics competitions as well as the most suitable for laying track.
Opening and Closing Ceremonies
of both Games. The first of the 80,000 seats have
already been put in place and the
The venue is already structurally remainder will be installed over
complete and will be finished a year the coming winter.
before the Games. Its cable-net roof
will provide the optimum conditions Work is well underway inside the
for athletes on the field of play Stadium, where there is a 60m
and cover two-thirds of spectators. warm-up track and 700 rooms,
The 14 lighting towers have been including medical rooms, showers,
lifted into place, taking the Stadium toilets and changing rooms.
to its full height, 60m above the field
of play. The floodlights will be tested The fitting out of the interior, from
and switched on for the first time plumbing in showers and toilets to
in autumn 2010. tiling changing rooms, will continue
through the rest of 2010 and the
Work is already progressing on the first part of 2011, so it is ready to
field of play: a drainage system has be handed over.
been installed, along with ducts

An aerial view of the Olympic Stadium. Its cable-net roof has a fabric
material covering, which will provide the optimum conditions for athletes
and cover two-thirds of spectators

12 The Big Build: Completion – Olympic Delivery Authority


!\\
accuracy to which the running track
will be laid

'"#X]RWTb
size of the two Panasonic TV screens
inside the Olympic Stadium

The Olympic Stadium’s first seats were installed in June 2010

The Big Build: Completion – Olympic Delivery Authority 13


Milestone 02

CcPacX]VQ[^RZb
By 27 July 2011: Construction Swimmers Rebecca Adlington and of the Modern Pentathlon. After
of the Aquatics Centre will be Eleanor Simmonds became household the Games the Centre will be
names at the Beijing 2008 Games. transformed into a much-needed
complete and the venue ready
The UK will be hoping we can repeat facility for the local community and
to be handed over. our medal success at home in the elite swimmers. The stands will be
new Aquatics Centre being built replaced with the Centre’s permanent
in the Olympic Park. glazed facade, leaving a venue
with a 2,500 capacity – although
The unique wave-like Centre, it will be possible to increase this
designed by international architect for major events.
Zaha Hadid, will be the gateway
to the Olympic Park in 2012 and The venue’s permanent structure and
the first venue that the majority of roof have already been completed,
spectators arriving at the Park from and the roof is covered and
Stratford Regional Station will see. watertight. The underside of the roof
They will walk across a vast land – the venue’s ceiling – is now being
bridge that spans a railway line, river lined with treated timber and this will
and the Aquatics Centre’s training be complete in spring 2011. Hidden
pool. The final section of this bridge from view by the spectacular
will be put in place by the end of wave-like roof, the two 50m
2010, once the steel structures of swimming pools and 25m diving
the venue’s two temporary ‘wing’ pool have been dug out, lined
seating stands have been built. with concrete and filled with water
to test they are watertight before
The foundations for these 42m-high they are tiled.
seating stands are nearing
completion. Their steel structures Tiling will begin in summer 2010
will be erected by the end of 2010, and be completed by the end of
then covered with a transparent the year. The pools can then be
cladding in the first part of 2011. filled with swimming water to test
The first concrete terracing units for the filtration tanks and system by
the venue’s permanent seating are the end of spring 2011, when it
already in place, and the installation will be ready to be handed over.
of the seats will be completed by
27 July 2011. The Water Polo Arena will be
located next to the Aquatics Centre.
The temporary stands increase the Planning permission is pending for
capacity of the venue to 17,500 this 5,000-capacity temporary
during the Games, when it will host venue and construction is due to
Swimming, Paralympic Swimming, start on site in spring 2011.
Diving and the Aquatics discipline

An artist’s impression of the Aquatics Centre during the London 2012 Games

14 The Big Build: Completion – Olympic Delivery Authority


! \X[[X^]
litres of water in the Aquatics
Centre’s pools

'&(
tiles in the Aquatics Centre

The three Aquatics Centre pools were lined and filled with water
to test them, before tiling begins in summer 2010

The Big Build: Completion – Olympic Delivery Authority 15


Milestone 03

2Tb_^ZTeT]dT
By 27 July 2011: Construction Following the success of Britain’s to let in abundant daylight, reducing
of the Velodrome will be cyclists at the Beijing 2008 Games, the need for artificial lighting. Its
there will be high expectations design collects rainwater that will
complete and the venue
for medal success at the London reduce mains water usage by more
ready to be handed over. 2012 Velodrome. than 70 per cent.

Sir Chris Hoy, who won three medals The structure of the 6,000-seat venue
in Beijing, joined other experts on the has been completed and its cable-net
venue’s design panel, to help ensure the roof lifted into place. The glass wall
best possible conditions for participants that will encircle the venue between
in the Cycling and Paralympic Cycling the lower and upper tiers is being put
events – with the aim of creating the in place and will be completed later
world’s fastest Velodrome. The speed this year. This will give spectators
of the track is determined by a range views across the Park and out to the
of factors including the slope of London skyline.
the track, the temperature and
environmental conditions. The installation of the rails for the
venue’s 6,000 seats has started, with
The ultra-fast track will be made of all seating due to be finished by the
Siberian pine – certified by the Forest end of 2010. The Velodrome is due to
Stewardship Council. The pine is being be completed in spring 2011, ready
prepared and will be delivered to the to be handed over.
Olympic Park in summer 2010, ahead
of its installation. This will enable the Meanwhile, a 6,000-seat BMX
timber to acclimatise before it is fitted, Circuit is being built alongside
to stop it expanding or contracting the Velodrome. An internationally
after it is put in place. During the renowned BMX track designer has
Games, a high temperature will be been appointed and construction will
maintained at track level to optimise start on site in spring 2011. It is due to
the performance of the athletes. be completed by late summer 2011.

The Velodrome is one of the most After the Games, the circuit will be
sustainable venues on the Park. Its reconfigured and joined by a new
lightweight structure and cable-net mountain bike track and road cycle
roof saved substantial amounts of circuit, forming a VeloPark for the local
material and associated carbon community, cycling clubs and elite
emissions during their manufacture. athletes. This new cycling hub will be
owned, managed and funded by the
The venue is naturally ventilated and Lee Valley Regional Park Authority.
has strategically positioned roof-lights

Workers complete the Velodrome’s cable-net roof

16 The Big Build: Completion – Olympic Delivery Authority


!&Z\
cabling used in the Velodrome’s
cable-net roof

"( ^R
Temperature at track level during
races at the London 2012 Games

A view inside the Velodrome, before its cable-net roof was covered

The Big Build: Completion – Olympic Delivery Authority 17


Milestone 04

<XVWcbRP\TaPPRcX^]
By 27 July 2011: Construction The International Broadcast Centre/ broadcasters and the media in good
of the International Broadcast Main Press Centre (IBC/MPC) will time for the start of the Games.
be a 24-hour hub for more than
Centre/Main Press Centre
20,000 broadcasters, journalists After the Games, the buildings
(IBC/MPC) will be complete and photographers during the will offer a total of 80,000sq m of
and ready for occupation by London 2012 Games. Together, business space with the potential
the Olympic Broadcasting they will convey the excitement to generate thousands of new jobs.
Service and the London 2012 of the London 2012 Games to The facilities have been designed
Organising Committee. an estimated four billion people to be adapted for a wide range of
around the world. potential tenants after the Games:
either single tenants occupying the
The giant structure of the IBC is entire buildings, or multiple tenants
already complete and fully clad. on each floor.
A temporary gantry structure on the
outside of the building has also been The multi-storey car park that will
finished. This will hold equipment serve the media during the Games
that will service the building, such and tenants of the development
as air-conditioning units, fans afterwards is also structurally
and back-up generators, thereby complete. It is due to be complete
maximising space within the building in autumn 2011, once the final work
and reducing background noise inside, such as lighting and lifts, has
for broadcasters. been finished and tested.

The MPC will have four storeys of Because the media will be working
offices and studios for journalists around the clock, the complex will
and photographers. Its 29,000sq m have a temporary catering village,
structure has been completed and is including a 4000-seat restaurant,
now being covered. It is due to be 800-capacity media conference
fully clad in autumn 2010. room and a 200m-long ‘high
street’, with outlets such as banks,
The building has a ‘brown roof’, newsagents, travel agents and
which uses seeds and logs reclaimed a post office.
from the Olympic Park construction
site to encourage new wildlife. A planning application for the
groundworks for these temporary
Throughout the rest of 2010 and the facilities has been submitted, with
first half of 2011, both the IBC and the main planning application due
MPC will be fitted out and furnished, to follow in early autumn 2010.
with both buildings complete by Construction is due to start on all the
27 July 2011. This will allow for facilities early in 2011 and will be
the installation of the equipment for well underway by 27 July 2011.

An artist’s impression of the International Broadcast Centre during the


London 2012 Games

18 The Big Build: Completion – Olympic Delivery Authority


% 
meals served each day in the
24-hour IBC/MPC catering village
during the London 2012 Games

!#
bird and bat boxes on the Main
Press Centre

An aerial view of the International Broadcast Centre/Main Press Centre (IBC/MPC)


showing the IBC (front), MPC (back left) and multi-storey car park (back right)

The Big Build: Completion – Olympic Delivery Authority 19


Milestone 05

>TcVPX]b
By 27 July 2011: Construction Handball Arena The retractable seating is due to be
of the Handball and Basketball The structure of the new multi-use fitted from spring 2011 and by 27 July
sports centre being built in the 2011 the venue will be fully complete
Arenas will be complete
west of the Olympic Park has been and ready to be handed over.
and the venues ready to be completed in the past year.
handed over. Basketball Arena
The cladding of the Arena’s walls The Basketball Arena will be one of
has started, and the venue’s copper the most heavily used venues within
covering will follow later this summer. the Olympic Park, with competition
To give it a distinctive appearance, events taking place every day during
the recycled copper has been the London 2012 Games, watched
aged, then treated to stop it ageing by around half a million spectators.
further, before it is installed. The roof
will feature 88 light pipes to allow During the Olympic Games, the
natural light into the venue, reducing Arena will host the Basketball
the demand for electric lights. preliminaries and quarter-finals, and
the Handball semi-finals and finals.
The concourse level that encircles During the Paralympic Games it
the venue will be glazed, enabling will be the venue for Wheelchair
visitors to the Park to see the sport Basketball and Wheelchair Rugby.
taking place inside and illuminating
the venue when lit at night. This, The Arena’s giant frame was erected
along with the wall and roof in less than three months during
covering, is due to be complete spring 2010. It has been covered
during autumn 2010. in fabric that will form the canvas
for spectacular lighting during the
The installation of the venue’s Games. The temporary seating and
timber-sprung field of play will accommodation around the venue
begin in early 2011 and is due will start to be installed this summer
to be complete in the spring. with the Arena on track to be
complete in spring 2011.
The Arena’s permanent terraced
seating will be fitted towards the Different contractors have been
end of 2010, followed by its employed to construct each
retractable seating. This will allow element of the venue, such as
the seating capacity to be flexible, its frame, seating and modular
enabling the venue to be used for accommodation. These parts are
different activities after the Games, owned by the respective contractors,
ranging from community sport to who will dismantle, take away and
international competition. reuse or recycle the parts elsewhere
after the Games.

A view from inside the completed structure of the Handball Arena

20 The Big Build: Completion – Olympic Delivery Authority


"$\
height of the doorways in the athlete’s
facilities at the Basketball Arena

$(
hours to get the Handball Arena
ready for the Modern Pentathlon
Fencing events after the Handball
finishes, including replacing the
Handball mat with the ten Fencing
pistes and installing new scoreboards

Workers finish covering the structure of the Basketball Arena

The Big Build: Completion – Olympic Delivery Authority 21


Milestone 06

GPeTb^U_a^VaTbb
By 27 July 2011: Construction Lee Valley White Water Centre Weymouth and Portland
of the Lee Valley White Water In spring 2011, the Lee Valley White The enhancements to the Weymouth
Water Centre in Hertfordshire will and Portland National Sailing
Centre will be complete and
be the first new London 2012 venue Academy (WPNSA) were completed
the venue handed over to Lee to open to the public – more than in 2008 – the first London 2012
Valley Regional Park Authority. a year before the London 2012 sporting venue to be finished. The
Games. People of all abilities – from works included the construction of
elite athletes to beginners – will a new slipway and 70 moorings,
be able to raft or canoe down the boat parking and crane piers.
two white water courses at the
centre, which will be run before The works are already benefiting the
and after the Games by the Lee sailing community, helping athletes to
Valley Regional Park Authority prepare for the Games and benefiting
(LVRPA). During the Olympic the local area before the Games begin.
Games the centre will host the
Canoe Slalom events. Eton Dorney
Work at a second sporting venue
The two courses are being built from was completed in spring 2010. Eton
scratch: a 300m competition course College Rowing Centre, near Windsor,
and a 160m intermediate/training Berkshire, will host the Rowing,
course. A new starting lake has been Paralympic Rowing and Canoe Sprint
constructed and the white water is events during the Games. The venue
created through a system of pumps has a 2,200m, eight-lane rowing
and obstacles placed along the course, warm-up lanes and competition
courses. A new facilities building facilities. Although the facilities were
is also being constructed. already world-class, improvements were
needed to ensure the venue met the
The lake, courses and pumps have particular requirements of the Games.
been finished, and the facilities
building is structurally complete. An additional cut-through has been
created at the 1,400m mark, to allow
The centre is due to be handed competitors to get from the return lane
over to the LVRPA in autumn 2010. to the competition course. Previously
Before then, the facilities building the only cut-through was at the 600m
and viewing mounds around the mark. Two bridges have also been
course will be completed and the installed. The first spans the new
two courses commissioned. LVRPA cut-through, while the other has
will own and operate the Lee Valley replaced the existing finish line
White Water Centre. bridge with a wider one.

The new finish line bridge at Eton Dorney was lifted into place early in 2010

22 The Big Build: Completion – Olympic Delivery Authority


'\_W
speed of parts of the competition
course at the Lee Valley White
Water Centre

"
sporting venues (Eton Dorney and
Weymouth and Portland) complete
and in use more than two years
ahead of the Games

An aerial view from May 2010 of the Lee Valley White Water Centre, showing the facilities
building (centre) and, in blue, the starting points of the intermediate and Olympic courses

The Big Build: Completion – Olympic Delivery Authority 23


Milestone 07

D^cWT\P]^aQ^a]
By 27 July 2011: Construction Eton Manor The tennis courts and stands are
work on Eton Manor and Work began in June 2010 on the due to start in autumn 2010 and will
final permanent sporting facilities be structurally complete by summer
Royal Artillery Barracks will
being built in the Olympic Park. 2011. The temporary pools and
be underway and on track buildings needed for the Games will
to be completed as planned Eton Manor will host Wheelchair follow and are due to be completed
in spring 2012. Tennis during the London 2012 in spring 2012.
Paralympic Games. Throughout the
Games, it will have five temporary Royal Artillery Barracks
training pools for participants in Unlike at most previous Games,
Aquatics events. competitors in the Shooting events
at the London 2012 Games will
After the Games, the area will be be close to the heart of the action,
transformed into sporting facilities enabling the participants to stay
for the local community, including with their teammates in the Olympic
a tennis centre with four indoor and Village. During their event, the
six outdoor courts, a hockey centre athletes – and spectators – will enjoy
with two pitches, and space for ten the spectacular backdrop of the
five-a-side football pitches that will be historic Royal Artillery Barracks in
added in the future. It is hoped that Woolwich, which date from the
the hockey pitches will be relocated 18th century.
from the Hockey Centre, which will
be constructed by the London 2012 Four temporary indoor ranges for
Organising Committee (LOCOG) Pistol and Rifle Shooting are being
within the Olympic Park. built, along with outdoor shotgun
ranges for Trap and Skeet events.
The detailed design of the Eton Temporary spectator grandstands
Manor facilities is complete and the will be provided at each Shooting
contractors undertaking different range. After the Games, the indoor
parts of the facilities have all 10m Shooting range will be taken
been appointed. Work to prepare down and relocated to provide
the ground levels and form the shooting facilities elsewhere in
foundations of the temporary the UK.
swimming pools is underway.
The proposed facilities have been
The main sports complex will house the granted planning permission and
hockey centre and the indoor tennis a design team has been appointed.
courts after the Games. Work has A construction contractor will be
begun on its foundations, which are appointed by the end of 2010 to
due to be complete in autumn 2010, start on site early in 2011.
followed by the structure early in 2011.

An artist’s impression of the new facilities at Eton Manor, where the Wheelchair
Tennis will take place during the London 2012 Paralympic Games

24 The Big Build: Completion – Olympic Delivery Authority


"
war memorials at Eton Manor that will
be stored off site during construction,
then returned to the newly landscaped
area after the Games

!
new tennis courts for use by the
local community at Eton Manor after
the Games

An aerial view (from east to west, with the A12 running down the left)
showing Eton Manor at the start of construction

The Big Build: Completion – Olympic Delivery Authority 25


Milestone 08

2TSbU^aPcW[TcTb
W^\TbU^a<^]S^]Tab
By 27 July 2011: The external An entire new community is taking After the Games, the Village will
structure of the Olympic Village shape on the Olympic Park in east be transformed into one-, two-,
London. More than 2,800 homes three- and four-bedroom properties.
will be finished with the internal
are being constructed on the Kitchens will be installed and
fit out complete in most of Olympic Village site, along with temporary partitions removed to
the blocks. a new educational academy, form the final living spaces and
multi-use community space and bedrooms. New timber or carpet
healthcare facilities. flooring will also be fitted.

There will be 11 residential plots, Construction has also started on


each made up of six to eight blocks, the new education campus being
with a mix of affordable homes and built within the Village site. After the
housing for sale and rent. Games, Chobham Academy will
provide 1,800 places for students
Five of these residential plots are aged 3–19 in nursery, primary and
structurally complete – one of which secondary schools, and an FE college
has been fully clad – and the others with adult-learning facilities. During
are approaching their full height. the Games, it will be used as an
Across all the plots, three-quarters of operations centre. The structure of
the floors are structurally complete. All the academy will be completed by
plots will be complete during autumn autumn 2010 and it will be clad
2010 and clad by the end of the year. by the end of the year.

As the blocks are completed, they Work has also started on the
will start to be fitted out. Temporary foundations of the Polyclinic, which
partitions will be put in to create will serve existing local communities
the rooms where around 17,000 and the residents of the Village
athletes and officials will stay during after 2012. Run by NHS Newham,
the Games. Bathrooms, lighting, the facilities will include multiple
telecommunications and temporary GP surgeries, outpatient and
flooring will also be installed. physiotherapy services, a children’s
clinic and facilities for X-ray and
By 27 July 2011, most of the blocks ultrasound. During the Games, the
will be fitted out with the rest facilities will be used by athletes.
completed in autumn 2011. The Polyclinic is due to be structurally
complete in spring 2011.

An aerial view of construction on Chobham Academy (bottom right), the new


educational facilities being built within the Olympic Village

26 The Big Build: Completion – Olympic Delivery Authority


&"
blocks across the 11 residential plots

!#')
affordable homes in the Olympic
Village after the Games, to be
managed by Triathlon Homes

An aerial view of the construction on the Olympic Village

The Big Build: Completion – Olympic Delivery Authority 27


Milestone 09

3WP]VX]VcWTUPRT
^UcWTTPacW
By 27 July 2011: Construction New green spaces The Park is a carefully designed
of all permanent bridges will The new parklands in the Olympic ecosystem with an interconnected
Park will be a venue in themselves series of habitats, such as otter holts,
be complete. All utilities will
for tens of thousands of spectators at sandmartin banks, bird and bat
be operational. Landscaping the London 2012 Games. Visitors will boxes, frog ponds, compost heaps
will be well advanced across be able to soak up the atmosphere and wormeries.
the Park. in the parklands and enjoy the rivers,
woodlands and ornamental gardens The Park’s landscape has been
– or watch the sporting action on designed to collect rainwater and
live screens within the Park. filter it slowly through a network of
frog ponds and reed beds, rather
Long after 2012, tens of thousands than let it drain straight back into
more visitors will be able to enjoy the the river system. The irrigation
meadows, gardens, woods and river needed to establish new plants will
walks in the parklands, which were use non-potable water from the new
inspired by the original Victorian waste-water treatment facility that will
public parks of London. recycle sewerage from the Northern
Outfall Sewer under The Greenway.
The north of the parklands will be
ecologically diverse, with a range Connecting communities
of new wildlife habitats, meadows, More than 30 bridges are being
woodlands and wetlands. Planting built to span the numerous rivers
in the north of the Park will be and railways that run through the
substantially complete during the Park and create links across the
coming autumn/winter, with the Park during the Games. After the
earthworks and planting complete Games, the majority will remain and
by 27 July 2011. There will also be connect the communities within and
spectator lawns at two of the highest surrounding the Park with the new
points of the Park, offering views parklands and sporting venues.
across London.
More than half of the bridges and
The southern parklands will have a underpasses are structurally complete
more ‘urban’ feel than in the north. with work underway on nearly all the
They will also be the location of remaining structures. The completed
the London 2012 Gardens. These structures include the five bridges
ornamental gardens will celebrate linking the Olympic Stadium ‘island’
the British tradition of collecting site with the rest of the Park, and a
and cultivating plants. Around 250 new link into the Park underneath
different species will be planted in the busy A12 dual carriageway in
different world zones. the north-east corner of the Park.

As well as the setting for the Games, A ‘backbone’ for regeneration


the parklands will also be a working Just as construction is transforming
landscape. The wetland bowls and the Olympic Park above ground, the
wet woodlands in the north of the ‘big build’ is also progressing under
Park will help to manage floodwater, the surface. An entirely new utilities
protecting the rest of the Park and infrastructure is being installed to
4,000 existing homes around the Park meet the demands of the London
from a one-in-a-hundred-year storm. 2012 Games, and to provide
a ‘backbone’ for the long-term
development of the area.

28 The Big Build: Completion – Olympic Delivery Authority


"%
different species in the
London 2012 Garden

# 
wetland plants in the Olympic Park

The first trees have been planted in the wet woodlands in the north of the
Olympic Park – view looking south to the Aquatics Centre

The Big Build: Completion – Olympic Delivery Authority 29


Milestone 09 continued

A new Energy Centre in the diverted, removed or disconnected.


west of the Park is ready to be The electricity pylons that dominated
operational in autumn 2010 and the landscape were removed by
will be commissioned in line with the end of 2008, with the power
requirements for heating across moved into two new 6km tunnels
the Park. Throughout the coming underneath the Park. By the
year it will begin providing heat end of 2010, the permanent
to the different construction sites. infrastructure for the new network
During the Games, the Centre will of utilities (gas, water, electricity,
provide heating, cooling (for air telecommunications and sewerage)
conditioning) and power for the will be complete and used by
venues across the Park. After the contractors on the Park.
Games, it will contribute power and
provide heating for the local area. All the contracts are in place for
the operation of these utilities to be
A Primary Substation has been adopted by private companies by
built alongside the Energy Centre 27 July 2011. For example, Thames
to distribute electricity efficiently Water will take on the water and
from the wider national network sewerage networks. The electricity
to the venues around the Park network is owned by Lee Valley
and the developments in the area Utilities, a wholly-owned subsidiary
after 2012. It was completed in of EDF, and Cofely will own and
autumn 2009 – almost three years operate the Energy Centre.
before the Games – when it began
supplying power to the Stratford Work has begun on a waste-water
City development. recycling plant in partnership with
Thames Water. This will help to
The original utility networks reduce the use of potable water
underneath the Park have been on the Park.

The Primary Substation, which was completed in autumn 2009, won the
Royal Institute of British Architects (RIBA) Award for ‘Commercial and
Industrial Building of the Year’ in May 2010

30 The Big Build: Completion – Olympic Delivery Authority


$ 
reduction in the use of potable
water that the Olympic Delivery
Authority is aiming to achieve on
the Olympic Park

The new Pumping Station (pictured) and sewer network within the Olympic Park
is operational. It will collect, convey and remove waste-water from the main
venues and buildings within the Park during and after the London 2012 Games

The Big Build: Completion – Olympic Delivery Authority 31


Milestone 10

7aTT][XVWcPWTPS
By 27 July 2011: Construction The Olympic Delivery Authority platforms, and new lifts and
work at Stratford Regional (ODA) is funding or contributing staircases installed. A third subway
funding to a series of improvements will be opened by the autumn.
Station will be complete, with
to transport infrastructure to create Together, these will improve
Londoners already benefiting a safe, reliable and accessible passenger flow at what will become
from hundreds of millions transport system for the increased the interchange for 10 rail routes
of pounds of additional numbers of passengers during with 19 platforms. In autumn 2010,
investment across London’s the Games. a new Central Line platform will
transport system. open, allowing passengers to exit
The improvements – many of which trains on both sides and interchange
are already complete – will leave or leave the station more easily.
lasting benefits after the Games and
transform this part of east London Next to SRS, a developer is building
into one of the best connected the new Stratford City shopping
areas of the capital. Londoners centre – within which will be a new
are already benefiting from the northern entrance/exit to the station
many enhancements that have – and a bridge linking Stratford
been completed. City to the existing town centre. The
bridge will also join up with the new
Stratford Regional Station mezzanine-level entrance/exit that
Currently 37,000 people use has been built for the ODA on the
Stratford Regional Station (SRS) south side of SRS. This new southern
during morning peak hours and this entrance/exit will open in autumn
is estimated to increase to 83,000 2010, while the shopping centre
by 2016. During the Games it will and bridge are scheduled to open
be one of the three ‘gateway’ stations in autumn 2011. During the Games,
to the Olympic Park, when it will spectators will be able to use the
be used by an estimated 120,000 new exits and bridge to reach
people, including around 80,000 the Olympic Park through the new
spectators at peak times. The ODA Stratford City shopping centre.
is investing around £125 million
to treble the station’s capacity and Two new platforms for the London
improve its accessibility. Overground’s North London Line
(NLL) opened at SRS in spring 2009.
Already, platforms have been The former NLL platforms at the
lengthened and widened, more station are being modified, so
space has been created on the they can be used as a stop

An artist’s impression of the new mezzanine-level entrance to Stratford


Regional Station. It will link to a bridge that will take spectators to the new
Stratford City shopping centre and on to the Olympic Park

32 The Big Build: Completion – Olympic Delivery Authority


!
different rail routes will serve Stratford
Regional Station during and after
the London 2012 Games, making it
the most connected station in London
other than King’s Cross St. Pancras

Later this year, a new staircase will lead from the front of Stratford Regional Station
up to the new mezzanine-level station entrance (centre), and from next year to a bridge
leading to the new Stratford City shopping centre

The Big Build: Completion – Olympic Delivery Authority 33


Milestone 10 continued

on a new branch of the Docklands Transport during the Games


Light Railway (DLR). This will run While Londoners start benefiting
from Canning Town to Stratford from improvements to transport
International Station. The new infrastructure two years or more
line – along with four new stations before the London 2012 Games
– is nearly complete and due to begin, the ODA is continuing to
open in 2010. develop its plans for how transport
will operate during the Games.
By the end of 2010, the ODA’s
improvements to SRS will be Comments have been received
complete. They will all be on the draft second edition of the
operational, except for the new ‘Transport Plan for the London 2012
northern exit/entrance, which will Olympic and Paralympic Games’
open when the developer opens during the consultation period and
the new shopping centre. an updated second edition of
the plan is due to be published
In addition, a series of other by the end of 2010.
improvements to London’s transport
infrastructure will also be in place Together with its delivery partners,
for the London 2012 Games. These the ODA is finalising the levels of
include: a second new Docklands service needed during the Games
Light Railway (DLR) line; the new across all transport modes. It is
East London Line; increased capacity also looking at venue-specific
and frequency on the Jubilee Line, transport needs, such as levels of
DLR and North London Line; new shuttle bus services, or Blue Badge
and improved piers for river services and bicycle parking.
on the Thames; a new ticket hall
at King’s Cross; and enhancements
to more than 100 walking and
cycling routes.

The introduction of three-car trains on the Docklands Light Railway to increase


capacity is among the improvements to transport infrastructure, benefiting
Londoners ahead of the London 2012 Games

34 The Big Build: Completion – Olympic Delivery Authority


!"
walking and cycling schemes on nine
routes are being created or enhanced
before the London 2012 Games

The Greenway, a 7km walking and cycling route, will provide access to the Olympic Park for around
20 per cent of Games spectators, including those arriving from West Ham Station. The Olympic Delivery
Authority has made improvements to a 2.3km section from Wick Lane to Manor Road (near West Ham
Station) to make it more accessible, safer, and more appealing

The Big Build: Completion – Olympic Delivery Authority 35


@aX^aXchcWT\Tb
The delivery of the venues and infrastructure for the London 2012
Games are underpinned by the Olympic Delivery Authority’s six
priority themes.

Design and accessibility


We are delivering design for the We also want the design of the range of disabilities both during and
London 2012 Games that combines venues within the Olympic Park to after the Games. We want to set an
excellence with innovation. We are deliver a striking visual statement excellent standard of accessibility
creating exciting, well-designed that reflects the importance of for disabled people, older people
venues that are an appropriate stage the Games, while ensuring they and families with children, which
for the greatest sporting and cultural are balanced with the urban will set a benchmark and act as
event on Earth. architecture and landscape that an inspiration to others.
define the area. After the Games
We are designing for the Games the venues must seamlessly connect
and legacy together. The venue with the parklands and urban
designs must obviously meet the neighbourhoods that surround them.
requirements of the Olympic and
Paralympic Games, but we are Inclusive design is at the heart of our
looking beyond 2012. We are only design process, and has been since
building permanent venues if there the project began. The Olympic
is a long-term use. We are being Village, the sporting venues, new
creative in the use of temporary transport services, supporting
venues and seating. facilities and the Park itself will be
accessible to people with a wide

The new green spaces within the Olympic Park have been designed to be
accessible and inclusive to all types of visitors, including wheelchair users,
families and people of all ages and faiths. To make sure everyone can move
through the parklands easily and comfortably, the pathways will be wide,
with smooth surfaces, shallow gradients and seating at regular intervals.

36 The Big Build: Completion – Olympic Delivery Authority


Employment and skills
Building the stage for the London Olympic Park, Olympic Village and We are establishing a link to skills
2012 Games will give people in Stratford City development – will development, including retraining
London and the UK unprecedented create around 30,000 jobs over the and sustainable employment, to
access to new jobs and career course of the construction period. equip people with the right skills
opportunities. We have the chance for future jobs in construction.
to get unemployed people into We want local people not only to
work and to improve the skills experience the excitement of hosting These efforts create a positive
within communities in east London the Games, but to help build them. employment and economic legacy
and beyond. We have established an integrated for London and the UK after the
approach to help local people to Games: the creation of new
As one of the largest construction get into jobs, develop skills and gain jobs; opportunities for continuing
projects in the country, we are new qualifications in construction, employment; an improved skills and
demonstrating our commitment in partnership with government, qualification base among local
to increasing skills and providing contractors, training organisations, people; and better links between
learning opportunities, particularly sector skills councils, Jobcentre Plus employers and people looking for
given the current challenging and job brokerage networks in work. This will leave a highly skilled
economic climate. the five Host Boroughs (Hackney, workforce that can help deliver
Newham, Tower Hamlets, Waltham the Games, and go on to have
We anticipate that the three major Forest and Greenwich). sustainable and rewarding careers
Stratford-based projects alone – the in construction after 2012.

!))
apprentices working on the
construction programme at the
end of March 2010

Apprentice Jamie Norris from Chingford had already completed his first year
at college, where he was studying to become an electrician, when he was
offered the chance to work on the Olympic Park. Jamie was approached
by one of the Employment and Skills Managers, working closely with the
company providing electrical supplies for the International Broadcast Centre/
Main Press Centre. He started on site in August 2009.

The Big Build: Completion – Olympic Delivery Authority 37


@aX^aXchcWT\Tb

Equality and inclusion


The momentum provided by the helps to promote equal opportunities the Games, as well as leave a lasting
London 2012 Games and the for all and eliminate discrimination in legacy for equality and inclusion.
substantial investment in the Lower the workplace. We are working with
Lea Valley can have a significant partner organisations to encourage We celebrate the diversity of the
impact on reducing historic and women, black, Asian and minority population of the UK, London and
long-standing inequalities. ethnic people, and disabled people, the five east London Host Boroughs
to train and apply for jobs in and are committed to realising the
We want the economic and social construction and other areas advantages of this diversity in
benefits of the regeneration of the where they have traditionally delivering our programme. We
area, and the design and build of the been under-represented. are already engaging with and
Olympic Park and venues, to have a involving the local communities to
positive impact on local communities What we are building for 2012 and help us deliver an accessible and
and the UK. An example of how we beyond will be inclusive for people inclusive Games.
are achieving this is ensuring our of all cultures, faiths and ages, and
procurement process is transparent, fully accessible to disabled people
fair and open to a wider range of with a wide range of impairments.
diverse suppliers.
We will also provide an accessible
The way that we are recruiting and transport network that will give
managing employees is fair, and everyone the opportunity to enjoy

!&
women helped into a range of jobs
on the Olympic Park by the Olympic
Delivery Authority’s ‘Women into
Construction’ project

Zaynab Mahmoud, who is on an electrical placement on the Olympic


Stadium, is one of the beneficiaries of the Olympic Delivery Authority’s
‘Women into Construction’ project. This has already helped more than 160
women into a range of jobs on the Olympic Park and provided 412 women
with careers advice and guidance. It has also entered a further 173 women
into pre-employment training in practical construction skills, such as
working at heights.

38 The Big Build: Completion – Olympic Delivery Authority


Health, safety and security
The health and safety of everyone has harm due to unplanned events on the Tier 1 contractors are examples
been and remains a key priority. As a our sites. During the past year we of the radical, systematic and
best-practice organisation we are fully have been able to celebrate our comprehensive programme to which
compliant with applicable UK and 13th period of a million hours worked we are committed. This systematic
European legislation and standards. without a reportable accident. approach is ensuring that our
We are continually improving workforce is properly protected –
by integrating health and safety As well as focusing on preventing safety is no accident.
considerations into planning, design harm, we are committed to enhancing
and construction operations. the well-being of all involved in The combination of worker
the project, which is why we have involvement and personal leadership
We are providing a safe and secure established comprehensive on-site in tackling risks is sustaining our
environment by designing venues, occupational health facilities high standards and improving our
facilities, infrastructure and transport performance. We are working with
to help eliminate health and safety Every project has a clear strategy all our staff, partners, suppliers and
hazards during construction, operation, for worker engagement, marked their workforces to embed this culture
maintenance and decommissioning – by one of our health and safety and give the highest priority to health,
and to meet the needs of operational awards following wholly independent safety and security issues, and share
security during the Games. adjudication. Developing a new it with others across industry. Our
health and safety culture survey organised approach is independently
We aim to prevent illnesses, injuries, and forming a Leadership Team certificated to the international health
business losses and environmental involving senior representatives of and safety standard OHSAS 18001.

!#
periods of a million hours worked
without a reportable accident

"
workers seen each month by the
occupational health teams on the
Olympic Park and Olympic Village,
providing pre-employment medicals,
health surveillance, minor treatments
and other services.

Good practice in health, safety and the environment was recognised at the
ODA’s second Health, Safety and Environment Awards in July 2010. Among
the winners was Kerri Chambers, an apprentice bricklayer on the Olympic
Stadium, who won the ‘Apprentice of the Year’ award. Other awards were
made to teams and individuals in categories such as ‘Lessons Learned’,
‘Excellence in Training’ and ‘Workforce Engagement’.

The Big Build: Completion – Olympic Delivery Authority 39


@aX^aXchcWT\Tb

Legacy
The London 2012 Games offer a the Olympic Delivery Authority, the overhead powerlines, enhancing
unique opportunity to revitalise the is focused on the creation of the the ecology of the area and creating
Lower Lea Valley, transforming one Park and the development of the green, open spaces. Infrastructure in
of the most underdeveloped areas of venues, including their post-Games the area will be enhanced, especially
the UK into a benchmark 21st century transformation to remove temporary public transport networks, utilities
urban environment that reflects the elements and leave the venues in and disabled access. By planning
diverse and vibrant population their legacy form. the Games and their legacy together
of the area. now, we can ensure that they are
The second, led by the Olympic remembered, not only as a summer
We are harnessing this potential Park Legacy Company, is focused of fantastic sport, but also as the
to create a new park for London. on what the Park will be used for in catalyst for the regeneration of one
In addition to world-class facilities the years ahead. The two are closely of the most underdeveloped areas
for sports including athletics, cycling, linked, with venues and parklands of the UK.
hockey, swimming and tennis, there being designed with their long-term
will be homes for a new community, use in mind.
and green spaces in and around the
Olympic Park. We are transforming the physical
environment in and around the Park
The work can broadly be split by clearing and cleaning the site,
into two phases. The first, led by improving the waterways, burying

'%
pence in every £1 the Olympic
Delivery Authority is spending
is going on the long-term
regeneration of the area

The Aquatics Centre is one of the five sporting venues within the Olympic Park
that will remain after the Games. Together with the new Lee Valley White
Water Centre and improved facilities at Eton Dorney and Weymouth and
Portland, they will leave a sporting legacy for the local communities, sport
clubs and elite athletes.

40 The Big Build: Completion – Olympic Delivery Authority


Sustainability
We are creating venues, facilities and cent reduction in carbon emissions and enrich the biodiversity of the
infrastructure for the London 2012 from permanent buildings on the Lower Lea Valley. We are currently
Games that leave a lasting social, Olympic Park (against 2006 Building transporting 63 per cent (by weight)
economic and environmental legacy Regulations) by 2013. of construction materials to the Park
for London and the UK. While we by rail or river – exceeding our target
do this, we are minimising any other Our target is to reduce the amount of 50 per cent.
adverse impacts during the design of drinking water used in new
and construction of the Olympic Park, permanent venues by 40 per cent Our approach is unprecedented for
venues, infrastructure and housing. (against 2006 standards). To do this a development of this nature. We are
we are optimising the opportunities on track to achieve the targets we set
The Olympic Delivery Authority for efficient water use by collecting ourselves and we are now capturing
(ODA) has set itself and its contractors and reusing rainwater, and using lessons we have learnt. We want to
working on the Park a comprehensive water-efficient appliances and share our knowledge with the public
range of targets, which are non-potable water for irrigation and private sectors, raising the bar for
embedded in systems, processes, and flushing toilets. industry and providing a challenging
tools and the culture of the project. step change for urban development
We are creating more than 100 in the UK.
We are putting in new energy hectares of open space, which
infrastructure, which will help us are designed to reduce the risk
to achieve our target of a 50 per of flooding in the river valley

!(
million tonnes of material has been
delivered to the Olympic Park by rail

)(
of construction waste has been
reused, recycled or recovered

More than 650 bird and bat boxes are being installed across the Olympic
Park, including within bridge structures (pictured) and on the ‘brown roof’
of the Main Press Centre.

The Big Build: Completion – Olympic Delivery Authority 41


The construction of the venues and infrastructure for the London 2012 Games
is funded by the National Lottery through the Olympic Lottery Distributor,
the Department for Culture, Media and Sport, the Mayor of London and
the London Development Agency.

© 2010 Olympic Delivery Authority

The official Emblems of the London 2012 Games are © London Organising
Committee of the Olympic Games and Paralympic Games Limited (LOCOG)
2007. All rights reserved.

The emblems of the National Lottery, the London Development Agency, the
Department of Culture, Media and Sport, and the Mayor of London are
reproduced with the permission of the Crown and the other copyright holders
respectively. All rights reserved.

This publication is available on request in other languages


and formats. To obtain these please:
Phone 0808 100 2012
Email enquiries@london2012.com
Quoting reference number ODA 2010/091
This document can be found in the publications section of
london2012.com

Published July 2010


Printed at an environmentally aware ISO14001-certified printer on recycled paper.
Olympic Delivery Authority
23rd floor, One Churchill Place
Canary Wharf, London E14 5LN
Reception +44 (0)20 3 2012 000
Fax +44 (0)20 3 2012 001
london2012.com

Potrebbero piacerti anche