Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
July 2010
DWT2XV2dX[S*
3^\_[TcX^]
Over the past three years the Olympic Delivery
Authority (ODA) has set out in advance the
milestones it has planned to achieve for different
In April 2007 the Olympic Delivery Authority
phases of the project.
(ODA) set out 10 major milestones that it
planned to achieve by the Closing Ceremony
The first 10 milestones – known as ‘Demolish, Dig,
of the Beijing 2008 Games.
Design’ – focused on preparing the site for the main
construction
These of the
milestones willvenues and
provide theinfrastructure
foundations for the
London
for 2012 Olympic
the delivery and Paralympic
of the venues Games,
and infrastructure
ofand
the the legacy
London beyond
2012 2012.
Olympic and Paralympic
Games and the legacy beyond.
The second 10 were the first phase of construction –
The delivery of these milestones on time and
‘The Big Build: Foundations’. They focused on putting
within budget will be underpinned by five
in place the foundations of the main venues and
priority themes: design and accessibility,
infrastructure in the Olympic Park. These were followed
equality and inclusion, health and safety,
by the next phase – ‘The Big Build: Structures’.
legacy and sustainability.
AtAllthe
these
endmilestones have
of 2007 the ODA now
is been delivered.
on track
toThe
hit project remains on track and within budget.
its milestones.
This document sets out 10 new milestones that the
This publication sets out these 10 milestones
ODA plans to achieve by 27 July 2011 – a date
and the progress made by the end of 2007.
one year from the Opening Ceremony of the
London 2012 Olympic Games.
The construction of the venues and infrastructure for the London 2012 Games is funded by the National Lottery
through the Olympic Lottery Distributor, the Department for Culture, Media and Sport, the Mayor of London and
the London Development Agency.
Milestone 06: Construction of the Lee Valley White Water Centre Page 22
will be complete and the venue handed over to Lee Valley Regional
Park Authority.
Milestone 07: Construction work on Eton Manor and Royal Artillery Page 24
Barracks will be underway and on track to be completed as planned
in spring 2012.
Milestone 08: The external structure of the Olympic Village will Page 26
be finished with the internal fit out complete in most of the blocks.
We are now entering our final year of the ‘big build’ – the construction of
John Armitt
the main venues and infrastructure on the Park – and we are setting ourselves
Chairman
10 challenging completion milestones for the coming year.
Olympic Delivery Authority
As an organisation, the Olympic Delivery Authority said in 2006 that it
would complete the main construction work by summer 2011, so the major
venues are ready to be handed over. We are on track to do this, but we
are not complacent: this remains the most challenging phase of the project.
Health and safety must remain our highest priority.
As the Games get closer, the eyes of the world will increasingly turn to
London. As the venues are completed, people will see for themselves
the exciting stage for the Games in 2012 and the lasting legacy for
David Higgins London and the UK that will be left as a result.
Chief Executive
Olympic Delivery Authority
For example, the Olympic Village has always had a later completion date
in autumn 2011.
With the main construction finished across the site, we will be able to open
up and begin work on the fringes of the Park. For example, the site of the
warm-up track in the south of the Park is currently the location of a logistics
hub and concrete batching plant. Eton Manor in the north of the Park will
be completed in spring 2012.
In the final year, works will also be underway on some of the temporary
facilities, including the Water Polo Arena, located next to the Aquatics Centre,
An artist’s impression of the inside of the the catering facilities in the International Broadcast Centre/Main Press Centre,
Water Polo Arena during the Games and the Shooting venue in Woolwich Arsenal.
05
04
03
02
01
07
08
09
Key to venues
An aerial view of the Olympic Park
looking from south to north, June 2010.
01 Olympic Stadium
02 Energy Centre and
Primary Substation
03 Handball Arena
04 International Broadcast
Centre/Main Press Centre
05 Velodrome
06 Basketball Arena
07 Olympic Village
08 Stratford City shopping centre
09 Aquatics Centre
BPXbX]VcWTQPa
By 27 July 2011: Construction On the evening of 27 July 2012, the for the cabling needed for the
of the Olympic Stadium will Olympic Stadium will be a burst of ceremonies, Olympic Broadcasting
sound, light and energy, when the Service and timing equipment.
be complete and the venue
Opening Ceremony marks the start The ground is now being prepared
ready to be handed over. of the London 2012 Games. and flattened in readiness for the
first layer of surfacing for the athletics
Throughout the Games, the Stadium track. The final track surface will
will be at the heart of the action, be laid in summer 2011, when the
hosting the Olympic and Paralympic environmental conditions will be
Athletics competitions as well as the most suitable for laying track.
Opening and Closing Ceremonies
of both Games. The first of the 80,000 seats have
already been put in place and the
The venue is already structurally remainder will be installed over
complete and will be finished a year the coming winter.
before the Games. Its cable-net roof
will provide the optimum conditions Work is well underway inside the
for athletes on the field of play Stadium, where there is a 60m
and cover two-thirds of spectators. warm-up track and 700 rooms,
The 14 lighting towers have been including medical rooms, showers,
lifted into place, taking the Stadium toilets and changing rooms.
to its full height, 60m above the field
of play. The floodlights will be tested The fitting out of the interior, from
and switched on for the first time plumbing in showers and toilets to
in autumn 2010. tiling changing rooms, will continue
through the rest of 2010 and the
Work is already progressing on the first part of 2011, so it is ready to
field of play: a drainage system has be handed over.
been installed, along with ducts
An aerial view of the Olympic Stadium. Its cable-net roof has a fabric
material covering, which will provide the optimum conditions for athletes
and cover two-thirds of spectators
'"#X]RWTb
size of the two Panasonic TV screens
inside the Olympic Stadium
CcPacX]VQ[^RZb
By 27 July 2011: Construction Swimmers Rebecca Adlington and of the Modern Pentathlon. After
of the Aquatics Centre will be Eleanor Simmonds became household the Games the Centre will be
names at the Beijing 2008 Games. transformed into a much-needed
complete and the venue ready
The UK will be hoping we can repeat facility for the local community and
to be handed over. our medal success at home in the elite swimmers. The stands will be
new Aquatics Centre being built replaced with the Centre’s permanent
in the Olympic Park. glazed facade, leaving a venue
with a 2,500 capacity – although
The unique wave-like Centre, it will be possible to increase this
designed by international architect for major events.
Zaha Hadid, will be the gateway
to the Olympic Park in 2012 and The venue’s permanent structure and
the first venue that the majority of roof have already been completed,
spectators arriving at the Park from and the roof is covered and
Stratford Regional Station will see. watertight. The underside of the roof
They will walk across a vast land – the venue’s ceiling – is now being
bridge that spans a railway line, river lined with treated timber and this will
and the Aquatics Centre’s training be complete in spring 2011. Hidden
pool. The final section of this bridge from view by the spectacular
will be put in place by the end of wave-like roof, the two 50m
2010, once the steel structures of swimming pools and 25m diving
the venue’s two temporary ‘wing’ pool have been dug out, lined
seating stands have been built. with concrete and filled with water
to test they are watertight before
The foundations for these 42m-high they are tiled.
seating stands are nearing
completion. Their steel structures Tiling will begin in summer 2010
will be erected by the end of 2010, and be completed by the end of
then covered with a transparent the year. The pools can then be
cladding in the first part of 2011. filled with swimming water to test
The first concrete terracing units for the filtration tanks and system by
the venue’s permanent seating are the end of spring 2011, when it
already in place, and the installation will be ready to be handed over.
of the seats will be completed by
27 July 2011. The Water Polo Arena will be
located next to the Aquatics Centre.
The temporary stands increase the Planning permission is pending for
capacity of the venue to 17,500 this 5,000-capacity temporary
during the Games, when it will host venue and construction is due to
Swimming, Paralympic Swimming, start on site in spring 2011.
Diving and the Aquatics discipline
An artist’s impression of the Aquatics Centre during the London 2012 Games
'&(
tiles in the Aquatics Centre
The three Aquatics Centre pools were lined and filled with water
to test them, before tiling begins in summer 2010
2Tb_^ZTeT]dT
By 27 July 2011: Construction Following the success of Britain’s to let in abundant daylight, reducing
of the Velodrome will be cyclists at the Beijing 2008 Games, the need for artificial lighting. Its
there will be high expectations design collects rainwater that will
complete and the venue
for medal success at the London reduce mains water usage by more
ready to be handed over. 2012 Velodrome. than 70 per cent.
Sir Chris Hoy, who won three medals The structure of the 6,000-seat venue
in Beijing, joined other experts on the has been completed and its cable-net
venue’s design panel, to help ensure the roof lifted into place. The glass wall
best possible conditions for participants that will encircle the venue between
in the Cycling and Paralympic Cycling the lower and upper tiers is being put
events – with the aim of creating the in place and will be completed later
world’s fastest Velodrome. The speed this year. This will give spectators
of the track is determined by a range views across the Park and out to the
of factors including the slope of London skyline.
the track, the temperature and
environmental conditions. The installation of the rails for the
venue’s 6,000 seats has started, with
The ultra-fast track will be made of all seating due to be finished by the
Siberian pine – certified by the Forest end of 2010. The Velodrome is due to
Stewardship Council. The pine is being be completed in spring 2011, ready
prepared and will be delivered to the to be handed over.
Olympic Park in summer 2010, ahead
of its installation. This will enable the Meanwhile, a 6,000-seat BMX
timber to acclimatise before it is fitted, Circuit is being built alongside
to stop it expanding or contracting the Velodrome. An internationally
after it is put in place. During the renowned BMX track designer has
Games, a high temperature will be been appointed and construction will
maintained at track level to optimise start on site in spring 2011. It is due to
the performance of the athletes. be completed by late summer 2011.
The Velodrome is one of the most After the Games, the circuit will be
sustainable venues on the Park. Its reconfigured and joined by a new
lightweight structure and cable-net mountain bike track and road cycle
roof saved substantial amounts of circuit, forming a VeloPark for the local
material and associated carbon community, cycling clubs and elite
emissions during their manufacture. athletes. This new cycling hub will be
owned, managed and funded by the
The venue is naturally ventilated and Lee Valley Regional Park Authority.
has strategically positioned roof-lights
"( ^R
Temperature at track level during
races at the London 2012 Games
A view inside the Velodrome, before its cable-net roof was covered
<XVWcbRP\TaPPRcX^]
By 27 July 2011: Construction The International Broadcast Centre/ broadcasters and the media in good
of the International Broadcast Main Press Centre (IBC/MPC) will time for the start of the Games.
be a 24-hour hub for more than
Centre/Main Press Centre
20,000 broadcasters, journalists After the Games, the buildings
(IBC/MPC) will be complete and photographers during the will offer a total of 80,000sq m of
and ready for occupation by London 2012 Games. Together, business space with the potential
the Olympic Broadcasting they will convey the excitement to generate thousands of new jobs.
Service and the London 2012 of the London 2012 Games to The facilities have been designed
Organising Committee. an estimated four billion people to be adapted for a wide range of
around the world. potential tenants after the Games:
either single tenants occupying the
The giant structure of the IBC is entire buildings, or multiple tenants
already complete and fully clad. on each floor.
A temporary gantry structure on the
outside of the building has also been The multi-storey car park that will
finished. This will hold equipment serve the media during the Games
that will service the building, such and tenants of the development
as air-conditioning units, fans afterwards is also structurally
and back-up generators, thereby complete. It is due to be complete
maximising space within the building in autumn 2011, once the final work
and reducing background noise inside, such as lighting and lifts, has
for broadcasters. been finished and tested.
The MPC will have four storeys of Because the media will be working
offices and studios for journalists around the clock, the complex will
and photographers. Its 29,000sq m have a temporary catering village,
structure has been completed and is including a 4000-seat restaurant,
now being covered. It is due to be 800-capacity media conference
fully clad in autumn 2010. room and a 200m-long ‘high
street’, with outlets such as banks,
The building has a ‘brown roof’, newsagents, travel agents and
which uses seeds and logs reclaimed a post office.
from the Olympic Park construction
site to encourage new wildlife. A planning application for the
groundworks for these temporary
Throughout the rest of 2010 and the facilities has been submitted, with
first half of 2011, both the IBC and the main planning application due
MPC will be fitted out and furnished, to follow in early autumn 2010.
with both buildings complete by Construction is due to start on all the
27 July 2011. This will allow for facilities early in 2011 and will be
the installation of the equipment for well underway by 27 July 2011.
!#
bird and bat boxes on the Main
Press Centre
>TcVPX]b
By 27 July 2011: Construction Handball Arena The retractable seating is due to be
of the Handball and Basketball The structure of the new multi-use fitted from spring 2011 and by 27 July
sports centre being built in the 2011 the venue will be fully complete
Arenas will be complete
west of the Olympic Park has been and ready to be handed over.
and the venues ready to be completed in the past year.
handed over. Basketball Arena
The cladding of the Arena’s walls The Basketball Arena will be one of
has started, and the venue’s copper the most heavily used venues within
covering will follow later this summer. the Olympic Park, with competition
To give it a distinctive appearance, events taking place every day during
the recycled copper has been the London 2012 Games, watched
aged, then treated to stop it ageing by around half a million spectators.
further, before it is installed. The roof
will feature 88 light pipes to allow During the Olympic Games, the
natural light into the venue, reducing Arena will host the Basketball
the demand for electric lights. preliminaries and quarter-finals, and
the Handball semi-finals and finals.
The concourse level that encircles During the Paralympic Games it
the venue will be glazed, enabling will be the venue for Wheelchair
visitors to the Park to see the sport Basketball and Wheelchair Rugby.
taking place inside and illuminating
the venue when lit at night. This, The Arena’s giant frame was erected
along with the wall and roof in less than three months during
covering, is due to be complete spring 2010. It has been covered
during autumn 2010. in fabric that will form the canvas
for spectacular lighting during the
The installation of the venue’s Games. The temporary seating and
timber-sprung field of play will accommodation around the venue
begin in early 2011 and is due will start to be installed this summer
to be complete in the spring. with the Arena on track to be
complete in spring 2011.
The Arena’s permanent terraced
seating will be fitted towards the Different contractors have been
end of 2010, followed by its employed to construct each
retractable seating. This will allow element of the venue, such as
the seating capacity to be flexible, its frame, seating and modular
enabling the venue to be used for accommodation. These parts are
different activities after the Games, owned by the respective contractors,
ranging from community sport to who will dismantle, take away and
international competition. reuse or recycle the parts elsewhere
after the Games.
$(
hours to get the Handball Arena
ready for the Modern Pentathlon
Fencing events after the Handball
finishes, including replacing the
Handball mat with the ten Fencing
pistes and installing new scoreboards
GPeTb^U_a^VaTbb
By 27 July 2011: Construction Lee Valley White Water Centre Weymouth and Portland
of the Lee Valley White Water In spring 2011, the Lee Valley White The enhancements to the Weymouth
Water Centre in Hertfordshire will and Portland National Sailing
Centre will be complete and
be the first new London 2012 venue Academy (WPNSA) were completed
the venue handed over to Lee to open to the public – more than in 2008 – the first London 2012
Valley Regional Park Authority. a year before the London 2012 sporting venue to be finished. The
Games. People of all abilities – from works included the construction of
elite athletes to beginners – will a new slipway and 70 moorings,
be able to raft or canoe down the boat parking and crane piers.
two white water courses at the
centre, which will be run before The works are already benefiting the
and after the Games by the Lee sailing community, helping athletes to
Valley Regional Park Authority prepare for the Games and benefiting
(LVRPA). During the Olympic the local area before the Games begin.
Games the centre will host the
Canoe Slalom events. Eton Dorney
Work at a second sporting venue
The two courses are being built from was completed in spring 2010. Eton
scratch: a 300m competition course College Rowing Centre, near Windsor,
and a 160m intermediate/training Berkshire, will host the Rowing,
course. A new starting lake has been Paralympic Rowing and Canoe Sprint
constructed and the white water is events during the Games. The venue
created through a system of pumps has a 2,200m, eight-lane rowing
and obstacles placed along the course, warm-up lanes and competition
courses. A new facilities building facilities. Although the facilities were
is also being constructed. already world-class, improvements were
needed to ensure the venue met the
The lake, courses and pumps have particular requirements of the Games.
been finished, and the facilities
building is structurally complete. An additional cut-through has been
created at the 1,400m mark, to allow
The centre is due to be handed competitors to get from the return lane
over to the LVRPA in autumn 2010. to the competition course. Previously
Before then, the facilities building the only cut-through was at the 600m
and viewing mounds around the mark. Two bridges have also been
course will be completed and the installed. The first spans the new
two courses commissioned. LVRPA cut-through, while the other has
will own and operate the Lee Valley replaced the existing finish line
White Water Centre. bridge with a wider one.
The new finish line bridge at Eton Dorney was lifted into place early in 2010
"
sporting venues (Eton Dorney and
Weymouth and Portland) complete
and in use more than two years
ahead of the Games
An aerial view from May 2010 of the Lee Valley White Water Centre, showing the facilities
building (centre) and, in blue, the starting points of the intermediate and Olympic courses
D^cWT\P]^aQ^a]
By 27 July 2011: Construction Eton Manor The tennis courts and stands are
work on Eton Manor and Work began in June 2010 on the due to start in autumn 2010 and will
final permanent sporting facilities be structurally complete by summer
Royal Artillery Barracks will
being built in the Olympic Park. 2011. The temporary pools and
be underway and on track buildings needed for the Games will
to be completed as planned Eton Manor will host Wheelchair follow and are due to be completed
in spring 2012. Tennis during the London 2012 in spring 2012.
Paralympic Games. Throughout the
Games, it will have five temporary Royal Artillery Barracks
training pools for participants in Unlike at most previous Games,
Aquatics events. competitors in the Shooting events
at the London 2012 Games will
After the Games, the area will be be close to the heart of the action,
transformed into sporting facilities enabling the participants to stay
for the local community, including with their teammates in the Olympic
a tennis centre with four indoor and Village. During their event, the
six outdoor courts, a hockey centre athletes – and spectators – will enjoy
with two pitches, and space for ten the spectacular backdrop of the
five-a-side football pitches that will be historic Royal Artillery Barracks in
added in the future. It is hoped that Woolwich, which date from the
the hockey pitches will be relocated 18th century.
from the Hockey Centre, which will
be constructed by the London 2012 Four temporary indoor ranges for
Organising Committee (LOCOG) Pistol and Rifle Shooting are being
within the Olympic Park. built, along with outdoor shotgun
ranges for Trap and Skeet events.
The detailed design of the Eton Temporary spectator grandstands
Manor facilities is complete and the will be provided at each Shooting
contractors undertaking different range. After the Games, the indoor
parts of the facilities have all 10m Shooting range will be taken
been appointed. Work to prepare down and relocated to provide
the ground levels and form the shooting facilities elsewhere in
foundations of the temporary the UK.
swimming pools is underway.
The proposed facilities have been
The main sports complex will house the granted planning permission and
hockey centre and the indoor tennis a design team has been appointed.
courts after the Games. Work has A construction contractor will be
begun on its foundations, which are appointed by the end of 2010 to
due to be complete in autumn 2010, start on site early in 2011.
followed by the structure early in 2011.
An artist’s impression of the new facilities at Eton Manor, where the Wheelchair
Tennis will take place during the London 2012 Paralympic Games
!
new tennis courts for use by the
local community at Eton Manor after
the Games
An aerial view (from east to west, with the A12 running down the left)
showing Eton Manor at the start of construction
2TSbU^aPcW[TcTb
W^\TbU^a<^]S^]Tab
By 27 July 2011: The external An entire new community is taking After the Games, the Village will
structure of the Olympic Village shape on the Olympic Park in east be transformed into one-, two-,
London. More than 2,800 homes three- and four-bedroom properties.
will be finished with the internal
are being constructed on the Kitchens will be installed and
fit out complete in most of Olympic Village site, along with temporary partitions removed to
the blocks. a new educational academy, form the final living spaces and
multi-use community space and bedrooms. New timber or carpet
healthcare facilities. flooring will also be fitted.
As the blocks are completed, they Work has also started on the
will start to be fitted out. Temporary foundations of the Polyclinic, which
partitions will be put in to create will serve existing local communities
the rooms where around 17,000 and the residents of the Village
athletes and officials will stay during after 2012. Run by NHS Newham,
the Games. Bathrooms, lighting, the facilities will include multiple
telecommunications and temporary GP surgeries, outpatient and
flooring will also be installed. physiotherapy services, a children’s
clinic and facilities for X-ray and
By 27 July 2011, most of the blocks ultrasound. During the Games, the
will be fitted out with the rest facilities will be used by athletes.
completed in autumn 2011. The Polyclinic is due to be structurally
complete in spring 2011.
!#')
affordable homes in the Olympic
Village after the Games, to be
managed by Triathlon Homes
3WP]VX]VcWTUPRT
^UcWTTPacW
By 27 July 2011: Construction New green spaces The Park is a carefully designed
of all permanent bridges will The new parklands in the Olympic ecosystem with an interconnected
Park will be a venue in themselves series of habitats, such as otter holts,
be complete. All utilities will
for tens of thousands of spectators at sandmartin banks, bird and bat
be operational. Landscaping the London 2012 Games. Visitors will boxes, frog ponds, compost heaps
will be well advanced across be able to soak up the atmosphere and wormeries.
the Park. in the parklands and enjoy the rivers,
woodlands and ornamental gardens The Park’s landscape has been
– or watch the sporting action on designed to collect rainwater and
live screens within the Park. filter it slowly through a network of
frog ponds and reed beds, rather
Long after 2012, tens of thousands than let it drain straight back into
more visitors will be able to enjoy the the river system. The irrigation
meadows, gardens, woods and river needed to establish new plants will
walks in the parklands, which were use non-potable water from the new
inspired by the original Victorian waste-water treatment facility that will
public parks of London. recycle sewerage from the Northern
Outfall Sewer under The Greenway.
The north of the parklands will be
ecologically diverse, with a range Connecting communities
of new wildlife habitats, meadows, More than 30 bridges are being
woodlands and wetlands. Planting built to span the numerous rivers
in the north of the Park will be and railways that run through the
substantially complete during the Park and create links across the
coming autumn/winter, with the Park during the Games. After the
earthworks and planting complete Games, the majority will remain and
by 27 July 2011. There will also be connect the communities within and
spectator lawns at two of the highest surrounding the Park with the new
points of the Park, offering views parklands and sporting venues.
across London.
More than half of the bridges and
The southern parklands will have a underpasses are structurally complete
more ‘urban’ feel than in the north. with work underway on nearly all the
They will also be the location of remaining structures. The completed
the London 2012 Gardens. These structures include the five bridges
ornamental gardens will celebrate linking the Olympic Stadium ‘island’
the British tradition of collecting site with the rest of the Park, and a
and cultivating plants. Around 250 new link into the Park underneath
different species will be planted in the busy A12 dual carriageway in
different world zones. the north-east corner of the Park.
#
wetland plants in the Olympic Park
The first trees have been planted in the wet woodlands in the north of the
Olympic Park – view looking south to the Aquatics Centre
The Primary Substation, which was completed in autumn 2009, won the
Royal Institute of British Architects (RIBA) Award for ‘Commercial and
Industrial Building of the Year’ in May 2010
The new Pumping Station (pictured) and sewer network within the Olympic Park
is operational. It will collect, convey and remove waste-water from the main
venues and buildings within the Park during and after the London 2012 Games
7aTT][XVWcPWTPS
By 27 July 2011: Construction The Olympic Delivery Authority platforms, and new lifts and
work at Stratford Regional (ODA) is funding or contributing staircases installed. A third subway
funding to a series of improvements will be opened by the autumn.
Station will be complete, with
to transport infrastructure to create Together, these will improve
Londoners already benefiting a safe, reliable and accessible passenger flow at what will become
from hundreds of millions transport system for the increased the interchange for 10 rail routes
of pounds of additional numbers of passengers during with 19 platforms. In autumn 2010,
investment across London’s the Games. a new Central Line platform will
transport system. open, allowing passengers to exit
The improvements – many of which trains on both sides and interchange
are already complete – will leave or leave the station more easily.
lasting benefits after the Games and
transform this part of east London Next to SRS, a developer is building
into one of the best connected the new Stratford City shopping
areas of the capital. Londoners centre – within which will be a new
are already benefiting from the northern entrance/exit to the station
many enhancements that have – and a bridge linking Stratford
been completed. City to the existing town centre. The
bridge will also join up with the new
Stratford Regional Station mezzanine-level entrance/exit that
Currently 37,000 people use has been built for the ODA on the
Stratford Regional Station (SRS) south side of SRS. This new southern
during morning peak hours and this entrance/exit will open in autumn
is estimated to increase to 83,000 2010, while the shopping centre
by 2016. During the Games it will and bridge are scheduled to open
be one of the three ‘gateway’ stations in autumn 2011. During the Games,
to the Olympic Park, when it will spectators will be able to use the
be used by an estimated 120,000 new exits and bridge to reach
people, including around 80,000 the Olympic Park through the new
spectators at peak times. The ODA Stratford City shopping centre.
is investing around £125 million
to treble the station’s capacity and Two new platforms for the London
improve its accessibility. Overground’s North London Line
(NLL) opened at SRS in spring 2009.
Already, platforms have been The former NLL platforms at the
lengthened and widened, more station are being modified, so
space has been created on the they can be used as a stop
Later this year, a new staircase will lead from the front of Stratford Regional Station
up to the new mezzanine-level station entrance (centre), and from next year to a bridge
leading to the new Stratford City shopping centre
The Greenway, a 7km walking and cycling route, will provide access to the Olympic Park for around
20 per cent of Games spectators, including those arriving from West Ham Station. The Olympic Delivery
Authority has made improvements to a 2.3km section from Wick Lane to Manor Road (near West Ham
Station) to make it more accessible, safer, and more appealing
The new green spaces within the Olympic Park have been designed to be
accessible and inclusive to all types of visitors, including wheelchair users,
families and people of all ages and faiths. To make sure everyone can move
through the parklands easily and comfortably, the pathways will be wide,
with smooth surfaces, shallow gradients and seating at regular intervals.
!))
apprentices working on the
construction programme at the
end of March 2010
Apprentice Jamie Norris from Chingford had already completed his first year
at college, where he was studying to become an electrician, when he was
offered the chance to work on the Olympic Park. Jamie was approached
by one of the Employment and Skills Managers, working closely with the
company providing electrical supplies for the International Broadcast Centre/
Main Press Centre. He started on site in August 2009.
!&
women helped into a range of jobs
on the Olympic Park by the Olympic
Delivery Authority’s ‘Women into
Construction’ project
!#
periods of a million hours worked
without a reportable accident
"
workers seen each month by the
occupational health teams on the
Olympic Park and Olympic Village,
providing pre-employment medicals,
health surveillance, minor treatments
and other services.
Good practice in health, safety and the environment was recognised at the
ODA’s second Health, Safety and Environment Awards in July 2010. Among
the winners was Kerri Chambers, an apprentice bricklayer on the Olympic
Stadium, who won the ‘Apprentice of the Year’ award. Other awards were
made to teams and individuals in categories such as ‘Lessons Learned’,
‘Excellence in Training’ and ‘Workforce Engagement’.
Legacy
The London 2012 Games offer a the Olympic Delivery Authority, the overhead powerlines, enhancing
unique opportunity to revitalise the is focused on the creation of the the ecology of the area and creating
Lower Lea Valley, transforming one Park and the development of the green, open spaces. Infrastructure in
of the most underdeveloped areas of venues, including their post-Games the area will be enhanced, especially
the UK into a benchmark 21st century transformation to remove temporary public transport networks, utilities
urban environment that reflects the elements and leave the venues in and disabled access. By planning
diverse and vibrant population their legacy form. the Games and their legacy together
of the area. now, we can ensure that they are
The second, led by the Olympic remembered, not only as a summer
We are harnessing this potential Park Legacy Company, is focused of fantastic sport, but also as the
to create a new park for London. on what the Park will be used for in catalyst for the regeneration of one
In addition to world-class facilities the years ahead. The two are closely of the most underdeveloped areas
for sports including athletics, cycling, linked, with venues and parklands of the UK.
hockey, swimming and tennis, there being designed with their long-term
will be homes for a new community, use in mind.
and green spaces in and around the
Olympic Park. We are transforming the physical
environment in and around the Park
The work can broadly be split by clearing and cleaning the site,
into two phases. The first, led by improving the waterways, burying
'%
pence in every £1 the Olympic
Delivery Authority is spending
is going on the long-term
regeneration of the area
The Aquatics Centre is one of the five sporting venues within the Olympic Park
that will remain after the Games. Together with the new Lee Valley White
Water Centre and improved facilities at Eton Dorney and Weymouth and
Portland, they will leave a sporting legacy for the local communities, sport
clubs and elite athletes.
!(
million tonnes of material has been
delivered to the Olympic Park by rail
)(
of construction waste has been
reused, recycled or recovered
More than 650 bird and bat boxes are being installed across the Olympic
Park, including within bridge structures (pictured) and on the ‘brown roof’
of the Main Press Centre.
The official Emblems of the London 2012 Games are © London Organising
Committee of the Olympic Games and Paralympic Games Limited (LOCOG)
2007. All rights reserved.
The emblems of the National Lottery, the London Development Agency, the
Department of Culture, Media and Sport, and the Mayor of London are
reproduced with the permission of the Crown and the other copyright holders
respectively. All rights reserved.