Resource Spreadsheet – (continued) 

 
11. Right Click in the spreadsheet area to Display Spreadsheet Options. Clear the Calculate Average box.  

Make sure box is NOT checked. 

 
 
 
 
 
 
 

 
 
 
 
 
 
 
 
21
   
Resource Spreadsheet – (continued) 
 
12. Roll‐up the lower center window if it is not summarized.  Next, right‐mouse‐click on the timescale in the 
Resource Usage spreadsheet and select TIMESCALE.  Adjust the time interval settings if necessary. 
 

Roll up if activities 
are not summarized 

NOTE: To can change the Timescale intervals select the DATE INTERVAL drop down and choose QUARTER / 
MONTH, YEAR/MONTH, WEEK/DAY, etc, etc.  Do not change the timescale at this time. 

Click down arrow for 
date interval selection 

22
   
Resource Spreadsheet – (continued) 
 
13. P6 will display the monthly billing estimate.  

Monthly Billing 
Estimate 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
23
   
Resource Profile – Creating Graphs for Manpower and Cost 
 
1. Choose VIEW, SHOW ON BOTTOM, RESOURCE USEAGE PROFILE.

The Man Power graph is present as the default setting is for UNITS.  Change this to COST. 

24
   
Resource Profile – (continued)

2. Choose DISPLAY, RESOURCE USEAGE PROFILE OPTIONS 

Make sure you have 
selected the LUMPSUM  
Resource 

3. On the DATA tab select DISPLAY COST and change the default graph settings. 
 
 
 

Select COST to show 
budgeted cost 
amounts. 
Change Bar Colors to 
what is shown here 

Select the Budgeted 
and Remaining Early 
Boxes  

 
 

25
   
Resource Profile – (continued)

The graphic below indicates the Cost usage over time graphically. 

4. For graphical manpower representations select the UNITS selection in the Resource Usage Profile Options. 
Click DISPLAY to change the Resource Usage Profile Options to Units.  See graphics below. 
     

26
   
Resource Profile – (continued)
 

Select UNITS to show 
budgeted man hour 
figures. 

Change Bar Colors to 
what is shown here 

 
To show the cumulative curve, select the CUMULATIVE selection boxes. Leave the SHOW LIMIT box 
unchecked until finalizing the resource parameters. 
 
The graph should look similar to the graphic below.  Notice the cumulative curve line present. 
 

If the bars do not look similar to the ones above select  EDIT, USER PREFERENCES and select the RESOURCE 
ANALYSIS tab and make sure the Interval for Time‐Distributed Resource Calculations is set to DAYS. 
 
 
27
   
Resource Profile – (continued)
 
This will display the Manpower units spread across time as a graph.  See graphic below.  By double clicking on 
the cumulative curve line the units at that moment in time will be displayed.  See graphic below 
 

 
 
Adjustments can be made to the timescale density or display by right clicking in the timescale area (in green). 
To change graphical colors or other parameters right click in the graph and select the Resource Usage Profile 
Options.  See the graphic below. 
 
 

For TIMESCALE 
changes 

For GRAPHICAL 
changes 

 
 

28
   
Resource Activity Assignment – Assigning Quantities to Activities 
 
As stated earlier, P6 has the ability to distinguish between labor, non‐labor, and materials in the activity’s 
resources.  Having already created a labor and non‐labor resource now create a material resource for the 
training schedule.  Make sure the activities details view is present at the bottom of the screen.  VIEW, SHOW 
ON BOTTOM, ACTIVITY DETAILS. 
 
Remember the steps for adding a Resource.  

1. Select Enterprise, Resources.  This will display ALL Resources.  Or select the Resources mode.   
 
2. Select DISPLAY, FILTER BY, CURRENT PROJECT’S RESOURCES to only show the current project’s resources.  
See graphic steps below. 
 

 
 
3. Select the ADD button on the command bar menu on the right of the screen to add a new resource. A 
dialog box will appear stating that the module needs to display ALL resources.  Select OK. 
 

 
After selecting OK, the Resource Wizard dialog box will appear to start the process of creating a new resource. 
 
 
 
 
 
 
 
 
29
   
Resource Profile – Assigning Quantities to Activities – (continued) 
 
4. The first dialog box is the Resource ID and Name selection.  Use the Resource ID and Name shown below, 
then select NEXT.  See graphic below. 
 

Make sure you 
populate both 
boxes, then select 
NEXT. 

 
 
5. The next dialog box is the Resource Type.  Select MATERIAL to represent Quantities, then select NEXT to 
move to the next dialog box.  See graphic below. 
 

 
 
 
 
 
 
30
   
Resource Profile – Assigning Quantities to Activities – (continued) 
 
6. The final dialog box for quantities is the Unit and Time Prices selection. 
 

Select FINISH  
 
 
As with the other resources, set the Default Units/Time and Max Units/Time to 0/d.  Select FINISH as this 
is the last screen needed to populate with information. 

Development of the Cost Code Structure 
 
Before Cost Codes can be created, it must be understood how the project is going to be built out.  Ideally, the 
CPM schedule has been negotiated in a manner that benefits M.C. Dean. The philosophy should always be; 
how we are going to attack the project so that it maximizes crew flow efficiencies.  Always look for repetitive 
tasks that can be linked together to create crew flow. Some examples of crews:  Underslab, Electric Room, 
Communication Room, Substation, Power Distribution, Mechanical Room, Wall Rough‐in, Overhead Rough‐in, 
Under floor Rough‐in, Fire Alarm, Security, etc… 

To accurately develop a Cost Code Structure for any Project, it must be done by having a detailed review 
process for every Contract Drawing Sheet (Effort lead by the Project Superintendent).  The Following steps 
should be applied to each Contract Drawing Sheet when reviewing to establish Labor Cost Codes. 

1. Determine the Area Identifier 
2. Determine the Crew Areas 
3. Determine the Special Systems 
4. Determine the Tracking System Activities 

 
 
 
 
31
   
Resource Profile – Assigning Quantities to Activities – (continued) 
 
The graphic below represents a Cost Code for installation of 1/2” to 1‐1/4” Fire Alarm Conduit in a Mechanical 
Room within a specific area (181). 

1 2 3 4
(Area Identifier) (Crew Area) (Special System) (Tracking Activity)

181 MR0 FA 0100


 
 
 
7. The next step in the process is to create Cost Codes to accompany the resource quantities.  Select 
ENTERPRISE, COST ACCOUNTS. 
 

 
 
 
 
 
 
 
 
 
 
32
   
Resource Profile – Assigning Quantities to Activities – (continued) 
 
8. The Cost Accounts dialog box will appear asking to display all cost accounts.   Select OK. 
 

Select OK to see 
all Cost Accounts 

 
 
9. In the newly created Cost Account entry, populate the Cost Account ID and Cost Account Name fields.  
Use the ID and Name show in the second graphic.  See graphics below. 
 

 
 

ID and Name can 
be entered in 
either location. 

 
 
 
33
   
Resource Profile – Assigning Quantities to Activities – (continued) 
 
10.  After creating the Resource Quantities and Cost Codes, the next step is to assign them to the proper 
activities.  Select the ACTIVITIES Mode and make sure the Activities Details window is open at the bottom 
of the screen with the RESOURCES tab selected.  See graphic below. 
 

 
 
11.  Right‐mouse click anywhere in the Activity Details section and select CUSTOMIZE RESOURCE COLUMNS.  
From the Resource Assignment Columns dialog box choose COST ACCOUNT under the GENERAL selection 
in the Available Options section.  See graphics below. 
 

 
 
 
 
 
 
 
 
 
34
   
Resource Profile – Assigning Quantities to Activities – (continued) 
 
12. With the newly created Cost Account column added, assign a new Resource Quantity and Cost Code to 
Activity C10000.  Select Add Resource button at the bottom of the Activity Details in the Resource tab.  See 
graphic below. 
 

 
 
 
13.  Next assign the newly created Resource Quantity 0100  1/2” to 1‐1/4” Conduit by double clicking on the 
code in the Assign Resources dialog box or by selecting the Assign button  . See graphic below. 
 

 
 
 
14. After assigning the Resource Quantity now assign the amount.  For activity C10000 assign 800 LF. 
       See graphic below. 
 

 
 
 
 
 
 
 
35
   
Resource Profile – Assigning Quantities to Activities – (continued) 
 
15.  In conjunction with loading quantities, cost codes can also be assigned to the Resource Quanitity. In the 
Cost Account column, select the lower right –hand corner of the cell which will bring up a selection dialog 
box.  Select B05ER0PS0100 from the available Cost Account IDs.  See dialog box below. 
 

Look for 
small box   
  Assign the Cost Code in  with dots
  this column 
 
 
 
The following graphic displays the correct resources residing in the Resource tab for activity C10000. 
 
 

 
 
 
 
 
 
 
 
36
   
Resource Profile – Assigning Quantities to Activities – (continued) 
 
Class Exercise: 
 
From the table below first create each Resource then create the corresponding Cost Code in the BASE 
project’s Resource and Cost Account dictionary.  Then poulate each of the activities highlighted in yellow with 
the corresponding quantities.  The units (LF or Ea) are listed for each activity as well in the chart below. 
 
  Quantities for each 
activity by Resource ID 

 
 
 
  Resource Name  Cost Account Name 
  Resource ID  Cost Account ID 

 
 
 
 
 
 
 
 
 
 
 
37
   
Resource Profile – Assigning Quantities to Activities – (continued) 
 
When all the Material Resource Quantities have been created, assigned them to the correct activities, given 
individual quantity measures, and assigned the correct Cost Codes check where they are listed in the body of 
the resource dictionary.   
 
1. To do that switch to the RESOURCE mode. In the RESOURCE mode scroll down to where the newly created 
codes appear. 
 
Use the MOVE 
keys to move up, 
indent or outdent 

Move up and indent under 
LUMPSUM Resource   
 
 
NOTE:  Initially the Current Project’s Resources will not be displayed until they have been assigned to an 
activity(s).  Moving the Resource Quantities up and under the existing LUMPSUM resource code helps locate 
the codes quicker when assigning codes for the first time. 
 
 
2. Move the Resource Quantity codes up and indent them underneath the existing LUMPSUM Resource 
Code.  See Graphic below.   
 
 

 
  Make sure your Unit of Measure 
  category is populated 
 
 
The next step is to view the individual Resource Quantity graphs.   
 
3. Switch back to the ACTIVITIES mode and display the RESOURCE USAGE PROFILE, by selecting VIEW, SHOW 
ON BOTTOM, Resource Usage Profile. 
 
 
38
   
Resource Profile – Assigning Quantities to Activities – (continued) 
 
4. Select each Resource Quantity on the left‐hand side of the Resource Usage window to view the graph on 
the right‐hand side of the bottom display.  See graphics below. 
 
For Quantity Resource 0100 1/2” to 1‐1/4” Conduit 
 

For Quantity Resource 0110 1‐1/2” to 5” Conduit 
 

For Quantity Resource 0200 Pull Wire #6 & Smaller 
 

 
 
 

39
   