Practice Questions
INSTRUCTIONS: Note the most suitable answer or
each multiple-choice question in the appropriate
space on the answer sheet.
20. As head o the PMO, you will receive per ormance reports
or all major projects. You decided to set a guideline or
project managers as per ormance reporting should—
a. Collect work per ormance in ormation on the status
o deliverables
b. Provide earned value data or project orecasting
c. Provide in ormation at an appropriate level or each
audience
d. Focus on cost and schedule variances rather than
scope, resources, quality, and risks
28. You have heard recently that the client calls your progress
reports the “Code o Hammurabi” because they seem to be
written in hieroglyphics and are completely indecipherable
to all but an antiquities scholar. This situation could have
been avoided by—
a. In orming the client at the start o the project about
the types o reports they will receive
b. Using risk management techniques to identi y
client issues
c. Hiring an expert report writer to prepare standard reports
d. Engaging in communications planning