3x660MW KORADI THERMAL POWER STATION

Unit # 10 AOH Progress Review Status


Section :AHP MAINTENANCE
PROGRESS REVIEW STATUS, as on WORK COMPLETED
S
N OVERHAUL ACTIVITY PERMIT NO. (%)
Friday, November 13, 2020

B/A Hopper internal inspection/repairing and painting


work
1) Refractory breaking and lifting
2) B/A hopper leakages attending work
3) B/A hopper repairing and painting
AHP-01

From To
Scheduled 14-Nov 3-Dec
Actual
Status NOT YET STARTED

Feed gate inspection and servicing/repairing


1) Feed gate inspection/Checking
2) Roller alignment/checking/ replacement
3) Air/water convertor tank servicing
AHP-02

From To
Scheduled 14-Nov 5-Dec
Actual
Status NOT YET STARTED

Seal trough work (cleaning and repairing)


1) Seal trough cleaning & inspection
2) Seal trough plate leakages attending, SS mesh inspection
and replacement if required
3) Seal trough flushing valves, make up valve servicing
AHP-03

From To
Scheduled 14-Nov 3-Dec
Actual
Status NOT YET STARTED

Clinker Grinder servicing/replacement


1) Grinder servicing, repairing
2) Replacement of worn out spares
3) Coupling checking, servicing
4) Sprocket chain checking & alignment and
replacement if required
AHP-04 5) Gear box/fluid coupling oil replacement
6) Replacement of Glands, Ropes etc.

From To
Scheduled 9-Nov 3-Dec
Actual
Status NOT YET STARTED

HP/LP line valves & jet pump work


1) Servicing of inlet valves of HP/LP line
2) Checking of Jet Pump & replacement if required
3) Replacement of Gaskets, Ropes etc.
AHP-05

From To
Scheduled 17-Nov 27-Nov
Actual
Status NOT YET STARTED
PROGRESS REVIEW STATUS, as on WORK COMPLETED
S
OVERHAUL ACTIVITY PERMIT NO.
N (%)

Coarse Ash Hopper internal inspection & Jet


pump/Feeder ejector/valve servicing
1) Coarse ash tank cleaning, washing, inspection &
repairing if required
2) KGV servicing, gland replacement
3) Feeder Hydro Ejector servicing
AHP-06 4) Jet Pump checking & servicing and replacement if
required

From To
Scheduled 14-Nov 3-Dec
Actual
Status NOT YET STARTED

ESP first row work


1) Checking ,servicing of Hydroejector of first row.
2) Servicing of ash valves, Water valves
3) Checking, servicing of jet pump & its valve.
AHP-07

From To
Scheduled 14-Nov 3-Dec
Actual
Status NOT YET STARTED

Modification of ESP internals


1) Rectification of ESP internals including water washing

AHP-08

From To
Scheduled 11-Nov 7-Dec
Actual
Status NOT YET STARTED

Replacement of ESP hoppers fluidizing pads


1) Removing old pads and replacement with new one if
required
AHP-09

From To
Scheduled 11-Nov 7-Dec
Actual
Status NOT YET STARTED

Scrapping of Intermediate Silo


1) Scrapping of Intermediate Silo

AHP-10

From To
Scheduled 11-Nov 3-Dec
Actual
Status NOT YET STARTED

Replacement of Bags & Cages of Bag filter Box


1) Replacement of Bags,
2) Replacement of Cages
AHP-11

From To
Scheduled 18-Nov 25-Nov
Actual
Status NOT YET STARTED
Unit No. 10 Annual Overhaul Bar Chart (NOV-2020)-MAINTENANCE
3 X 660 MW KTPS KORADI

10-Nov-20
11-Nov-20
12-Nov-20
13-Nov-20
14-Nov-20
15-Nov-20
16-Nov-20
17-Nov-20
18-Nov-20
19-Nov-20
20-Nov-20
21-Nov-20
22-Nov-20
23-Nov-20
24-Nov-20
25-Nov-20
26-Nov-20
27-Nov-20
28-Nov-20
29-Nov-20
30-Nov-20

10-Dec-20
11-Dec-20
12-Dec-20
13-Dec-20
9-Nov-20

1-Dec-20
2-Dec-20
3-Dec-20
4-Dec-20
5-Dec-20
6-Dec-20
7-Dec-20
8-Dec-20
9-Dec-20
Total days
SR DATE

Start Day

End Day
NO ACTIVITY

DAY 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
Ash Handling Plant
1 B/A Hopper internal inspection/repairing and painting work 6 25 20 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

2 Feed gate inspection and servicing/repairing 6 27 22 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

3 Seal trough work (cleaning and repairing) 6 25 20 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

4 Clinker Grinder servicing/replacement 1 25 25 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

5 HP/LP line valves & jet pump work 9 19 11 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

6 Coarse Ash Hopper internal inspection & Jet pump/Feeder ejector/valve servicing 6 25 20 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

7 ESP first row work 6 25 20 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

8 Modification of ESP internals 3 29 27 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

9 Replacement of ESP hoppers fluidizing pads 3 29 27 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

10 Scrapping of Intermediate Silo 3 25 23 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

11 Replacement of Bags & Cages of Bag filter Box 10 17 8 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35