Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Formula Factor
Lead Type Km
Sajilo Asajilo Sajilo Asajilo
Distance in Pakki Sadak 222 1.75/100* distance in km 2.4/100*km 3.885 5.328
Distance in Kacchi Sadak 0 2.4/100*distance in km 2.7/100*distance in km 0 0
Distance to be Traveled by Man/Khacchad 0.1 3/3.2*distance in km 4/3.2*distance in Km 0.09375 0.125
S.No Description of Items Rate in Dhangadi Unit Lead in Pakki Sadak Lead in Kacchi Sadak Lead By Man/Khacchad Sub-Total Unit Remarks Total Unit
A CIVIL ITEMS
75 0.52mm 24 gauge Colour CGI sheet medium (14000 per 250.00 bundle (56 kg) 3.885 0 0.125 254.01 Kg 14000/56 (per kg) 828.45428072219 Per Sq.m
bundle)
76 1100 No (3'x6') 5% transportation 1155 Per No. (866.25/1.8)/2 (1.5'x6' 320.833333333333 Per Meter
26 Gauge Colour Plain Sheet size sheet per Meter)
77 Sanitary Items
78 Urinal (10.5"x14.5"x12.5" (Good Quality) 1650 No 1732.5 No 5% transportation charge 1732.5 Per No
79 Orrisa pan local (local) 1100 No 1155 No 5% transportation charge 1155 Per No
80 Commode (Local) 1650 No 1732.5 No 5% transportation charge 1732.5 Per No
81 Low level Flushing Cistern plastic 2200 No 2310 No 5% transportation charge 2310 Per No
82 50*40cm Oval Wash Basin 2500 No 2625 No 5% transportation charge 2625 Per No
83 1000 Litre PVC Water Tank
84 1 Hp IS Electric Motor Mono Block Type 16000 No 16800 No 16800 Per No
85 CI Cover (20kg) No No Ktm Rate
86 Towel Rod 625 No 656.25 No 5% transportation charge 656.25 Per No
87 C.P. Soap Dish 525 No 551.25 No 5% transportation charge 551.25 Per No
88 12" x 18" mirror 1050 No 1102.5 No 5% transportation charge 1102.5 Per No
89 1-1/4" C.P. Pipe with Coupling 925 No 971.25 No 5% transportation charge 971.25 Per No
90 1-1/4" C.P. Pipe 'P' or 'S' Trap 1100 No 1155 No 5% transportation charge 1155 Per No
91 Pipe Connector 220 No 231 No 5% transportation charge 231 Per No
92 Sink (18x38x8") steel 4400 No 4620 No 5% transportation charge 4620 Per No
93 Washer Copuling 525 No 551.25 No 5% transportation charge 551.25 Per No
94 Bib Cock Brass 300 No 315 No 5% transportation charge 315 Per No
95 C.P. Bib Cock 788 No 827.4 No 5% transportation charge 827.4 Per No
96 Stop Cock 900 No 945 No 5% transportation charge 945 Per No
97 1/2" connector Stop cock 700 No 735 No 5% transportation charge 735 Per No
98 PVC Pipe 110mm (4kg Pressure) 2800 pcs 2940 pcs 5% transportation charge 2940 Per No
99 PVC Pipe 75mm (4kg Pressure) 1450 Pcs 1522.5 Pcs 5% transportation charge 1522.5 Per No
100 GI pipe @ 16 mm 170 Nos 178.5 No 5% transportation charge 178.5 Per No
101 Elbow @ 16 mm 46 Nos 48.3 No 5% transportation charge 48.3 Per No
102 Socket @ 16 mm 42 Nos 44.1 No 5% transportation charge 44.1 Per No
103 Gate valve @ 16 mm 824 Nos 865.2 No 5% transportation charge 865.2 Per No
104 Equal Tee @ 16 mm 73 Nos 76.65 No 5% transportation charge 76.65 Per No
105 Union @ 16 mm 128 Nos 134.4 No 5% transportation charge 134.4 Per No
106 Gi Nipple @16mm 83 Nos 87.15 No 5% transportation charge 87.15 Per No
107 Brass tap (Heavy) @ 16 mm 669 Nos 702.45 No 5% transportation charge 702.45 Per No
108 42" Ceiling Ceiling Fan (Ns/IS) 3300 No 3465 No 5% transportation charge 3465 Per No
109 Exhaust fan 12" IS/NS 3500 No 3675 No 5% transportation charge 3675 Per No
110 8" Dome light 495 No 519.75 No 5% transportation charge 519.75 Per No
111 Meter Box (plastic) 200 No 210 No 5% transportation charge 210 Per No
112 MCB (6 AMP)-SP 255 No 267.75 No 5% transportation charge 267.75 Per No
113 MCB (15 AMP)-SP 375 No 393.75 No 5% transportation charge 393.75 Per No
114 MCB (15 AMP)-D.P. 660 No 693 No 5% transportation charge 693 Per No
115 MCB (30 AMP)-S.P. 440 No 462 No 5% transportation charge 462 Per No
116 MCB (30 AMP)-D.P. 1200 No 1260 No 5% transportation charge 1260 Per No
117 CFL 15 Watt Spiral 365 No 383.25 No 5% transportation charge 383.25 Per No
118 Gum 210 Kg 3.885 213.885 Kg 213.885 Per kg
119 H.D.P.E Pipe 272 Kg 3.885 275.885 Kg 275.885 Per kg
Gabion Boxes
Size/No. of Diaphragm
(3*1*1)/2 4269 No. 4482.45 No. 5% transportation charge 4482.45 Per No.
Collection of stone,
Breaking to required
size ,Screening and staking
3 up to 10m all complete.
5-10mm 6 md 660.00 4,077.00
10-20 mm 4 md 660.00 2,718.00
20-40 mm 2.5 md 660.00 1,698.75
LIDAR)
FY:2076/077
unit
Sand Unit
wt =1600
Rs
Stone
Unit wt
=2400
Rs
Rs
Rs
Rs
Ordinary Rock
Medium Rock
2039.40
Medium Rock
3300.00
99.00
3399.00
3399.00
16451.16
Boulder Mix Soil
1080.88
169.95
Government of Nepal
Ministry of Federal Affairs and General Administration
Dogadakedar Rural Municipality
Deulek, Baitadi
Summary of Rates F/Y 2075/76
S.n Description of Work Unit Rate Remarks
A Civil rate
#REF!
#REF!
S. N. Description Of works Quantity Unit Per Cum Bag Toal Bag/ kg Rate Amount Remarks
1 #REF! #REF! #REF! 4.4 #REF! 850.00 #REF!
2 #REF! #REF! #REF! 2 #REF! 850.00 #REF!
3 Brick #REF! nos. 560 #REF! 11.20 #REF!
4 #REF! #REF! #REF! 3.18 #REF! 850.00 #REF!
5 #REF! #REF! #REF! 8 #REF! 850 #REF!
6 #REF! #REF! #REF! 85.00 #REF!
7 #REF! #REF! #REF! 0.1076 #REF! 850 #REF!
8 #REF! #REF! #REF!
a Primer #REF! Lt 396 #REF!
b Emulsion Paint #REF! Lt 780 #REF!
9 #REF! #REF! #REF! #REF! #REF!
10 #REF! #REF! #REF!
a Primer #REF! Lt 396 #REF!
b Enamel Paint #REF! Lt 600 #REF!
11 #REF! #REF! #REF! 1153 #REF!
12 #REF! #REF! #REF! 600 #REF!
13 #REF! - LS 65000 65000.00
14 #REF! #REF! #REF! 0.1064 #REF! 850 #REF!
15 #REF! #REF! #REF! 3354.45 #REF!
16 #REF! #REF! #REF! 85.22 #REF!
17 #REF! 27289.87
18 #REF! #REF!
Sub-Total #REF!
Vat @13% #REF!
Total #REF!
MEASUREMENT BOOK
No of bill : First running bill
#REF!
Date of aggrement: 2075-10-24
Chairman of consumers committee: Bisharam Singh Karki
Date of measurement: 2076-01-19
Date of work order: 2075-10-24 Cheque no.
S.No Description of the work No. L B H Quantity Unit Rate Amount Remarks
GROUND FLOOR
1 Earth work Excavation
A Building -1
i Column Foundation 14 5.00 5.00 5.00 1750.00
ii Tie beam
Grid A-A, B-B 2 42.67 1.00 2.00 170.68
Grid C-C 1 9.17 1.00 2.00 18.33
Grid 1-1,2-2,5-5,6-6 4 8.5 1.00 2.00 68.00
Grid 3-3,4-4 2 12.5 1.00 2.00 50.00
iii Septic Tank 1 11.16 8.16 8.00 728.52
Sub- Total 2785.53 cu.ft
B Building -2
i Column Foundation 6 5.00 5.00 5.00 750.00
ii Tie beam
Grid A-A, B-B,C-C 3 15.25 1.00 2.00 91.50
Grid 1-1,2-2 2 20.25 1.00 2.00 81.00
Sub- Total 922.50 cu.ft
Total 3708.03 cu.ft
Grand Total 104.98 cu.m #REF! #REF!
2 Backfilling work of all types of soil and all types of rock
A Building -1
i Column Foundation
Traingular Portion 14 A= 1/2bh 5.00 5.00 350.00
Rectangular portion 14 A= bh 16.00 5.00 1120.00
ii Tie beam
Grid A-A, B-B 2 42.67 0.25 1.25 26.67
Grid C-C 1 9.17 0.25 1.25 2.86
Grid 1-1,2-2,5-5,6-6 4 8.50 0.25 1.25 10.63
Grid 3-3,4-4 2 12.50 0.25 1.25 7.81
iii Hall
Room A 1 12.33 13.00 2.00 320.58
Room B 1 12.50 13.00 2.00 325.00
Room C & D 2 12.83 13.00 2.00 667.16
Room E 1 13.67 13.00 2.00 355.42
Varanda 1 13.17 8.00 2.00 210.67
Sub-Total 3396.80 cu.ft
B Building -2
i Column Foundation
Traingular Portion 6 A= 1/2bh 5.00 5.00 150.00
Rectangular portion 6 A= bh 16.00 5.00 480.00
ii Tie beam
Grid A-A, B-B,C-C 3 15.25 0.25 1.25 14.30
Grid 1-1,2-2 2 20.25 0.25 1.25 12.66
iii Hall
Room A1 1 14.75 19.75 2.00 582.63
Room A2 1 14.25 19.75 2.00 562.88
Sub-Total 1802.45 cu.ft
Total 5199.26 cu.ft
Grand Total 147.20 cum #REF! #REF!
3 Soling Work
Stone Soling
A Building -1
i Column 14 5.00 5.00 0.67 233.33
ii Tie beam
Grid A-A, B-B 2 A= 25.59 0.83 42.65
Grid C-C 1 A= 5.33 0.83 4.44
Grid 1-1,2-2,5-5,6-6 4 A= 5.08 0.83 16.93
Grid 3-3,4-4 2 A= 7.91 0.83 13.18
iii Septic tank base 1 8.16 8.16 0.67 5.44
iv Hall
Room A 1 12.33 13.00 0.33 53.43
Room B 1 12.5 13.00 0.33 54.17
Room C 1 13.67 13.00 0.33 59.24
Room D 1 12.584 13.00 0.33 54.53
Room E 1 12.584 13.00 0.33 54.53
Varanda 1 12.167 8.00 0.33 32.45
Sub- Total 624.32 cu.ft
B Building -2
i Column 6 5.00 5.00 0.67 100.50
ii Tie beam
Grid A-A, B-B,C-C 3 A= 11.98 0.83 29.95
Grid 1-1,2-2 2 A= 8.50 0.83 14.17
iii Hall
Room A1 1 14.75 19.75 0.33 97.10
Room A2 1 14.25 19.75 0.33 93.81
Sub- Total 335.53 cu.ft
Total 959.86 cu.ft
Grand Total 27.18 cu.m #REF! #REF!
4 (1:3:6) P.C.C Work on Foundation
A Building -1
i Column 14 5.00 5.00 0.33 115.50
ii Hall
Room A 1 12.33 13.00 0.25 40.07
Room B 1 12.5 13.00 0.25 40.63
Room C 1 13.67 13.00 0.25 44.43
Room D 1 12.584 13.00 0.25 40.90
Room E 1 12.584 13.00 0.25 40.90
Varanda 1 12.167 8.00 0.25 24.33
Sub- Total 346.76 cu.ft
B Building -2
i Column 6 5.00 5.00 0.33 49.50
ii Hall
Room A1 1 14.75 19.75 0.25 72.83
Room A2 1 14.25 19.75 0.25 70.36
Sub- Total 192.69 cu.ft
Total 539.44 cu.ft
Grand Total 15.27 cu.m #REF! #REF!
5 Brick masonary work (1:4)
A Building -1
i Sub-structure
9" B/W below PL
Grid A-A,B-B 2 62.67 0.75 1.00 94.00
Grid C-C 1 13.17 0.75 1.00 9.88
Grid 1-1,2-2,5-5,6-6 4 12.50 0.75 1.00 37.50
Grid 3-3,4-4 2 20.50 0.75 1.00 30.75
ii Super Structure
9" B/W above PL
Grid A-A 1 62.67 0.75 8.00 376.01
Grid B-B 1 49.50 0.75 8.00 296.99
Grid 1-1,2-2,3-3,4-4,5-5,6-6 6 12.50 0.75 8.00 450.00
iii Septic Tank
Long wall 2 9.66 0.75 1.00 14.49
Short Wall 2 8.16 0.75 1.00 12.24
Sub-Total 1321.86 cu.ft
Deduction
i Door
D1 4 4.00 0.75 7.00 84.00
ii Window
W1 6 5.50 0.75 5.00 123.75
W2 1 4.00 0.75 3.00 9.00
iii Ventilation V 1 2.00 0.75 1.50 2.25
iv Landing beam 1 13.17 0.75 0.75 7.41
Sub-Total -226.41 cu.ft
Total 1095.45 cu.ft
B Building -2
i Sub-structure
9" B/W below PL
Grid A-A,B-B,C-C 3 19.25 0.75 1.00 43.31
Grid 1-1,2-2 2 28.25 0.75 1.00 42.38
ii Super Structure
9" B/W above PL
Grid A-A,B-B,C-C 3 19.25 0.75 8.00 346.50
Grid 1-1,2-2 2 30.58 0.75 8.00 366.96
Sub-Total 799.15 cu.ft
Deduction
i Door
D1 2 4.00 0.75 7.00 42.00
ii Window
W1 2 6.00 0.75 5.00 45.00
W3 2 4.83 0.75 3.00 21.74
Sub-Total -108.74 cu.ft
Total 690.41 cu.ft
Total After Deduction 1785.87 cu.ft
Grand Total 50.56 cu.m #REF! #REF!
6 Stone Masonry Work (1:4)
Septic tank
Long wall 2 11.16 1.48 6.50 214.20
Short Wall 2 8.16 1.48 6.50 156.62
Sub-Total 370.83 cu.ft
Grand Total 10.50 cu.m #REF! #REF!
7 P.C. C (1:1.5:3)for R.C.C work
A Building -1
i Rectangular Footing 14 5.00 5.00 0.50 175.00
ii Trapezoidal Footing 14 v=h/3(A1+A2+SQRT(A1A2) 217.00 A1=5'*5',A2=1'*1'
iii Column up Plinth level 14 1.00 1.00 2.58 36.12 15.5
iv Column above Plinth Level 14 1.00 1.00 9.00 126.00
v Tie beam
Grid A-A, B-B 2 62.67 0.75 0.75 70.50
Grid C-C 1 13.17 0.75 0.75 7.41
Grid 1-1,2-2,5-5,6-6 4 12.50 0.75 0.75 28.13
Grid 3-3,4-4 2 20.50 0.75 0.75 23.06
vi Plinth beam
Grid A-A, B-B 2 62.67 0.75 0.83 78.33
Grid C-C 1 13.17 0.75 0.83 8.23
Grid 1-1,2-2,5-5,6-6 4 12.50 0.75 0.83 31.25
Grid 3-3,4-4 2 20.50 0.75 0.83 25.63
vii Slab beam
Grid A-A, B-B 2 62.67 0.75 1.00 94.00
Grid C-C 1 13.17 0.75 1.00 9.88
Grid 1-1,2-2,5-5,6-6 4 12.50 0.75 1.00 37.50
Grid 3-3,4-4 2 20.50 0.75 1.00 30.75
viii Landing beam 1 13.17 0.75 0.75 7.41
ix Cantilever beam 8 3.60 0.75 1.00 21.60
x Waist Slab 2 7.83 4.00 0.42 26.11
xi Landing 1 8.00 4.00 0.42 13.33
xii Sill band 1 57.16 0.75 0.33 14.15
xiii Septic tank slab 1 9.75 9.67 0.33 31.43
Sub-Total 1112.80 cu.ft
B Building -2
i Rectangular Footing 6 5.00 5.00 0.50 75.00
ii Trapezoidal Footing 6 v=h/3(A1+A2+SQRT(A1A2) 93.00 A1=5'*5',A2=1'*1'
iii Column upto Plinth level 6 1.00 1.00 2.58 15.48 15.5
iv Column above Plinth Level 6 1.00 1.00 9.00 54.00
v Tie beam
Grid A-A, B-B,C-C 3 19.25 0.75 0.75 32.48
Grid 1-1,2-2 2 28.25 0.75 0.75 31.78
vi Plinth beam
Grid A-A, B-B,C-C 3 19.25 0.75 0.83 36.09
Grid 1-1,2-2 2 28.25 0.75 0.83 35.31
vii Slab beam
Grid A-A, B-B,C-C 3 19.25 0.75 1.00 43.31
Grid 1-1,2-2 2 28.25 0.75 1.00 42.38
vii Slab
Room A2 1 10.50 21.25 0.42 92.97
viii Cantilever beam 3 3.50 0.75 1.00 7.88
ix Hidden beam 1 31.25 0.75 0.75 17.58
x Sill band 1 20.33 0.75 0.33 5.03
Sub-Total 582.29 cu.ft
Total 1695.09 cu.ft
Grand Total 47.99 cu.m #REF! #REF!
8 Reinforcement work with cutting,bending,placing all complete
A Building 1
12mm bar @ 150mm c/c
i R/F Cage for mesh on bothway 308 1.52 0.89 417.22
spacing
ii Column upto Plinth level
Main bar 24 2.26 12 mm main bar 0.89 48.18
Main bar 88 2.11 16 mm main bar 1.58 292.87
a Lateral ties
Square stirrups 126 1.14 7mm bar @ 150mm c/c 0.30 43.56
spacing
7mm bar @ 150mm c/c
Diamond stirrups 126 0.94 spacing 0.30 35.82
iii Column above Plinth level
Main bar 24 2.87 12 mm main bar 0.89 61.18
Main bar 88 2.87 16 mm main bar 1.58 398.83
a Lateral ties
7mm bar -L/4 @ 125mmc/c
Square stirrups 308 1.14 0.30 106.48
& 150mm c/c at mid
7mm bar -L/4 @ 125mmc/c
Diamond stirrups 308 0.94 0.30 87.55
& 150mm c/c at mid
iv Tie beam
a Main bar
Grid A-A, B-B (Top Bar) 4 21.38 12mm bar 0.89 76.02
Grid A-A, B-B (Bottom Bar) 4 21.54 12mm bar 0.89 76.58
Grid C-C (Top Bar) 2 5.07 12mm bar 0.89 9.02
Grid C-C (Bottom Bar) 2 5.23 12mm bar 0.89 9.30
Grid 1-1,2-2,5-5,6-6 (Top Bar) 8 4.87 12mm bar 0.89 34.63
Grid 1-1,2-2,5-5,6-6 (Bottom Bar) 8 5.03 12mm bar 0.89 35.76
Grid 3-3,4-4 (Top Bar) 4 7.61 12mm bar 0.89 27.07
Grid 3-3,4-4 (Bottom Bar) 4 7.77 12mm bar 0.89 27.63
b Extra Bar 28 1.52 12mm bar 0.89 37.93
c Lateral ties
7mm bar -L/4 @ 125mmc/c
Grid A-A, B-B 336 0.86 0.30 87.76
& 150mm c/c at mid
7mm bar -L/4 @ 125mmc/c
Grid C-C 34 0.86 0.30 8.88
& 150mm c/c at mid
Grid 1-1,2-2,5-5,6-6 132 0.86 7mm bar -L/4 @ 125mmc/c 0.30 34.48
& 150mm c/c at mid
7mm bar -L/4 @ 125mmc/c
Grid 3-3,4-4 112 0.86 & 150mm c/c at mid 0.30 29.25
v Plinth Beam
Grid A-A, B-B (Top Bar) 4 21.34 16mm bar 1.58 134.88
Grid A-A, B-B ( Bottom Bar) 4 21.34 16mm bar 1.58 134.88
Grid A-A, B-B (Top Bar) 2 21.44 12mm bar 0.89 38.11
Grid A-A, B-B ( Bottom Bar) 2 21.34 12mm bar 0.89 37.93
Grid C-C (Top Bar) 2 5.03 16mm bar 1.58 15.90
Grid C-C (Bottom Bar) 2 5.03 16mm bar 1.58 15.90
Grid C-C (Top Bar) 1 5.13 12mm bar 0.89 4.56
Grid C-C (Bottom Bar) 1 5.03 12mm bar 0.89 4.47
Grid 1-1,2-2,5-5,6-6 (Top Bar) 8 4.83 16mm bar 1.58 61.03
Grid 1-1,2-2,5-5,6-6 (Bottom Bar) 8 4.83 16mm bar 1.58 61.03
Grid 1-1,2-2,5-5,6-6 (Top Bar) 4 4.93 12mm bar 0.89 17.51
Grid 1-1,2-2,5-5,6-6 (Bottom Bar) 4 4.83 12mm bar 0.89 17.17
Grid 3-3,4-4 (Top Bar) 4 7.57 16mm bar 1.58 47.86
Grid 3-3,4-4 (Bottom Bar) 4 7.57 16mm bar 1.58 47.86
Grid 3-3,4-4 (Top Bar) 2 7.67 12mm bar 0.89 13.63
Grid 3-3,4-4 (Bottom Bar) 2 7.57 12mm bar 0.89 13.46
a Extra Bar 28 1.52 12mm bar 0.89 37.93
b Lateral ties
Grid A-A, B-B 258 0.91 7mm bar @150mm c/c 0.30 71.35
Grid C-C 27 0.91 7mm bar @150mm c/c 0.30 7.47
Grid 1-1,2-2,5-5,6-6 104 0.91 7mm bar @150mm c/c 0.30 28.76
Grid 3-3,4-4 86 0.91 7mm bar @150mm c/c 0.30 23.78
vi Slab Beam with cantilever
Grid A-A, B-B (Top Bar) 4 22.50 16mm bar 1.58 142.24
Grid A-A, B-B ( Bottom Bar) 4 22.50 16mm bar 1.58 142.24
Grid A-A, B-B (Top Bar) 2 22.60 12mm bar 0.89 40.18
Grid A-A, B-B ( Bottom Bar) 2 22.50 12mm bar 0.89 40.00
Grid C-C (Top Bar) 2 7.26 16mm bar 1.58 22.95
Grid C-C (Bottom Bar) 2 7.26 16mm bar 1.58 22.95
Grid C-C (Top Bar) 1 7.36 12mm bar 0.89 6.54
Grid C-C (Bottom Bar) 1 7.26 12mm bar 0.89 6.46
Grid 1-1,2-2,5-5,6-6 (Top Bar) 8 5.99 16mm bar 1.58 75.75
Grid 1-1,2-2,5-5,6-6 (Bottom Bar) 8 5.99 16mm bar 1.58 75.75
Grid 1-1,2-2,5-5,6-6 (Top Bar) 4 6.09 12mm bar 0.89 21.65
Grid 1-1,2-2,5-5,6-6 (Bottom Bar) 4 5.99 12mm bar 0.89 21.31
Grid 3-3,4-4 (Top Bar) 4 8.74 16mm bar 1.58 55.21
Grid 3-3,4-4 (Bottom Bar) 4 8.74 16mm bar 1.58 55.21
Grid 3-3,4-4 (Top Bar) 2 7.67 12mm bar 0.89 13.63
Grid 3-3,4-4 (Bottom Bar) 2 8.74 12mm bar 0.89 15.53
a Extra Bar 28 1.52 12mm bar 0.89 37.93
b Lateral ties
7mm bar -L/4 @ 125mmc/c
Grid A-A, B-B 336 1.02 & 150mm c/c at mid 0.30 103.25
Grid 3-3,4-4 112 1.02 7mm bar -L/4 @ 125mmc/c 0.30 34.42
& 150mm c/c at mid
vii Landing beam
Main bar 4 4.47 12mm bar 0.89 15.90
Lateral ties 25 0.86 7mm bar @150mm c/c 0.30 6.53
viii Septic tank cover Slab
Shorter span 20 2.84 12mm bar @ 150mm c/c 0.89 50.55
spacing
12mm bar @ 150mm c/c
Longer Span 20 2.87 spacing 0.89 50.99
ix Sill band
a Main bar 2 17.42 12mm bar 0.89 30.97
b Lateral ties 118 0.28 7mm bar -L/4 @ 150mm c/c 0.30 9.97
Sub-Total 3970.62 kg
Deduction
Septic tank manhole cover
Shorter span 1 0.89 0.89 0.79
Longer Span 1 0.81 0.89 0.72
Sub-Total -1.51 kg
Total 3969.10 kg
B Building -2
i R/F Cage for mesh on bothway 132 1.52 12mm bar @ 150mm c/c 0.89 178.81
spacing
ii Column upto Plinth level
Main bar 16 2.26 12 mm main bar 0.89 32.12
Main bar 32 2.11 16 mm main bar 1.58 106.50
a Lateral ties
Square stirrups 54 1.14 7mm bar @ 150mm c/c 0.30 18.67
spacing
Diamond stirrups 132 0.94 7mm bar @ 150mm c/c 0.30 37.52
spacing
iv Tie beam
a Main bar
Grid A-A, B-B,C-C (Top Bar) 6 6.93 12mm bar 0.89 36.95
Grid A-A, B-B,C-C (Bottom Bar) 6 7.09 12mm bar 0.89 37.79
Grid 1-1,2-2 (Top Bar) 4 9.98 12mm bar 0.89 35.47
Grid 1-1,2-2 (Bottom Bar) 4 10.13 12mm bar 0.89 36.03
b Extra Bar 12 1.52 12mm bar 0.89 16.26
c Lateral ties
Grid A-A, B-B,C-C 147 0.86 7mm bar -L/4 @ 125mm & 0.30 38.40
150mm c/c
Grid 1-1,2-2 148 0.86 7mm bar -L/4 @ 125mm & 0.30 38.66
150mm c/c
v Plinth Beam
a main bar
Grid A-A, B-B,C-C (Top Bar) 6 6.89 16mm bar 1.58 65.28
Grid A-A, B-B,C-C (Bottom Bar) 6 6.89 16mm bar 1.58 65.28
Grid A-A, B-B,C-C (Top Bar) 3 6.98 12mm bar 0.89 18.62
Grid A-A, B-B,C-C (Bottom Bar) 3 6.89 12mm bar 0.89 18.36
Grid 1-1,2-2 (Top Bar) 4 9.93 16mm bar 1.58 62.79
Grid 1-1,2-2 (Bottom Bar) 4 9.93 16mm bar 1.58 62.79
Grid 1-1,2-2 (Top Bar) 2 10.03 12mm bar 0.89 17.83
Grid 1-1,2-2 (Bottom Bar) 2 9.93 12mm bar 0.89 17.66
b Extra Bar 12 1.52 12mm bar 0.89 16.26
c Lateral ties
Grid A-A, B-B,C-C 117 0.91 7mm bar -L/4 @ 125mm & 0.30 32.36
150mm c/c
Grid 1-1,2-2 114 0.91 7mm bar -L/4 @ 125mm & 0.30 31.53
150mm c/c
vi Slab Beam with cantilever
a main bar
Grid A-A, B-B,C-C (Top Bar) 6 8.05 16mm bar 1.58 76.32
Grid A-A, B-B,C-C (Bottom Bar) 6 8.05 16mm bar 1.58 76.32
Grid A-A, B-B,C-C (Top Bar) 3 8.15 12mm bar 0.89 21.73
Grid A-A, B-B,C-C (Bottom Bar) 3 8.10 12mm bar 0.89 21.60
Grid 1-1,2-2 (Top Bar) 4 10.03 16mm bar 1.58 63.40
Grid 1-1,2-2 (Bottom Bar) 4 10.03 16mm bar 1.58 63.40
Grid 1-1,2-2 (Top Bar) 2 10.13 12mm bar 0.89 18.01
Grid 1-1,2-2 (Bottom Bar) 2 10.03 12mm bar 0.89 17.83
b Extra Bar 12 1.52 12mm bar 0.89 16.26
c Lateral ties
Grid A-A, B-B,C-C 147 0.91 7mm bar -L/4 @ 125mm & 0.30 40.65
150mm c/c
Grid 1-1,2-2 148 0.91 7mm bar -L/4 @ 125mm & 0.30 40.93
150mm c/c
vii Hidden beam
a Main bar 4 9.83 12mm bar 0.89 34.94
b Lateral ties 79 0.86 7mm bar -L/4 @ 125mm & 0.30 20.63
150mm c/c
viii Sill band
a Main bar 2 20.32 12mm bar 0.89 36.12
b Lateral ties 41 0.28 7mm bar -L/4 @ 150mm c/c 0.30 3.46
Sub-Total 1820.33 kg
Total 5789.43 kg
Grand Total 5789.43 kg #REF! #REF!
9 Preparation of Formwork for Beam Slab, Column etc.
A Building -1
i Rectangular Footing 14 20.00 0.50 140.00
ii Trapezoidal Footing 14 20.00 1.50 420.00
iii Column upto Plinth level 14 4.00 2.58 144.48
iv Column above Plinth level 14 4.00 9.00 504.00
v Tie beam
Grid A-A, B-B 2 62.67 1.50 188.01
Grid C-C 1 13.17 1.50 19.75
Grid 1-1,2-2,5-5,6-6 4 12.50 1.50 75.00
Grid 3-3,4-4 2 20.50 1.50 61.50
vi Plinth beam
Grid A-A, B-B 2 62.67 1.67 208.90
Grid C-C 1 13.17 1.67 21.95
Grid 1-1,2-2,5-5,6-6 4 12.50 1.67 83.33
Grid 3-3,4-4 2 20.50 1.67 68.33
vii Slab Beam with cantilever
Grid A-A, B-B 2 66.17 2.00 264.68
Grid C-C 1 20.17 2.00 40.33
Grid 1-1,2-2,5-5,6-6 4 16.00 2.00 128.00
Grid 3-3,4-4 2 20.50 2.00 82.00
viii Landing beam 1 13.17 1.50 19.75
ix Waist Slab 2 7.83 4.00 62.67
x Landing 1 8.00 4.00 32.00
xi Sill band 1 57.16 0.66 37.73
Sub-Total 2602.40 sq.ft
B Building -2
i Rectangular Footing 6 20.00 0.50 60.00
ii Trapezoidal Footing 6 20.00 1.50 180.00
iii Column upto Plinth level 6 4.00 2.58 61.92
iv Column above Plinth level 6 4.00 9.00 216.00
v Tie beam
Grid A-A, B-B,C-C 3 19.25 1.50 86.63
Grid 1-1,2-2 2 28.25 1.50 84.75
vi Plinth beam
Grid A-A, B-B,C-C 3 19.25 1.67 96.25
Grid 1-1,2-2 2 28.25 1.67 94.17
vii Slab Beam with cantilever
Grid A-A, B-B,C-C 3 22.75 2.00 136.50
Grid 1-1,2-2 2 28.25 2.00 113.00
viii Hidden beam 1 31.25 30.50 953.13
ix Sill band 1 20.32 0.66 13.41
Sub-Total 2095.75 sq.ft
Total 4698.15 sq.ft
Grand Total 436.63 sq.m #REF! #REF!
10 Door & Window Chaukhat (Tudi Wood)
A Building-1
i Door
D1 4 18.00 0.33 0.25 5.94
D2 1 16.50 0.33 0.25 1.36
ii Window
W1 6 35.50 0.33 0.25 17.57
W2 1 17.00 0.33 0.25 1.40
Ventilation V 1 7.00 0.33 0.25 0.58
Sub- Total 26.85 cu.ft
B Building-2
i Door
D1 2 18.00 0.33 0.25 2.97
ii Window
W1 2 35.50 0.33 0.25 5.86
W3 2 21.66 0.33 0.25 3.57
Sub- Total 12.40 cu.ft
Total 39.26 cu.ft
Grand Total 1.11 cu.m #REF! #REF!
Sub - Total #REF!
VAT @ 13 % 169965.16
Grand-Total #REF!
Pre - income TAX @ 1.5% 19611.37
Rural municipality Contribution #REF!
Peoples contribution #REF! #REF!
Payment to be done #REF!
Estimated By : Checked By: Approved By:
Government of Nepal
Ministry of Federal Affairs and General Administration
Dogadakedar Rural Municipality
Office of Rural Municipality
Deulek, Baitadi
#REF!
#REF!
S. N. Description Of works Quantity Unit Per Cum Bag Toal Bag/ kg Rate Amount Remarks
1 (1:3:6) P.C.C Work on Foundation 15.27 cu.m 4.43 67.66 850 57510.50
2 Brick masonary work (1:4) 50.56 cu.m 2 101.12 850 85956.22
3 Brick 50.56 cu.m 560 28314.99 11.20 317127.88
4 Stone Masonry Work (1:4) 10.50 cu.m 3.18 33.39 850.00 28378.8354175
5 P.C. C (1:1.5:3)for R.C.C work 47.99 cu.m 8 383.94 850.00 326348.95
6 Reinforcement work with
cutting,bending,placing all 5789.43 kg 85.00 492101.961709
complete
Total 1307424.34
Vat @13% 169965.16
Sub Total 1477389.50
Total Quantity as BoQ Work Completed till this bill Work Completed as Previous bill Recently completed work
Item
Description Unit Remarks
No Quantity Rate Amount Quantity Amount Quantity Amount Quantity Amount
1 #REF! ### #REF! #REF! #REF! 104.98 #REF! 0.00 #REF! 104.98 #REF!
Backfilling work of all types of soil and
2 #REF! #REF! #REF! 147.20 #REF! 0.00 #REF! 147.20 #REF!
all types of rock ###
3 #REF! ### #REF! #REF! #REF! 27.18 #REF! 0.00 #REF! 27.18 #REF!
4 #REF! ### #REF! #REF! #REF! 15.27 #REF! 0.00 #REF! 15.27 #REF!
5 #REF! ### #REF! #REF! #REF! 50.56 #REF! 0.00 #REF! 50.56 #REF!
6 #REF! ### #REF! #REF! #REF! 10.50 #REF! 0.00 #REF! 10.50 #REF!
7 #REF! ### #REF! #REF! #REF! 47.99 #REF! 0.00 #REF! 47.99 #REF!
8 #REF! ### #REF! #REF! #REF! 5789.43 #REF! 0.00 #REF! 5789.43 #REF!
9 #REF! ### #REF! #REF! #REF! 436.63 #REF! 0.00 #REF! 436.63 #REF!
10 Door & Window Chaukhat (Tudi Wood) cu.m #REF! #REF! #REF! 1.11 #REF! 0.00 #REF! 1.11 #REF!
11 #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
12 #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
13 #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
14 #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
15 #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
16 #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
17 #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
18 #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
19 #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
20 #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
21 #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
22 #REF!
### #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
### #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
### #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
### #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
### #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
### #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
### #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
### #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
### #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
### #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
### #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
### #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
### #REF! ### #REF! #REF! #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF!
### #REF! ### #REF! #REF! #REF! 0.00 #REF! #REF! #REF! #REF! #REF!
xv #REF! pt. 1.00 #REF! #REF! 0.00 #REF! #REF! #REF! #REF! #REF!
VAT @13% #REF! 169965.16 169965.16
Grand Total #REF! #REF! #REF!
13 CGI Ridge
24Gauge Colour Plain Sheet for ridge cover 1 18 18.00 rm 770.00 13860.00
Total of Civil & Architectural Works(without VAT) 4922282.49
Electrification @1.9% 93523.37
Total without VAT@13% 5015805.86
Contengencies@1% 50158.059
VAT @ 13 % 322322.10
Grand-Total one Guest house 5388286.01
Grand-Total two Guest house 10776572.03
Office Contribution 9698914.827
Public Contribution 1077657.203 10.00%
Estimated By: Checked By: Approved By:
Government of Province
Ministry of Industry,Tourism, Forestry & Environment
Sudurpaschim Province.
Provisional Tourism Development Program Implementation Unit.
(PTDPIU)
Dhangadi, Kailali
Office Code:
Detail Estimate & Abstract of Cost
Name of Project : Preparation of DPR Of Tripura Sundari Mandir Conservation and Upgradation. F.C.G.O.Form No.: 501
Location :Dasharathchand Municipality - 8 Baitadi Previous F.C.G.O Form No.: NA
Estimated Completion time: Fiscal Year:-2076/077
Budget Sub Topic No:
S.No Description of the work No. L B H Quantity Unit Rate Amount Remarks
A CIVIL WORKS
1 Earthworks Excavation
Field Cutting 1 15 6 1.8 162.00
Footing1 4 1.5 1.5 1.5 13.50
Footing2 4 1.8 1.8 1.8 23.32
Sub-Total 198.82 Cum 543.84 108126.2688
2 Stone Soling
Soling upto Plinth Level 1 11.9 2.9 1.5 51.76
Footing1 4 1.5 1.5 0.2 1.80
Footing2 4 1.6 1.6 0.2 2.04
Sub-Total 55.60 Cum 3145.20 174873.12
3 PCC(1:1.5:3)
Footing1 4 1.5 1.5 0.15 1.35
Footing2 4 1.6 1.6 0.15 1.53
Sub-Total 2.88 Cum 17834.99 51364.7712
4 PCC(1:1.5:3) For RC Works
Footing1 4 1.5 1.5 0.5 4.50
Footing1 4 1.6 1.6 0.5 5.12
Upto Plinth Level
Column1 4 0.45 0.45 2.85 2.30
Column2 4 0.6 0.6 2.85 4.10
For Super Structure
Column
Column1 4 0.45 0.45 4.57 3.70
Column2 4 0.6 0.6 7.62 10.97
Beam
On Level 2
Long Side 2 11.89 0.3 0.3 2.14
Short Side 3 2.13 0.3 0.3 0.57
On level 4
Long Side 2 4.57 0.3 0.3 0.82
Short Side 2 2.13 0.3 0.3 0.38
Slab
On Level 2 1 13.77 4.13 0.125 7.11
On Level 4 1 6.57 4.13 0.125 3.39
Deduction column
Column1 -4 0.45 0.45 0.125 -0.10
Column2 -4 0.6 0.6 0.125 -0.18 Level 2
Column2 -4 0.6 0.6 0.125 -0.18 Level 4
Sub-Total 44.64 Cum 17834.99 796141.02
5 Reinforcement@1% of RC works 3504.18 Kg 119.30 418041.79
6 Plastering Works(1:4) 20mm
Column
Column1 16 0.45 4.57 32.90
Column2 16 0.6 7.62 73.15
Beam
On Level 2
Long Side 6 11.89 0.3 21.40
Short Side 9 2.13 0.3 5.75
On level 4
Long Side 6 4.57 0.3 8.23
Short Side 6 2.13 0.3 3.83
Slab
On Level 2 1 13.77 4.13 56.87
On Level 4 1 6.57 4.13 27.13
Deduction beam area
On Level 2
Long Side -2 11.89 0.3 -7.13
Short Side -3 2.13 0.3 -1.92
On level 4
Long Side -2 4.57 0.3 -2.74
Short Side -2 2.13 0.3 -1.28
Sub-Total 216.20 Sqm 492.34 106444.99
7 38mm Screeding On ground Level
1 11.9 2.9 34.51
Sub-Total 34.51 Sqm 673.17 23231.10
9 Punning on ground level 34.51
Sub-Total 34.51 Sqm 267.60 9234.88
10 Painting works
Two coat weathercoat paint with one coat
primer( same as plastering works) 216.20 Sqm 267.35 57801.66
A Gabion Boxes
Earthwork in Gabion Base in
ordinary soil
1 35 4 2.5 175.00 Cum 543.84 95172.00
Gabion Box WORK
3X1X1 45 45.00 Nos 4482.45 201710.3
Filling Stone in Gabion Boxes
45 3 1 1 135.00 Cum 3145.20 424602.00
Sub Total 721484.25
Vat@13% 26222.33
Contengencies@1% 7214.84
Total 754921.43
Office Contribution 679429.28
Public Contribution 75492.14 10.00%
Government of Province
Ministry of Industry,Tourism, Forestry & Environment
Sudurpaschim Province.
Provisional Tourism Development Program Implementation Unit.
(PTDPIU)
Dhangadi, Kailali
Office Code:
Detail Estimate & Abstract of Cost
Name of Project : Preparation of DPR Of Tripura Sundari Mandir Conservation and Upgradation. F.C.G.O.Form No.: 501
Location :Dasharathchand Municipality - 8 Baitadi Previous F.C.G.O Form No.: NA
Estimated Completion time: Fiscal Year:-2076/077
Budget Sub Topic No:
S.No Description of the work No. L B H Quantity Unit Rate Amount Remarks
BUILDING
A CIVIL WORKS
Block 1
1 Earth Works
1.1 SITE CLEARANCE & MOBILIZATION :
Total Area 1 15.00 6.00 90.00
Net Quantity 90.00 Sqm 27.19 2447.10
1.2 EARTHWORK IN EXCAVATION :
i Field Cutting 1 15.00 6.00 0.80 72.00
ii Excavation for footing
Footing 4 2.03 2.03 1.50 24.72
iii Excavation for foundation Beam Providing 10mm
clearance in each
Along grid 1-1 & 2-2 2 3.17 0.65 1.50 6.18 side
Along grid A-A & B-B 2 2.17 0.65 1.50 4.23
Net Quantity 107.13 cu.m 543.84 58261.58
1.3 Back filling work For all types of Soil
and all types of Rock @40% of E/W 42.85
excavation
Net Quantity 42.85 cu.m 169.95 7282.70
1.4 Soling Work
Soling for footing
Footing 4 1.83 1.83 0.20 2.67
Soling for Wall foundation
Along grid 1-1 & 2-2 2 3.17 0.45 0.20 0.57
Along grid A-A & B-B 2 2.17 0.45 0.20 0.39
Ground floor room
1 4.6 3.60 0.50 8.28
Net Quantity 11.91 cu.m 3145.20 37459.33
2 CONCRETE WORKS
1.5 (1:2:4) P.C.C Work on Foundation
Footing 4 1.83 1.83 0.10 1.33
Wall Foundation
Along grid 1-1 & 2-2 2 3.17 0.45 0.10 0.29
Along grid A-A & B-B 2 2.17 0.45 0.10 0.20
Net Quantity 1.81 cu.m 13619.44 24659.36
2.2 P.C.C. FOR R.C.C. WORKS(1:1.5:3)
Footing 4 1.83 1.83 0.50 6.69
Column upto Plinth level 4 0.4 0.40 1.35 0.86
Plinth beam
Along grid 1-1 & 2-2 2 4.60 0.27 0.35 0.86
Along grid A-A & B-B 2 3.60 0.27 0.35 0.68
Ground floor
Column 4 0.40 0.40 3.50 2.24
Beam
Along grid 1-1 & 2-2 2 5.60 0.27 0.35 1.05 Adding Cantilever
Along grid A-A & B-B 2 4.60 0.27 0.35 0.86 Adding Cantilever
First floor
Column 4 0.40 0.40 3.50 2.24
Beam Adding Cantilever
Along grid 1-1 & 2-2 2 6.60 0.27 0.35 1.24 Adding Cantilever
Along grid A-A & B-B 2 5.60 0.27 0.35 1.05
Top floor
Column Adding Cantilever
4 0.40 0.40 3.50 2.24
Along grid 1-1 & 2-2 Adding Cantilever
2 6.60 0.27 0.35 1.24
Along grid A-A & B-B 2 5.60 0.27 0.35 1.05
Slab
GF 1 12.00 6.00 0.13 9.00
FF 1 12.00 6.00 0.13 9.00
TF 1 12.00 6.00 0.13 9.00
Deduction
column -4 0.40 0.40 0.13 -0.08
Staircase part -3 2.10 1.00 0.13 -0.78
Staircase
Waist Slab 1 12.00 1.20 0.15 2.16
Landing Slab 1 2.40 1.20 0.15 0.43
Tread & Riser 38 0.28 1.20 0.18 1.12
Total 52.15 Cum 17834.99 930005.55
3 Reinforcement work with cutting,bending,placing all complete@0.9%of RCC works
36.84 Quintel
Total 3684.04 Kg 119.30 439498.85
4 FORM WORKS
Tread & Riser 4 0.28 0.28 0.50 1.68
Column upto Plinth level 4 0.4 0.40 1.35 6.48
Plinth beam
Along grid 1-1 & 2-2 2 4.60 0.27 0.35 6.62
Along grid A-A & B-B 2 3.60 0.27 0.35 5.22
Ground floor
Column 4 0.40 0.40 3.50 16.80
Beam
Along grid 1-1 & 2-2 2 5.60 0.27 0.35 8.02
Along grid A-A & B-B 2 4.60 0.27 0.35 6.62
First floor
Column 4 0.40 0.40 3.50 16.80
Beam
Along grid 1-1 & 2-2 2 6.60 0.27 0.35 9.42
Along grid A-A & B-B 2 5.60 0.27 0.35 8.02
Top floor 0.00
Column 4 0.40 0.40 3.50 16.80
Along grid 1-1 & 2-2 2 6.60 0.27 0.35 9.42
Along grid A-A & B-B 2 5.60 0.27 0.35 8.02
Slab
GF 1 12.00 6.00 0.13 3.75
FF 1 12.00 6.00 0.13 3.75
TF 1 12.00 6.00 0.13 3.75
Deduction
column -4 0.40 0.40 0.13 -0.60
Staircase part -3 2.10 1.00 0.13 -1.95
Staircase
Waist Slab 1 12.00 1.20 0.15 3.78
Landing Slab 1 2.40 1.20 0.15 0.90
Tread & Riser 38 0.28 1.20 0.18 11.70
Total 145.00 Sqm 699.98 101497.10
5 MASONRY WORKS
5.1 Stone masonary work (1:4) upto plinth Level
wall Foundation
Along grid 1-1 & 2-2 2 4.6 0.45 1.35 11.09
Along grid A-A & B-B 2 3.6 0.45 1.35 20.24
Total 31.33 cum 11413.82 357592.76
5.2 BRICK MASONRY WORKS(1:4 c/s)
GF & FF
Along grid 1-1 & 2-2 4 4.60 0.23 3.50 14.81
Along grid A-A & B-B 4 3.60 0.23 3.50 11.59
Deduction
Windows
W1 -4 1.8 0.23 1.80 -2.98
Door
D1 -2 1.00 0.23 2.40 -1.10
Total 22.32 Cum 18506.07 413055.48
6 DOOR & WINDOWS WORKS
Supplying and fixing of Swing
Door of aluminium section in
naturally anodized color Section
size (101*44.5*1.2 mm) fitted with
5 mm clear glass all complete as
per need and specification all
complete work as direceted by site
6.1
incharge.
Door
D1 2 1.00 2.40 4.00 Sqm 10350.00 41400.00
6 Form works
90 0.80 1.30 93.60 sqm 699.98 65518.13
7 Plaster work(1:4)
90 0.80 1.30 93.60 sqm 373.59 34968.02
Two coat weathercoat painting work
8 with one coat primer
Including top of post 90 1.00 1.30 117.00 sqm 267.35 31279.95
Providing 2" GI Pipe For Railing
9 Works 3 200.00 600.00 rm 855.75 513450.00
Sub Total 826665.22
Vat@13% 86394.17
Cotengencies@1% 8266.65
Total 921326.05
Office Contribution 829193.44
Public Contribution 92132.60 10.00%
Government of Province
Ministry of Industry,Tourism, Forestry & Environment
Sudurpaschim Province.
Provisional Tourism Development Program Implementation Unit.
(PTDPIU)
Dhangadi, Kailali
Office Code:
Detail Estimate & Abstract of Cost
Name of Project : Preparation of DPR Of Tripura Sundari Mandir Conservation and Upgradation. F.C.G.O.Form No.: 501
Location :Dasharathchand Municipality - 8 Baitadi Previous F.C.G.O Form No.: NA
Estimated Completion time: Fiscal Year:-2076/077
Budget Sub Topic No:
S.No Description of the work No. L B H Quantity Unit Rate Amount Remarks
1 Bell house
Column 14 0.23 2 2.4 15.456
Floor 1 8.5 4 0.4 13.6
Roof 1 8.5 4 0.4 13.6
2 Toilet
1 6.125 2.8 3 51.45
Deduction room -3 1.8 1.5 2.4 -19.44
3 Gate
1 12.6 1 5 63
Deduction Open entrance -2 1.5 1 4 -12
4 Side Post
90 0.3 0.3 2 16.2
141.866 m3 1785.00 253230.8
Sub Total 253230.8
Cotengencies@1% 2532.308
Total 255763.1
Office Contribution 230186.8
Public Contribution 25576.31
Government of Province
Ministry of Industry,Tourism, Forestry & Environment
Sudurpaschim Province.
Provisional Tourism Development Program Implementation Unit.
(PTDPIU)
Dhangadi, Kailali
Office Code:
Detail Estimate & Abstract of Cost
Name of Project : Preparation of DPR Of Tripura Sundari Mandir Conservation and Upgradation. F.C.G.O.Form No.: 501
Location :Dasharathchand Municipality - 8 Baitadi Previous F.C.G.O Form No.: NA
Estimated Completion time: Fiscal Year:-2076/077
Budget Sub Topic No:
S.No Description of the work No. L B H Quantity Unit Rate Amount Remarks
1 Tile Cladding In Stage stairs
4 6.8 0.3 8.16
4 6.8 0.3 8.16
5 7.6 0.3 11.4
5 7.6 0.3 11.4
6 10 0.3 18
3 6.6 2 39.6
5 2.8 0.3 4.2
5 2.8 0.3 4.2
6 7.6 0.3 13.68
6 7.6 0.3 13.68
2 7.6 0.3 4.56
Total Quantity 137.04 m2 4606.77 631312.028
Sub Total 631312.028
Vat@13% 82070.5637
Contengencies@1% 6313.12028
Total 719695.712
Office Contribution 647726.141
Public Contribution 71969.57 10.00%
Government of Province
Ministry of Industry,Tourism, Forestry & Environment
Sudurpaschim Province.
Provisional Tourism Development Program Implementation Unit.
(PTDPIU)
Dhangadi, Kailali
Office Code:
Detail Estimate & Abstract of Cost
Name of Project : Preparation of DPR Of Tripura Sundari Mandir Conservation and Upgradation. F.C.G.O.Form No.: 501
Location :Dasharathchand Municipality - 8 Baitadi Previous F.C.G.O Form No.: NA
Estimated Completion time: Fiscal Year:-2076/077
Budget Sub Topic No:
S.No Description of the work No. L B Kg/m Total Weight Unit Rate Amount Remarks
A ROOFING/TERRACING WORKS
1 Building 1
Metal Works
No of Truss 4
Side Post NB40M 2 0.30 3.56 8.54
King Post NB40M 1 0.50 3.56 7.12
Purlin NB 32M 5 7.00 3.10 108.50
Bottom chord N32 3 6.00 3.10 55.80
Rafter NB 40M 2 3.36 3.56 95.69
Bottom chord N40 1 3.20 3.56 11.39
Purlin & Runner Plates 20 0.18 0.06 78.5 282.60
Bolts 35 0.07 9.80
Vertical Post NB65M 9 3.00 6.42 173.34
752.79 Kg 189.64 142758.87
2 Building-2
Metal Works
No of Truss 6
Side Post NB40M 2 0.50 3.56 21.36
Side Post NB40M 2 0.20 3.56 8.54
King Post NB40M 1 0.80 3.1 14.88
Purlin NB 32M 7 14.10 3.1 305.97
Bottom chord N32 3 13.10 3.56 139.908
Rafter NB 40M 2 3.50 3.56 149.52
Bottom chord N40 1 6.80 3.56 145.25
Purlin & Runner Plates 40 0.18 0.06 78.5 33.91
Bolts 50 0.07 0.89 18.69
Vertical Post NB65M 13 3 6.42 250.38
1088.41 Kg 189.64 206406.45
3 CGI Sheet Roofing
Building-1
1 7.00 4.70 32.9
Building-2
1 14.10 7.80 109.98
142.88 Sqm 1281.97 183167.87
4 CGI Sheet Ridge
Building-1
1 7.00 7
Building-2
1 14.10 14.1
21.1 rm 770.00 16247.00
5 Construction of foundation for Vertical Post(1:1.5:3) 22 0.30 0.30 0.5 0.99 cum 17834.99 17656.64
Sub Total 566236.83
Vat@13% 73610.79
Contengencies@1% 5662.37
Total 645509.99
Office Contribution 580958.99
Public Contribution 64551.00 10.00%
Government of Province
Ministry of Industry,Tourism, Forestry & Environment
Sudurpaschim Province.
Provisional Tourism Development Program Implementation Unit.
(PTDPIU)
Dhangadi, Kailali
Office Code:
Detail Estimate & Abstract of Cost
Name of Project : Preparation of DPR Of Tripura Sundari Mandir Conservation and Upgradation. F.C.G.O.Form No.:
Location :Dasharathchand Municipality - 8 Baitadi Previous F.C.G.O Form No.:
Estimated Completion time: Fiscal Year:-2076/
Budget Sub Topic
Description of the work
S.No No. L B H Quantity Unit Rate
1 Earthwork Excavation
1 30 1.2 2.2 79.2 Cum 543.84
2 Stone Masonry Wall(1:3 C/s)
1.5m from foundation upto
ground level 1 30 1 6.5 195 Cum 12051.23
Sub Total
Vat@13%
Contengencies@1%
Total
Office Contribution
Public Contribution
ment
ation Unit.
Amount Remarks
43072.128