Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Sl. No EQUIPMENT LOAD (MW)/STEAM GENERATION (TPH) REASONS / REMARKS (If any)
C. Water Chemistry:
Boiler Water Parameters Cooling Water Parameters
pH Conductivity(µS/cm)
Dated 30.10.2020
Parameters
Range Actual Range Actual
Parameters Range Actual
DM Water(at B/L) (6.5 – 7.0) * <0.20 pH 7.2 –8.5 7.40
Main Steam sample (8.5 - 9.5) <5.0 Conductivity < 6000 2200
AB-1 (9.0 - 10.0) <50 Chloride <1600 355
Drum Sample
AB-2 (9.0 - 10.0) <50 FRC 0.20 - 0.5 0.00
HRSG1 (SHP) (9.0 - 10.0) <50 COC based on MgH. 3.0-6.0 6.30
HRSG2 (SHP) (9.0 - 10.0) <50 Remarks if any:
Drum Sample
HRSG1 (MP) (9.8 - 10.6) <3000
HRSG2 (MP) (9.8 - 10.6) <3000
Condensate CSTG (8.5-9.5) <5.0
*DM water pH at DM plant O/L is 6.5 to 7.0. However morpholine is dosed to elevate pH & pH parameter at CPP B/L is 6.5 to 9.0&
Conductivity at CPP B/L is 0 to 2.0.
B. Status/major events from last working day/major & chronic issues By SIC :
1. CW chlorination not happening. 1 week problem
Maintenance: Two valves to be repaired and tested for passing and then fix back.
2. GT Lub oil levels low
Maintenance: Expected: 4– 11 -20
3. CST crane not available vendor not responding.
Please check alternate service provider as this is a minor job
C. Safety Observations:
D. Current Issues:
Sl. Initiation
Issue Estimated date of completion or plans Resp.
No date
th
On 29 , C&I investigated and found Axial vib pickup was faulty.
CT fan# B axial & radial vibration alarm were
1 28.10.20 Changed. Also cable connection terminals were found having C&I
coming frequently
salt deposits. Corrected.
28.10.20 New card to be purchased. Available at local market. A weeks
2 In Gas detection system HMI getting hanged. C&I
time is required.
At the time of NPH tank-A changeover Valve 28.10.20 Ops and Mtc together stroked the valve. Proximity switch
3 feedback is not coming in DCS. adjusted. However, overlap of the contact so the switch works C&I
above 85% to be sure will be done.
GT-1 transformer cooling Fan-3 Vibration. 28.10.20
4 Corrected temporarily. Defect raised for S/D E
Poor illumination in CT Fan area, to be
5 12.10.2020 Completed E
improved.
Bulk acid storage tank drain line flange joint
6 13.10.2020 Will be taken up after emptying of tank by 01.12.2020. M
leakage observed.
7 SHP CBD line leakage observed in HRSG-1 13.10.2020 Completed M
8 6.6 kV bus coupler tripping is to be rectified. 22.10.2020 Setting to be revised. E
F. Pending Issues (to shift from current issues which are more than a month old, to be discussed on first Monday of every month):
Initiation
No Issue Plans EDC Resp.
date
1 Mass flow meter: 12-11-19 Naphtha B/L mass flow meter could not be replaced
- Installation technical limit needs to be because of mismatching of flanges. A separate
verified from manual. report will be made and circulated on the issue
0 0 0 5
I. Reminder:
PR Status, Pending Material Inspection, Critical system study related to GT,Pending TBA Status (more than 8 days),and Status of rejected
material, Emergency procurement issues.