Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Sl. No EQUIPMENT LOAD (MW)/STEAM GENERATION (TPH) REASONS / REMARKS (If any)
C. Water Chemistry:
Boiler Water Parameters Cooling Water Parameters
pH Conductivity(µS/cm)
Dated 04.11.2020
Parameters
Range Actual Range Actual
Parameters Range Actual
DM Water(at B/L) (6.5 – 7.0) * 8.2 <0.20 1.5 pH 7.2 –8.5 7.30
Main Steam sample (8.5 - 9.5) NA <5.0 NA Conductivity < 6000 1000
AB-1 (9.0 - 10.0)9.6 <50 48 Chloride <1600 355
Drum Sample
AB-2 (9.0 - 10.0) 9.7 <50 53 FRC 0.20 - 0.5 0.00
HRSG1 (SHP) (9.0 - 10.0) SD <50 SD COC based on MgH. 3.0-6.0 5.70
HRSG2 (SHP) (9.0 - 10.0) 9.9 <50 73 Remarks if any:
Drum Sample
HRSG1 (MP) (9.8 - 10.6) SD <3000 SD Suspected NAOH in TSP, will be better controlled
HRSG2 (MP) (9.8 - 10.6) 10.6 <3000 180 from December 1st week.
Condensate CSTG (8.5-9.5) 8.8 <5.0 2.61
*DM water pH at DM plant O/L is 6.5 to 7.0. However morpholine is dosed to elevate pH & pH parameter at CPP B/L is 6.5 to 9.0&
Conductivity at CPP B/L is 0 to 2.0.
B. Status/major events from last working day/major & chronic issues By SIC :
1. HRSG-1 shutdown jobs are under progress.
C. Safety Observations:
1. GT-2 turbine compartment & LGB compartment temperature is very high: Continuous monitoring is to be done to see the further
deterioration of temperature profile.
2. Turbine compartment overall exhaust temp near BT fan suction is 123degC, Highest is 323degC & LGB compartment exhaust tunnel
area max temp is 250degC.
D. Current Issues:
F. Pending Issues (to shift from current issues which are more than a month old, to be discussed on first Monday of every month):
Initiation
No Issue Plans EDC Resp.
date
Mass flow meter:
Naphtha B/L mass flow meter could not be replaced
- Installation technical limit needs to be
1 12-11-19 because of mismatching of flanges. A separate - Inst
verified from manual.
report will be made and circulated on the issue.
Communication started with Woodward for onsite
GT-2 SRV & GCV both are having Inst/
2 08-5-2019 services & to identify the spares of repair kit. -
passing. Mech
E-mail to be sent by 20.10.2020.
PO placed for servo motors on 17.09.2019 (No-
3 CSTG CV hunting 09-5-2019 3046478), follow up is being done for material Oct’2020 Inst
dispatch.
New Feed Control valve for AB/HRSGs Inst/
4 22.11.2019 PR raised(PR No-1067757) -
to be procured. Mech
PO NO: 3046926, Delivery date is over. Follow up is
5 AB-2 soot blower MOV is not working. 20.07.2020 - Inst
being done. Delivery Date: 19.03.2020
0 0 0 0
I. Reminder:
PR Status, Pending Material Inspection, Critical system study related to GT, Pending TBA Status (more than 8 days),and Status of rejected
material, Emergency procurement issues.