Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
KK4
2020
DECLARATION
We hereby declare that the work in this final year design project is our own except for
the quotations and summaries which have been duly acknowledged.
Praise to Allah, the most gracious the most merciful. Thank you for giving us strength
and spirit to us to complete this project. We will never complete this challenging Final
Year Design Project if we did not receive some help from these people.
First and foremost, we would like to express our highest appreciation to our
beloved supervisor, Prof Dr Ir Siti Kartom Kamarudin, Assoc. Prof Dr Masli Irwan
Rosli, and our industrial mentor, Miss Hemavathi Silvamany for their concern and
guidance in this project. Special thanks to our lecturers Ir Dr Syuhaida Harun, Dr
Rosiah Rohani, Prof Ir Dr Abdul Wahab, Dr Darman Nordin, Prof Ir Dr Sobri Tarrif, ,
Dr Teow Yeit Haan, Dr Ir Nor Yuliana Yuhana and Assoc Prof Dr Shahbudin Masdar
@ Mastar for guiding and giving us knowledge complete this project. Without the
encouragement and patience, we believe that we would hardly finish our tasks before
the due date. Also, we would like to express our highest gratitude to our parents for
giving us all the moral support when we really need one. Thank you very much and
may god bless your help,
Lastly, we would like to thank all our coursemates, seniors, and those who are
involved in helping our in this project directly and indirectly. Without all of the help
it is impossible for us to complete this project. Your kindness and cooperation is
highly appreciated. Just words alone cannot illustrate how much we thank you all.
MONETISATION OF POME INTO RENEWABLE GAS AND GREEN CHEMICALS
ABSTRACT
The proposed design project is to build a processing plant that produces methanol and
bioflocculant from the palm oil mill effluent (POME). This purpose of this study is to
minimize the waste from palm oil mill and at the same time converting is to valuable
materials. This study aims to produce bioflocculant at 2000 tonnes /year. In the first
phase, the study began with feasibility study of the product based on several factors
such as supply and demand, product price and production process of the product.
After that, it is followed by a rough draft of the methanol and bioflocculant production
processes. From the draft, several factors that need to be considered such as type of
reactors, type of separation units, plant location and utility have been collected and
evaluated in order to select the most efficient unit process for treating POME and
produce desired product. The location chosen for the operation is Lahad Datu, Sabah.
This process is started by lowering the POME temperature to 30oC. Later, POME will
be treated through anaerobic digester which is UASB reactor to produce biogas that
will be then used to produce methanol. Caustic scrubbing will be performed to
separate H2S gas from the biogas mixture. After that, the treated biogas will be
processed to produce methanol and 99.9% purity of methanol can be produced after
purification process. The liquid obtained after the anaerobic process in the UASB
reactor will be used to produce bioflocculant in the MBBR reactor with the presence
of B.marisflavi type bacteria. Furthermore, the initial economic study to estimate
gross profit was carried out taking into account the sale price of the product with the
total price of raw materials as well as the capital expenditure of process unit
purchases. The results shows that gross profit earned was RM 378 million. Second
phase study of this project is to perform mass and energy balance by manual
calculation and simulations software. Heat integration analysis in processing plants is
carried out and as much as 75% of the energy can be recovered. Moreover, process
control analysis (P&ID) was conducted to control the process and to optimize product
production while maintaining high product quality. Waste treatment system is also
designed to minimize waste produced and ensuring that the waste released is in
compliance with established standards. Safety analyzes such as HAZOP and HIRARC
are also carried out to ensure that the process plant is safe and in compliance with the
regulations set by safety agencies such as OSHA 1994. Economic analysis of this
study was also conducted to determine the rate of return on investment, payback
period and net present value. The analysis shows that the rate of return is 0.4, the
payback period is 2.3 years and the net present value is RM 85.6 million. Detailed
calculations of the design of each process unit are also carried out individually to
ensure the loading and specification of each process unit to ensure plant safety.
ABSTRAK
Kajian projek reka bentuk yang dijalankan adalah untuk pembinaan sebuah kilang
yang menghasilkan metanol dan pengumpal-bio daripada efluen kilang minyak kelapa
sawit(POME). Kajian ini dijalankan adalah bagi meminimakan sisa buangan daripada
minyak kelapa sawit dan pada masa yang sama menggunakan sisa tersebut untuk
menghasilkan suatu bahan yang boleh menjana pendapatan. Kajian ini menyasarkan
penghasilan pengumpal-bio sebanyak 2000 tan/tahun .Pada fasa pertama, kajian
dimulakan dengan menilai kebolehpasaran produk berdasarkan beberapa faktor seperti
permintaan semasa dan bekalan, harga dan cara penghasilan produk tersebut. Selepas
itu, draf kasar bagi proses penghasilan metanol dan pengumpal-bio dijalankan. Dari
draf tersebut, faktor yang diambil kira seperti jenis reaktor, jenis unit pemisahan,
pelan lokasi dan utiliti telah dikumpul dan dinilai untuk memilih proses yang paling
efisien dalam proses merawat POME dan penghasilan produk. Lokasi yang dipilih
untuk menjalankan operasi adalah Lahad Datu, Sabah. Proses ini dimulakan dengan
menurunkan suhu POME kepada 30oC. Kemudian, POME akan dirawat melalui
proses pencernaan anerobik di dalam reaktor UASB untuk menghasilkan biogas yang
akan digunakan untuk menghasilkan metanol. Pembersihan kaustik akan dijalankan
bagi memisahkan gas H2S dari campuran biogas. Selepas itu, biogas yang telah
dirawat akan diproses untuk menghasilkan metanol dan 99.9% metanol dapat
dihasilkan selepas proses penulenan. Cecair yang diperoleh selepas proses anerobik
dalam reaktor UASB akan digunakan untuk menghasilkan pengumpal-bio di dalam
reaktor MBBR dengan kehadiran bakteria jenis B.marisflavi. Selain itu, kajian awal
ekonomi untuk menganggar untung kasar dijalankan dengan mengambil kira harga
jualan produk dengan jumlah harga bahan mentah serta perbelanjaan modal pembelian
unit proses. Hasil kajian menunjukkan untung kasar yang diperolehi adalah sebanyak
RM 378 juta. Fasa kedua kajian adalah dengan membuat pengiraan imbangan jisim
dan imbangan tenaga secara manual dan simulasi telah dijalankan. Analisis
penyepaduan tenaga dalam loji proses dijalankan dan sebanyak 75% tenaga dapat
dipulihkan. Seterusnya, kajian analisis kawalan proses (P&ID) telah dijalankan bagi
mengawal proses dan bagi mengoptimumkan penghasilan produk di samping
menghasilkan produk yang bermutu. Sistem rawatan sisa buangan loji juga
dikenalpasti dengan meminimakan bahan buangan dan memastikan sisa buangan yang
dilepaskan adalah menepati piawaian yang telah ditetapkan. Analisis keselamatan
seperti HAZOP dan HIRARC juga dijalankan untuk memastikan loji proses adalah
selamat dan menepati undang-undang yang telah ditetapkan oleh agensi keselamatan
seperti OSHA 1994. Analisis ekonomi bagi kajian ini juga dijalankan bagi mengetahui
kadar pulangan pelaburan, tempoh bayaran pulangan pelaburan dan nilai semasa
bersih. Hasil analisis menunjukkan kadar pulangan adalah 0.4, tempoh bayaran
pulangan adalah 2.3 tahun dan nilai semasa bersih adalah RM 85.6 juta. Pengiraan
terperinci reka bentuk setiap unit proses juga dijalankan secara individu bagi
memastikan muatan dan spesifikasi setiap unit proses untuk menjamin keselamatan
loji.
EXECUTIVE SUMMARY
In this design project, a sustainability palm oil mill effluent (POME) treatment
pathway in palm oil mill industry has been designed. Besides treating POME in an
effective way, our designed plant is able to produce green chemicals such as
polysaccharide bioflocculant, methanol and other by-products. The produced
polysaccharide can widely be used in flocculating algae. This nontoxic and
biodegradable flocculant have high potential to be commercialized. The methanol
produced can act as a basic building block in the production of other chemicals such
as plastics, solvent, fuel and paints. Two by products are produced which is the sludge
oil and sludge. The sludge oil can be sold to other industries to produce chemicals like
perfume or biodiesel. The sludge has high organic content which can serve as an
organic fertilizer to the oil palm plantation itself.
This plant is designed into two main parts which are the biochemical and
chemical plant. The POME treatment and bioflocculant production will be done in the
biochemical plant while the methanol production will take place in the chemical plant.
First and foremost, the most important raw material need in our plant is POME. This
hot POME is received from Felda Global Ventures (FGV) Mercu Puspita Palm Oil
Mill will be stored and cooled down in the cooling pond. Once the POME is at 37°C,
it will undergo anaerobic process in up flow anaerobic sludge blanket (UASB) reactor
to produce biogas. This biogas will serve as the raw material in the chemical plant.
The anaerobically digested POME will then be sent to moving bed bioreactor
(MBBR) for aerobic process to take place. The anaerobic process will produce the
bioflocculant. The bioflocculant will undergo a downstream process to reduce the
moisture content to 10%. The POME then will enter the wastewater treatment to be
treated until it meets the Standard B limit before been discharged.
The biogas consists of methane and carbon dioxide will undergo scrubbing
process to remove the trace amount of hydrogen sulphide before been supplied to the
chemical plant. Next, the biogas will undergo methane steam reforming process
followed by methanol forming process. Both of this process occurs in two different
packed bed reactors. The methanol will undergo a purification process to produce
99.9% purity methanol.
Mass and energy balance are conducted for the whole plant using manual and
simulation calculations. Two simulation software have been used which is the
Superpro Designer® in calculation of the biochemical plant while iCON in calculation
of the chemical plant. The manual calculation and simulation calculation have been
compared for both mass and energy balance. The error percentage obtained is about
9.4%. Besides, heat integration has been done in our designed plant by using the pinch
analysis steps in order to reuse the heat energy and minimize the total energy wastage.
The total heat energy recovery from heat integration is 75%.
Control system have been designed for each equipment that involve in the
production plant. Degree of freedom analysis have been done to determine the number
of parameters that should be controlled in the equipment. The control strategies have
been stated for each equipment. Basically, the chemical plant requires more control
system compared to the biochemical plant because chemical process is highly specific
in terms of the reaction and separation process. Piping system and suitable pipe size
have been determined for each stream. A piping and instrumentation diagram (P&ID)
have been drawn for the production plant.
A detailed design for all the equipment involves in the production plant have
been done. This is to ensure a proper manufacture and construction of all the
equipment. Mechanical design for six major equipment has been done which is the
UASB reactor (T-101, T-102 and T-103), MBBR (T-105), cooler (CO-101), methanol
forming reactor (R-102), phase separator (S-102) and distillation column (C-101).
This mechanical design will show the maximum allowable working pressure
(MAWP), the wall thickness and suitable support for that particular equipment. For
the equipment involves in biochemical process, mostly the equipment are made up of
carbon steel and concrete while for chemical process, the equipment are mostly made
up of carbon steel.
Economic evaluation for this production is carried out in order to identify the
profit for the whole process. The sales price for the bioflocculant is RM 90 per kg
with the design life 25 years. Our production is expected to not make profit for the
first two years because construction is still ongoing and by the third year, half of the
processing plant will be operated. Minimum acceptable rate of return (MARR) is 0.3
because the process is producing new product and high risk. As the economic analysis
been conducted, the return of investment (ROI) is 0.4 and the value is generally higher
that MARR. It is acceptable as it could offer higher return of investment compared to
the expected rate. Besides, payback period (PBP) is 2.3 years and it is lower than
PBPreference which is 2.5 years. It could attract investors as it offers early payback
period. Moreover, the net present value (NPV) and net discounted flow rate of return
(DCFRR) is RM 85.6 million and 0.544 respectively. This process could give positive
net present value and it shows that our production is feasible and could make profit
from it.
For plant safety, all the potential hazards of all chemicals and microbe
involving in the production are identified by referring to the material safety data sheet
(MSDS). All the chemical hazards, toxic and flammable materials in this production
are identified in which the most flammable material in our plant is methane.
Flammable gas detector will be placed in our plant to detect any leakage of methane.
Legislative requirements which are applicable to bioflocculant and methanol
production plant are identified as well. Hazard identification, risk assessment and risk
control (HIRARC) study is conducted throughout the plant to evaluate all possible
hazards and their related risks. Hazard system is done based on each equipment to
identify the sources, receptors, how it is transmitted and the barrier.
Page
DECLARATION ii
ACKNOWLEDGEMENT iii
ABSTRACT iv
ABSTRAK v
EXECUTIVE SUMMARY vi
LIST OF CONTENT x
LIST OF TABLES xvii
CHAPTER I INTRODUCTION
1.1 Background 1
1.2 Source of raw material 2
1.3 Product usage 3
1.4 By-products 5
1.4.1 Biomass 5
1.4.2 Ethanol 5
1.4.3 Methane 6
1.4.4 Carbon dioxide 7
1.4.5 Carbon Monoxide 7
CONCLUSION 217
REFERENCE 219
LIST OF TABLES
No Table Page
Table 6.5 The inlet and outlet stream for each component for M-101 97
Table 6.12 Design pressure for each part of gas holder SR-101 102
Table 6.16 Design pressure for each part of gas scrubber, SR-101 104
Table 6.20 The inlet and outlet stream for each component for R-101 107
Table 6.22 Results for design of packed bed reactor R-101 111
Table 7.5 Summary of the COD and BOD value of each wastewater
stream. 120
Table 7.6 BOD and COD concentration after equalization tank 121
Table 7.7 Mass flow rates for inlet and outlet of NaOH regeneration in
R-101 127
Table 7.8 Summary of BOD and COD after each process 128
Table 8.11 Susggested values for risk and minimum acceptable return on
investment 146
Table 10.4 Minimum distances between units of various hazard category 209
Table 11.5 Operating conditions dimension for phase separator S-102 214
Table 11.7 Dimension for the steel welding neck flanges(in mm) 215
Table 11.8 Summary for design condition of distillation column C-101 215
LIST OF FIGURES
Figure 2.3 Graph of supply and demand of bioflocculant from year 2016
to 2030 10
Figure 2.4 Graph of supply and demand of methanol from year 2016 to
2030 11
Figure 5.10 Schematic diagram of (a) butterfly valve and (b) diaphragm
valve 77
INTRODUCTION
1.1 BACKGROUND
Thera two main product that produced for our plant which is methanol and
bioflocculant. Methanol is an alcohol with simplest of long series of organic
compound. This compound consist one methyl bond with a functional group which is
hydroxy group (OH) and chemical formula CH3OH, or emperical formula CH4O.
Methanol also widely known as methyl alcohol. This compound is volatile, colourless,
toxic, highly flammable, poisonous liquid and distinctive odour that similar to ethanol.
Figure 1.1 below shows the structural formula of methanol.
Next, flocculant is function as agent which also known as flocking agent for
stimulate aggregation of colloids, cells and suspended solids which are commonly
used for waste water treatment, drinking water production and fermentation process. It
can be classified into three groups which is inorganic flocculants, organic synthetic
flocculants also known as bio-flocculant and naturally occurring flocculants. Bio-
flocculant can be produced from plant parts or biomass. This flocculant also can be
derived from microbe, either from single culture or mixed culture of two different
2
microorganism. Table 1.1 below shows the chemical and physical properties for both
products.
Malaysia is one of the main Palm Oil supplier in the world. The production of palm
oil in Malaysia is rapidly growth where the palm oil planted area is growth from 193
000 hectares in 1970 to 5.74 million hectares in 2016 (Ain et al. 2018). Palm Oil Mill
Effluent (POME) can be obtained from palm oil production because POME is by-
product for this production. There are also product other than POME are being
produced from palm oil processing which is palm kernel (OPK), crude palm oil, palm
oil fronds (OPF) and empty fruit bunches. POME is the most expensive and difficult
waste to manage due to high content of suspended solids and large volume tonnes
generated at a time. This is because the POME shoulde be treated well by aerobic,
anaerobic/facultative process before it discharged into landfills and river to prevent
occurence of water pollution. The raw POME that been received from mill is usually
has temperature 70-80oC with initial pH of 4.5-6.5. It presence as thick brownish
colour liquid with unpleasent odor. The composition of POME are mainly water, oil,
suspended solid, dissolved solid and sand. Table 1.2 below shows the properties of
POME.
3
Methanol are mainly used organic synthesis, as a fuel, solvent, and antifreeze. It also
represents one of the most important chemical raw material for more than hundred
consumer that we used in our daily life such as plastics, building material, CDs and
DVDs and variety of pharmaceutical and health product. Indeed, the primary use of
methanol is in the chemical industry, as either a feedstock, solvent or cosolvent. This
alcohol is a key component in the production of renewable biodiesel fuels and has
potential to use as clean-burning fuel which can be blended directly into gasoline or
used as a fuel additive to reduce emissions. Other advantages of this clean-burning
fuel are it can reduce the greenhouse gas emission by 25% to 35% compared to
traditional gasoline, reducing urban zone and emission are also less reactive. Next,
methanol also contributes in wastewater treatment plant which is it function to
eliminate harmful nitrates.
The products that will be produced in the plant are biogas, fertilizer, sludge oil
and polysaccharide bioflocculant. The biogas will be produced from the anaerobic
process in which it will be captured and used as energy in the plant. The sludge
produced in the plant can be used as fertilizer as it has rich source of nutrient. Two
product that will be commercialised are the sludge oil and bioflocculant. The sludge
4
Next, the main product in our plant is polysaccharide bioflocculant. The type
of bioflocculant is BM-8 as it is produced from Bacillus marisflavi. This bioflocculant
BM-8 is made up of 75% polysaccharide and 24% protein (Bukhari et al. 2018). It has
the potential in harvesting microalgae. The mechanism for the flocculation of
bioflocculant BM-8 is as shown in Figure 1.3.
Bioflocculant
BM-8
Patching
Algae cells
Algae have negative surface charge while the bioflocculant BM-8 is positively
charged. The charge among the algae will be neutralized upon addition of
bioflocculant. The algae will come together and form a large particle which will settle
easily. Graph in Figure 1.4 shows the efficiency of bioflocculant BM-8 in flocculating
algae compared to other commercialized agents which Polyaluminium Coagulant –
High purity (PAC-HP), Polyaluminium Coagulant – Sulphate (PAC-S),
Polyaluminium Coagulant – calcium (PAC-V) and Polyaluminium Coagulant –
Industrial class (PAC-IV).
5
Recovery (%)
Concentration (mg/L)
Figure 1.3 Efficiency of bioflocculant BM-8 compared to other agents
Based on the graph, bioflocculant BM-8 able to recover 60% of algae by using
100mg/L while for other flocculating agents, it requires more than 500mg/L to recover
60% of algae. These results show that the bioflocculant produced is highly efficient
and able to be commercialized.
1.4 BY-PRODUCTS
1.4.1 Biomass
Biomass are been produced by agriculture industry and it is carbon based and is
composed of a mixture of organic containing hydrogen, usually including atoms of
oxygen, nitrogen and also small quantities of other atoms, including alkali, alkaline
earth and heavy metals. POME that we used as raw material also contains large
amount of biomass. The main component inside biomass is cellulose (40-60%),
hemicellulose (20-40%) and lignin (10-24%). In this plant, biomass is been utilized as
fertilizer for plant.
1.4.2 Ethanol
Ethanol is similar like methanol which is organic compound that have same functional
group (OH) but different in number of carbons. It has chemical formula C2H6O and
6
figure 1.2 below shows the structure of ethanol. The physical and chemical properties
of this alcohol are been shown in table 1.3.
Properties Values
1.4.3 Methane
Properties Value
Carbon dioxide also the main component inside natural gas beside methane. There are
also small amount of carbon dioxide inside air which is 0.04%. This gas is been
produced by all aerobic organisms includes human and animal when they they
metabolize carbohydrates and lipids to produce energy by respiration. The physical
and chemical properties of carbon dioxide are been shown in table 1.5.
Properties Value
Carbon monoxide is an odorless, colorless and tasteless flammable gas that can give
harm to us because it uses hemoglobin as an oxygen carrier. It can be found in fumes
produced from combustion of fuel in car or motorcycle. This gas also can be produced
indoors and will poison human and animal who breathe it. The physical and chemical
properties of carbon monoxide are been shown in table 1.6.
Properties Value
Molecular Formula CO
Molecular Weight (g/mol) 28.01
Boiling point (oC) -191.5
Melting point (oC) −205
Density (kg/m3) 1.14
pH 6
ECONOMY ISSUES
2.1 INTRODUCTION
Flocculating agents are generally divided into 3 types which are inorganic flocculants,
organic synthetic flocculants and naturally occurring flocculants where bioflocculants
are naturally occurring flocculants. Bioflocculants used highly in biotechnologies due
to their outstanding flocculation properties, biodegradability, eco-friendly and free of
secondary pollution risk (Aljuboori et al. 2014). Methanol is a simple alcohol with the
formula of CH3OH and it is used as fuel for combustion to generate heat and/or
electrical energy, fuel for vehicles and as solvent and feedstock for the generation of
other chemicals (Leonie 2017). Methanol is commercially produced from synthesis
gas by using the low pressure technology.
Flocculants are widely used in water treatment plants as well as in water purifiers. The
process of water treatment includes grates, sedimentation, granular filtration,
coagulation, flocculation, and disinfection. Flocculants also find applications in the
food and beverages industry for the treatment of wastewater. Further, in the mining
industry, these are used for the removal of red muds from minerals during the
treatment process. Increasing demand for specific formulations in emerging
economies tends to create ample opportunity for the growth of the industry (OMR
Global 2019).
9
The global methanol market was estimated at USD 21.4 billion in 2016 and is
expected to witness significant growth on account of the rising demand for
petrochemical derived products such as olefins, adhesives, detergents, solvents,
plastics, lubricants and fibers. It is extensively utilized in the automotive industry. It
can be mixed with gasoline and utilized in the core combustion engines of
automobiles.
Figure 2.2 Global methanol market volume, by end use, 2014-2024 (kilotones)
Figure 2.3 Graph of supply and demand of bioflocculant from year 2016 to 2030
Figure 2.4 Graph of supply and demand of methanol from year 2016 to 2030
Bioflocculants are used in the wastewater treatment field for removing suspended
solids and metal ions, at which colloids come out of suspension in the form of floc or
flakes (Zaki et al. 2014). Bioflocculant can also be used for treating dye wastewater.
Methanol is used in everyday products, such as plastics, paints, cosmetics and fuels.
It is also an energy resource used in the marine, automotive, and electricity sectors,
and an emerging renewable energy resource. It is possible that, in the not-to-distant
future, most liquid-consuming transportation vehicles that are cars, trucks, trains, and
planes may use methanol as their energy source (Luyben 2010).
CHAPTER III
3.1.1 Reaction
In this process design, both chemical and biochemical reaction is involved in the
production of product. For chemical reaction, it involves in the syngas synthesis and
methanol synthesis. Next, for biochemical reaction, it involves anaerobic and aerobic
process. Anaerobic process is involved in the production of biogas while aerobic
process is involved in the production of bioflocculant.
3.1.2 Stoichiometry
i. Syngas synthesis
i. Anaerobic Process
All this reaction condition must be met in for a complete reaction to product enough
product. The reaction condition for both chemical and biochemical reaction are as
shown below:
i. Chemical reaction
i. Syngas synthesis
The rate law for each of the following equation are as below:
The partial pressure equation for each of the components are as below:
Equation (3.8) to (3.19) are solved using Polymath® software by inserting some of the
constant values below. A graph of concentration of reactant/product against
conversion is plotted to determine the conversion from X=0.1 to X =1.0. The results
and graphs are as shown in Table 3.3 and Figure 3.1 respectively.
Constant used:
The rate law for each of the following equation are as below:
R1= KM*((PCO2*PH2)-(1/KpM)*(PM*PH2O/(PH2^2)))
/(1+Ka*(PH2O/PH2)+Kb*sqrt(PH2)+Kc*PH2O) …(3.20)
R2 = KR*(PCO2-(1/KpR)*(PCO*PH2O/PH2))
/(1+Ka*(PH2O/PH2)+Kb*sqrt(PH2)+Kc*PH2O) …(3.21)
The partial pressure equation for each of the components are as below:
Ka = 3453.38 …(3.32)
Kb = 0.499*exp(17197/(R*T)) …(3.33)
Kc = (6.62*10^11)*exp(124119/(R*T)) …(3.34)
KM = (1.07)*exp(36696/(R*T)) …(3.35)
KR = (1.22*10^10)*exp(-94765/(R*T)) …(3.36)
KpM = exp((7059.73/T)-47.415) …(3.37)
KpR = exp((-4773.26/T)-4.672) …(3.38)
Equation (3.20) to (3.38) are solved using Polymath® software by inserting some of
the constant values below. A graph of concentration of reactant/product against
conversion is plotted to determine the conversion from X=0.1 to X =1.0. The graph
and results are as shown in Table 3.4 and Figure 3.2 respectively.
18
Constant used:
3.1.5 Selectivity
Where
Where
SM = Selectivity of Methanol
3.1.6 Catalyst
Catalyst is a substance that is used to increase the rate of reaction without undergoing
any change to itself. Catalyst is only used in the production of methanol. Both
chemical reaction, syngas synthesis and methanol synthesis require different type of
catalyst. In syngas synthesis reaction, the required catalyst is nickel doped alumina
(NiO/α-Al2O3). This catalyst is suitable in steam reforming to produce syngas. Next,
in methanol synthesis reaction, the catalyst used is aluminium oxide coated with
copper and zinc which is also known as Cu/ZnO/Al2O3. The function of copper and
zinc is to promote and increase the methanol formation while aluminium oxide is for
methanol dehydration. Table 3.5 below shows the properties of the catalyst used.
Type of Catalyst
Properties Nickel doped alumina Aluminium oxide coated with
copper and zinc
Chemical Formula NiO/α-Al2O3 Cu/ZnO/Al2O3
Physical State Solid Solid
Melting Point (°C) 1955 2072
21
In designing the process for production of bioflocculant and methanol, there are a few
major constraints faced. First and foremost, there is no commercialized technology in
the production of methanol or bioflocculant by utilizing POME as the raw materials.
The design is very new as it is based from lab scaled studies. To add on, the
equipment used such as MBBR is a new type of technology that requires more studies
on the type of carries used etc. Secondly, is to cater a high flowrate of POME inlet
from the nearby palm oil mill. The received POME will be stored in a large cooling
pond before been pumped to anaerobic digestion tank. Next, it involves some
flammable chemicals such as methane and methanol. These chemicals will be placed
further from the buildings and any possible ignition sources. Besides that, the syngas
synthesis and methanol synthesis occur at a very high temperature and pressure. For
syngas synthesis, the temperature and pressure required is 700°C and 25 bar while for
methanol synthesis, the temperature and pressure required is 250°C and 50 bar. These
two reactors will be isolated from other process equipment which releases heat. Proper
safety features and maintenance will be designed for these reactors.
The input for designed plant are POME, ethanol, water and a microbe which is B.
marisflavi. The POME will undergo anaerobic process to produce biogas which will
be fed to the chemical reaction to produce methanol. The remaining POME will
undergo aerobic process to produce bioflocculant. The effluent will be wastewater that
will be treated further before been discharger. The sludge oi is obtained by skimming
the POME before the anaerobic process. Figure below shows the input-out model
structure for this plant.
22
The production rate of bioflocculant is 369.5 kg/h and the production rate of methanol
is 150.4kg/h. The plant operates for 355 days in a year which is equivalent for 8520
hours. Plant can produce about 3.1 thousand tonnes of bioflocculant and 1.3 thousand
tonnes of methanol annually. This plant capacity is decided based on the economic
analysis of bioflocculant and methanol
The obtained biogas is about 28m3 per ton POME. This biogas consists of 51%
of methane and 49% of carbon dioxide. It will be sent to the chemical plant. The
remaining glucose is 374.4 kg/hr
Syngas synthesis reaction (Assume r1, r2 and r3 are for rate of reaction (3.1), (3.2) and
(3.3) respectively)
The obtained value for r1, r2 and r3 for conversion, X= 0.8 are as below:
r1 = 27250000 kmol/hr
r2 = -17550000 kmol/hr
r3 = 17.37895 kmol/hr
Methanol synthesis reaction (Assume r4 and r5 are for rate of reaction (3.4) and (3.5)
respectively)
The obtained value for r4 and r5 for conversion, X= 0.8 are as below:
r4 = -0.000005516 kmol/hr
Economic potential analysis for level 2 is done to determine the gross profit of the
production plant. Table 3.6 below shows a summary of the raw material involved in
the production of bioflocculant and methanol while figure 3.6 shows the economic
potential curve for level 2. The formula used in level 2 calculation is:
Based on the curve, the conversion is selected at 0.8. This is because after 0.8
conversion, the profit becomes constant.
Process design for level 3 includes the cost for all reactors and compressors that been
used for the whole process. Details for reactor system are considered. Design
variables such as reactor sizing, compressor requirement, heat management and
excess reactacts are considered.
First, the POME will undergo anaerobic reaction which occurs in the upflow
anaerobic sludge blanket (UASB) reactor to produce biogas. Three UASB reactor is
available to cater a high volume of POME inlet. The biogas consist of methane and
carbon dioxide will be the raw material for methanol production while the remaining
POME will undergo aerobic reaction which occurs in the moving bed bioreactor
(MBBR).
In the chemical plant, syngas synthesis takes place in the syngas reactor while
the methanol synthesis occurs in the methanol reactor. Overall, the total number of
reactors are six where four from the biochemical plant and two from chemical plant.
UASB shows a great production for biogas of 28m3 with only 10 days retention time
and 96% COD removal (Fang et al. 2011). For aerobic reactor, MBBR is used to
produce bioflocculant at the same time it has a high COD removal which is 90% in
two and a half days (Vijayaraghavan et al. 2007).
For syngas and methanol synthesis, it is suitable to use packed bed reactor.
This is because the reaction involves gaseous reactant and catalysed by solid catalyst.
Reaction that takes place in the reactor can absorb or release heat. This will affect the
temperature and have deviation from set temperature. In order to maintain the
26
specified temperature, the reactor must be jacketed which have flow of hot or cold
water. Heat effect and adiabatic temperature is calculated to determine it is adiabatic
or isothermal. The calculation formula for adiabatic temperature by assuming the
average specific heat can be used is as shown below:
Where
Cpi = Specific heat of each product i which includes reactant and impurities
X = Conversion
Spreadsheet is used to solve the adiabatic temperature for all the four types of
reactors which is UASB, MBBR, syngas reactor and methanol reactor. The data is
tabulated in Table 3.7 and the graph is shown in figure 3.7.
Ta (°C)
Conversion UASB MBBR Syngas Reactor Methanol
Reactor
0.1 304.42 303.57 699.98 250.03
0.2 305.24 303.93 699.97 250.05
0.3 305.82 304.25 699.95 250.08
0.4 306.25 304.52 699.94 250.12
0.5 306.58 304.78 699.92 250.15
0.6 306.84 305.00 699.91 250.18
0.7 307.06 305.21 699.89 250.22
0.8 307.39 305.39 699.88 250.26
0.9 307.46 305.56 699.86 250.31
1.0 307.52 305.71 699.85 250.35
In the chemical reactors, the syngas synthesis reactor shows a small decrease
in temperature showing it is an endothermic reaction. The temperature difference
between inlet and outlet is only 0.13°C. For methanol synthesis reactor, the
temperature increases showing it is an exothermic reaction. The temperature
difference between inlet and outlet is only 0.32°C. Thus, both of these reactors can be
operated as adiabatic reactors because it shows small difference in temperature.
Reactor sizing involves the calculation of the size of each reactor based on the
conversion.
For syngas synthesis packed bed reactor, the sizing table is as shown below.
The optimum sizing is taken at conversion of 0.8.
X SCO2 SH2 r1 r2 r3 v
0.1 4.53 3 1.36 -0.006 0.004 0.059
0.2 2.32 2.94 2.60 -0.014 -0.003 0.062
0.3 1.53 2.84 3.66 -0.038 -0.028 0.067
0.4 1.02 2.7 4.73 -0.097 -0.087 0.071
0.5 0.714 2.59 5.67 -0.189 -0.018 0.074
0.6 0.493 2.52 6.64 -0.332 -0.322 0.081
0.7 0.357 2.48 7.50 -0.497 -0.487 0.086
0.8 0.255 2.46 8.38 -0.681 -0.688 0.091
0.9 0.188 2.44 9.14 -0.891 -0.881 0.098
1 0.138 2.44 9.86 -1.080 -1.070 0.104
For methanol synthesis packed bed reactor, the sizing table is as shown below.
The optimum sizing is taken at conversion of 0.8 as well.
29
X SCO2 SH2 r1 r2 v
0.1 4.53 3 1.02 0.632 0.083
0.2 2.32 2.94 1.86 0.070 0.142
0.3 1.53 2.84 2.69 0.480 0.130
0.4 1.02 2.7 3.38 0.939 0.127
0.5 0.714 2.59 4.05 1.390 0.126
0.6 0.493 2.52 4.62 1.766 0.129
0.7 0.357 2.48 5.17 2.135 0.132
0.8 0.255 2.46 5.63 2.443 0.136
0.9 0.188 2.44 6.09 2.745 0.140
1.0 0.138 2.44 6.46 2.996 0.145
R= Gas constant
Outlet temperature :
30
T1 = Temperature inlet
P2 = Pressure outlet
P1 = Pressure inlet
n = polytropic index
W= Power
= Compressor efficiency
Annual cost that have been calculated for all compressors are as follows :
Criteria Value
Inlet pressure (bar) 1
Outlet pressure (bar) 3
Power (kW) 23.5
Installation cost, Kpk (RM) 3,933.22
Annual cost, Kpt (RM) 81,933.22
X (RM) (RM)
0.1 494.1542513 50666.85986 1713413.152
0.2 529.7445463 53640.30456 1836592.456
0.3 562.3230277 56330.69661 1949337.288
0.4 589.53184 58556.17063 2043492.067
0.5 616.2048095 60719.93225 2135786.627
0.6 638.4815702 62514.15563 2212864.998
0.7 660.3194891 64262.12527 2288421.325
0.8 678.5581908 65714.03418 2351522.177
0.85 696.4376367 67130.54002 2413377.836
0.9 711.3700067 68308.5491 2465036.131
1 725.141259 69391.01739 2512676.245
a. UASB reactor
Annual cost of a reactor, Krt can be calculated by using the following equation :
Design material’s factor, Fm and pressure factor, Fp is as shown in Table 3.13 and
Table 3.14.
Construction material Fm
Carbon steel 1.00
Stainless steel (chromium-molibdenum) 2.15
Stainless steel 3.75
Pressure (bar) Fp
1.6 1.00
6.8 1.05
13.6 1.15
20.4 1.20
27.2 1.35
34.0 1.45
40.8 1.60
47.6 1.80
54.4 1.90
61.2 2.30
68.0 2.50
The values for IMSD is taken based on 2009 index which is 1487.2. Design material
factor, Fm , pressure factor, Fp and installation factor, FI are at 3.75, 1.00 and 1.5
respectively. Design material is taken based on the stainless steel value. The value of
pressure factor is taken based on operating pressure at 1 bar. All the value for
installation factor is the standard values for installation in Malaysia. The annual cost
for all three UASB reactor are based on the characteristics below:
Criteria Value
Conversion 0.8
Working volume (m3) 538.16
Total volume (m3) 645.78
Number of reactors 3
Diameter (m) 8.18
Krt(RM) for each reactor 7,799,413.21
Total Krt (RM) 23,398,239.64
b. Aerated tank
Annual cost of a reactor, Krt can be calculated by using the following equation :
Criteria Value
Conversion 0.8
Working volume (m3) 520.72
Total volume (m3) 624.87
Krt (RM) for reactor 2,753,003.00
The values for IMSD is taken based on 2009 index which is 1487.2. Design material
factor, Fm , pressure factor, Fp and installation factor, FI are at 3.75, 1.00 and 1.5
respectively. Design material is taken based on the stainless steel value. The value of
pressure factor is taken based on operating pressure at 1 bar. All the value for
installation factor is the standard values for installation in Malaysia. The annual cost
for two packed bed reactors are based on the characteristics below:
Annual cost of a reactor, Krt can be calculated by using the following equation:
34
Criteria Value
Diameter 0.35
Working volume (m3) 0.1
Total volume (m3) 0.12
Krt (RM) for reactor 34,292.51
Criteria Value
Diameter 0.39
Working volume (m3) 0.15
Total volume (m3) 0.18
Krt (RM) for reactor 47,905.98
Hence, the economic potential for level 3 is shown in Table 3.19 and Figure 3.8.
Process design level 4 involving all separation units that been used throughout the
process. Separation process is a process to separate two or more mixture to obtain
high purity of product. Separation unit is very important in any process that involve
removing impurities, recycling reactant or the further purification of desired product.
The separation units that been used in this process are distillation column, centrifuge,
settlement tank, dryer, phase separator and scrubber.
Installation cost:
Annual cost:
36
The conditions and calculated cost for distillation column are shown in Table 3.20
Criteria Value
Diameter (m) 0.4572
Length (m) 10.69
Area of condenser (m2) 6.297408
Area of reboiler (m2) 7.021412
Km (RM) 3,211,068.85
Kmt (RM) 1,070,356.28
3.4.2 Centrifuge
The condition and calculated cost for both two centrifuges are shown in Table 3.21
Criteria Value
Diameter (m) 3.1
Height (m) 5.1
Number of centrifuges 2
Volumetric flowrate (L/hr) 33.87
Krt for each centrifuge (RM) 1370.97
Total Krt of centrifuges (RM) 2741.95
Annual cost for settlement tank can be calculated by using following equation:
37
The condition and calculated cost for both two settlement tank are shown in Table
3.22
Criteria Value
Volume (m3) 282.53
Diameter (m) 9.25
Height (m) 4.203
Number of settlement tank 2
Krt for each settlement tank (RM) 2,164,732.89
Total Krt of settlement tank (RM) 4,329,465.78
3.4.4 Dryer
The condition and calculated value for dryer as shown in Table 3.23
Criteria Value
Area (m2) 0.9628
Tfeed,in (oC) 30
Tproduct,out (oC) 90
Tsteam,in (oC) 350
Tsteam,out (oC) 122.54
Krt for dryer (RM) 12,148.60
38
Installation cost:
Annual cost:
The conditions and calculated cost for phase separator are shown in Table 3.24
Criteria Value
Diameter (m) 0.821
Height (m) 4.520
Km for phase separator (RM) 5,086,414.13
Kmt for phase separator (RM) 1,695,471.37
3.4.6 Scrubber
a = constant = 17 400
b = constant = 79
39
n = 0.85
To calculate the shell mass of the gas scrubber, equation below is used:
Lc = vessel length, m
tw = wall thickness, m
To calculate the annual cost of the gas scrubber, equation below is used:
Where IMSd = Marshall and Swift index based on year 2010 = 1487.2
The condition and calculated cost for scrubber as shown in Table 3.25
Criteria Value
Shell mass 125.26
Length (m) 1.55
Diameter (m) 0.52
Ce 22 194.82
Krk for scrubber (RM) 893,180.20
Krt for scrubber (RM) 297,726.49
40
Conversion, X Fep3 (RM) Total cost for all separation units (RM) Fep4 (RM)
0.1 374,437,178.08 7,407,910.47 371,274,025.90
0.2 375,689,778.92 7,407,910.47 372,526,626.80
0.3 376,945,124.79 7,407,910.47 373,781,972.60
0.4 377,978,985.83 7,407,910.47 374,815,833.70
0.5 379,005,875.84 7,407,910.47 375,842,723.70
0.6 379,850,126.29 7,407,910.47 376,686,974.10
0.7 380,689,196.62 7,407,910.47 377,526,044.50
0.8 381,380,311.48 7,407,910.47 378,217,159.30
0.9 382,066,523.13 7,407,910.47 378,903,371.00
1 382,632,666.62 7,407,910.47 379,469,514.50
The process flow diagram for production of bioflocculant and methanol is attached in
Appendix.
The process involved biochemical and chemical reaction. Biochemical reaction begin
from the raw material POME till producing biogas and bioflocculant. Chemical
reaction begin from utilizing the biogas produced from biochemical reaction to form
methanol.
Biochemical process will take place first in the production plant. Firstly, the
main raw material which is the palm oil mill effluent (POME) will be received from
nearby mill and been stored in the cooling pond. It is left about 8 to 12 hours for
cooling process. Then, the sludge oil will be skimmed from the top of the cooling
pond. The POME will be pumped into the UASB. In UASB, anaerobic process takes
place where the methanogens in the POME will produce methane and carbon dioxide
which is known as biogas. This biogas will be used as raw material is chemical
process. The hydraulic retention time (HRT) in the UASB is 10 days (Fang et al.
2011). The POME will then be sent to a settlement tank to separate the solid biomass
from water. After that, POME will be pumped to MBBR. In MBBR, aerobic process
takes place to produce bioflocculant. MBBR is a type of aerated tank which uses
specific carrier that contains microbe (Smitha et al. 2017). The microbe used for
aerobic process is B. marisflavi which is a type of microbe isolated from POME itself.
The HRT in MBBR is 2.5 days (Nurul-Adela et al. 2016). After aerobic process, the
remaining wastewater will be centrifuged to remove all the solid biomass. All the
solid biomass will be dewatered using a screw press to form a cake. This biomass
cake can be used as fertilizer. The wastewater from centrifuge will be pumped to the
mixer. The wastewater contains bioflocculant will be mixed with ethanol (Nurul-
Adela et al. 2016). This process will make the bioflocculant to solidify. Then, the
42
bioflocculant will be separated from wastewater. Bioflocculant will be dried and sent
for packing while the wastewater will be pumped to the wastewater treatment system.
The biogas with CO2 and CH4 composition of 50%v/v and 50%v/v will be produced
with trace amount of H2S of 1000ppm. After the scrubbing process, the H2S
concentration will be reduced until 30ppm. Then, it will be mix with another stream
which containing steam and it will be compressed to 32 bar and heated until 700⁰C
before flowed into the methane steam reforming reactor. In the packed bed reactor,
which contain NiO/α-Al2O3 catalyst, Methane and steam will be converted into syngas
at 80% conversion (Abd Nasir et al. 2019). Then, it will flow through another phase
separator. The liquid stream will be sent to the waste water treatment while the vapor
stream will be cooled, mix with recycle stream and compressed to 250 ⁰C and 50bar
before flowed into the methanol forming reactor which is a packed bed reactor with
Cu/ZnO/Al2O3 as the catalyst (Lücking n.d.). After the reaction, the unsaturated vapor
will be separated in the phase separator and the liquid stream will be sent to the
distillation column. 40% of the vapor stream will be recycled and the rest will be
purged as the fuel for the furnace. The distillation column is operated at 1 bar, top
temperature at 68⁰C and bottom temperature at 103⁰C to separate methanol from
water- methanol mixture. The top product is methanol at purity of 99% and bottom
product is methanol-water mixture and will be sent to waste water treatment
The growth curve of Bacillus marisflavi in the POME is as shown in figure 6.1. The
lag phase takes about 2 hours where the bacteria will adapt to the new environment
and get ready to grow. The second phase is at the log phase where the bacteria
multiply at the highest rate due to abundant of nutrient. The log phase occurs for 16
hours. Next, it will undergo stationary phase. In this phase the bacteria will have equal
growth and dead rate due to completion of nutrients and increase in waste products.
Finally, the bacteria will enter the dead phase where the bacteria are no longer active.
Based on this figure, the duration of cultivation of bacteria in the seed fermenter will
be 16 hours. This is because the bacteria will undergo stationary phase followed by
43
dead phase after 16 hours. These bacteria will be introduced to main fermenter with
aerobic condition for production of bioflocculant.
Where :
Table below shows the information of the growth of B. marisflavi in the present of
glucose as the limiting substrate based on the source Nuradela et al. 2016.
45
Based on the information on the growth of B. marisflavi as in table 3.28 and the
1/ μmax = 1.9873
Ks / μmax = 526.2
Ks = 264.78 g/L
Thus, the value of μmax is 0.5032 hr-1 and the value of Ks is 264.78 g/L
47
The overall mass balance is calculated using the formulas and with the aid of
Microsoft Excel. The optimum conversion is taken from the data obtain using
Polymath® software which is at 80%.
i. iCON ®
ii. Superpro®
For UASB
49
For MBBR
Energy balance is the arithmetic balancing of energy inputs versus outputs for a
system. It is used to determine the heat released or absorbed during the reaction. The
reaction is exothermic if the heat is released and is endothermic if heat is absorbed. To
compute energy balance for the production of methanol and bio-flocculant, the
required data such as standard enthalphies of formation and coefficient of molar heat
capacity of components are tabulated in Table 3.32, Table 3.33, Table 3.34 and Table
3.35. The comparison between manual and iCON calculations are tabulated in Table
3.36.
Assumption:
1. There are no kinetic energy, potential energy and work done by the system.
…3.1
51
2
…3.2
T1 = reference temperature
Component Cp (kJ/kgK)
Glucose, C6H12O6 181.83
Palmitic Acid, C16H32O2 472.00
Water, H2O 29.60
Methane, CH4 58.06
52
Component Cp (kJ/kgK)
Methane 4.438
Carbon monoxide 1.174
Carbon dioxide 1.22
Water 4.187
Hydrogen 14.9
Methanol 4.785
HEAT INTEGRATION
4.1 INTRODUCTION
There are 8 utilities involved for the pinch analysis which are the cooler and heater. A
total of 5 hot streams and 3 cold streams involved. Table 4.1 shows the process data
for each utility unit.
In problem table method, the actual stream temperature Tact is converted into interval
temperature Tint using equations (4.1) and (4.2) as shown.
After Tact converted into Tint, the heat balance for the streams are carried out using
equation (4.3) and is tabulated in Table 4.2. After that, the value of QHmin, Qcmin and
Tpinch is dtermined.
The temperature interval where heat is equal to zero is the pinch point and the pinch
temperature could be determined. The minimum required heat for hot utility process,
QHmin is the heat introduced to the top when pinch point established. While the heat at
the bottom is minimum required heat for cold utility process, QCmin. The infromation
from the heat cascade and graph composite curve is concluded in Table 4.4.
The summary obtained from heat cascade above is listed in table 4.5 below.
700 CP
4 68 68 30 0.015519139
5 90 90 30 0.0159174
690
Network design only are performed when the representation grid is divided into
below pinch and above pinch. There are some conditions that need to be obeyed when
performing heat exchange. For above pinch, the heat capacity of hot stream must
lower or equal to cold stream (CPH ≤ CPC) and only hot utilities allowed. For below
pinch, the heat capacity of hot stream must greater or equal to cold stream (CP H ≥
CPC) with only utility allowed. Figure 4.3 for below pinch and figure 4.4 above pinch.
57
700℃
1 700℃ 350℃
C 23.9kW
9.76kW
2 350℃ 150℃
C 11.1kW
3 250℃ 111kW 50℃ 39.4kW
4 68℃ C
30℃ 0.6kW
0.6kW
5 90℃ C
30℃ 1.0kW
1.0kW
160℃ 30℃ 6 29.4kW
1.9k
690℃
700℃
The total energy recovery is the energy saved after heat exchanger network is
performed using pinch analysis.
CHAPTER V
5.1 INTRODUCTION
Piping and instumentation diagram (PID) is a drawing that shows the details of piping
and instrumentation equipments in the plant including valves, fittings and their
arrangement. It is differ from process flow diagram (PFD) that only shows the
arrangement of the major equipments and their pipes interconnection. In this section,
basic instrumentation and control system for bioflocculant production plant are
introduced.
These instruments normally involve in the control system for main processing
units in the plant. They may be incorporated in automatic control loops or a manual
operating of the proces operation. Intruments will monitor the critical process
variables and will be fitted with automatic alarms to alert the operators regarding
critical hazardous situations and make adjustment to control the parameter. This is
very crucial especially for a chemical plant to ensure safe operations.
One of the steps during process design of a chemical plant in constructing control
systems. In this step, a chemical engineer will select the control a equipment to
control by find their control objectives, manipulated variables, controlled parameter as
well as the control configuration connecting manipulation and measurements. Any
variation of the process variables from the desired value may affect the product
quality. The objective of the implementing control system is to ensure the safety of the
plant and to achieve a stable production rate as well as desired product quality. To
59
ensure the plant is safe, process variables involved must be kept in within the knows
safe operating condition range. Any dangerous situation must be able to be detected as
soon as possible and automatic shutdown systems should be implemented.
There will be one or more control objectives on each unit operation to ensure the
smooth productuion and safe operation. The primary objectives when specifying
instrumentation and control schemes are listed as follow (Sinnot 2009)
iv. To operate ar efficient low cost and commensurate with the other
objectives
The controller used in unit operation can be either feed-forward control or feedback
control, depending on the control objectives. The controller functions normally by a
basis where any disturbace affects the controlled variable and the variable deviates
from set point, the controller changes its output in such a way as to return the
controlled variable to set point. Table below shows the types of instrumentation
applied on the unit process with its objectives.
60
Table 5.1 Types of intrumentation applied on the unit process with its objectives
Intrumentations Objectives
Flow
- Flow controller (FL) - Indicates and control the flow rate in the pipeline
- Flow transmitter - Detect and send signals of deviations in the flow to
controller
Level
- Level controller (LC) - Control the level of liquid in the unit operation by
- Level tranmitter (LT) regulating the input or output of liquid flow rate
- Element to detect deviation of level in unit operation
Pressure
- Pressure controller (PC) - Indicate and control pressure of the pipeline or
- Pressure transmitter (PT) pressure vessel
- Detect and send signals of the pressure deviations to
controller
Temperature
- Temperature controller (TC) - Control the temperature of the main stream by
- Temperature transmitter regulating the flow rate of the utility line
(TT) - Element to detect the deviation in temperature
Composition
- Composition controller (AC) - Control the material composition of a stream
- Composition transmtter (AT) - Detect the changes of stream material composition
Packed bed reactors of R-101 is used for producing syngas while R-102 is used to
produce methanol gas. Information below shows the mathemathical model for two
types of packed bed reactors which is R-101 and R-102
Criteria Value
Number of variables 6
Number of equations 2
Disturbances 2
Degree of freedom 2
Controller needed 2
62
PIC
23
TT
22
PT
23
TIC
22
C.w in
C.w out
Criteria Value
Number of variables 6
Number of equations 2
Disturbances 2
Degree of freedom 2
Controller needed 2
Phase separator S-101 is to separate syngas and water while S-102 is used to separate
methanol and unreacted syngas. Informations below shows the mathemathical model
for phase separator
64
Volume
Criteria Value
Number of variables 5
Number of equations 2
Disturbances 1
Degree of freedom 2
Controller needed 2
opening when
the level is
over the
maximum
allowable
volume.
Distillation coulm C-101 is used to separate methanol and water to get 99.9% purity
of methanol as the top product. Informations below shows mathemathical model for
distillation column
Since
Criteria Value
Number of variables 10
Number of equations 4
Disturbances 2
Degree of freedom 4
Controller needed 4
Reflux ratio
Criteria Value
Number of variables 4
Number of equations 2
Disturbances 1
Degree of freedom 1
Controller needed 1
Overall control needed 5
The valve is
close when the
pressure below
than set point
Temperature To avoid Temperature Flowrate of Open valve Diaphragm
overheating inside cooling water when the valve –
within set point distillation temperature because good
103℃ column at higher then set flow control
103℃ point.
Close the valve
when the
temperature
lower than set
point
Level of To avoid Level of fluid Flow rate of Increase valve Globe valve –
distillation spillage of in distillation bottom product opening when because good
column containment column at stream 68 the level is flow control
over the
68
maximum
allowable
volume.
Close the valve
when level is
not over
maximum
allowable
volume.
Level of reflux To prevent Reflux drum Output flow Open valve Globe valve –
drum overflow in level rate of the when the level because good
drum distillate is over the flow control
product maximum
allowable
value.
Close the valve
when the level
not over
maximum
allowable
value.
Composition To maintain Purity of Flow rate of Open the valve Globe valve –
the purity of Methanol is liquid reflux when not get because good
the final (99.9%) back to set purity of flow control
product distillation methanol to
column regulate flow
rate of liquid
reflux and
close the valve
when the
purity
achieved.
Scrubber SR-101 is used to scrub H2S gas from the biogas before further process.
Informations below shows mathemathical model for scrubber
PV = nRT
Volume
Criteria Value
Number of variables 10
Number of equations 4
70
Disturbances 3
Degree of freedom 3
Controller needed 3
Dryer D-101 is used to dry desired product which is bioflocculant before being
transferred to storage tank. Informations below shows mathemathical model for dryer
71
FC
13
FT
13
Volume
Criteria Value
Number of variables 7
Number of equations 4
72
Disturbances 2
Degree of freedom 1
Controller needed 1
Three UASB reactors T-101, T-102 and T-103 are being arranged in parallel to
produce biogas from palm oil mill effluent. Information below shows the
mathemathical model for UASB reactors
Win = Wout
Height
Criteria Value
Number of variables 10
Number of equations 5
Disturbances 2
Degree of freedom 3
Controller needed 3
The temperature is not controlled since the present of cooling pond before the UASB
Table 5.17 Control configurations for T-101, T-102, T-103
inlet flows of
sodium
hydroxide
Aerated tank T-105 is used to sparge the liquid from settlement tank. Informations
below shows mathemathical model for aerated tank
Win = Wout
Height
75
Criteria Value
Number of variables 11
Number of equations 5
Disturbances 2
Degree of freedom 4
Controller needed 3
Gas holder GH-101 is used as storage tank for the gas being scrubbed from H2S gas.
Informations below shows the mathemathical model for gas holder
76
Volume
Criteria Value
Number of variables 7
Number of equations 3
Disturbances 3
Degree of freedom 1
Controller needed 1
5.4 VALVES
There are several valves used for different purposes in methanol and bioflocculant
production plant:
Generally, the types of valves used in chemical plant are gate valve, plug
valve, ball valve, globe valve, diaphragm valve and butterfly valve. We choose
butterfly valve and diaphragm in production of bioflocculant and methanol.
Diaphragm valve is usually used to handle stream containing solid or hazards while
butterfly valve to handle vapour. Schematic diagram of butterfly valve and diaphragm
are shown in figure 5.10 (a) and (b).
Figure 5.10 Schematic diagram of (a) butterfly valve and (b) diaphragm valve
Piping system is one of the important parts of chemical process industry. Pipes are
used to convey solids or fluids from one place to another. Industrial piping can be
manufactured from various types of materials, such as fiberglass, steel, aluminium,
plastics and so on. Basically, piping system involves pipes, flanges, gaskets, fittings,
valves, bolting and pipe support. Beside selecting the right piping material, pipe
diameter is an important aspect in desigining the piping system. To get the optimum
78
and safe plant operations, the suitable pipe diameter for every single stream needs to
be determined. Diameter of pipes is identified by its nominal size with optimum
diameter calculation. As for our plant using stainless steel of pipe because it has good
resistance towards corrosion and ease fabrication. All the piping used are stainless
steel Schedule 40. The sizing of pipe is determined based on ASME/ANSI B36.19
Stainless Steel Pipe. In production plant, there are two phases of flows (liquid, vapor
and mixture).
a. Liquid flow
Stainless steel optimum diameter can be ustimate by using the economic pipe
diameter as show in equation below (sinnot 2006).
b. Vapor flow
For long pipe, the gas velocity can approach the sonic velocity (Crowl & Louver
2002). The velocity of sound is determined using the thermodynamic reaktionship.
(1/2)
(1//2)
…(5.4)
79
Qm = ρUA ...(5.5)
…(5.6)
Using equation given, the diameter of pipe for vapour stream can be
determined. The diameter is then compared with the standards based on ANSI/ASME
B36.10M:1995 Wrought Steel Pipe Seamless and Welded to determine the nominal
pipe dimension. Table 5.11 shows the results obtained. While table 5.12 shows the
specification of nominal pipe in vapour flow.
c. Mixture Flow
Lines transporting gas and liquid in two-phase flow should be sized primarily on the
basis of flow velocity. Flow velocity should be kept at least below fluid erosional
velocity. The velocity above which erosion may occur can be determined by the
following empirical equation (5.7):
80
...(5.8)
Table 5.22, table 5.23 and table 5.24 show the pipe sizing for liquid stream,
vapour streams and mixed stream respectively.
Table 5.22 Pipe sizing for liquid streams
Stream G(kg/h) G(kg/s) Density(kg/m^3) Doptimum(m) Doptimum(in) Dnominal(in) Dout(in) t(in) Din(in)
1 36016 10.00444 997 0.17895187 7.04535301 8.00 8.625 0.32 7.891
2 36016 10.00444 997 0.17895187 7.04535301 8.00 8.625 0.32 7.891
3 216 0.06 997 0.013167246 0.518395804 0.75 1.05 0.11 0.824
4 35800 9.944444 997 0.178403714 7.02377205 8.00 8.63 0.32 7.891
5 11933.3 3.314806 997 0.101875894 4.010864126 5.00 5.56 0.28 6.065
6 11933.3 3.314806 997 0.101875894 4.010864126 5.00 5.56 0.28 6.065
7 11933.3 3.314806 997 0.101875894 4.010864126 5.00 5.56 0.28 6.065
8 11933.3 3.314806 997 0.101875894 4.010864126 5.00 5.56 0.28 6.065
9 11933.3 3.314806 997 0.101875894 4.010864126 5.00 5.56 0.28 6.065
10 11933.3 3.314806 997 0.101875894 4.010864126 5.00 5.56 0.28 6.065
22 33946.4 9.429556 997 0.173631432 6.835886831 8.00 8.63 0.32 7.891
23 33946.4 9.429556 997 0.173631432 6.835886831 8.00 8.63 0.32 7.891
24 45 0.0125 997 0.00591646 0.23293162 0.38 0.68 0.10 0.493
29 33879.9 9.411083 997 0.173457878 6.829053986 8.00 8.63 0.32 7.891
30 33879.9 9.411083 997 0.173457878 6.829053986 8.00 8.63 0.32 7.891
34 513.2 0.142556 997 0.020472446 0.806002252 1.00 1.32 0.13 1.049
35 33850.3 9.402861 997 0.173380573 6.826010486 8.00 8.63 0.32 7.891
36 33850.3 9.402861 997 0.173380573 6.826010486 8.00 8.63 0.32 7.891
37 363.9 0.101083 997 0.017180049 0.676380243 0.38 0.68 0.10 0.493
38 34214.3 9.503972 997 0.174328925 6.863347226 8.00 8.63 0.32 7.891
39 33522.6 9.311833 997 0.172522511 6.792228525 8.00 8.63 0.32 7.891
45 24.2 0.006722 2130 0.003280824 0.129166384 0.25 0.54 0.09 0.364
46 24.2 0.006722 2130 0.003280824 0.129166384 0.25 0.54 0.09 0.364
55 0.7 0.000194 921.9979 0.000728033 0.02866273 0.25 0.54 0.088 0.364
66 494.2 0.137278 877.6736 0.021025402 0.827772181 1.00 1.32 0.133 1.049
82
52 700 1751.67 32.978 8.3857 1.316E-05 1866.886 5.2522E-05 0.00818 0.321932 0.38 0.675 0.091 0.493
53 700 1751.67 32.978 8.3857 1.316E-05 1866.886 5.2522E-05 0.00818 0.321932 0.38 0.675 0.091 0.493
53a 492 1377.27 32.978 3.7689 3.303E-05 1655.393 0.00013179 0.01295 0.509962 0.75 1.05 0.113 0.824
56 350 1121.67 32.978 0.3039 0.0004539 1493.909 0.00181112 0.04802 1.890456 2 2.375 0.154 2.067
57 450 1301.67 32.978 7.477 1.713E-05 1609.319 6.8333E-05 0.00933 0.367204 0.38 0.675 0.091 0.493
58 350 1121.67 38.786 37.516 0.0001092 1377.523 8.3246E-05 0.01029 0.405298 0.5 0.84 0.109 0.622
59 150 761.67 38.786 11.0433 2.758E-05 1135.141 8.4957E-05 0.0104 0.409443 0.5 0.84 0.109 0.622
60 250 941.67 38.786 20.2639 1.352E-05 1262.163 4.164E-05 0.00728 0.286647 0.375 0.675 0.091 0.493
61 250 941.67 47.146 19.7099 1.532E-05 1144.803 4.7199E-05 0.00775 0.305183 0.375 0.675 0.091 0.493
61a 260 959.67 46.464 23.5829 4.787E-06 1164.143 2.3919E-05 0.00552 0.217253 0.25 0.54 0.088 0.364
63 50 581.67 46.464 23.5829 6.149E-06 906.3246 3.0723E-05 0.00625 0.246222 0.25 0.54 0.088 0.364
64 50 581.67 46.464 23.5829 8.424E-07 906.3246 1.1372E-05 0.0038 0.149798 0.25 0.54 0.088 0.364
65 30 545.67 46.464 23.5829 2.519E-06 877.8301 1.998E-05 0.00504 0.198558 0.25 0.54 0.088 0.364
69 68 614.07 70.444 745.2456 1.008E-08 756.294 2.4221E-07 0.00056 0.021862 0.125 0.405 0.068 0.269
84
Density T Dnominal
Stream P(psia) (ibm/ft3) G(lbm/s) (℃) T(®R) R Z ve(ft/s) A(ft2) D(inch) (inch) Dout(inch) t(inch) Din(inch)
12 14.504 62.24 7.19197478 37 558.27 1.3155 0.0007 12.6755 9.377682 11.9692 12 12.75 0.406 11.94
14 14.504 62.24 7.19197478 37 558.27 1.3155 0.0007 12.6755 9.377682 11.9692 12 12.75 0.406 11.94
16 14.504 62.24 7.19197478 37 558.27 1.3155 0.0007 12.6755 9.377682 11.9692 12 12.75 0.406 11.94
17 14.504 62.24 14.3839496 37 558.27 1.3155 0.0007 12.6755 9.377682 11.9692 12 12.75 0.406 11.94
18 14.504 62.24 21.5759856 37 558.27 1.3155 0.0007 12.6755 9.377682 11.9692 12 12.75 0.406 11.94
21 14.504 62.24 0.78729588 30 545.67 1.3155 0.0007 12.6755 9.377057 11.96881 12 12.75 0.406 11.94
25 14.504 62.24 0 37 558.27 1.3155 0.0007 12.6755 9.377682 11.9692 12 12.75 0.406 11.94
27 14.504 62.24 0.03974448 30 545.67 1.3155 0.0007 12.6755 9.377057 11.96881 12 12.75 0.406 11.94
31 14.504 62.24 0.01812691 30 545.67 1.3155 0.0007 12.6755 9.377057 11.96881 12 12.75 0.406 11.94
32 14.504 62.24 0.01812691 30 545.67 1.3155 0.0007 12.6755 9.377057 11.96881 12 12.75 0.406 11.94
43a 15.9544 62.24 1.10359824 30 545.67 1.3155 0.0007 12.6755 9.379763 11.97053 12 12.75 0.406 11.94
54 43.512 0.02 0.55293205 350 1121.67 0.03697 1 707.1068 9.470082 12.02803 14 14 0.437 13.13
62 435.12 2.35 0.71576806 50 581.67 0.0438 0.6362 65.23281 14.43778 14.85141 16 16 0.5 15
CHAPTER VI
DETAILED DESIGN
The main function of cooling pond in our plant is to reduce the temperature of POME
obtained directly from the palm oil mill. POME will be received from the mill at a
temperature of 85°C (Zainal et al. 2017). This temperature is not suitable for
anaerobic process because the microbe that involves is mesophilic which work best in
the temperature range of 35°C to 40°C (Choong et al. 2017). A cooling pond is chosen
rather than tank because it is low in construction and operation cost. It is also easy to
operate and maintain in which skilled workers are not required. This cooling pond
also serves as a storage of POME. The general information of POME required for the
design of cooling pond is as below. The calculations can be referred in appendix A1.
Information Value
Inlet flowrate of POME (kg/h), F 36000
Inlet temperature of POME, T in (K) 358.15
Outlet temperature of POME, T out (K) 308.15
Heat capacity of water, Cp (kJ/kg.K) 4.2
Convective heat transfer coefficient, h (W/m2.K) 369
Emissivity of water, ε 0.96
Stefan constant, σ (W/m2.K) 5.670 × 10-8
The design of cooling pond is based on the energy balance on the cooling pond.
Assumption made to calculate the heat transfer at the surface of cooling pond is heat is
86
transferred through convection and radiation only. The overall heat formula is shown
as below
Heat is transferred from the cooling pond to the atmosphere. This is because the
temperature in the cooling pond is higher compared to the atmosphere. The formula
for the heat transferred in the cooling pond is as below.
= (36000)(4.2)(358.15-308.15)
= 7560000 kJ/hr
Thus, the rate of heat transfer from the cooling pond to atmosphere is 7560000 kJ/hr
Heat by convection means heat is transferred from one place to another thorough the
fluid. In this case, heat is transferred from the cooling pond to the atmosphere through
the air as the fluid. The calculation of heat transferred by convection in the cooling
pond is as below.
= (369)(A)(358.15-308.15)
87
= 18450 A kJ/hr
Heat transferred by radiation involves the when the high energy electron emits energy
to fall back to low energy level. The water molecule on the surface of the pond may
emit energy to release heat. The calculation of heat transferred by radiation in the
cooling pond is as below.
= (0.96)(5.670× 10-8)A(358.154-308.154)
= 404.8 A kJ/hr
The area of cooling pond is calculated by using the energy balance equation in the
cooling pond
Q = Qconvection + Qradiation
A = 400 m2
The retention time in the cooling pond is about one day as the temperature must be
reduced from 85°C to 37°C (Rahman 2017). The supply of POME will be 16 hours
since it’s the working hours in the palm oil mill per day. The volume calculation of
the pond is as below by taking 20% of safety factor for volume:
= 36 m3/hr × 16 hr × 1.2
= 691.2m3
400 = L2
L = 20 m
The length and the width of the cooling pond is 20m × 20m
691.2 = H × 400
H = 1.73 m
The construction of cooling pond is relatively easy because just have to dig a large
area of hole. The hole must be covered with liner which have some important function
for ponding system. High density polyethylene (HDPE) pond liner will be used to
cover the surface of the ground. The function of this pond line is to prevent
contaminant from POME entering the ground. It also helps to prevent the water loss to
the ground. This is the most economical way for constructing a cooling pond with an
easy operation and maintenance.
The diagram below shows the schematic diagram of the cooling pond. The dimension,
20 shown
liner, inlet and outlet piping system are also m in the diagram.
Inlet Outlet
1.73 m
HDPE
l
i
n
e
r
89
6.2 UPFLOW ANAEROBIC SLUDGE BLANKET, UASB (T-101, T-102 & T-103)
Designed by: Ravinkumar A/L Manimaran (A158192)
6.2.1 Introduction
Upflow anaerobic sludge blanket (UASB) reactor is a column type tank reactor that
will be used in anaerobic process. It is widely used in industrial wastewater treatment
in chemical and sewage industries (Lier et al. 2015). The detailed design of UASB
requires some information. The hydraulic retention time (HRT) for UASB in treating
POME is about 10 days for an efficient production of biogas and chemical oxygen
demand (COD) removal (Ohimain et al. 2017). The volume required to contain
POME for 10 days is 5760 m3. To cater a large volume of POME, three identical
UASB is used. Each UASB with a volume of 2304 m3 with 20% extra as safety factor.
The calculation for UASB are done according to the formula by Bal et al. 2010.The
calculations can be referred in appendix A1.
Information Value
Inlet (m3/h) 36
Inlet (m3/day) 576
HRT (days) 10
HRT (hours) 240
3
Volume (m ) 5760
Number of Tanks 3
3
Volume of one tank (m ) 1920
Safety Factor (%) 20
Volume after extra (%) 2304
90
Since the designed UASB is a column type tank reactor, the ratio of H: D used is 3:1
(Clapp et al. 2018). The height and diameter are calculated using the volume formula
by assuming the UASB is a tall cylindrical tank.
H = 29.77 m
The volumetric hydraulic load (VHL) is the volume of wastewater supplied daily into
the UASB per unit volume of the UASB.
Thus, the volumetric hydraulic loading rate of the POME into the UASB is 0.25 per
day
The volumetric organic load (Lv) is defined as the amount of organic matter supplied
daily to the UASB per unit volume of UASB. The influent substrate concentration
(So) is 51 kg COD/m3 (Zainal et al. 2017). The calculation for Lv is shown below.
.day
91
Thus, the organic loading rate of the organic material into the UASB is 12.75 kg/m 3
per day.
The sludge loading rate (Ls) referred to the amount of organic matter that is supplied
to the UASB per unit of biomass in the UASB. The total volatile solid in POME (M)
is 34 kgVS/m3 (Zainal et al. 2017). The calculation for Ls is shown below.
.day
Thus, the sludge loading rate into the UASB is 864 kg COD/kg VS per day.
Upflow velocity (ν) of the POME is calculated from the relation between the inlet
flowrate and the cross sectional area of the UASB. The calculation of ν is as shown
below.
= 0.4652 m/hr
Thus, the velocity if POME pumped into the UASB is about 0.4652 m/hr.
92
The COD at the influent is 51 kg COD/m3 (Zainal et al. 2017) while the removal
efficiency of UASB is 96.5% for the HRT of 10 days (Ohimain et al. 2017).
It can be assumed that the BOD is about 50% of the COD for POME (Chong et al.
2018). The BOD for effluent from POME is 892.5 mg COD/L.
Ex = COD removal
efficiency TSS = 102(96.5)(240)-0.24
= 2641.66 mg/L
The amount of sludge produced is highly related to the COD of the POME inlet. The
production of solid sludge can be calculated by using the equation below.
The yield of solid can be assumed at 0.2 kgTSS/day since POME is high in COD
The gas hood will be located at the top of the UASB. The main function of the gas
hood is to collect the biogas. The area of gas hood interface is calculated from the
equation below.
2
94
Thus, the area and diameter of the gas hood is 21.3 m2 and 5.2 m respectively.
6.3.1 Introduction
Settling tank is a low cost technology that is widely used in a wastewater treatment
plant to remove solid from wastewater. Sufficient time have to be allowed for the
settling of solid to take place (Rozema 2015). Settling tank is located right after the
UASB in our plant. The main function of this settlement tank is to remove the sludge
from the anaerobically treated POME. The HRT in the settling tank is about 10 hours
to allow the sludge to settle down efficiently. The characteristics of the sludge are as
shown in table below. The calculation can be referred in appendix A1.
Settling velocity is the speed of the particle to settle down in the settling tank. The
settling velocity of the sludge particle have to be calculated as shown below by
referring formulas from Rozema 2015.
= 0.27 inches/min
Thus, the settling velocity of the sludge particle in the settling tank is 0.27 inches/min.
95
The area of the settling tank can be calculated by using the settling velocity of sludge
particle and inlet volumetric flowrate of anaerobically treated POME. The calculation
is as shown below by referring the formula from Rozema 2015.
A = 87.48 m2
The settling tank that will be used in our plant is an open cylindrical shape.
A = πr2
The volume of settling tank is calculated by using the flowrate into the settling tank
and 20% as the safety factor for volume.
= 36 m3/hr × 10 hr × 1.2
= 432 m3
The height of the settling tank is calculated by using the volume and area.
V = AH
96
= 4.94 m
Thus, the diameter and height of the settling tank is 10.55 m and 4.94 m respectively.
Table 6.4 below shows the overall calculation that related to the measurement for
MBBR reactor construction. The calculation can be referred in appendix A2.
The mixer M-101 are located right after centrifuge CF-101 which is the biomass is
been removed from the wastewater. The function of the mixer is to mix the
wastewater that contains bioflocculant with ethanol. This process will make the
bioflocculant to solidify and occurs at 30oC and 3 bar. The calculations can be referred
in appendix part A3.
Table 6.5 The inlet and outlet stream for each component for M-101
Hence,
H/D ratio = 2
D = Di = 5.94 m
H = 2 (5.94) = 11.88m
Impeller width, Wi
Diameter impeller, Di
99
Thickness of disc, x
Table 6.6 shows the summary of the calculation for design of Mixer M-101.
Parameter Results
Operating pressure 3 bar
Operating temperature 30 °C
Volume of mixer 328.6 m3
Height of mixer, H 11.88 m
Diameter of mixer, D 5.94 m
Impeller width, Wi 0.40 m
Diameter of impeller, Di 1.98 m
Height of impeller above vessel floor, C 1.98 m
Length of impeller, Li 0.50 m
Diameter of impeller base, Dd 1.32 m
Thickness of disc, x 0.08 m
100
This unit reduces the dryer service fluid humidity. Table 6.7 shows the design
summary. The calculations can be referred in appendix part A4.
The bioflocculant is dried in rotary dryer. Table 6.8 shows the design summary. The
calculations can be referred in appendix part A4.
Belt press is used in sludge dewatering . Table 6.9 shows the design summary. The
calculations can be referred in appendix part A4.
Kettle reboiler (H-101) is used to generate steam at 2 bar and 120.21°C for the syngas
reforming reaction. Table 6.10 shows the process parameter and dimension of kettle
reboiler. The calculations can be referred in appendix part A4.
6.10.1 Introduction
Gas holder, GH-101 act as holding tank for the gas such as methane and cabon
dioxide before distribute it to reactor for further process. HRT for the gases in gas
holder is 24 hours
Type of material for conctructing gas holder is stainless steel 304. This material have
higher melting point compares to other type of stainless steel and could store biogas. It
is also not cause harmful to the people either during production or use (R.C Bourg,
2012)
GH-101 will be contstructed in cylindrical shape with flat head for top and bottom of
the shell. Below are the design parameters for the gas holder. The calculations can be
referred in appendix part A2.
102
Parameter Unit SI
Operating pressure, PO 1.01 kPa
Operating temperature, T 30oC
Diameter vessel, Di 8.75 m
Radius, R 4.38 m
Height of vessel, Hs 13.12 m
Layout Vertical
Operating pressure of gas holder is higher than atmospheric pressure and resulting it
to have internal pressure. Design pressure of each part of the vessel is being calculated
by using PD = PO + 0.433h where h is the height of each part of the column. Safety
factor of 10% is taken.
Table 6.12 Design pressure for each part of gas holder SR-101
As there is no corrosive material pass through SR-101, corossion allowance that could
be consider is 2mm(0.0785 in).
The wall thickness, t for each part of the pressure vessel has to be calculated in order
to get the minimum wall thickness, tmin under internal pressure.
Based on the nominal thickness in the market, the thickness of the vessel is 10mm and
it is slightly higher that calculated minimum thickness of the vessel.
103
Parameter Value
6.11.1 Introduction
Gas scrubber is used to separate hydrogen sulphide from biogas. It is located after
UASB reactor where the biogas been produced. Sodium hydroxide is act as solvent to
be reacted with hydrogen sulphide and will be out as bottom product as lean sodium
hydroxide.
Stainless steel SA-240 is chosen as it provide good corrosion resistance towards acids
with good weldability. It also could provide good area reduction rate at low
temperature. It is also good to resist intergranular corrosion.
SR-101 will be constructed in cylindrical shape for the middle with ellipsoidal shape
for head and bottom of the shell. Below are the design parameters of scrubber. The
calculations can be referred in appendix part A2.
104
Parameter Unit SI
Operating pressure, PO 202 kPa
Operating temperature, T 30oC
Diameter vessel, Di 1.49 m
Radius, R 0.74 m
Height of vessel, Hs 4.99 m
Layout Vertical
Table 6.16 Design pressure for each part of gas scrubber, SR-101
As there is no corrosive material pass through SR-101, corossion allowance that could
be consider is 2mm(0.0785 in).
The wall thickness, t for each part of the pressure vessel has to be calculated in order
to get the minimum wall thickness, tmin under internal pressure.
Based on stainless steel gauge thickness, gauge number 10 has been chosen as it have
the closest nominal thickness to the minimum thickness from the calculation. The
nominal thickness is 3.571mm which is slightly higher than minimum thickness.
Parameter Value
6.12.1 Introduction
In our plant we used heater to increase the temperature before it goes into the reactor.
The temperature need to increase from 690℃ to 700℃ by using steam as service
fluid. The calculations can be referred in appendix part A5.
Parameter Value
Total flowrate process fluid (kg/hr) 902.9
Temperature Shell Inside (℃) 690
Temperature Shell Outside (℃) 700
Temperature Tube Inside (℃) 750
Temperature Tube Outside (℃) 700
Assumption Overall heat transfer coefficient, Uo 30
(W/m2 ◦C)
Tube Side
Triangular pitch
Outer diameter, do (mm) 20
106
Packed bed reactors are commonly used in chemical reactions whereas it is filled with
solid catalyst particles that most often used to catalyst gas reactions. The syngas
reactor is located right after the gas holder (GH-101) where biogas are been stored
after hydrogen sulphide scrubbed away from it. The methane and steam will be
converted into syngas at 80% conversion in this reactor (R-101). The catalyst used for
this reaction is NiO/α-Al2O3. The calculations can be referred in appendix part A3.
107
Table 6.20 The inlet and outlet stream for each component for R-101
Reaction:
The rate law for the reaction is a first order reactor, therefore,
Stoichiometry,
= =
where y =
=
109
X is the conversion
= 0.0917 m3
110
By taking ratio height shell to diameter 1:4 where Hvessel = 4D while taking ratio 1:2
for diameter to height head for both bottom and top, D = 2Hhead. Hence, the height for
packed bed reactor is 1.05 m with 0.0875 m head height for both bottom and top.
Condition Values
Operating pressure, Po 25 bar (362.6psi)
Temperature, T 973.15K (700oC)
Length Shell 1.05 m
Length Vessel 1.225 m
Diameter 0.35 m
= = 0.735 m
Table 6.22 shows the summary of the calculation for design of packed bed reactor R-
101.
Parameter Results
Operating pressure 25 bar
Operating temperature 750 °C
Height of reactor, H 1.225 m
Diameter of reactor, D 0.35 m
Volume for reaction 0.108 m3
Height of bed, Hbed 0.735 m
Diameter of bed, Dbed 0.35 m
Weight of catalyst 141.372 kg
53a 54
Parameter Value
Total flowrate process fluid (kg/hr) 902.9
Temperature Shell Inside (℃) 492
Temperature Shell Outside (℃) 350
Temperature Tube Inside (℃) 150
Temperature Tube Outside (℃) 350
Assumption Overall heat transfer coefficient, Uo 100
(W/m2 ◦C)
Tube Side
Square pitch
Outer diameter, do (mm) 20
Inner diameter, di (mm) 16
Length of tube, L (m) 1.78
Area of one tube, At (m2) 0.11
Number of tubes 58
Number of tube passes 2
Linear fluid velocity, ut (m/s) 1.68
Heat transfer coefficient, hi (W/m2 ◦C) 268.21
Pressure drop, ∆Pt (kPa) 0.33
Shell Side
Pull-through floated head type
Number of shell passes 1
Bundle diameter, Db (mm) 264.82
Shell diameter, Ds (mm) 353.82
Baffle cut (%) 25
Baffle spacing, IB (mm) 79.76
Tube pitch, Pt (mm) 25
Equivalent diameter, de (mm) 14.2
Shell side Mass velocity, Gt (kg/sm2) 50.09
Heat transfer coefficient, hs (W/ m2 ◦C) 678.48
Pressure drop, ∆Ps (kPa) 12.15
Overall heat transfer coefficient, Uo (W/m2 ◦C) 301.79
This unit operates at 350 oC and 3 bar. Table 6.4 shows the calculation summary. The
calculations can be referred in appendix part A4.
113
This unit operates at 50 oC and 30 bar. Table 6.25 shows the calculation summary.
The calculations can be referred in appendix part A4.
In C-101, the feed contains methanol and water. The function of C-101 is to separate
methanol from water to increase the purity of final product. Methanol is identified as
the light key component (LK) while water as the heavy key (HK) component since
methanol has lower boiling point compared to water.
114
The design of reflux drum RD-101 is summarized in table below: The calculations can
be referred in appendix part A6.
CHAPTER VII
WASTE MANAGEMENT
7.1 INTRODUCTION
In this methanol and bioflocculant production plant, there are a few types of waste
generated including gaseous waste and liquid waste. The waste can only be discharged
after being treated to reduce the impacts towards environment and public health.
Figure 1 shows the waste generation in the process.
Waste
Liquid discharge
Sludge dewatering Stream 34
from belt press
Fertilisers
Gaseous waste and liquid waste is generated during the process of the chemical plant.
The content and of the waste produced is identified.
Gaseous waste produced contains air, ethanol and water from bioflocculant
dehydration in the main process
a. Wastewater
Wastewater produced from the process included treated POME and methanol.
Lean NaOH solution contains NaHS produced from the hydrogen sulfide scrubber.
a. Gaseous waste
b. Wastewater
The ethanol and water in the gaseous waste stream will be stripped off from the vapor
phase and the stream 43a characteristics considered because the wastewater together
with other waste stream after equalization tank in waste treatment process. The
characteristics of wastewater is shown in table 7.3:
Total Concentration of
Ethanol Methanol Suspended Sludge Water
Stream flowrate waste
(kg/h) (kg/h) solid(kg/h) (kg/h) (kg/h)
(kg/h) (mg/L)
34 0 0 - 43 513 556 77310
39 62 0 36 0 33461 33559 2944
43a 249 0 0 0 37 286 137950
68a 0 25 0 0 237 262 94181
Lean NaOH solution is the used caustic solution after H2S scrubbing process. NaHS
produced from the process is the waste generated. The characteristics of the waste
produced is shown in table 7.4:
Stream NaHS (kg/h) NaOH (kg/h) Water (kg/h) Total flowrate (kg/h)
46 1.92 0.13 29 31
Chemical Oxygen Demand (COD) is the oxygen needed for the chemical oxidation of
the organics and oxidizable inorganics contained in wastewater. COD for the
120
Biochemical oxygen demand (BOD) is the oxygen needed by the microbe in the
wastewater to break down organic material. The concentration of BOD in the brewery
wastewater is 0.6- 0.7 of COD for all types of contaminants (Brito et al. 2007). For
this BOD estimation, 0.7 of COD is used in calculating BOD.
Oxidation reaction:
Table 7.5 Summary of the COD and BOD value of each wastewater stream.
After the equalization tank, all the wastewater is mixed and treated using
activated sludge process. Due to different amount of flow in inlet stream, the COD
concentration is obtained by using formula: COD concentration = total COD amount/
total flowrate. The COD and BOD of wastewater after mixing in equalization tank is
shown in table 7.6.
Phase COD concentration (mg/l ) BOD concentration (mg/l ) COD Amount (mg)
L 14279 9995 4.95E+08
∑COD amount in stream 68a,43a, 39, 34= ∑COD amount in outlet stream
7.3.3 Conclusion
From the calculation done, the COD concentration calculated is 14279 mg/L and the
BOD concentration is 9995 mg/L. Standard B is abided for the wastewater discharge
limit as the discharge point is at the downstream of a river. COD and BOD of the
waste stream exceeds the discharge limit of Standard B effluent according to the
Environment Quality Act 1974, which is 200mg/L and 50mg/L respectively.
Therefore, treatment is needed before the waste is discharged.
122
Waste minimization and waste reduction strategy is carried out by regenerate the
scrubber solution and reduce the waste content in the industrial effluent.
The fuel gas in stream 65 is incinerated and the carbon monoxide is converted
to carbon dioxide using platinum catalyst in the catalytic converter. The vapor from
all the pressure relief valve in main production process will also be incinerated in this
incinerator.
The gaseous waste in stream 43a contains only ethanol, water and air. The
gaseous waste is sent to the equalization tank to separate the ethanol and water out of
the vapor mixture by scrubbing it using wastewater and aerate the wastewater. Ethanol
and water in the vapor mixture will retain in the liquid phase and the concentration of
the oxygen of the outlet gas will be lowered due to the aeration of the wastewater
before undergoing activated sludge process.
a. Incineration
Before releasing to the atmosphere, the fuel gas will be combusted using an
incinerator to reduce hazardous gas emission and generate energy from the gas. The
reactions involved in the combustion process are as follows:
platinum crystal is needed for this reaction and the catalyst is self-regenerative with
the presence of oxygen gas. The reaction involved in the catalyst converter is:
2CO + O2 → 2CO2
The flue gas that have been incinerated will have only trace amount of carbon
monoxide and it will be removed through gas stack so that the concentration at ground
level will safe.
= 1.94 m
Effective stack height, H = 31.94 m
Hence, the final stack height will be 31.94m which is approximately 32m.
With a stack at 31.94 m, we can ensure that the concentration of hazardous material at
ground level is safe.
124
Volume of each tank is considered with 10% addition to prevent overflow due to
wastewater flowrate surge, V= 69.32 x (1+10%) =76.257 m³
Diameter : 3.2 m
Height : 9.6 m
Number of tanks :3
c. Phytoremediation
concentration when treating wastewater with initial BOD and COD concentration of
350 mg/L and 721 mg/L. The wastewater in this waste treatment plant is 199.9 mg/L
and 285.6 mg/L after aerobic digestion. Thus, phytoremediation is applicable to this
wastewater treatment plant..
Height : 2m
2011; Visser et al. 1997). The reaction is carried out with existence of nutrient
medium containing 4mg/l NH4Cl, 1mg/l MgSO4.7H2O and 2 g/l KH2PO4 with
aeration. The fermentation broth is flowed to the next settling tank and the elemental
sulfur will be settle down in the tank. The elemental sulfur will be centrifuged and it
can be used as the addictive in the fertilizers. The liquid from the centrifuge will be
flowed back to the bioreactor. The regenerated caustic solution in settling tank will be
pumped back to the H2S scrubber.
The tank size is 250m3 and able to accommodate the fermentation broth for 8
hours retention time for higher conversion if there is any fluctuation in NaOH purity.
The pH is controlled by administration of NaOH into the bioreactor.
Side Reaction:
2 NaHS + 4 O2 → Na2SO4+H2SO4
Table 7.7 Mass flow rates for inlet and outlet of NaOH regeneration in R-101
128
The gaseous waste containing ethanol is scrubbed, and the purified air is vented out of
the system. The BOD and COD of Wastewater will be reduced to 8mg/l and 17.1mg/l
after the activated sludge and phytoremediation. The new COD and BOD value is
under the discharge limit of standard B in Emission Standard for Industrial Effluent
2009. The wastewater will be discharged to the environment after the waste treatment
process. The sludge in the pond will be cleaned from the pond every three months and
mix with the sludge produced in the main process to be belt pressed and marketed as
fertilizers.
The NaOH is regenerated from NaHS through the biological treatment and
recycle to the main process. Solid sulfur, also known as bio-sulfur or elemental sulfur
produced from the process can be used in fertilizer formulation, composting and
production of sulfuric acid (Järvensivu 2015).
129
CHAPTER VIII
ECONOMIC ANALYSIS
8.1 INTRODUCTION
Besides constructing the plant and start the operation, a large amount of money
need to be invested for :
Production of bioflocculant was designedto operate for 25 years from year 2022 to
2047. Constuction of the plant would takes up about 3 years which is from year 2020
to 2022. Several factors such as changing in demand of bioflocculant, new technology
discovery, process changes and eqiupment changing were considered when designing
the operating life of the plant.
Scrap value is the net amout of money obtain from sales of used properties that is no
longer useful for the production plant, over and above any changes involved in
removal and sale. Scrap value is estimated to be 15% of fixed assests at the end of the
design life.
During the first operating year, ptoduction rate of bioflocculant is 50%, followed by
90% during the secong year and 100% for upcoming years. The reason is rhat during
start-up of the plant, the labirs, workers and staff are newly to operate effectively apart
from giving sufficient time for the company to test maket value of the product. After
having steady market and enough skilled labors, the plant will operate at full capacity.
A large amount of money is needed to prepare for start-up and construction industrial
plant. The money is used for purchase and installed all the needed equipment, building
and others. Capital investment includes land capital, fixed capital and working capital.
= Working Capital
= Land Capital
Fixed capital represents the total cost of the plant ready to start operate. This cost not
only include cost for construction but also includes the cost of design, contractor
involved and other engineering. The cost paid for construction are basically includes
all of equipment in plant and their installation, construction supervision, all
instrumentation, piping and control devices, auxiliary facilities and building such as
administrative office and control tower. Purchase cost for each equipment are been
done using CAPCOST and also compared the price with online shopping sites such as
alibaba and made-in-china. The comparison are been made to know the current price
for that equpiment and price might be change due to differences material and
thickness used for variety functions of equipment such as heavy duty pump are used
for early stage process that consist of POME that contains high amount of suspended
solids. The installation cost are been calculated by multiple the purchase cost with
installation factor. The factor for each equipment are been determined based on table
in lecture note according to type of equipment as example 20-60% for centrifugal
separtor and 30-60% for compressor.
a. Direct cost
Purchased-equipment - 28.525
Purchased-equipment - 14.20
installation
Purchased equipment 100 28.525
delivery
Instrumentation and 26.0 7.417
controls (installed)
Piping (Installed) 31 8.843
Electrical system 10 2.853
(Installed)
Building (including 29 8.272
services)
Yard improvement 12 3.423
Service facilities 55 15.689
(installed)
Total 86.146
134
b. Indirect costs
Therefore, the fixed capital investment for our plant is RM 116.501 million.
Working capital is the additional investment that needed for start the plant up. It must
over and above the fixed capital, operate it to the point when the income is achieved.
It includes the cost of start-up, initial catalyst charges, raw materials, and intermediate
process, finished product inventories and fund to cover outstanding accounts from
135
customers. Most of the working capital are being withstand and recovered at the end
of the project. Therefore, the working capital cost are being estimated based on the
total capital investment.
We need a large area of land for our plant because our plant is combination of
biological and chemical pathway. The area for future expansion of our plant also must
be considered in determine the area for the plant location. Our plant required about 20
acres land to build the plant. The land cost in FGV Mercu Puspita Mill area is RM 33,
000 per acre. So, the land capital cost is RM 825, 000. Table 8.4 shows the total
capital investment for our plant.
The total product cost are the sum of two component which comprises the general
expenses in the plant and the manufacturing cost. The simplify equation of total
product cost are as shown below:
Manufacturing cost are the main cost that is required in the production and processing
the main products of the plant which is the methanol and bioflocculant. This
manufacturing cost can be subcategorized into three different categories which is
Direct Manufacturing Cost, Fixed Manufacturing Cost and Plant Overhead Cost.
The simplified equation for manufacturing cost is as shown below which the sum of
all three categories of manufacturing is cost.
136
Direct manufacturing cost are the expenses that directly involved in the production of
products. It will be directly proportional to the rate of production of product or the
plant capacity. There are some cost are taken into consideration when calculating the
direct manufacturing cost:
i. Raw material
Raw material are the most important component in the direct manufacturing cost. A
constant and proper supply of raw material is required for a good production process
in the plant. In the production of methanol and bioflocculant, the raw materials needed
are water, sodium hydroxide, nutrient medium, ethanol and POME. The estimation of
required raw materials and the cost of raw materials are shown in table below:
Raw Materials Mass Flowrate Mass Flowrate Price per unit Price (RM) in
(kg/h) (kg/year) (RM/kg) million
Water 250.8 2167000 0.005 0.011
Sodium 1.2 10370 10.30 0.11
Hydroxide
Nutrient Medium 45 388800 44.1 1.715
Ethanol 78.5 678250 6.30 4.270
POME 36000 311000000 No charge No charge
Total 6.106
Labour are the workers involve in the production plant. Labourers can be divided into
two categories which is skilled labour and unskilled labour. The wages for the labour
is different depends on the type of labourers, industries and locations which is set by
the Labour Department of the Ministry of Human Resource. Ulrich method have been
137
used to estimate the labour requirement in the production plant. The first table shows
the number of operator required for each equipment. The second table shows the
calculation for cost of labour per year.
Conditions Value/Units
Operation per hour 24
Operation hour in one year 24 x 355 = 8520
Shift per day 3
Hour per shift 24/3 = 8
Number of shift per year 8520/8 = 1065
Shift per operator per year 254
Operator required per shift 4.2
Number of operator per shift 9.8
Total operating labor 41
Cost of one labor (RM/month) 2000
Cost of one labor (RM/year) 24000
Cost of total operating labor (RM million / year) 1.0
Based on the calculation using Ulrich method, the total operating labour cost is
RM 1.0 million each year
iii. Utilities
Steam, compressed air, electricity and cooling water are some types of utilities. It is
highly depended on the source of supply, location of plant and the amount needed. As
a rough approximation, utility costs for ordinary chemical processes amount to 10% to
138
20% of the total product cost. For utilities in our plant, it cost RM 23.7 million per
year
Operating supplies are the consumable items such as charts, lubricants, test chemicals,
custodial supplies and similar supplies which cannot be considered as raw materials or
maintenance and repairs. The cost for theses types of supplies is about 15% of total
cost for maintenance and repairs. For operating supplies, it cost RM 0.9 million per
year.
Laboratory expenses involves the test for control of operations, product quality
control and improvement of the current product. This laboratory charges are generally
calculated by estimating the employee hours involved and multiplying this by the
139
appropriate rate. This cost may be taken as 10% to 20% of the operating labour. For
laboratory expenses in our plant, it cost RM 0.2 million per year.
Cost for catalyst and solvents are important and should be estimated based on catalyst
requirement and price for the process. Catalyst is required in the reactor for syngas
production and methanol production. The cost of catalyst is estimated about 10% of
the cost of raw materials. For catalyst and solvent, the cost is 0.6 million because the
catalyst only required in small amount for chemical reaction.
Patents are the payment done due to usage of process that is developed by other
company or person. Patents covers many products and manufacturing processes. To
use patents owned by others, it is necessary to pay for the patent rights or a royalty
based on the amount of material produced. Even when the company involved in the
operation obtained the original patent, a certain amount of the total expense involved
in the development and procurement of the patent rights should be borne by the plant
as an operating expense. The patents and royalty cost is estimated at 0 to 6% of the
total product cost. The cost for patents and royalty is about RM 7.1 million. This
patents covers the patented methanol production process.
x. Summary
The summary of direct manufacturing cost for each of the component are as stated
below:
b. Fixed manufacturing
Fixed charge which is also known as fixed costs are the costs that change in little or
not at all with the amount of production in the plant. This shows that fixed charge is
not affected by the quantity of methanol and bioflocculant produced in the plant.
Fixed charges includes depreciation, local property taxes, insurance and loan interest.
i. Financing
Financing cost is the interest payable for the capital cost obtained by borrowing from
financial institutions such as the bank. Interest is considered to be the compensation to
be paid for the use of borrowed money. A fixed rate of interest is established at the
time the capital is borrowed. Therefore interest is definite cost if it is necessary to
borrow the capital used to make the investment for the plant. Annual interest rates
usually amount to 5% to 10% of the total value of borrowed capital. The total
financing cost is RM 21 million.
The magnitude of local property taxes depends on the particular locality of the plant
and the regional laws. Annual property taxes for plants in percentages of fixed capital
investment are in the range of 2% to 4% in highly populated areas while 1% to 2% in
less populated area. This production plant will be established in Lahad Datu, Sabah,
Malaysia. It can be considered that this is a less populated area. So the local taxes is
estimated at 2%. The total taxes for our plant is about RM 2.3 million.
Property insurance rates depends on the types of process being carried out in the
manufacturing plant. It also highly related to the extent of available protection
facilities. The premium rates amount to about 1% of the fixed capital investment per
year. The total property insurance for our plant is about RM 1.2 million.
141
iv. Summary
The summary of fixed manufacturing cost for each of the component are as stated
below:
Plant overheads costs are expenditures required for routine general plant service
whereby non-manufacturing machinery, equipment and buildings are required to
provide such services. The fixed charges and direct costs for these items are part of
the plant overhead costs. Plant overhead costs for a process plant is about 50% to 70%
percent of the total expenses for operating labour, supervision and maintenance.
Plant overhead cost = 0.6 x (Operating Labour Cost + Supervision and Clerical
Labour
= RM 9.6 million
The total cost of manufacturing is the sum of direct manufacturing cost, fixed costs
and plant overheads cost. The calculation of total cost of manufacturing methanol and
bioflocculant are as shown below.
Total manufacturing cost = Direct Manufacturing Cost + Fixed Cost + Plant Overhead
Cost
142
= RM 88.7 million
General expenses are the cost that is related to the management and administrative
level which is not directly involved to the manufacturing process. The general
expenses can be categorized into administrative expenses, distribution and marketing,
and research and development expenses. The simplified equation for general expenses
are as below:
a. Administrative expenses
Administrative expenses are directly connected with executive and admin activities
that include among salaries and wages for administrators, secretaries, accountants,
computer support staff, engineering and legal personnel. Besides that, administrative
expenses also comprises the cost for office supplies, equipment, administrative
buildings and other related items and activities. Administrative cost can be estimated
at 15% to 25% of the operating labour cost.
No manufacturing operation can be considered a success until the products have been
sold or put to some profitable uses. Distribution and marketing cost includes salaries,
wages, supplies and other expenses for sales office. Besides that, it also includes
travelling expenses, shipping expenses, cost of containers and advertising expenses.
Distribution and marketing costs vary widely for different types of plants depending
on the produced product, other product sold by the company, plant location and
company policies. For a process plant, the distribution and market cost are about 2%
to 20% of the total product cost
143
Research and development cost are the expenses that required for study on improving
the current operation process and quality of product. This expenses includes salaries
of all personnel, equipment for research, costs of materials and consultants fees. These
cost amount to about 2% to 5% of the total product cost.
d. Summary
The of general expenses cost for each of the component are as stated below:
= RM 118.5 million
8.4 DEPRECIATION
Depreciation is a measure of the decrease in the value of an asset iver time. Physical
facilitties, including costs such as design and engineering, shipping and fiels erection
of the plant deprecible. Land in not depreciable, but improvements to the land, suach
as grading and adding utility services are depriciable. Some companies use
deprecation as a means to set aside a fund to replace a plant when it is no longer
operable. There are five methods in determining the depreciation value :
i. Straight-line method
144
The calculation method for depreciation value for this plant is straight-line
method. In this method, the property value is assumed to decrease linearly with time
over the service life. Annual depreciation charge is shown below ;
Where,
S = Salvage or scrap value of the plant or equipment at the end of its service life
The total income and total expenditure in the design plant at full capacity is
considered to determine the breakeven point which is at 2.3 years as shown in Figure
8.1
Where :
Net profit usually is not constact from year to year for a project. Total
investment also changes if additional investments are made during project operation.
Therefore, the ROI for a project is determined as an average during the life of project
is given by :
Where :
-b = the year the first investment made in the project based on year 1 as the
start of operation of the project
ROI that has been determined is then compared with a rate of return value
known as the Minimum Acceptable Rate of Return (MARR) that is given by the
symbol mar . the value of mar depends in the type of process and the level of risk for
the project. The value of mar can be taken from the following table :
Table 8.11 Susggested values for risk and minimum acceptable return on investment
b. Payback period
The profitability measure of payback period, or payout period is the length of time
necessary for the total return to equal to the capital investment. The initial fixed
capital investment and the annual cash flow are usually in this calculation by using the
following equation :
The net present value, NPV is the total of the present worth oa all cash flows minus
the present worth of all capital investments, as defined by
Where
fdi,j = selected present worth factor for the cash flows with interest rate,i in
yearj
The discounted cash flow rate of return, DCFRR is the return obtained from an
investment in which all investments and cash flows are discounted. It is determines by
setting the NPV equal to zero and sloving for the discount rate that satisfies the
resulting relation. Thus ,
149
The DCFRR is only of concern when the project rates favourably compared to
the value of mar used in calculating the net present value. Clearly if the NPV that is
calculated equals zero, then the mar used is the DCFRR. However, if the NPV is
greater than zero, then the DCFRR must be calculated from equation above. For the
project to be favourable, the discounted cash flow rate of return must be greater than
the mar used. By using Microsoft Excel defined function “Goal-Seek”, our DCFRR
value can be computed as 27%. Since the value of i for a project is greater than marr,
then the project is said to be attractive. Following table summarizes our calculation of
DCFRR for our plant.
Discounted Cumulative
Income Depreciation Taxable Tax Discount cash flow or discounted
Production Expenditure (revenue) Gross charges income payable Net profit Cash flow factor at I present value cash flow
Year rate (RM) (RM) profit (RM) (RM) (RM) (RM) (RM) (RM) = MARR (RM) (RM)
0 0 34950360 0 0 0 - 0 -34950360 -34950360 1 -34950360 -34950360
1 0 69900720 0 0 0 - 0 -69900720 -69900720 0.77 -53769784.6 -88720144.6
2 0.5 20047000 102314550 82267550 4660048 77607502 19401875.5 62865674.5 67525722.5 0.59 39956048.8 -48764095.8
3 0.9 109609754.8 184166190 74556435.2 4660048 69896387.2 17474096.8 57082338.4 61742386.4 0.46 28103043.4 -20661052.4
4 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.35 24661697.1 4000644.7
5 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.27 18970536.2 22971180.9
6 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.21 14592720.2 37563901.1
7 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.16 11225169.4 48789070.4
8 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.12 8634745.7 57423816.1
9 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.09 6642112.0 64065928.1
10 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.07 5109317.0 69175245.1
11 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.06 3930243.8 73105488.9
12 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.04 3023264.5 76128753.4
13 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.03 2325588.1 78454341.4
14 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.03 1788913.9 80243255.3
15 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.02 1376087.6 81619342.9
16 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.02 1058528.9 82677871.8
17 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.01 814253.0 83492124.9
18 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.01 626348.5 84118473.3
19 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.01 481806.5 84600279.9
151
20 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.01 370620.4 84970900.3
21 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.00 285092.6 85255992.9
22 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.00 219302.0 85475294.9
23 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.00 168693.9 85643988.7
24 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.00 129764.5 85773753.2
25 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.00 99818.8 85873572.1
26 0 -88710612 0 -88710612 -88710612 -88710612 0.00 -96704.9 85776867.2
15 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.00 103961 -187429
16 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.00 67320 -120109
17 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.00 43593 -76516
18 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.00 28228 -48288
19 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.00 18279 -30009
20 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.00 11837 -18172
21 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.00 7665 -10507
22 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.00 4963 -5544
23 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.00 3214 -2330
24 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.00 2081 -249
25 1 118480816 204629100 86148284 4660048 81488236 20372059 65776225 70436273 0.00 1348 1099
26 0 -88710612 - -88710612 -88710612 (88710612) 0.00 -1099 0
CHAPTER IX
9.1 INTRODUCTION
It is important to identify the hazards and reduce the risk before an accident can occur.
Hazard has the potential to cause harm or damage to people, property and also the
environment, while risk is a measure of human injury, environmental damage or
economic loss in terms of both the incident likelihood and severity or magnitude of
the loss or injury. Industrial risk must be managed appropriately by identifying
hazard, assessing risk, controlling risk and communicating risk.
Possible hazard associated with the operation processing plant has to abide by the
standards in the national law. The standards issued by the government are to ensure
the safety of people, property and environment. Any activity around the production
plant needs to obey and obtain permission from Department of Environment (DOE)
and the Department of Occupational Safety and Health (DOSH). The related acts
which must be followed by our production plant are:
EIA is required to carry out to ensure the safety of the public is safeguarded,
the environment is protected and sustainability criteria is considered. The objective of
EIA guideline is to establish and integrate procedures for carrying out risk analysis of
new major hazardous industrial installations, storage and transportation facilities. For
our plant, waste generated from our plant such as wastewater containing ethanol,
methanol and treated pome and lean sodium hydroxide will have proper treatment
method before being discharged according to the standard.
According to the act, it shall be the duty of every employer and self-employed person
to ensure, the safety, health and welfare at work of all his employees and it shall be
the duty of every employer and every self-employed person to conduct his
undertaking in such manner as to ensure, not being his employees, who may be
affected thereby are not thereby exposed to risks to their safety or health. This
regulations is enforced by the Department of Safety and Health (DOSH).
Under Safety Health Regulation 1997, any chemical and allied industry with
more than 100 employees is required to employ Safety and Health Officer (SHO).
Employer is to establish Safety and Health Committee if there are 40 and more
persons employed and it is directed by the director general of Department of
Occupational Safety and Health (DOSH). Safety and health committee are required to
review measure taken to ensure and safety and health at workplace, investigate
matters at workplace which is considered not safe or risky to health and that has been
brought to the attention of the employer, and is to attempt to resolve the matters.
It is an act to provide for the control of factories with respect to matters relating to
safety, health and welfare of persons therein, the registration and inspection of
machinery and for matters connected therewith. Regulation 5 states that no person
shall manufacture or cause to be manufactured any steam boiler or unfired pressure
vessel without the permission in writing of the Chief Inspector. Regulation 10 explain
156
that every steam boiler must have the essential fittings that are safety valves, water
gauges, steam pressure gauge, low water alarm, inspector’s test attachment,
nameplate, manhole door and others.
Hazards can be categorized into five types that are chemical hazard, health hazard,
mechanical hazard, thermodynamic hazard, electric and electromagnetic hazard. There
are several components in our plant that can be included in hazard system which are
methane, carbon dioxide, ethanol, carbon monoxide, methanol and sodium hydroxide.
The chemicals involved in the production of bioflocculant and methanol are methane,
carbon dioxide, ethanol, carbon monoxide, methanol and sodium hydroxide.
heated)
Methanol No No Yes (May form Yes (Highly Yes Yes
explosive flammable)
vapour-air
mixture)
Sodium No Yes Yes (Heat No Yes Yes
hydroxide release resulting
in fire or
explosion risk)
The chemicals involved are classified based on its toxicity and are tabulated in Table
9.2. The Permissible Allowable Limit (PEL), Threshold Limit Value (TLV),
Immediate Dangerous to Life and Health values (IDLH) and Emergency Response
Plan Guidelines (ERPG) are stated.
The specified chemicals are categorized based on their flammability stating its flash
points, Lower Flammable Limit (LFL), Upper Flammable Limit (UFL) and Auto
Ignition Temperature (AIT) which is tabulated in Table 9.3.
Chemical Description Flash point (oC) LFL (v/v %) UFL (v/v %) AIT (oC)
container
Ethanol Highly flammable 25 3.3 19 368.8
Carbon Extremely flammable NA 12.5 74.0 605
monoxide gas
Methanol Burns with clean, 12.2 6.72 36.5 385
clear flame, being
almost invisible in
daylight
Note that:
HIRARC is the short form of Hazard Identification, Risk Assessment and Risk
Control. The objective is to provide a systematic method to evaluate hazards and their
related risks. HIRARC is one of the general duties as prescribed under the
Occupational Safety Health Act 1994 (Act 154) for employers to provide a safe
workplace to employees and people associated with the chemical plant. This provide
an objective approach of an identified hazard and also a method to mitigate the risk
based on table 9.4 and table 9.5. The reaction consideration is based on table 9.6.
Table 9.7 shows the risk matrix to decide whether the risk is either low, medium or
high.
Severity (S)
Likelihood (L)
1 2 3 4 5
5 5 10 15 20 25
4 4 8 12 16 20
3 3 6 9 12 15
2 2 4 6 8 10
1 1 2 3 4 5
HIRARC is conducted throughout the plant. Following are the HIRARC for
each process and general works involved that supports to the process of methanol
production. In our plant, HIRARC will be managed on these aspects which includes
plant wide, storage, compressor and chemical reaction.
Table 9.8 HIRARC study of plantwide
Likelihood
hazards, Noise, Existing Control Measures L
Severity
Chemical (What action has been x
Substances, Dust, taken to reduce the S Additional control
No. Main process Work Activity Ergonomics Effect? effect?) ) measures
1 General Regular Slippery floor Physical Injury PPE - Safety boots -
Maintenance maintenance Buddy System 2 2 4
and Work instruction
Cleaning Pro Falling from height Physical injury, PPE - Safety harness -
cess may lead to death Buddy System 2 4 8
Work instruction
Inhalation of toxic gases Asphyxiation PPE- protective mask -
(suffocation, may Medical clinic 1 4 4
lead to death) Work instruction
Cuts injury involving Physical Injury PPE - Safety boots -
machinery Buddy system 2 2 4
Work instruction
Cleaning of tank Slippery floor Physical Injury PPE - Safety boots -
Buddy system 2 2 4
Work instruction
Falling from height Physical injury, PPE - Safety harness
may lead to death Buddy System 2 4 8 -
Work instruction
161
Likelihood
Severity
Mechanical hazards, Electrical
hazards, Thermal hazards, Noise, Existing Control Measures
Work Chemical Substances, Dust, (What action has been taken to Risk Additional control
No. Main process Activity Ergonomics Effect? reduce the effect?) (LxS) measures
1 R-101 Reaction in Overpressure inside reactor Explosion Work instruction 3 5 15 Ensure no ignition
Reactor tank Emergency Response Plan (ERP) source nearby
High pressure alarm Regular maintenance
Pumping of Pipe leakage May cause PPE - Gloves, Safety boots, face 2 2 4 Regular maintenance
POME into bacterial infection mask
reactor of liquid effluent Leakage detector system
Pumping of Pipe leakage and release of gas Explosion Work instruction 3 5 15 Ensure no ignition
gas product out with ignition source Emergency Response Plan (ERP) source nearby
162
Tank rupture Leakage of gas Emergency Response Plan (ERP) 3 4 12 Ensure no ignition
High pressure alarm source nearby
Regular maintenance
Pumping of Pipe leakage May cause PPE - Gloves, Safety boots, face 2 2 4 Regular maintenance
gas into tank bacterial infection mask
of liquid effluent Leakage detector system
163
Pumping of Pipe leakage and release of gas Explosion Work instruction 3 5 15 Ensure no ignition
gas out of with ignition source Emergency Response Plan (ERP) source nearby
tank Leakage detector system Regular maintenance
Pipe leakage and release of toxic Asphyxiation Emergency Response Plan (ERP) 3 4 12 Ensure no ignition
gas (suffocation, may Leakage detector system source nearby
lead to death) Regular maintenance
S-101 Separation High level in separator Overflow Work instruction 2 3 6 Ensure no ignition
4 Separation of process Emergency Response Plan (ERP) source nearby
liquid and High level alarm Regular maintenance
vapour Pumping of Pipe leakage and release of Explosion Work instruction 3 5 15 Ensure no ignition
mixture into mixture with ignition source Emergency Response Plan (ERP) source nearby
separator Leakage detector system Regular maintenance
Pumping of Pipe leakage and release of gas Explosion Work instruction 3 5 15 Ensure no ignition
vapour out of with ignition source Emergency Response Plan (ERP) source nearby
separator Leakage detector system Regular maintenance
Pipe leakage and release of toxic Asphyxiation Emergency Response Plan (ERP) 3 4 12 Ensure no ignition
gas (suffocation, may Leakage detector system source nearby
lead to death) Regular maintenance
Pumping of Pipe leakage and release of liquid Explosion Work instruction 3 5 15 Ensure no ignition
liquid out of with ignition source Emergency Response Plan (ERP) source nearby
separator Leakage detector system Regular maintenance
S-102 Separation high level in separator Overflow Work instruction 2 3 6 Ensure no ignition
5 Separation of process Emergency Response Plan (ERP) source nearby
liquid and High level alarm Regular maintenance
vapour Pumping of Pipe leakage and release of Explosion Work instruction 3 5 15 Ensure no ignition
mixture into mixture with ignition source Emergency Response Plan (ERP) source nearby
separator Leakage detector system Regular maintenance
Pumping of Pipe leakage and release of gas Explosion Work instruction 3 5 15 Ensure no ignition
vapour out of with ignition source Emergency Response Plan (ERP) source nearby
separator Leakage detector system Regular maintenance
Pipe leakage and release of toxic Asphyxiation Emergency Response Plan (ERP) 3 4 12 Ensure no ignition
164
Overall Bioflocculant
Process unit:
Hazard Identification, Risk Assessment, Risk Control (HIRARC) Production Location Biological reaction
Date: 23/3/2020 Prepared by KK4
Review date: Approved by
Hazard Identification Risk Assessment Risk Control
Hazard
Likelihood
Severity
Mechanical hazards, Electrical
hazards, Thermal hazards, Noise, Existing Control Measures
Work Chemical Substances, Dust, (What action has been taken to Risk Additional control
No. Main process Activity Ergonomics Effect? reduce the effect?) (LxS) measures
1 Cooling Draining of Drain leakage which causes Physical Injury PPE - Gloves, Safety boots, face
Pond C-101 POME into slippery floor mask 3 3 9 Regular maintenance
cooling pond Leakage detector system
Storage of Overflow Physical Injury PPE - Gloves, Safety boots, face Regular maintenance
POME mask 2 2 4
2 UASB T-101 Pumping of May cause PPE - Gloves, Safety boots, face
POME into Pipe leakage bacterial infection mask 2 2 4 Regular maintenance
UASB of liquid effluent Leakage detector system
Work instruction Ensure no ignition
Reaction in
Overpressure in tank Explosion Emergency Response Plan (ERP) 3 5 15 source nearby
tank
High pressure alarm Regular maintenance
3 Settlement Separation of High level in tank Overflow Work instruction 2 2 4 Ensure no ignition
168
tank T-104 solid biomass Emergency Response Plan (ERP) source nearby
from water High level alarm Regular maintenance
Pumping of May cause PPE - Gloves, Safety boots, face
POME into Pipe leakage bacterial infection mask 2 2 4 Regular maintenance
tank of liquid effluent Leakage detector system
4 T-105 Pumping of May cause PPE - Gloves, Safety boots, face
MBBR POME into Pipe leakage bacterial infection mask 2 2 4 Regular maintenance
MBBR of liquid effluent Leakage detector system
8 Conveyor Transportatio
CV-102 PPE - Gloves, Safety boots, face
n of Operator’s mistake Physical injury 2 2 4 Regular maintenance
mask
bioflocculant
Carbon dioxide Health -May displace oxygen Thermal radiation -Operators on duty. -Wall of storage tank.
and cause suffocation. transmission. -Residents nearby. -Personal protective
-May explode if heated. equipment for operators.
-Regular maintenance
check for every pipeline.
Sodium hydroxide Health, Chemical -Strongly irritating and Thermal radiation -Operators on duty. -Wall of storage tank.
corrosive. transmission. -Residents nearby. -Personal protective
-May cause severe burns equipment for operators.
and permanent damage to -Regular maintenance
any tissue in contact. check for every pipeline.
Carbon monoxide Health -Toxic if inhaled. Thermal radiation -Operators on duty. -Wall of storage tank.
-May cause damage to transmission. -Residents nearby. -Personal protective
organs. equipment for operators.
-May explode if heated. -Regular maintenance
check for every pipeline.
Ethanol Health -May form explosive Thermal radiation -Operators on duty. -Wall of storage tank.
mixtures with air. transmission. -Residents nearby. -Personal protective
-Highly flammable. equipment for operators.
-Regular maintenance
check for every pipeline.
172
Methanol Health -Over-exposure may Thermal radiation -Operators on duty. -Wall of storage tank.
result to death. transmission. -Residents nearby. -Personal protective
-Hazardous in case of equipment for operators.
skin contact, eye contact, -Regular maintenance
ingestion or inhalation. check for every pipeline.
Boiler Thermodynamic -Low water level and Thermal radiation -Operators on duty. -Wall of storage tank.
excessive pressure may transmission. -Residents nearby. -Personal protective
lead to explosion. equipment for operators.
-Regular maintenance
check for every pipeline.
Pressure vessel Thermodynamic -May cause explosion Thermal radiation -Operators on duty. -Wall of storage tank.
-May cause permanent transmission. -Residents nearby. -Personal protective
injuries on affected equipment for operators.
people -Regular maintenance
check for every pipeline.
Microbe (Bacillus Biological -May be contaminated When in direct contact -Operators on duty. -Personal protective
marisflavi) -May be toxic to human with the contaminated -Residents nearby. equipment for operators.
health microbe
9.6 HAZOP STUDY
The HAZOP (Hazards and Operability) study is a formal procedure to identify hazards in chemical process facility. The procedure is effective
in identifying hazards and is well accepted by the chemical industry. HAZOP studies are conducted on all equipments that are involved in the
production of biofolocculant and methanol. HAZOP studies are divided into two parts which is chemical and biological process. The HAZOP
studies for major equipments are shown below and the others are shown in Appendix B.
Hazop for the most hazardous equipments are stated in this chapter. Other equipments are stated in the appendix B.
a. R-101
High High temperature Valve cooled water Vessel or pipeline Temperatu Scheduled maintenance and
inside reactor. failed closed rupture re inspection.
controller Install high temperature
alarm
176
High High pressure Outlet flow too low Vessel or pipeline Pressure Scheduled maintenance and
inside reactor. rupture relief valve inspection.
Pressure Install high pressure alarm
Explosion controller Install gas detectors
177
High High level inside High flow into Overflow inside Temperature Scheduled maintenance and
reactor. reactor reactor controller inspection.
Install high temperature
alarm
178
b. R-102
High High pressure Outlet flow too low Vessel or pipeline None Scheduled maintenance and
inside reactor. rupture inspection.
Release of Install high pressure alarm
flammable biogas
gas cloud
184
High High temperature Valve cooled water Vessel or pipeline Temperature Scheduled maintenance and
inside reactor. failed closed rupture controller inspection.
Install high temperature
alarm
185
High High level inside High flow into Overflow inside Temperature Scheduled maintenance and
reactor. reactor reactor controller inspection.
Install high temperature
alarm
186
c. S-101
High High pressure Outlet flow of gas too low Vessel or Pressure Scheduled maintenance and
inside separator. Malfunction of pressure pipeline rupture controller inspection.
relief valve Release of Pressure Install gas detectors
flammable relief valve Install high pressure alarm
biogas gas
cloud
192
High High level of Outlet flow of liquid too low Overflow inside Level controller Scheduled maintenance and
containment inside High flow of raw material column inspection.
separator. into separator Install high pressure alarm
193
d. C-101
No No feed flow into Pipe broken or No separation occurs None Scheduled inspection and
distillation column plugged maintenance at pipe and
Valve failed close valve
Install low level alarm
High More feed flow into Valve failed open Overflow and spillage of Level controller of Scheduled inspection and
distillation column containment column maintenance at level
controller
No No flow of outlet top Pipe broken Over containment in reflux drum None Scheduled inspection and
product Full clogging of pipe Rupture of reflux drum maintenance at pipe
198
No No flow of outlet bottom Pipe broken Overflow in distillation column None Scheduled inspection and
product Full clogging of pipe Spillage of containment maintenance at pipe
Install high level alarm
High More flow of outlet bottom Valve failed open Separation efficiency decrease None Scheduled inspection and
product Pipe might rupture maintenance at pipe and
Low level in distillation column valve
High High temperature in the Condenser not Overheat or damage of column Temperature Scheduled inspection and
column working well Specification of product is not met controller maintenance at column
High High temperature in Condenser Produces off-spec product Flow controller at Scheduled inspection and
condenser malfunction Failed to convert gas to water condenser maintenance at condenser
Water failed to flow
Install high temperature
alarm
204
High High temperature in High flow of steam Produces off-spec product None Scheduled inspection and
reboiler through reboiler maintenance at reboiler
10.1 INTRODUCTION
Plant location play an important roles on the profability of a project. It also has effect
to on scope for fututre expansion. There are several major factor that must be
considered in selection for suitable plant location. Among the major factors are listed
below:-
The availability and price of the product will often determine the plant
location. This is because it will give huge impact mainly in cost when there are
no supply of raw material nearby the plant site. Plants producing huge amount
of chemical are usually located close to the source of the major raw material
The transport of materials and products to and from the plant will be very
important factor in selection of plant location. It will be very convenient when
the site selected is close to at least two major forms of transport: road, airport,
sea port and rail.
206
As we all know, huge area of land is needed for plant construction. Area for
future expansion of plant also need to considered for this factor . Next,
reasonable land price are necessary for saving cost.
v. Availability of labouur
Plant with huge production capacity need a high amount of workforce. The
plant location play important role when the site locate at easy to access are or
near the residental area.
They are four places that been research and considered to be our plant location. These
four locations will be compared to each other based on raw material supply, land
availability and land prices, transport facilities, labour availability and utilities. The
list of the comparison for the four location are shown in Table 10.1 and for each
location are being evaluate and rate based on marks for each factor. These are being
shown at Table 10.2
Price RM 33, 000 per RM 250,000 per RM 150,000 per RM 500,000 per
acre acre acre acre
207
Mill Nearby (Raw FGV Mercu Seri Morib Palm Muar Palm Oil Pantai Remis
material source) Puspita Mill Oil Sdn Bhd Mill Bhd Palm Oil Mill
Utilities High electric supply High electric supply High electric supply with
with low cost with medium cost high cost
Public facilities More public facilities Slightly more public Less public facilities
provided utilities provided provided
Labor availability High amount of labor Slightly high amount of Low amount of labor
available labor available available
Residential Near with site area Slightly far with site area Far with site area
distance
Mark must be given for all four locations selected for each factor based on the
mark analysis. Based on the comparison of total score for all four locations, location
208
with highest mark are the finalize location for our plant. Table 10.3 shows the scoring
for each location selected based on the mark analysis listed in Table 10.2
Based on the marks evalution, Lahad Datu, Sabah has the higesht score and the first
ranking among the suggested locations. It is chosen as our finalized plant location due
to following the reason:-
About 20 acres of land is purchased and the cost of the land is approximately
RM 26.9 million whereas the price of land at that area is RM 33, 000 per acre. Our
209
plant located near the FGV Mercu Puspa Mill. Figure 10.1 shows the exact land that
we choose for our plant site location.
In order to reduce the effect of controllable and uncontrollable factors that will
contribute to losses, layout arrangement and spacing is important. One of
uncontrollable factor that we considered is the wind direction. The wind direction at
our plant site location is northwest. Based on our plant layout, we placed our main
gate, administration building, car park, office, workshop and warehouse at upwind.
While, we placed all the tank farm and equipments that may spill flammable liquid at
the downwind to reduce the loss potential from an explosion or fire.
The spacing required between the various blocks based upon the relative hazard of
each process. By evaluating the process hazards and then we classifying them in high
hazard (HH), intermediate hazard (IH) and moderate hazard (MH) groups
Distance (in m) MH IH HH
MH 15 30 60
IH 30 60
HH 60
CHAPTER XI
MECHANICAL DESIGN
By considering the internal pressure for UASB, the mechanical calculation for the
Table 11.1. The calculations can be referred in appendix part C1.
Table below shows the overall calculation that related to the measurement for MBBR
reactor construction. The calculations can be referred in appendix part C2.
0.015< 355.06
2
Area of one bolt, Ab mm 176.95
Distance from the edge of the skirt to the outer edge of m 0.076
the ring, Lr
Actual width required, Lb m 0.905
Base ring thickness, tb m 0.103
Type of flanged joint - Slip on flange joint
By considering the internal pressure of the vessel, reactor R-102, the conditions that
are needed for the design have been calculated through series of formulae stated. The
conditions for the design our distillation column have been summarized and tabulated
as followed in Table 11.3. The calculations can be referred in appendix part C3.
(88.973< 122)
Elastic stability N/mm2 (∑σ)compressive < σc
By considering the internal pressure of the vessel, Cooler CO-101, the conditions that
are needed for the design have been calculated through series of formulae stated. The
conditions for the design our cooler have been summarized and tabulated as followed
in Table 11.4. The calculations can be referred in appendix part C4.
Phase separator (S-102) is a vertical vessel used to purify methanol through phase
separation. The type of shell is cylindrical while the type of head is ellipsoidal head
with ratio 2:1.Table 11.5 summarizes the operating conditions and dimension of S-
102. The calculations can be referred in appendix part C5.
Since the operating pressure is greater than the atmospheric pressure, the vessel is
designed based on the internal pressure. Construction material is stainless steel type
304 with corrosion allowance of 2 mm and maximum allowable stress of 19290 psi.
Table 11.7 Dimension for the steel welding neck flanges(in mm)
Stream Nominal d1 D B T d4 f d2 k d3
Pipe Size
62 (in) 406 438 711 60 158.75 533 2 35 629 533
63 (out) 14 16 95 14 52 35 2 16 67 38
63 (out) 33 41 155 21 68.33 73 2 22 114 70
By considering the internal pressure of the vessel, distillation column C-101, the
conditions that are needed for the design have been calculated through series of
formulae stated. The conditions for the design of distillation column have been
summarized and tabulated as followed in Table 11.8. The calculations can be referred
in appendix part C6.
CONCLUSION
In this plant, the plant capacity for the production of bioflocculant is 2000
tonnes annually while for methanol is 800 tonnes annually. The sales price for the
bioflocculant is RM 90 per kg with the design life 25 years. Besides, payback period
(PBP) is 2.3 years and it is lower than PBPreference which is 2.5 years. It could attract
investors as it offers early payback period.
Our plant will be located at Lahad Datu, Sabah. The selection is based on the
suitability of land for transport, availability of raw materials, manpower, infrastructure
and etc. Our plant will be located near the FGV Mercu Puspita palm oil mill. We
obtain our main raw material, which is the POME from this palm oil mill. About 36
m3/hour of POME will be supplied to our plant. The detailed plant layout has been
drawn in order to have a structured plant which is high in safety.
The received POME will undergo anaerobic process to produce biogas. This
biogas will be used in the production of methanol by methane reforming and methanol
forming reactor. The remaining POME will undergo aerobic process to produce
bioflocculant. Now the POME is already low in COD and BOD content. It will enter
the waste treatment plant before been discharged to the nearby river. The discharge
limit in that area is Standard B. Green technologies are used in treating the POME to
produce biogas and bioflocculant such as UASB, MBBR and phytoremediation.
role in this plant. Mechanical design have been done to some of the major equipment
such as the UASB reactor (T-101, T-102 and T-103), MBBR (T-105), cooler (CO-
101), methanol forming reactor (R-102), phase separator (S-102) and distillation
column (C-101). This major equipment is either a pressure vessel or most crucial
equipment in this plant.
Lastly, the safety of the whole plant has been analyzed by using a few studies
such as HIRARC and HAZOP studies. The chemical and biohazard have been
determine such as flammability of biogas and methanol. HAZOP studies have been
done for each equipment in order to obtain suggestion to improve the safety of the
plant. Some of the improvement from HAZOP studies are to add pressure relief valve
in pressurized vessel and flammable gas detector in the plant.
REFERENCE
Abd Nasir, M. A. et al. 2019. The use of acidified palm oil mill effluent for
thermophilic biomethane production by changing the hydraulic retention time in
anaerobic sequencing batch reactor. International Journal of Hydrogen Energy,
3373–3381. doi:10.1016/j.ijhydene.2018.06.149
Ain, N. et al. 2018. MALAYSIA: 100 YEARS OF RESILIENT PALM OIL
ECONOMIC PERFORMANCE. Journal of Oil Palm Research, 30(1), 13–25.
doi:10.21894/jopr.2018.0014
Al-dawery, S. 2013. METHANOL REMOVAL FROM METHANOL-WATER
MIXTURE USING MUNICIPAL ACTIVATED SLUDGE 8(5), 578–587.
Bal, A. S. & Dhagat, N. N. 2001. Upflow Anaerobic Sludge Blanket Reactor - A
Review. Indian Journal of Environmental Health 43(2): 1–83.
Barbour, W., Oommen, R., Sagun Shareef, G., Vatavuk, W. M. & EPA. 1995. Section
5 - SO 2 and Acid Gas Controls.
Brito, A. G. et al. 2007. Brewery and winery wastewater treatment: Some focal points
of design and operation. Utilization of By-Products and Treatment of Waste in
the Food Industry, 109–131. doi:10.1007/978-0-387-35766-9_7
Caballero, A. R. et al. 2011. Treatment of High Ethanol Concentration Wastewater By
Constructed Wetlands : Enhanced Cod Removal and Bacterial Community
Dynamics 1–15.
Choong, Y. Y., Chou, K. W. & Norli, I. 2018. Strategies for improving biogas
production of palm oil mill effluent (POME) anaerobic digestion: A critical
review. Renewable and Sustainable Energy Reviews 82(August): 2993–3006.
Sinnott, R. K. 2005. Chemical Engineering Design 4th ed, hlm. 4th Edisi .
Elsevier.
Janssen, A. J. H. et al. 2000. New Developments of the Thiopaq Process for the
Removal of H2S From Gaseous Streams. Preprints of Sulphur 2000 Conference,
29, 179–187.
Järvensivu, R. 2015. Reuse Possibilities for Elemental Sulfur Sludge 1–43. Retrieved
from
https://www.theseus.fi/bitstream/handle/10024/97660/Roni_Jarvensivu_final.pdf
?sequence=1
activated sludge (IFAS) and moving bed biofilm reactors (MBBR) using
stainless steel pipe diffusers, manifold, and down pipes. 86th Annual Water
Environment Federation Technical Exhibition and Conference, WEFTEC 2013
6: 3781–3808. doi:10.2175/193864713813685403
Ødegaard, H., Gisvold, B. & Strickland, J. 2000. The influence of carrier size and
shape in the moving bed biofilm process. Water Science and Technology 41(4–
5): 383–391. doi:10.2166/wst.2000.0470
Ohimain, E. I. & Izah, S. C. 2017. A review of biogas production from palm oil mill
effluents using different configurations of bioreactors. Renewable and
Sustainable Energy Reviews 70(December 2014): 242–253.
Rusten, B., McCoy, M., Proctor, R. & Siljudalen, J. G. 1998. The innovative moving
bed biofilm reactor/solids contact reaeration process for secondary treatment of
municipal wastewater. Water Environment Research 70(5): 1083–1089.
doi:10.2175/106143098x123435
Van Lier, J. B., Vashi, A., Van Der Lubbe, J. & Heffernan, B. 2010. Anaerobic
sewage treatment using UASB reactors: Engineering and operational aspects.
Environmental Anaerobic Technology: Applications and New Developments
59–89.
APPENDIX A
DETAILED DESIGN
CHAPTER I
1.1 INTRODUCTION
The main function of cooling pond in our plant is to reduce the temperature of POME
obtained directly from the palm oil mill. POME will be received from the mill at a
temperature of 85°C (Zainal et al. 2017). This temperature is not suitable for anaerobic
process because the microbe that involves is mesophilic which work best in the
temperature range of 35°C to 40°C (Choong et al. 2017). A cooling pond is chosen
rather than tank because it is low in construction and operation cost. It is also easy to
operate and maintain in which skilled workers are not required. This cooling pond also
serves as a storage of POME. The general information of POME required for the design
of cooling pond is as below
The design of cooling pond is based on the energy balance on the cooling pond.
Assumption made to calculate the heat transfer at the surface of cooling pond is heat is
transferred through convection and radiation only. The overall heat formula is shown
as below
Heat is transferred from the cooling pond to the atmosphere. This is because the
temperature in the cooling pond is higher compared to the atmosphere. The formula for
the heat transferred in the cooling pond is as below.
= (36000)(4.2)(358.15-308.15)
= 7560000 kJ/hr
Thus, the rate of heat transfer from the cooling pond to atmosphere is 7560000 kJ/hr
Heat by convection means heat is transferred from one place to another thorough the
fluid. In this case, heat is transferred from the cooling pond to the atmosphere through
3
the air as the fluid. The calculation of heat transferred by convection in the cooling pond
is as below.
= (369)(A)(358.15-308.15)
= 18450 A kJ/hr
Heat transferred by radiation involves the when the high energy electron emits energy
to fall back to low energy level. The water molecule on the surface of the pond may
emit energy to release heat. The calculation of heat transferred by radiation in the
cooling pond is as below.
= (0.96)(5.670× 10-8)A(358.154-308.154)
= 404.8 A kJ/hr
The area of cooling pond is calculated by using the energy balance equation in the
cooling pond
Q = Qconvection + Qradiation
A = 400 m2
4
The retention time in the cooling pond is about one day as the temperature must be
reduced from 85°C to 37°C (Rahman 2017). The supply of POME will be 16 hours
since it’s the working hours in the palm oil mill per day. The volume calculation of the
pond is as below by taking 20% of safety factor for volume:
= 36 m3/hr × 16 hr × 1.2
= 691.2m3
400 = L2
L = 20 m
The length and the width of the cooling pond is 20m × 20m
691.2 = H × 400
H = 1.73 m
The construction of cooling pond is relatively easy because just have to dig a large area
of hole. The hole must be covered with liner which have some important function for
ponding system. High density polyethylene (HDPE) pond liner will be used to cover
the surface of the ground. The function of this pond line is to prevent contaminant from
POME entering the ground. It also helps to prevent the water loss to the ground. This
is the most economical way for constructing a cooling pond with an easy operation and
maintenance.
The diagram below shows the schematic diagram of the cooling pond. The dimension,
liner, inlet and outlet piping system are also shown in the diagram.
20 m
Inlet Outlet
1.73 m
HDPE
liner
CHAPTER II
2.1 INTRODUCTION
Upflow anaerobic sludge blanket (UASB) reactor is a column type tank reactor that will
be used in anaerobic process. It is widely used in industrial wastewater treatment in
chemical and sewage industries (Lier et al. 2015). The detailed design of UASB
requires some information. The hydraulic retention time (HRT) for UASB in treating
POME is about 10 days for an efficient production of biogas and chemical oxygen
demand (COD) removal (Ohimain et al. 2017). The volume required to contain POME
for 10 days is 5760 m3. To cater a large volume of POME, three identical UASB is
used. Each UASB with a volume of 2304 m3 with 20% extra as safety factor. The
calculation for UASB are done according to the formula by Bal et al. 2010.
Information Value
3
Inlet (m /h) 36
3
Inlet (m /day) 576
HRT (days) 10
HRT (hours) 240
3
Volume (m ) 5760
Number of Tanks 3
3
Volume of one tank (m ) 1920
Safety Factor (%) 20
Volume after extra (%) 2304
7
Since the designed UASB is a column type tank reactor, the ratio of H:D used is 3:1
(Clapp et al. 2018). The height and diameter are calculated using the volume formula
by assuming the UASB is a tall cylindrical tank.
2
D 2 D 2
V = Hπr = Hπ( ) = (3D)π( )
2 2
3 4V 3 4(2304)
D=√ =√ = 9.924 m
3π 3π
H = 29.77 m
The volumetric hydraulic load (VHL) is the volume of wastewater supplied daily into
the UASB per unit volume of the UASB.
Q
VHL = where Q = inlet volumetric flowrate of the UASB (m3/day)
V
576 m3 /day
VHL = = 0.25 m3 / m3 .day
2304 m3
Thus, the volumetric hydraulic loading rate of the POME into the UASB is 0.25 per
day
The volumetric organic load (Lv) is defined as the amount of organic matter supplied
daily to the UASB per unit volume of UASB. The influent substrate concentration (So)
is 51 kg COD/m3 (Zainal et al. 2017). The calculation for Lv is shown below.
8
Lv = 12.75 kg COD/m3.day
Thus, the organic loading rate of the organic material into the UASB is 12.75 kg/m3 per
day.
The sludge loading rate (Ls) referred to the amount of organic matter that is supplied to
the UASB per unit of biomass in the UASB. The total volatile solid in POME (M) is 34
kgVS/m3 (Zainal et al. 2017). The calculation for Ls is shown below.
Thus, the sludge loading rate into the UASB is 864 kg COD/kg VS per day.
Upflow velocity (ν) of the POME is calculated from the relation between the inlet
flowrate and the cross sectional area of the UASB. The calculation of ν is as shown
below.
Q
ν= where Q = inlet volumetric flowrate of the UASB (m3/hr)
A
36
ν= 9.924 2
= 0.4652 m/hr
(π)( )
2
9
Thus, the velocity if POME pumped into the UASB is about 0.4652 m/hr.
ExSo
Ceff = So - where Ceff = COD at the effluent (kg COD/m3)
100
The COD at the influent is 51 kg COD/m3 (Zainal et al. 2017) while the removal
efficiency of UASB is 96.5% for the HRT of 10 days (Ohimain et al. 2017).
(96.5)(51)
Ceff = 51 - = 1.785 kg COD/m3 = 1785 mg COD/L
100
It can be assumed that the BOD is about 50% of the COD for POME (Chong et al.
2018). The BOD for effluent from POME is 892.5 mg COD/L.
= 2641.66 mg/L
The amount of sludge produced is highly related to the COD of the POME inlet. The
production of solid sludge can be calculated by using the equation below.
The yield of solid can be assumed at 0.2 kgTSS/day since POME is high in COD
The gas hood will be located at the top of the UASB. The main function of the gas hood
is to collect the biogas. The area of gas hood interface is calculated from the equation
below.
Qg
Kg = where, Kg = biogas release rate (m3gas/m2.hr)
Ai
106.522
5 = Ai
11
106.522
Ai = = 21.304 m2
5
𝐷 2
Ai = π ( 2 )
A 21.304
D= 2√ π = 2√ = 5.2 m
π
Thus, the area and diameter of the gas hood is 21.3 m2 and 5.2 m respectively.
12
CHAPTER III
3.1 INTRODUCTION
Settling tank is a low cost technology that is widely used in a wastewater treatment
plant to remove solid from wastewater. Sufficient time have to be allowed for the
settling of solid to take place (Rozema 2015). Settling tank is located right after the
UASB in our plant. The main function of this settlement tank is to remove the sludge
from the anaerobically treated POME. The HRT in the settling tank is about 10 hours
to allow the sludge to settle down efficiently. The characteristics of the sludge are as
shown in table below.
Settling velocity is the speed of the particle to settle down in the settling tank. The
settling velocity of the sludge particle have to be calculated as shown below by referring
formulas from Rozema 2015.
= 0.27 inches/min
Thus, the settling velocity of the sludge particle in the settling tank is 0.27 inches/min.
The area of the settling tank can be calculated by using the settling velocity of sludge
particle and inlet volumetric flowrate of anaerobically treated POME. The calculation
is as shown below by referring the formula from Rozema 2015.
Q
A = 1.604 × V where, A = Area of settling tank (ft2)
p
m3 264.17 gal 1 hr
Q = 36 × 3 × =158.508 gal/min
hr 1m 60 mins
158.508
A = 1.604 × =941.65 ft2
0.27
A = 87.48 m2
The settling tank that will be used in our plant is an open cylindrical shape.
A = πr2
A 87.48
r = √ =√ = 5.276 m
π π
14
The volume of settling tank is calculated by using the flowrate into the settling tank and
20% as the safety factor for volume.
= 36 m3/hr × 10 hr × 1.2
= 432 m3
The height of the settling tank is calculated by using the volume and area.
V = AH
V 432 m3
H = =
A 87.48 m2
= 4.94 m
Thus, the diameter and height of the settling tank is 10.55 m and 4.94 m respectively.
1.1 INTRODUCTION
MBBR reactor is an open tank for aeration process in order to produce bioflocculant by
using specialised bacteria which is Bacillus marisflavi. Moving bed biofilm reactor
(MBBR) is an advanced wastewater treatment technology that gives high treatment
efficiency with low operating and maintenance cost and robust operation procedure. The
effectivity of removing up to 90% of chemical oxygen demand and 95% of biological
oxygen demand with nutrients from effluent stream had been proven when there is
sufficient retention time (Jenkins and Sanders 2012). Moreover, the process is based on bio
carriers that will attract the biomass and grow them on the surface (Ødegaard et al. 2000).
Other specialty is that the bio carriers can be used up to 10 years and can be operated
continuously without the need for backwashing, and low head-loss. ((Rusten et al. 1998).
The biofilms that grows on the surface of the bio carriers would suspended throughout the
entire volume of the reactor (Qiqi et al. 2012). Furthermore, MBBR reactor is better than
other aerated reactors such as membrane bioreactor (MBR), activated sludge process (ASP)
and sequencing batch bioreactor (SBBR) in terms of operating cost, efficiency of suspended
solids removal and installation space required. MBBR reactor takes up small space as it can
maximizes surface area through the carriers.
Figure 11.1 Schematic showing the principles of MBBR reactor
Vessel design for MBBR reactor are separated into few parts according into its design
specification. Every value and assumptions that have been made are comes with evidence.
1.2.1 Material selection
MBBR reactor is operating at 1.01 bar with temperature 30oC. The material that will be
used to construct MBBR reactor is poured reinforced concrete grade M30. Concrete been
choose as the construction material because this reactor need to hold up a huge volume of
sludge with 24 hours HRT. The volume of the tank is 979m3 while considering the safety
factor. Concrete is the best material to be choosen as it could hold high volume of sludge
and can winstand a good amount of tensile stress. Mix ratio for cement to sand to aggregate
for this concerete is 1:0.75:1.5. The compressive strength of M30 concrete is 4350psi.
The mechanical design of MBBR reactor is subjected under ASME internal pressure
procedure and EUROCODE 2 for concrete materials. MBBR reactor is lie under internal
pressure because its absolute pressure is higher than atmospheric pressure. MBBR reactor
in an open tank and rectangular in shape. It consist of air diffuser at the bottom of the tank
and MBBR carrier that will be poured before the process start. This tank is embedded on
the floor.
Criteria Value
Operating pressure, Po 1 bar
Operating temperature, T 30oC
Joint efficiency, E 1 ( full radiography)
Corrosion allowance, CA 2 mm
Length, L 14.5 m
Width, W 9.79 m
Height, h 6.9 m
h = Height, ft
PD = 25.01 psi
Diffuser design for an aerobic system is considering few aspects such as length of manifold,
number of laterals, size of diffuser hole and etc. Calculation for diffuser design is shown
below.
𝑄𝑎𝑖𝑟,𝑡𝑜𝑡𝑎𝑙
𝑡𝑜𝑡𝑎𝑙 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑜𝑟𝑖𝑓𝑖𝑐𝑒 = = 8000 𝑜𝑟𝑖𝑓𝑖𝑐𝑒
𝑄𝑜𝑟𝑖𝑓𝑖𝑐𝑒,𝑚𝑎𝑥
𝐿𝑚𝑎𝑛𝑖𝑓𝑜𝑙𝑑
𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑙𝑎𝑡𝑒𝑟𝑎𝑙𝑠 𝑝𝑒𝑟 𝑚𝑎𝑛𝑖𝑓𝑜𝑙𝑑 = + 1 = 27(𝑖𝑛𝑡𝑒𝑔𝑒𝑟)
𝐿𝑑𝑖𝑓𝑓𝑢𝑠𝑒𝑟 𝑠𝑝𝑎𝑐𝑖𝑛𝑔
Ldiffuser spacing is typically starts at the largest interval. After considering the size for
the oxygen inlet to the manifold, the Lmanifold is reduced and the total number of laterals for
manifold for this process is 24 laterals. Lorifice spacing is generally taking at the minimum
spacing which is 38mm.
3672
𝑎𝑖𝑟 𝑓𝑙𝑜𝑤𝑟𝑎𝑡𝑒 𝑝𝑒𝑟 𝑜𝑟𝑖𝑓𝑖𝑐𝑒, 𝑄′𝑜𝑟𝑖𝑓𝑖𝑐𝑒 = = 1.7 𝑚3 /ℎ𝑟
2160
Q’orifice is 1.7 m3/hr which is higher than Qorifice, min and lower than Qorifice,maz. The
value is acceptable as it is in the range for the air flowrate per orifice.
1.75 − 1.7
𝑝𝑒𝑟𝑐𝑒𝑛𝑡𝑎𝑔𝑒 𝑒𝑟𝑟𝑜𝑟 = × 100 = 2.85%
1.75
Calculated perecentage error is 2.85% and it is lower than 5%. The value is
acceptable.
𝑄𝑎𝑖𝑟 𝑓𝑙𝑜𝑤
𝑎𝑖𝑟 𝑓𝑙𝑜𝑤 𝑣𝑒𝑙𝑜𝑐𝑖𝑡𝑦 =
𝐴𝑚𝑎𝑛𝑖𝑓𝑜𝑙𝑑 × 𝑁𝑔𝑟𝑖𝑑,𝑤𝑖𝑑𝑡ℎ × 𝑁𝑔𝑟𝑖𝑑,𝑙𝑎𝑡𝑒𝑟𝑎𝑙
3672
= = 17309.1 𝑚/ℎ𝑟
22 0.3 2
( 7)×( 2 ) ×3×1
17309.1
𝑎𝑖𝑟 𝑓𝑙𝑜𝑤 𝑣𝑒𝑙𝑜𝑐𝑖𝑡𝑦 = = 4.8 𝑚/𝑠
3600
MBBR carrier is to provide a surface where biofilm can grow. Type of material for MBBR
carrier is high density poly ethylene (HDPE) material. This material been choose because
it have almost same density as water and it could been process easily in MBBR reactor.
Type of biocarrier is PE01 that have 4 room with diameter and height are 12 mm and 9 mm
respectively. By the rule of thumb, 60% of reactor is media and 40% is water. This MBBR
carrier can be used up to 10 years and could have high biofilm load,
Thickness for concrete wall is been verified based on three criteria. First, wheather the wall
is exterior or interior. In this case, the wal for MBBR reactor is fall to interior wall as is
play less inposrtant role in insulating the reactor from heat and cold. Second, what are the
wall is made of. It is either strong or weak materials. Strong materials need thinner wall
and vice versa. Lastly, the climate. As our production is in Malaysia that have tropical
climates, thinner walls is preferable. Value of thickness for the wall is based on nominal
thickness of concrete wall. Table below show the minimum thickness for few types of
concrete wall.
Based on the table above, the minimum thickness for the concrete wall of MBBR
reactor is 12.5 cm.
Type of pipe support for manifold pipe is pipe shoe clamp. It is choosen as it can stop pipes
from rubbing against dissimilar metals. It means that they are able to prevent
electrochemical transfer and galvanic corrosion. It also keep insualtion from grinding
against objects or rupturing. In the same way, they should minimize the movement and
wear that comes with heat transfer.
1.2.8 Combined loading
Combined loading must be designed to winstand the worst combination of loading without
failure. A trial thickness is assumed based on the calculated and resultant stress from all
loads determined to ensure that the maximum allowable stress intensity is not exceeded at
any point.
a. Primary stress
P = 0.1 N/mm2
Di = 14500 mm
t = 125 mm
𝑃𝐷𝑖
σL = = 1.8125 𝑁/𝑚𝑚2
4𝑡
𝑃𝐷𝑖
σh = = 3.625 𝑁/𝑚𝑚2
2𝑡
𝑊
σw =
𝜋 (𝐷𝑖 + 𝑡)𝑡
Where ;
W = Wv + WI ;
𝑊𝑣 = 240𝐶𝑣 𝐷𝑚 (𝐻𝑣 + 0.8𝐷𝑚 )𝑡
Cv = 1.02 m
Dm = 14.7 m
Hv = 6.9 m
Hence, Wv = 19072 N
Direct stress, σw = 0.0016 N/mm2
𝑀 𝐷
σb = ± 𝐼 ( 2𝑖 + 𝑡)
𝑣
𝑊𝑥 2
𝑀=
2
x = Hv = 6.9 m
Deff = 14.9 m
Pw = 1280 N/m2
W = 19072 N/m
M = 454008.96 Nmm
π
Iv = 64 (Do 4 − D1 4 ) = 2.49 x 1014 mm4
The torsional shear stresses can be neglected in preliminary vessel design because these loads will
normally be small, where, τ = 0
1
σ1 = 2 [σh + σz + √(σh − σz )2 + 4τ2 ]
1
σ2 = 2 [σh + σz − √(σh − σz )2 + 4τ2 ]
= 3.65 N/mm2 = σh
1
σ2 = 2 [𝜎ℎ + 𝜎𝑧 − √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
= 3.625 N/mm2 = σh
1
σ2 = 2 [𝜎ℎ + 𝜎𝑧 − √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
= 1.79 N/mm2 = σz (downwind)
c. Maximum allowable stress intensity (∆σMAX)
Assume τ = 0, σ3 = 0.5
For upwind condition,
σ1 – σ3 = 2.9 N/mm2
Hence, the maximum allowable stress intensity, (∆σmax) = 2.9 N/mm2. According to
EUROCODE 2, maximum allowable stress at temperature 303 oF is S = 30 N/mm2 . Since,
(∆σmax) = 2.9 N/mm2 ˂ S = 30 N/mm2, therefore, the design is safe to use.
d. Elasticity stability
E t
Critical buckling stress, c
31 v2 R
p
Modulus of elasticity, E of concrete M30 is 5.47 N/mm2.
σc = 355.06 N/mm2
(∑ 𝜎) = 0.015 𝑁/𝑚𝑚2
𝑐𝑜𝑚𝑝𝑟𝑒𝑠𝑠𝑖𝑣𝑒
Since the value of (∑ 𝜎)𝑐𝑜𝑚𝑝𝑟𝑒𝑠𝑠𝑖𝑣𝑒 ˂ σc, therefore, the design is safe to use.
From the analysis of combined loading, the material we chose has fulfilled both
requirements of maximum stress intensity and elastic stability:
The anchor bolts are assumed to share the overtuning load equallt and the bolt area
required :
1 4Ms
Ab = [ − W]
Nb fb Db
With, Ab = area of one bolt at the root of the thread, mm2
Nb = number of bolts
fb = maximum allowable bolt stress, N/mm2
Ms = bending moment at the base, Nm
W = weight of the vessel, N
Db = bolt circle diameter, m
Bolt spacing = 2278.57 mm. Bolt spacing > 600 mm, therefore the bolt spacing is
acceptable.
1 4Ms
Ab = [ − W]
Nb fb Db
1 4(90410.92 )
Ab = [ − 6502.24 ]
8 × 125 1.574
Ab = 176.95 mm2
Taking the bearing pressure as 3.5 N/mm2, the minimum width of the base ring, Lb
Fb 1
Lb = × 3
fc 10
Lb = 0.9 mm
The required thickness for thickness base ring is found by treating the ring as cantilever
beam:
3𝑓𝑐′
𝑡𝑏 = 𝐿𝑟 √
𝑓𝑟
Take Lr = 76 mm,
Actual width required = Lr + ts + 50 mm
= 171 mm
𝐹𝑏
𝑓𝑐′ = = 18.52 N/mm2
171
3𝑓 ′
Base ring thickness, tb = 𝐿𝑟 √ 𝑓 𝑐
𝑟
= 103.4 mm
1.2.10 Flanged joint
Flanged joints are used for connecting pipes to the vessels. Type of flanged joints that been
used for this reactor is slip on flanges. It is preferred because of it is the cheapest compared
to other type of flanges, easy adjustment and it is generally used for pipe work. This flanges
joint is located at the inlet and outlet stream. Type B flanges is for inlet and outlet of liquid
and type A flanges is for the gas stream inlet at the bottom of the tank.
Type BC(mm) R(mm) H(mm) T(mm) T1(mm) T2(mm) B(mm) OD(mm) ID(mm)
A 298.45 269.75 246.13 44.45 26.29 42.93 22.35 342.9 221.49
B 431.80 381.00 365.25 55.62 30.27 54.10 25.4 482.6 327.15
1.3 SUMMARY
Table below shows the overall calculation that related to the measurement for MBBR
reactor construction
Table 11.4 Summary of MBBR reactor
0.015< 355.06
Area of one bolt, Ab mm2 176.95
Distance from the edge of the skirt to the outer edge of m 0.076
the ring, Lr
Actual width required, Lb m 0.905
Base ring thickness, tb m 0.103
Type of flanged joint - Slip on flange joint
SCRUBBER
1.4.1 Introduction
Gas scrubber is used to separate hydrogen sulphide from biogas. It is located after UASB
reactor where the biogas been produced. Sodium hydroxide is act as solvent to be reacted
with hydrogen sulphide and will be out as bottom product as lean sodium hydroxide. At the
top product of gas scrubber, methane and carbon dioxide will be produce and being
transferred to the next equipment to further the process
Random tower packing column is selected as they are not limited to reduction of
pressure drop throughout the column (Gurbilek 2013). It also could have high capacity
compared to trays column that have same efficiency. Type of liquid distributors used is
gravitational type such as orifice distributor as it promote better contact compared to spray
nozzles (Barbour et al. 1995).
Stainless steel SA-240 is chosen as it provide good corrosion resistance towards acids with
good weldability. It also could provide good area reduction rate at low temperature. It is
also good to resist intergranular corrosion (International Stainless Steel Forum 2012).
SR-101 will be constructed in cylindrical shape for the middle with ellipsoidal shape for
head and bottom of the shell. Below are the design parameters of scrubber.
Operating pressure of scrubber is higher than atmospheric pressure and resulting it to have
internal pressure. Design pressure of each part of the vessel is being calculated by using PD
= PO + 0.433h where h is the height of each part of the column. Safety factor of 10% is
taken.
PJ = 1.1Po
Pgage = Po - Patm
Ellipsoidal height, he
𝐷𝑖 1.49
he = = = 0.037 m
4 4
ℎ
L = ℎ𝑐 + 2 ( 3𝑒 ) = 4.49 m
As there is no corrosive material pass through SR-101, corossion allowance that could be
consider is 2mm(0.0785 in).
The wall thickness, t for each part of the pressure vessel has to be calculated in order to get
the minimum wall thickness, tmin under internal pressure.
Based on stainless steel gauge thickness, gauge number 10 has been chosen as it have the
closest nominal thickness to the minimum thickness from the calculation. The nominal
thickness is 3.571mm which is slightly higher than minimum thickness.
The maximum allowable working pressure for each of vessel part, MAWPp is the maximum
internal pressure including the static head pressure. However, any metal thickness
considered as corrosion allowance must be excluded from the calculation.
1.5.1 Introduction
Gas holder, GH-101 act as holding tank for the gas such as methane and cabon dioxide
before distribute it to reactor for further process. HRT for the gases in gas holder is 24
hours. Gas holder is located before the chemical stream process for methanol because to
ensure that the biogas is stored and have enough amount of biogas to be operated to produce
methanol. The gas holder containing biogas that already free from hydrogen sulphide that
make it less toxic and less corrosive gas. Volume of gas holder by considering safety factor
is 7904 m3.
Type of material for conctructing gas holder is stainless steel 304. This material have higher
melting point compares to other type of stainless steel and could store biogas. It is also not
cause harmful to the people either during production or use (R.C Bourg, 2012)
GH-101 will be contstructed in cylindrical shape with flat head for top and bottom of the
shell. Below are the design parameters for the gas holder.
PJ = 1.1Po
Pgage = Po - Patm
Table 2.2 Design pressure for each part of gas holder SR-101
Type of part PD (bar) PJ (bar)
Cylindrical shell 2.32 2.55
As there is no corrosive material pass through SR-101, corossion allowance that could be
consider is 2mm(0.0785 in).
The wall thickness, t for each part of the pressure vessel has to be calculated in order to get
the minimum wall thickness, tmin under internal pressure.
Based on the nominal thickness in the market, the thickness of the vessel is 10mm and it is
slightly higher that calculated minimum thickness of the vessel.
1.5.5 Maximum Allowable Working Pressure
The maximum allowable working pressure for each of vessel part, MAWPpart is the
maximum internal pressure including the static head pressure. However, any metal
thickness considered as corrosion allowance must be excluded from the calculation.
The smallest value of MAWPpart is been chosen to become MAWPvessel. Thus, MAWPvessel
is 2.72bar
Packed bed reactors are commonly used in chemical reactions whereas it is filled with solid
catalyst particles that most often used to catalyse gas reactions. The syngas reactor is located
right after the gas holder (GH-101) where biogas are been stored after hydrogen sulphide
scrubbed away from it. The methane and steam will be converted into syngas at 80%
conversion in this reactor (R-101). The catalyst used for this reaction is NiO/α-Al2O3
Table 1.1 The inlet and outlet stream for each component for R-101
Reaction:
The rate law for the reaction is a first order reactor, therefore,
−𝑟𝑎 ′ = 𝑘𝑃𝑎
= 𝑘𝑅𝑇𝐶𝑎
Stoichiometry,
𝑃
𝑣 = 𝑣𝑒 (1 + 𝜀𝑋) ( 𝑃𝑜 )
𝐹𝑎
𝐶𝑎 = 𝑣
𝐶𝑎𝑜 (1−𝑋) 𝑃𝑜 𝐶𝑎𝑜 (1−𝑋)
= ( 𝑃 )= 𝑦
1+𝜀𝑋 1+𝜀𝑋
𝑃𝑜
where y = 𝑃
(13.88)(0.8)
𝑉=
1870(1 − 0.4)(8.38 + (−0.681) + (−0.688))
= 0.0917 m3
1
𝑉 = [𝜋(𝐷2 )(3𝐷)]
4
By taking ratio height shell to diameter 1:4 where Hvessel = 4D while taking ratio 1:2 for
diameter to height head for both bottom and top, D = 2Hhead. Hence, the height for packed
bed reactor is 1.05 m with 0.0875 m head height for both bottom and top.
Condition Values
Operating pressure, Po 25 bar (362.6psi)
Temperature, T 973.15K (700oC)
Length Shell 1.05 m
Length Vessel 1.225 m
Diameter 0.35 m
1.1.3 DESIGN OF BED
Pressure drop for packed bed reactor are calculated using Ergun equation as below;
∆𝑃 𝑉(1 − 𝜀)2 𝜌𝑓 𝑉 2 (1 − 𝜀)
= 150 2 2 + 1.75
𝐿 ∅𝑠 𝐷𝑝 𝜀 3 ∅𝑠 𝐷𝑝 𝜀 3
Table 1.3 shows the summary of the calculation for design of packed bed reactor R-101.
Parameter Results
Operating pressure 25 bar
Operating temperature 750 °C
Height of reactor, H 1.225 m
Diameter of reactor, D 0.35 m
Volume for reaction 0.108 m3
Height of bed, Hbed 0.735 m
Diameter of bed, Dbed 0.35 m
Weight of catalyst 141.372 kg
Pressure drop, ∆𝑃 0.083 bar
The methanol forming reactor is located right after the compressor (K-104) where the mixture
of recycle gas and syngas produced from R-101 are compressed to 250oC and 50 bar. The
methanol are been forming inside this reactor using the feed from syngas. The catalyst used for
this reaction is Cu/ZnO/Al2O3 and it is endothermic reaction so there are no temperature
changes inside this reactor
Stream 61
60
R-102
60
Stream 60
Table 1.4 The inlet and outlet stream for each component for R-102
60
Substance Inlet (Stream 60), Outlet (Stream 61), Density, kg/m3
kg/h kg/h
149.0 149.0 0.656
Methane
Methanol 1.2 181.4 792
Water 136.4 237.7 997
Carbon Monoxide 381.4 381.4 1.14
Hydrogen 51.6 17.6 0.0899
Carbon Dioxide 449.2 201.8 1.98
Total 1168.80 1168.85
Reaction:
Stoichiometry,
𝑃
𝑣 = 𝑣𝑒 (1 + 𝜀𝑋) ( 𝑃𝑜 )
𝐹𝑎
𝐶𝑎 = 𝑣
𝐶𝑎𝑜 (1−𝑋) 𝑃𝑜 𝐶𝑎𝑜 (1−𝑋)
= ( 𝑃 )= 𝑦
1+𝜀𝑋 1+𝜀𝑋
𝑃𝑜
where y = 𝑃
𝐹𝑜 𝑋
𝑉=
ρc (1 − e)(−r)
(20.58)(0.8)
𝑉=
1190(1 − 0.285)(8.38 + (5.63) + (2.443))
= 0.136 m3
1
𝑉 = [𝜋(𝐷2 )(3𝐷)]
4
By taking ratio height shell to diameter 1:4 where Hvessel = 4D while taking ratio 1:2 for
diameter to height head for both bottom and top, D = 2Hhead. Hence, the height for packed
bed reactor is 1.10 m with 0.0915 m head height for both bottom and top.
Condition Values
Operating pressure, Po 50 bar (725.2 psi)
Temperature, T 523.15K (250oC)
Length Shell 1.10 m
Length Vessel 1.283 m
Diameter 0.366 m
Pressure drop for packed bed reactor are calculated using Ergun equation as below;
∆𝑃 𝑉(1 − 𝜀)2 𝜌𝑓 𝑉 2 (1 − 𝜀)
= 150 2 2 + 1.75
𝐿 ∅𝑠 𝐷𝑝 𝜀 3 ∅𝑠 𝐷𝑝 𝜀 3
Table 1.3 shows the summary of the calculation for design of packed bed reactor R-102.
Parameter Results
Operating pressure 50 bar
Operating temperature 250 °C
Height of reactor, H 1.283 m
Diameter of reactor, D 0.366 m
Volume for reaction 0.108 m3
Height of bed, Hbed 0.7698 m
Diameter of bed, Dbed 0.366 m
Weight of catalyst 127.63 kg
Pressure drop, ∆𝑃 0.0479 bar
The mixer M-101 are located right after centrifuge CF-101 which is the biomass is been
removed from the wastewater. The function of the mixer is to mix the wastewater that contains
bioflocculant with ethanol. This process will make the bioflocculant to solidify and occurs at
30oC and 3 bar.
Stream 37a
Stream 36
Stream 38
Table 1.7 The inlet and outlet stream for each component for M-101
H/D ratio = 2
D = Di = 5.94 m
H = 2 (5.94) = 11.88m
1 1
Impeller width, Wi 𝑊𝑖 = 𝐷= (5.94) = 0.40 𝑚
5 5
1 1
Diameter impeller, Di 𝐷𝑖 = 𝐷= (5.94) = 1.98 𝑚
3 3
1 1
Height of impeller from vessel floor, C 𝐶= 𝐷= (5.94) = 1.98 𝑚
3 3
1 1
Length of impeller width, Li 𝐿𝑖 = 𝐷= (5.94) = 0.50 𝑚
4 4
2 2
Diameter of impeller base, Dd 𝐷𝑑 = 𝐷= (5.94) = 1.32 𝑚
3 3
Table 1.3 shows the summary of the calculation for design of mixer M-101.
Parameter Results
Operating pressure 3 bar
Operating temperature 30 °C
Volume of mixer 328.6 m3
Height of mixer, H 11.88 m
Diameter of mixer, D 5.94 m
Impeller width, Wi 0.40 m
Diameter of impeller, Di 1.98 m
Height of impeller above vessel floor, C 1.98 m
Length of impeller, Li 0.50 m
Diameter of impeller base, Dd 1.32 m
Thickness of disc, x 0.08 m
1
CHAPTER I
Kettle reboiler (H-101) is used in steam generation for the syngas reforming reaction. In
this reboiler, steam will be generated from water at 2 bar.
Design Calculation
Physical properties of the process fluid (water) at 2 bar are shown in Table 1.1.
Assume heat loss is 5%, maximum heat load (duty) = 1.05 x 167.44 = 175.81 kW
Assume U equal to 1000 W/m2 ∙°C and both shell and tube sides are isothermal
(Sinnott 2005), steam is available at 3 bar and steam saturation temperature is 133.6°C.
Minimum bend radius is taken as 45mm and proposed layout gives 30 U-tubes, tube
outer limit diameter is 510 mm.
Boiling coefficient,
3 3 3
Hnb = 0.104 (220.6)0.69(13.39 x103)0.7[1.8 (220.6)0.17 + 4 (220.6)1.2 +10 (220.6)10]
3
=2965.7 W/m2∙°C
Steam condensing coefficient and steam fouling coefficient is 8000 W/m2∙°C and
5000 W/m2∙°C. Water fouling coefficient is 6000 W/m2∙°C and tube material is carbon
steel, kW = 55 W/m∙°C (Sinnott 2005).
30
1 1 1 30x10−3 ln
= + + 25 + 30 ( 1 + 1 )
𝑈𝑂 2965.7 6000 2 ∗ 55 25 5000 8000
UO = 1078.7 W/m2∙°C
The deviation from the original estimate of 1000 W/m2∙°C. is only 5.6% , the design
is acceptable.
Take liquid level as 600mm from base, free board = 1010- 600 = 410mm
410 mm
600 mm
510mm
Phase separator (S-102) in the process is to separate liquid from the gaseous mixture
containing methane, carbon dioxide, carbon monoxide, hydrogen, before the further
separation of the methanol from the waste water in distillation column (C-101). The inlet
of the phase separator consists of methane, carbon dioxide, carbon monoxide, hydrogen,
water and methanol. At the end of the separation, water and methanol will be leave as
bottom product while methane, carbon dioxide, carbon monoxide, hydrogen, and some
amount of water and methanol will leave as top product. The inlet temperature and pressure
of the stream are 50 oC and 30 bar. Figure 1.3 shows the phase separator to be designed and
the flow rate of each component at the inlet and outlet after flash calculation . In order to
know the vapor fraction of the phase separator, isothermal flash calculation is being done
first. F63CH4 = 149 kg/h
F63CD = 201.8 kg/h
F63CM = 381.4 kg/h
F63H = 17.6 kg/h
F62CH4 = 149 kg/h F62W = 1.8 kg/h
F62CD = 201.8 kg/h F62M = 6.4 kg/h
F62CM= 381.4 kg/h
F62H = 17.6 kg/h
F62W = 237.7 kg/h
F62M= 181.4 kg/h
F66W = 235.9 kg/h
F66M = 175 kg/h
Then by using Roult’s law, find the K-value for each compenent,
Ki = Psat/P
Make an initial guess for the vapor fraction, V which is ranging from 0 to 1 and
iterative procedure is repeated until total moles of vapor with its mole fraction, y is 1. Table
1.2 shows the Vguess and the ∑y obtained. ∑y is 1 when vapor fraction is at 0.64. After
obtaining the V and y value, x can be calculated. Table 1.3 shows the summary of the
calculation.
zi K i
∑ yi = ∑ =1
1 + V(K i − 1)
i i
xi = yi/Ki
Vguess ∑y
0.83 1.1
0.72 1.07
0.64 1
Vessel Diameter
Physical properties of the liquid and vapor in the vessel were determined and shown in
table In order to start calculating the diameter and height of the phase separator, some of
the physical properties of the streams need to be determined first.Table 1.4 shows the
physical properties needed to calculate the diameter and height of vessel.
Terminal velocity,
ut = 0.58 m/s
As the separation design at k value already includes an exit mist eliminator, a design
factor of 100% is apply. Thus, ut = ud = 0.58 m/s
Dv calculated is too small, iteration have been made and vessel diameter is 0.86m.
Vessel Height
Figure 1.4 shows the schematic diagram of phase separator. The height of the separator will
be calculated by section as shown in the diagram.
h7
h6
D
h5
h4
h3
h2
h1
For height from low liquid level (LLL) to bottom tangent line, h1,
V = 0.00013 x 25 x 60 = 0.195 m3
For surge height or height from normal liquid level (NLL) to HLL, hn
hn = 0.078 m
h2 = hL + hn =0.466 m
For height from HLL to the inlet nozzle, if h3 calculated is less than 0.3, then h3 is 0.3m.
For inlet nozzle diameter, if h4 calculated is less than 0.4064m, then set h4 at
0.4064m.
𝑣𝐿
λ=𝑣 = 0.001
𝐿 +𝑣𝑉
Where vm = vL + vv (m3/s),
ρm = ρL λ + ρV (1 − λ) (kg/m3)
h6 = 0.15 m
For height from mist eliminator to the top tangent line, if h7 calculated is less than
0.3 m, set h7 at 0.3 m.
Height of separator,
hT = h1 + h2 + h3 + h4 + h5 + h6 + h7
hT = 2.37 m
VT = π(Dv/2)2hT = 1.367 m3
Table 1.5 shows the summary of the results obtained from manual calculation of the
phase separator S-102.
Phase separator (S-101) in the process is to separate liquid from the gaseous mixture
containing methane, carbon dioxide, carbon monoxide, hydrogen, water and methanol
before the material stream flow into the compressor. This is to reduce the risk of compressor
failure due to liquid in the compressor. This separator serve as a knock out drum before the
gas compression. The inlet of the phase separator consists of methane, carbon dioxide,
carbon monoxide, hydrogen and water. At the end of the separation, small amount of water
will leave as bottom product while methane, carbon dioxide, carbon monoxide, hydrogen,
and water will leave as top product. The inlet temperature and pressure of the stream are
350 oC and 3 bar. Figure 1.5shows the phase separator to be designed and the flow rate of
each component at the inlet and outlet after flash calculation . In order to know the vapor
fraction of the phase separator, isothermal flash calculation is being done first.
Then by using Roult’s law, find the K-value for each compenent,
Ki = Psat/P
Make an initial guess for the vapor fraction, V which is ranging from 0 to 1 and
iterative procedure is repeated until total moles of vapor with its mole fraction, y is 1. Table
1.6 shows the Vguess and the ∑y obtained. ∑y is 1 when vapor fraction is at 0.49. After
obtaining the V and y value, x can be calculated. Table 1.7 shows the summary of the
calculation.
zi K i
∑ yi = ∑ =1
1 + V(K i − 1)
i i
xi = yi/Ki
Vguess ∑y
0.9987 1
Vessel Diameter
Physical properties of the liquid and vapor in the vessel were determined and shown in
table In order to start calculating the diameter and height of the phase separator, some of
the physical properties of the streams need to be determined first.Table 1.8 shows the
physical properties needed to calculate the diameter and height of vessel.
Terminal velocity,
ut = 3.243 m/s
15
As the separation design at k value already includes an exit mist eliminator, a design
factor of 100% is apply. Thus, ut = ud = 3.243 m/s
Dv calculated is too small, iteration have been made and vessel diameter is 0.71 m
Vessel Height
Figure 1.6 shows the schematic diagram of phase separator. The height of the separator will
be calculated by section as shown in the diagram.
h7
h6
D
h5
h4
h3
h2
h1
For height from low liquid level (LLL) to bottom tangent line, h1,
For surge height or height, hn from normal liquid level (NLL) to HLL, hn
hn = 1.4958 x10-5 m
For height from HLL to the inlet nozzle, if h3 calculated is less than 0.3, then set h3 at 0.3m.
For inlet nozzle diameter, if h4 calculated is less than 0.4064m, then h4 is 0.4064m.
𝑣𝐿
λ=𝑣 = 0.001
𝐿 +𝑣𝑉
Where vm = vL + vv (m3/s),
ρm = ρL λ + ρV (1 − λ) (kg/m3)
h6 = 0.15 m
18
For height from mist eliminator to the top tangent line, if h7 calculated is less than
0.3 m, set h7 at 0.3 m.
Height of separator,
hT = h1 + h2 + h3 + h4 + h5 + h6 + h7 = 1.968 m
VT = π(Dv/2)2hT = 1.1 m3
Summary of Calculation
Table 1.9 shows the summary of the results obtained from manual calculation of the phase
separator S-2.
A desiccant air dryer uses special drying agent beads (silica gel) to absorb water vapor
from an air stream. Silica gel is regenerative so that the drying agent doesn’t need replacing
in order to provide vapor-free compressed air consistently. Figure 1.7 shows the schamatic
diagram of belt press.
F33 W = 1516.7 kg/h
Design Detail
In desiccant dryer, the air intake from the atmosphere is first dehumidified before used as
to dry bioflocculant in rotary dryer. The flowrate of the sludge is 1516.7 kg/h which is
equivalent to 1.517m3/hr. Based on the details provided, desiccant dryer model D-2 from
Van Air Systems can be adapted in this process and the specification is shown in table 1.10.
.
The bioflocculant is is being dried from 49% initial moisture to 10% final moisture in rotary
dryer. Hot air enters at 135°C with a humidity of 0.015.The exit gas temperature is 90°C
with a humidity of 0.097. The exit solid has a temperature of 80°C while bioflocculant
enter the dryer at 30°C. The diagram of rotary dryer is shown in figure.
GS = 1516.7kg/hr
Y1
F42 W = 40.3 kg/h
F40 W = 77.1 kg/h F42 BF = 329.2 kg/h
F40 E =248.6 kg/h
F42 BF = 248.6 kg/h
Figure 1.8 Rotary Dryer, D-101
Design calculation
The equation above is the enthalpy equation in the rotary dryer and the parameter
of the drying process is shown in table 1.11 (Mujumdar & Hall 2006; Sinnott 2005). Figure
1.9 shows the solid and gas temperature profiles in a counter-current rotary dryer.
Figure 1.9 Solid and gas temperature profiles in a counter-current rotary dryer.
22
Calculation of diameter of the shell need to be performed to obtain the rotating shell
diameter.
Humid volume of the inlet gas (135°C, Y2 = 0.015), VH2 = 0.15 m3/kg dry air
Humid volume of the exit gas (90°C, Y1 = 0.098), VH1 = 0.062 m3/kg dry air
Total volume needed maximum volumetric flowrate with 10% more volume for
minor process upset. Total volume is 5.03 m3. Take the maximum superficial air velocity
to be 1.2 m/s (this is 20% less than the maximum allowable velocity since part of the dryer
is filled with the moving solid, and the entire cross-section is not available for gas flow).
Diameter, d = 2.3m.
The dryer is considered to consist of three zones as shown in Figure 1.9. The temperature
and humidity or moisture content of the streams can be obtained by material and energy
balance.
23
i. Zone III
Only heating of the solid occurs in this zone; there is little water left for vaporization. At
the boundary between zones III and II, the solid is at TSB (= TSA) = 41°C
Humid heat of the gas entering zone III, CHB = [1.005 + (1.88) x (0.015)] = 1.033
kJ/kg.∙K (this remains constant in zone III, since the humidity does not change in this
section).
TGB = 133°C
At the boundary B, ∆TB = 133 – 41 = 92°C, at end 2, ∆T2 = 135 – 100 = 35°C
Log mean temperatur in zone III (∆T)m = (92 – 35)/[ln(92 – 35)] = 14.14°C
Number of heat transfer units, (NtG)III = (T2 – TGB)/(∆T)m = (135 – 35)/14 = 0.126
24
ii. Zone II
In order to calculate (NtG)II, we need the value of TGA. This can be obtained by heat
balance.
TGA = 102.00°C
133 – 102
Number of heat transfer units, (NtG)II = (TGB - TGA)/(∆T)m = = 0.41
75.54
25
Before calculating (NtG)I, let us check the validity of the assumed value of the exit
gas temperature, TG1 = 90°C, by making an energy balance over zone I.
H’G1 = 173
TG1 = 86°C
iii. Zone I
Length of the dryer, L = (NtG) x (LT) = 3.07 x 10.42 = 31.99 m, round off to 32m.
Thus , the length of dryer is 32m and the diameter of the dryer is 2.3m
27
Belt press also known as belt press filteris an industrial machine, used for solid/liquid
separation processes, particularly the dewatering of sludges in the chemical industry.in this
proess water is separated from the sludge before the sludge can be dicharged as fertilisers.
Design Detail
In belt press, the slurry sludge is dewatered to produce fertilizers. The flowrate of the sludge
is 1311.5 kg/h which is equivalent to 1.311 m3/hr. Based on the details provided by FRC
System International, belt press model PC-7 from FRC can be adapted in this process. The
specification of belt press model PC-7 is shown in table 1.12.
Total flowrate that enter the cooler, CO-101 is 902.9 kg/h which are water, Methane, Carbon
Dioxide, Carbon Monoxide and Hydrogen.
53a 54
T1 =T492°C o
1 = 150 C
TT 2=
2 = 350°C
130o
C
T2 = 350°C
t2 = 121oC
o
t1t=
1=110 C
150°C
𝑇 −𝑇 492−350 𝑡 −𝑡 350−150
R = 𝑡1−𝑡2 = 350−150 = 0.71 S = 𝑇2 −𝑡1 = 492−150 = 0.58
2 1 1 1
Ft = 0.7
Tm = Ft Tlm = (0.7) (169.35) = 118.54ᵒC
𝑄 78.055𝑥103
Provisional area, A = 𝑈𝑇 = (100)(118.54) = 6.58 m2
𝑚
Choose internal diameter of 16 mm, outer diameter of 20 mm and length of 1.78 m as well as
carbon steel as the material.
Area of one tube = 𝜋𝑑𝐿 = 𝜋(20 𝑥10−3 )(1.78) = 0.11 m2
Tube
150+350
Mean Temperature = = 250 ℃
2
Total flow area, A = Number of tube per pass x Tube cross sectional area
= (29)(201.1x10^-6) = 0.005832 m2
𝑚 0.197
Tube velocity, ut = 𝜌𝐴 = (20.09)(0.005832) = 1.68 m/s
𝜌𝑢𝑑𝑒
Re = = 2.84E+04
𝜇
𝐶𝑝 𝜇
Pr = = 0.9235
𝑘𝑓
L/di = 111.25
According to figure 12.23 of Towler & Sinnot 2013,
jh = 0.0038;
Heat transfer coefficient, hi = 268.21W/m2 ᵒC
Shell
Choose 25 per cent baffle cut, from Figure 12.29 of Towler & Sinnot 2013,
jh = 0.0038
ℎ𝑖 𝑑𝑒 1
= 𝑗ℎ 𝑅𝑒𝑃𝑟 3
𝑘𝑓
Heat transfer coefficient, hs = 448.0938 W/m2 ᵒC
Overall Coefficient
The different between overall coefficient and initial assumed value is 26.13% which is in
between 0 to 30%, thus it is acceptable.
Pressure Drop (Tube)
= 333.0669 N/m2
= 0.04831 psi
= 76568.97 N/m2
= 11.1054 psi
Since the pressure drop for shell and tube is low thus the design for cooler (CO-101) is
satisfied.
Summary of Design
Parameter Value
Tube Side
Square pitch
Outer diameter, do (mm) 20
Inner diameter, di (mm) 16
Length of tube, L (m) 1.78
Area of one tube, At (m2) 0.11
Number of tubes 58
Number of tube passes 2
Linear fluid velocity, ut (m/s) 1.68
Heat transfer coefficient, hi (W/m2 ◦C) 268.21
Pressure drop, ∆Pt (kPa) 0.33
Shell Side
Pull-through floated head type
Number of shell passes 1
Bundle diameter, Db (mm) 264.82
Shell diameter, Ds (mm) 353.82
Baffle cut (%) 25
Baffle spacing, IB (mm) 79.76
Tube pitch, Pt (mm) 25
Equivalent diameter, de (mm) 14.2
Shell side Mass velocity, Gt (kg/sm2) 50.09
Heat transfer coefficient, hs (W/ m2 ◦C) 678.48
Pressure drop, ∆Ps (kPa) 12.15
Overall heat transfer coefficient, Uo (W/m2 ◦C) 301.79
Total flowrate that enter the Heat Exchanger, HE-103 is 1168.9 kg/h which are water, Methane,
Carbon Dioxide, Carbon Monoxide and Hydrogen.
61b
41d 41e
61
T1 =T250°C o
1 = 150 C
TT 2=
2 = 100°C
130o
C
T2 = 90°C
t2 = 121oC
o
t1t=
1=110 C
30°C
𝑇 −𝑇 250−100 𝑡 −𝑡 90−30
R = 𝑡1−𝑡2 = = 2.5 S = 𝑇2 −𝑡1 = 250−30 = 0.2727
2 1 90−30 1 1
Ft = 0.85
Tm = Ft Tlm = (0.85) (108.87℃) = 92.54ᵒC
𝑄 136.07𝑥103
Provisional area, A = 𝑈𝑇 = = 29.41 m2
𝑚 (50)(92.54)
Choose internal diameter of 16 mm, outer diameter of 20 mm and length of 1.78 m as well as
carbon steel as the material.
Area of one tube = 𝜋𝑑𝐿 = 𝜋(20 𝑥10−3 )(1.78) = 0.11 m2
Tube
90+30
Mean Temperature = = 60 ℃
2
Total flow area, A = Number of tube per pass x Tube cross sectional area
= (131) (201.1x10^-6) = 0.026343 m2
𝑚 3.1497
Tube velocity, ut = 𝜌𝐴 = (1.222)(0.026343) = 97.84 m/s
𝜌𝑢𝑑𝑒 1.22(97.84)(16𝑥10−3 )
Re = = =9.57E+04
𝜇 2𝑥105
𝐶𝑝 𝜇 (0.72𝑥103 )(2𝑥10−5 )
Pr = = = 6.0741
𝑘𝑓 0.00237
L/di = 111.25
According to figure 12.23 of Towler & Sinnot 2013,
jh = 0.00283
Heat transfer coefficient, hi = 72.74w/m2 ᵒC
Shell
𝐶𝑝 𝜇 (2.7937𝑥103 )(6.24𝑥10−5 )
Pr = = =0.9235
𝑘𝑓 0.1887
Choose 25 per cent baffle cut, from Figure 12.29 of Towler & Sinnot 2013,
jh = 0.0038
ℎ𝑖 𝑑𝑒 1
= 𝑗ℎ 𝑅𝑒𝑃𝑟 3
𝑘𝑓
Heat transfer coefficient, hs = 614.18 W/m2 ᵒC
Overall Coefficient
The different between overall coefficient and initial assumed value is 3.47% which is in
between 0 to 30%; thus it is acceptable.
Pressure Drop (Tube)
= 58400.14 N/m2
= 8.4680 psi
= 314.45 N/m2
= 0.046 psi
Since the pressure drop for shell and tube is low thus the design for Heat Exchanger (HE-
103) is satisfied.
Summary of Design
Parameter Value
Tube Side
Triangular pitch
Outer diameter, do (mm) 20
Inner diameter, di (mm) 16
Length of tube, L (m) 1.78
Area of one tube, At (m2) 0.11
Number of tubes 262
Number of tube passes 2
Linear fluid velocity, ut (m/s) 97.84
Heat transfer coefficient, hi (W/m2 ◦C) 72.74
Pressure drop, ∆Pt (kPa) 54.40
Shell Side
Pull-through floated head type
Number of shell passes 1
Bundle diameter, Db (mm) 468.12
Shell diameter, Ds (mm) 558.12
Baffle cut (%) 25
Baffle spacing, IB (mm) 111.62
Tube pitch, Pt (mm) 25
Equivalent diameter, de (mm) 14.2
Shell side Mass velocity, Gt (kg/sm2) 26.06
Heat transfer coefficient, hs (W/ m2 ◦C) 614.16
Pressure drop, ∆Ps (kPa) 0.314
Overall heat transfer coefficient, Uo (W/m2 ◦C) 51.795
Calculation of the other Heat Exchanger are the same by using formula as Cooler CO-101 and
Heat Exchanger H-103. Summarize detail design are shown in table below for Cooler CO-102,
Cooler CO-103, Cooler CO-104, Cooler CO-105, Cooler CO-106, Heater H-101 and Heat
Exchanger HE-101.
Parameter Value
Total flowrate process fluid (kg/hr) 1168.9
Temperature Shell Inside (℃) 320
Temperature Shell Outside (℃) 150
Temperature Tube Inside (℃) 80
Temperature Tube Outside (℃) 150
Assumption Overall heat transfer coefficient, Uo 50
(W/m2 ◦C)
Tube Side
Triangular pitch
Outer diameter, do (mm) 20
Inner diameter, di (mm) 16
Length of tube, L (m) 1.78
Area of one tube, At (m2) 0.11
Number of tubes 178
Number of tube passes 2
Linear fluid velocity, ut (m/s) 0.167
Heat transfer coefficient, hi (W/m2 ◦C) 15.70
Pressure drop, ∆Pt (kPa) 7.06
Shell Side
Pull-through floated head type
Number of shell passes 1
Bundle diameter, Db (mm) 392.90
Shell diameter, Ds (mm) 482.91
Baffle cut (%) 25
Baffle spacing, IB (mm) 96.58
Tube pitch, Pt (mm) 25
Equivalent diameter, de (mm) 14.2
Shell side Mass velocity, Gt (kg/sm2) 34.81
Heat transfer coefficient, hs (W/ m2 ◦C) 48.93
Pressure drop, ∆Ps (kPa) 0.62
Overall heat transfer coefficient, Uo (W/m2 ◦C) 9.95
Parameter Value
Total flowrate process fluid (kg/hr) 1168.9
Temperature Shell Inside (℃) 100
Temperature Shell Outside (℃) 50
Temperature Tube Inside (℃) 30
Temperature Tube Outside (℃) 50
Assumption Overall heat transfer coefficient, Uo 500
(W/m2 ◦C)
Tube Side
Triangular pitch
Outer diameter, do (mm) 20
Inner diameter, di (mm) 16
Length of tube, L (m) 4.83
Area of one tube, At (m2) 0.30
Number of tubes 30
Number of tube passes 2
Linear fluid velocity, ut (m/s) 0.46
Heat transfer coefficient, hi (W/m2 ◦C) 2698.38
Pressure drop, ∆Pt (kPa) 2.95
Shell Side
Split ring floated head type
Number of shell passes 1
Bundle diameter, Db (mm) 175.35
Shell diameter, Ds (mm) 225.35
Baffle cut (%) 25
Baffle spacing, IB (mm) 45.07
Tube pitch, Pt (mm) 25
Equivalent diameter, de (mm) 14.2
Shell side Mass velocity, Gt (kg/sm2) 159.85
Heat transfer coefficient, hs (W/ m2 ◦C) 2172.02
Pressure drop, ∆Ps (kPa) 24.88
Overall heat transfer coefficient, Uo (W/m2 ◦C) 705.08
Parameter Value
Total flowrate process fluid (kg/hr) 150.4
Temperature Shell Inside (℃) 68
Temperature Shell Outside (℃) 30
Temperature Tube Inside (℃) 26
Temperature Tube Outside (℃) 30
Assumption Overall heat transfer coefficient, Uo 600
(W/m2 ◦C)
Tube Side
Triangular pitch
Outer diameter, do (mm) 20
Inner diameter, di (mm) 16
Length of tube, L (m) 4.83
Area of one tube, At (m2) 0.30
Number of tubes 2
Number of tube passes 2
Linear fluid velocity, ut (m/s) 1.45
Heat transfer coefficient, hi (W/m2 ◦C) 7178.03
Pressure drop, ∆Pt (kPa) 14.32
Shell Side
Split ring floated head type
Number of shell passes 1
Bundle diameter, Db (mm) 51.41
Shell diameter, Ds (mm) 101.41
Baffle cut (%) 25
Baffle spacing, IB (mm) 20.28
Tube pitch, Pt (mm) 25
Equivalent diameter, de (mm) 14.2
Shell side Mass velocity, Gt (kg/sm2) 101.57
Heat transfer coefficient, hs (W/ m2 ◦C) 910.04
Pressure drop, ∆Ps (kPa) 1.83
Overall heat transfer coefficient, Uo (W/m2 ◦C) 616.60
Parameter Value
Total flowrate process fluid (kg/hr) 285.4
Temperature Shell Inside (℃) 90
Temperature Shell Outside (℃) 30
Temperature Tube Inside (℃) 26
Temperature Tube Outside (℃) 30
Assumption Overall heat transfer coefficient, Uo 300
(W/m2 ◦C)
Tube Side
Triangular pitch
Outer diameter, do (mm) 20
Inner diameter, di (mm) 16
Length of tube, L (m) 4.83
Area of one tube, At (m2) 0.30
Number of tubes 5
Number of tube passes 2
Linear fluid velocity, ut (m/s) 0.80
Heat transfer coefficient, hi (W/m2 ◦C) 4177.59
Pressure drop, ∆Pt (kPa) 4.38
Shell Side
Split ring floated head type
Number of shell passes 1
Bundle diameter, Db (mm) 77.86
Shell diameter, Ds (mm) 127.86
Baffle cut (%) 25
Baffle spacing, IB (mm) 25.57
Tube pitch, Pt (mm) 25
Equivalent diameter, de (mm) 14.2
Shell side Mass velocity, Gt (kg/sm2) 121.23
Heat transfer coefficient, hs (W/ m2 ◦C) 649.04
Pressure drop, ∆Ps (kPa) 15.67
Overall heat transfer coefficient, Uo (W/m2 ◦C) 428.34
Parameter Value
Total flowrate process fluid (kg/hr) 902.9
Temperature Shell Inside (℃) 690
Temperature Shell Outside (℃) 700
Temperature Tube Inside (℃) 750
Temperature Tube Outside (℃) 700
Assumption Overall heat transfer coefficient, Uo 30
(W/m2 ◦C)
Tube Side
Triangular pitch
Outer diameter, do (mm) 20
Inner diameter, di (mm) 16
Length of tube, L (m) 1.78
Area of one tube, At (m2) 0.11
Number of tubes 82
Number of tube passes 2
Linear fluid velocity, ut (m/s) 1.47
Heat transfer coefficient, hi (W/m2 ◦C) 46.25
Pressure drop, ∆Pt (kPa) 0.07
Shell Side
Pull through floated head type
Number of shell passes 1
Bundle diameter, Db (mm) 276.55
Shell diameter, Ds (mm) 364.55
Baffle cut (%) 25
Baffle spacing, IB (mm) 72.91
Tube pitch, Pt (mm) 25
Equivalent diameter, de (mm) 14.2
Shell side Mass velocity, Gt (kg/sm2) 56.02
Heat transfer coefficient, hs (W/ m2 ◦C) 7681.71
Pressure drop, ∆Ps (kPa) 14.78
Overall heat transfer coefficient, Uo (W/m2 ◦C) 36.16
Parameter Value
Total flowrate process fluid (kg/hr) 902.9
Temperature Shell Inside (℃) 700
Temperature Shell Outside (℃) 492
Temperature Tube Inside (℃) 350
Temperature Tube Outside (℃) 690
Assumption Overall heat transfer coefficient, Uo 50
(W/m2 ◦C)
Tube Side
Triangular pitch
Outer diameter, do (mm) 20
Inner diameter, di (mm) 16
Length of tube, L (m) 2.39
Area of one tube, At (m2) 0.15
Number of tubes 326
Number of tube passes 2
Linear fluid velocity, ut (m/s) 1.40
Heat transfer coefficient, hi (W/m2 ◦C) 129.60
Pressure drop, ∆Pt (kPa) 0.06
Shell Side
Pull through floated head type
Number of shell passes 1
Bundle diameter, Db (mm) 516.85
Shell diameter, Ds (mm) 608.85
Baffle cut (%) 25
Baffle spacing, IB (mm) 121.77
Tube pitch, Pt (mm) 25
Equivalent diameter, de (mm) 14.2
Shell side Mass velocity, Gt (kg/sm2) 16.91
Heat transfer coefficient, hs (W/ m2 ◦C) 162.26
Pressure drop, ∆Ps (kPa) 4.32
Overall heat transfer coefficient, Uo (W/m2 ◦C) 61.34
CHAPTER I
1.1 INTRODUCTION
Distillation column is a unit operation used to separate components which have different
volatility by using boiling point as a reference. In C-101, the feed contains methanol
and water. The function of C-101 is to separate methanol from water to increase the
purity of final product. Methanol is identified as the light key component (LK) while
water as the heavy key (HK) component since methanol has lower boiling point
compared to water. Figure 1.1 shows distillation column C-101 with its operating
condition tabulated in Table 1.1. Table 1.2 shows the flow rate of each stream
connecting to the column.
69 CO-104 Distillate
RD-101 70
66 P-107
Feed
Bottom
67 68
C-101
H-102
The type of tray that has been used in this distillation column is sieve tray column
because sieve tray column has good efficiency due to its minimum back mixing. Besides
that, the cost for sieve tray is relatively low.
The pressure vessel design codes and standards include lists of acceptable materials, in
accordance with the appropriate material standards. Since flash tank deals with
relatively clean fluids which is free of corrosive and erosive components, hence a
carbon steel SA-516 is selected as construction material.
3
Assumptions:
Assumptions:
At steady state there are no any material losses, material accumulation and
material generation.
There is no any chemical reaction inside the column
F=D+W
18.85 = D + W
Material balance:
Fx = Dx + Wx
D = 8.054 kmol/hr
W = 10.796 kmol/hr
4
0 0 100
0.3 0.66 78
0.9 0.96 66
1 1 64.5
85
80
Vapour
75
Liquid
70
65
60
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Methanol composition
q=1
For many systems the optimum selection of the design reflux ratio will lie between 1.2
to 1.5 times the minimum reflux ratios. Assume operating reflux ratio is 1.25 of
minimum reflux ratio.
𝑅𝑚𝑖𝑛
= 0.4872
𝑅𝑚𝑖𝑛 + 1
𝑅𝑚𝑖𝑛 = 0.95
R = 1.25 × 𝑅𝑚𝑖𝑛
R = 1.25 × 0.95
R = 1.1875
1.1875
= 1.1875+1
= 0.5429
y = 0.5429x + 0.45
6
According to Figure 1.3, the vapour- liquid equilibrium curve counts number of
theoretical plates.
There are total condenser and partial reboiler. Total condenser does not act as
equilibrium stage, but partial reboiler acts as equilibrium stage. So, reboiler stage need
to reduce from total theoretical stages.
= 14
1.1875 = 𝐿𝑜 /8.054
𝐿𝑜 = 9.564 𝑘𝑚𝑜𝑙/ℎ𝑟
Ln = Lo = 9.564 kmol/hr
7
Material balance:
Vn = Lo + D
Vn = 9.564 + 8.054
Vn = 17.618 kmol/hr
According to given data, feed is at saturated liquid condition therefore all feeding
liquids join with stripping section liquid.
Lm = F + Ln
Lm = 18.85 + 9.564
Lm = 28.414 kmol/hr
Vm = Vn
Vm = 17.618 kmol/hr
Temperature (◦C) Density of liquid mixture (kg/m3) Density of vapour mixture (kg/m3)
77 892.15 1.45
65 761.12 1.11
ρL = 826.6 kg/m3
ρV = 1.28 kg/m3
8
Similarly;
𝐿 𝜌𝑉
𝐹𝐿𝑉 = √
𝑉 𝜌𝐿
9.564 1.28
𝐹𝐿𝑉 = √
17.618 826.6
𝐹𝐿𝑉 = 0.0214
K1 = 0.084
The flooding velocity can be estimated from the correlation given by Fair.
𝜌𝐿 − 𝜌𝑉
𝑈𝑓 = 𝐾1 √
𝜌𝑉
826.6 − 1.28
𝑈𝑓 = 0.084√
1.28
𝑈𝑓 = 2.13 𝑚/𝑠
Ua = 0.8 × 2.13
Ua = 1.71 m/s
9
= 32 × 0.5 + 18 × 0.5
= 25 kg/kmol
Vn = 0.122 m3/s
𝑉𝑛
= 𝑈𝑎
𝐴𝑛
0.122
𝐴𝑛 =
1.71
𝐴𝑛 = 0.0717𝑚2
An = Ac – Ad
Assume Ad = 12% of Ac
An = Ac – 0.12Ac
An = 0.88Ac
0.0717 = 0.88 × Ac
Ac = 1.85 m2
𝜋𝐷𝑐2
𝐴𝑐 =
4
𝜋𝐷𝑐2
1.85 =
4
Dc = 1.534 m
28.414 1.095
𝐹𝐿𝑉 = √
17.618 922.6
10
𝐹𝐿𝑉 = 0.0556
K1 = 0.08
922.64 − 1.095
𝑈𝑓 = 0.08√
1.095
𝑈𝑓 = 2.32 𝑚/𝑠
Ua = 0.8 × 2.32
Ua = 1.86 m/s
Vm = 0.122 m3/s
𝑉𝑛
= 𝑈𝑎
𝐴𝑛
0.122
𝐴𝑛 =
1.86
𝐴𝑛 = 0.0659 𝑚2
An = 0.88Ac
Ac = 1.75 m2
Dc = 1.49 m
Hole size less than 6.5 mm. Entrainment may be greater with larger hole sizes. (Page
No. 568 Coulson & Richardson 6th volume 4th edition).
For a plate, there is one downcomer on the plate and top downcomer also affected to
bottom plate. Therefore, two downcomer areas need to be reduced from the active area.
Aa = Ac – 2Ad
Aa = Ac – (0.12 × 2Ac)
Aa = 0.0619 m2
Ah = 0.1Aa
= 0.00619 m2
0.0062
Area of a hole =π× 4
= 2.83 × 10-5 m2
0.00619
Number of hole in a plate = 2.83 × 10−5
= 219
Aa = 0.0569 m2
Ah = 0.1Aa
Ah = 0.00569 m2
0.00569
Number of hole in a plate = 2.83 × 10−5
= 201
12
Maximum and minimum temperatures of inside the column are respectively 100˚C and
65˚C. Assume liquid temperature is average temperature of column. Assume properties
of liquid mixture equal to water properties.
100+65
Average temperature of column = 2
= 82.5˚C
Surface tension of liquid at 82.5˚C is calculated according to their molar basis of feed.
σL = 0.0513 N/m
Uv = Ua
Uv = 1.86 m/s
Since there are both vapour and liquid densities, the average density is taken.
ρV = 1.19 kg/m3
ρL = 874.62 kg/m3
𝑎𝑟𝑒𝑎 𝑜𝑓 ℎ𝑜𝑙𝑒𝑠
FA = Fractional Area = 𝑡𝑜𝑡𝑎𝑙 𝑐𝑜𝑙𝑢𝑚𝑛 𝑐𝑟𝑜𝑠𝑠 𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑎𝑙 𝑎𝑟𝑒𝑎
0.005691
FA = 0.625
FA = 0.00911
0.0513
𝐷𝑔 =
0.0004862 × 1.86
Dg = 56.83
0.0004862
𝑆𝑐 =
874.62 × 5 × 10−9
Sc = 111
ℎ𝑤 × 𝑈𝑣 × 𝜌𝑣
𝑅𝑒 =
𝜇𝐿 × 𝐹𝐴
Therefore,
14
0.89 =
𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑎𝑐𝑡𝑢𝑎𝑙 𝑠𝑡𝑎𝑔𝑒𝑠
= 0.08 m
= 7.69 m
Feed composition of methanol is 0.29. This value is at 11th plate (theoretical) of the
column. To calculate the actual feed tray location, the value need to be divided with
column efficiency.
11
Therefore feed tray location = 0.89
= 12.33
= 13th plate
15
2.1 INTRODUCTION
A reflux drum is to hold the condensed vapour from the top of the column so that liquid
which is known as reflux can be recycled back to the column. Methanol which is in
vapour phase moves up the column, and as it exits the top of the column, it is cooled by
a condenser. The condensed liquid which is methanol is stored in the reflux drum RD-
101. Some of this liquid is recycled back to the top of the column and this is called
the reflux. The methanol that is removed from the system is known as
the distillate or top product of the distillation column. Figure 2.1 shows reflux drum
RD-101 with its operating conditions tabulated in Table 2.1.
69
CO-104
RD-101
70
Assumptions:
= 1.1875 × 150.4
= 178.6 kg/hr
= 14.88 m3
= 29.77 m3
3 4𝑉
Diameter of drum =√
3𝜋
3 4 29.77
= √3 𝜋
18
= 2.33 m
= 2.33 × 3
= 6.99 m
APPENDIX C
MECHANICAL DESIGN
V) PHASE SEPARATOR
Upflow anaerobic sludge blanket (UASB) reactor is a column type tank reactor that will
be used in anaerobic process. It is widely used in industrial wastewater treatment in
chemical and sewage industries (Lier et al. 2015). The detailed design of UASB
requires some information. The hydraulic retention time (HRT) for UASB in treating
POME is about 10 days for an efficient production of biogas and chemical oxygen
demand (COD) removal (Ohimain et al. 2017). The volume required to contain POME
for 10 days is 5760 m3. To cater a large volume of POME, three identical UASB is
used. Each UASB with a volume of 2304 m3 with 20% extra as safety factor. The
calculation for UASB are done according to the formula by Bal et al. 2010
Information Value
Inlet (m3/h) 36
3
Inlet (m /day) 576
HRT (days) 10
HRT (hours) 240
3
Volume (m ) 5760
Number of Tanks 3
3
Volume of one tank (m ) 1920
Safety Factor (%) 20
Volume after extra (%) 2304
2
Since the designed UASB is a column type tank reactor, the ratio of H:D used is 3:1
(Clapp et al. 2018). The height and diameter are calculated using the volume formula
by assuming the UASB is a tall cylindrical tank.
D 2
2
D 2
V = Hπr = Hπ( ) = (3D)π( )
2 2
3 4V 3 4(2304)
D=√ =√ = 9.924 m
3π 3π
H = 29.77 m
The volumetric hydraulic load (VHL) is the volume of wastewater supplied daily into
the UASB per unit volume of the UASB.
Q
VHL = where Q = inlet volumetric flowrate of the UASB (m3/day)
V
576 m3 /day
VHL = = 0.25 m3 / m3 .day
2304 m3
Thus, the volumetric hydraulic loading rate of the POME into the UASB is 0.25 per
day
The volumetric organic load (Lv) is defined as the amount of organic matter supplied
daily to the UASB per unit volume of UASB. The influent substrate concentration (So)
is 51 kg COD/m3 (Zainal et al. 2017). The calculation for Lv is shown below.
Lv = 12.75 kg COD/m3.day
Thus, the organic loading rate of the organic material into the UASB is 12.75 kg/m3 per
day.
The sludge loading rate (Ls) referred to the amount of organic matter that is supplied to
the UASB per unit of biomass in the UASB. The total volatile solid in POME (M) is 34
kgVS/m3 (Zainal et al. 2017). The calculation for Ls is shown below.
Thus, the sludge loading rate into the UASB is 864 kg COD/kg VS per day.
Upflow velocity (ν) of the POME is calculated from the relation between the inlet
flowrate and the cross sectional area of the UASB. The calculation of ν is as shown
below.
Q
ν= where Q = inlet volumetric flowrate of the UASB (m3/hr)
A
36
ν= 9.924 2
= 0.4652 m/hr
(π)( 2 )
Thus, the velocity if POME pumped into the UASB is about 0.4652 m/hr.
4
ExSo
Ceff = So - where Ceff = COD at the effluent (kg COD/m3)
100
The COD at the influent is 51 kg COD/m3 (Zainal et al. 2017) while the removal
efficiency of UASB is 96.5% for the HRT of 10 days (Ohimain et al. 2017).
(96.5)(51)
Ceff = 51 - = 1.785 kg COD/m3 = 1785 mg COD/L
100
It can be assumed that the BOD is about 50% of the COD for POME (Chong et al.
2018). The BOD for effluent from POME is 892.5 mg COD/L.
Ex = COD removal
efficiency TSS = 102(96.5)(240)-0.24
= 2641.66 mg/L
The amount of sludge produced is highly related to the COD of the POME inlet. The
production of solid sludge can be calculated by using the equation below.
The yield of solid can be assumed at 0.2 kgTSS/day since POME is high in COD
The gas hood will be located at the top of the UASB. The main function of the gas hood
is to collect the biogas. The area of gas hood interface is calculated from the equation
below.
Qg
Kg = where, Kg = biogas release rate (m3gas/m2.hr)
Ai
106.522
5= Ai
106.522
Ai = = 21.304 m2
5
𝐷 2
Ai = π ( 2 )
6
A 21.304
D= 2√ π = 2√ = 5.2 m
π
Thus, the area and diameter of the gas hood is 21.3 m2 and 5.2 m respectively.
7
CHAPTER II
2.1 INTRODUCTION
A pressure vessel any closed vessel with diameter more than 150 mm that can withstand
at the pressure difference more than one bar, which is to be designed to fulfill the
process requirements. Consequently, pressure vessels are be designed to withstand
either internal or external pressure.
Anaerobic process in our plant occurs in the UASB. The POME from cooling pond will
enter the UASB in which the retention time 10 days. The anaerobic process produces
biogas which will be collected and stored in the gas holder. Three identical UASB (T-
101, T-102 and T-103) will be used to cater large volume of POME. The capacity of
each UASB is 2304 m3.
The operating temperature in UASB is about 37oC while the POME will be pumped
into the UASB at 3 bar. So the design pressure is 3 bar. POME have a pH of 4 which is
acidic but it does not poses corrosive effect towards the tank (Bukhari et al. 2018).
Carbon steel SA-516 grade 70 is selected as the construction material since it has a
lower price than other materials and is available in a wide range of standard forms and
sizes (Sinnott et al. 2013). Iron is the main composition of this material. Carbon steel
8
SA-516 grade 70 have a minimum tensile strength of 70000 psi and maximum thickness
of 205 mm. The maximum allowable stress for carbon steel SA-516 at 37 oC is 17100
psi.
The UASB is designed with a vertical vessel with 3:1 ellipsoidal head at the top
and the bottom. This UASB is designed under internal pressure, 43.51 psi (3 bar). The
construction material is carbon steel SA-516 grade 70, with corrosion allowance of 4
mm. The design and operating condition for UASB is shown in Table 2.1.
9
For top part, the ratio of the ellipsoidal head is H:D = 2:1
D
=2
2h
9.92
he =
4
= 2.48 m
For the bottom part, the apex angle for the conical bottom is 40o.
D 9.92
L = tan2 α = tan240
= 5.95 m
hc = H − ℎ𝑒 − 𝐿
= 21.34 m
The height for the ellipsoidal head, cylindrical shell and conical head is tabulated in
Table 2.2.
10
Since the operating pressure of UASB is 3 bar which is greater than atmospheric
pressure (Pa > Patm), the UASB were designed as internal pressure. Firstly, the design
pressure for each part of the vessel is calculated by using equation:
PD =PO +0.433h
Po = operating pressure
PD = design pressure
h = height (ft)
Hence,
i. Ellipsoidal top head
PD = 43.51 + 0.433 (8.13) = 47.04 psi
ii. Cylindrical shell
PD = 43.51 + 0.433 (8.13 + 70.01) = 77.35 psi
iii. Conical bottom head
PD = 43.51 + 0.433 (8.13 + 70.01 + 19.52) = 85.61 psi
A safety factor about 10% is added to design pressure for safety purpose. The new
design pressure is Pj = 1.10PD and the data is tabulated in the Table 2.3.
11
The wall thickness formulas for each part of the vessel are from ASME Code UG-32
(d) and UG-27 (c). The maximum allowable stress value, S is from ASME Code given
in Subpart 1 of Section II, Part D.
PD (51.742)(390.72)
Thickness, t = = =0.5912 in
2SE-0.2P 2(17100)(1)-(0.2)(51.741)
PD (94.39)(390.72)
Thickness, t = = = 1.409 in
2cos α(SE+0.2P) 2cos(40)((17100)(1))-(0.2)(94.39)
Thus, the overall thickness, toverall is determined, which is the highest value of minimum
thickness calculated for each part.
toverall = 1.409 in
= 35.80 mm
t = 35.80+ 4 = 39.80 mm
tmin = tnominal – CA
= 40 mm – 4 mm
= 36 mm (1.417 in)
The maximum allowable working pressure (MAWP) for a pressure vessel is determined
by calculating every part using internal pressure procedure. The formula of internal
design pressure for each part of the vessel can be found in ASME Code UG-32 part (D)
and UG-27 part (c). By using tmin from the calculation above, the MAWPvessel is
calculated.
2SEt 2(17100)(1)(1.417 )
MAWPellipsoidal = = = 123.94 psi
D+0.2t 390.72+0.2(1.417 )
Circumferential
SEt (17100)(1)(1.417 )
MAWPc = = = 123.49 psi
R+0.6t (195.36)+0.6(1.417 )
Longitudinal
2SEt 2(17100)(1)(1.417 )
MAWPL = = = 248.78 psi
R-0.4t (195.36)-0.4(1.417 )
The value of MAWPpart and pressure at top is obtained and tabulated as shown below.
The smallest value of pressure at top will be taken as the MAWPvessel as it shows the
maximum allowable pressure at the weakest point on the vessel.
Thus, MAWPvessel = 52.93 psi which is higher than the operating pressure. The design
is acceptable.
Besides pressure, a pressure vessel subjected to other loads that can be categorized into
major and subsidiary loads. Hence, it must be designed to withstand the worst
combination of loading without failure. There are the sources of combined loading
which are internal and external pressure, weight loads, wind loads, earthquake (seismic
load), and eccentric loads (Sinnott et al. 2013). All of these are related to primary
stresses and summarized into principal stresses in the end of calculation
Primary stresses are due to longitudinal and circumferential stresses, direct stress,
bending stress and torsional shear stress.
14
PDi
σL =
4t
0.3 (9924)
= = 18.61 N/mm2
4(40)
PDi
σh =
2t
0.3 (9924)
= = 37.22 N/mm2
2(40)
W
σw = where, W = Wv + WI
π (Di+t)t
Cv = 1.15
Hv = 24.15 m
t = 40 mm
= 3532708.1 N
W
Direct stress, σw =
π (Di+t)t
3532708.1
=
π (9924+40)40
15
c. Bending stresses, σb
M D
σb = ± ( i +t)
I 2 v
Wx2
M=
2
x = Hv = 24.14 m
Deff (including insulation) = Do = Di +2t = 9.964 m
Pw = 1280 N/m2
W = Pw Deff =(1280)(9.964) = 12753.92 N/m
(12753.92)(24.14)2
M= = 3716107.12 Nm = 3.716 x 106 Nmm
2
π π
Iv = (Do 4 - D1 4 ) = (99644 -99244 ) = 7.72 x 1012 mm4
64 64
M Di
Hence, Bending stresses, σb = ± ( 2 +t)
Iv
The torsional shear stresses resulting from torque caused by loads offset from the vessel
axis. These loads will normally be small and can be neglected in preliminary vessel
design.
16
1
σ1 = 2 [σh +σz +√(σh - σz )2 +4τ2 ]
1
σ2 = 2 [σh +σz -√(σh - σz )2 +4τ2 ]
σz (upwind) = σL + σW + σb
σz (downwind) = σL + σW - σb
1
σ1 = 2 [σh +σz +√(σh - σz )2 +4τ2 ]
1
= 2 [37.22+21.43+√(37.22- 21.43)2 +4(0)2 ]
17
= 37.22 N/mm2
1
σ2 = 2 [σh +σz -√(σh - σz )2 +4τ2 ]
1
= 2 [37.22+21.43-√(37.22- 21.43)2 +4(0)2 ]
= 21.43 N/mm2
1
σ1 = 2 [σh +σz +√(σh - σz )2 +4τ2 ]
1
= 2 [37.22+21.42+√(37.22- 21.42)2 +4(0)2 ]
= 37.22 N/mm2
1
σ2 = [σh +σz -√(σh - σz )2 +4τ2 ]
2
1
= 2 [37.22+21.42-√(37.22- 21.420)2 +4(0)2 ]
= 21.43 N/mm2
σ1 – σ3 = 37.22 – 0
= 37.22 N/mm2
σ2 – σ3 = 21.43 – 0
= 21.43 N/mm2
S = 117.9 N/mm2
Since, (∆σmax) = 37.22 N/mm2 ˂ S = 117.9 N/mm2, the designed UASB is safe to
operate.
E t
Critical buckling stress, c =
(
3 1− v2 ) R
p
For steel at ambient temperature, E = 200000 N/mm2 with a safety factor of 12, the
Since the value of (∑ 𝜎)𝑐𝑜𝑚𝑝𝑟𝑒𝑠𝑠𝑖𝑣𝑒 ˂ σc, the critical value of buckling is not exceeded.
The design of UASB is safe to operate.
From the analysis of combined loading, the material we chose has fulfilled both
requirements of maximum stress intensity and elastic stability:
The vessel support must be designed to withstand the weight of the vessel, contents and
any superimposed loads such as wind loads. Support will impose localized loads on the
vessel wall and the design must be checked to ensure resulting stress concentrations are
19
below the maximum allowable design stress. It is also important to allow the ease of
access to the vessel and the fittings for inspection and maintenance (Sinnott et al. 2013).
The UASB does not have any vessel support because the it is directly attached
to the concrete base below. The height of the tank is about 29 m in which supports are
not suitable. The UASB can be bolt to the base on the ground.
The loads carried by the vessel will be transmitted to the foundation slab base ring. The
moment produced by wind and other lateral loads will tend to overturn the pressure
vessel. This will be opposed by the couple set up by the weight of the vessel and the
tensile load of the anchor bolts (Sinnott et al. 2013).
The anchor bolts are assumed to share the overturning load equally and the bolt area
required:
1 4Ms
Ab = [ ]−W
Nb fb Db
Nb = number of bolts
Assumptions:
• bolt circle diameter, Db = 10.16 m
• circumference of bolt circle = 31.92 m
• maximum allowable bolt stress, fb = 125 N/mm2
• take number of bolts as 20
20
31.92×1000
Bolt spacing = = 1596 mm
20
Therefore, the bolt spacing is acceptable as it follows the guidelines which is the bolt
spacing must be more than 600mm.
1 4Ms
Ab = [ ] -W
Nb fb Db
1 4 (3719005.17 )
Ab = [ ] - 3532708.1
20×125 10160
Ab = 1412.5 mm2
Use M45 bolts with a root area of 353 mm2 is suitable to be used to bolt the UASB
onto the concrete base (Sinnott et al. 2013).
4Ms W
Fb = [ + ]
πD2s πDs
4(3719) 3532708.1
Fb = [ 2+ ]
π x 9.964 π×9.964
Fb = 112900 Nm-1
Taking the bearing pressure as 3.5 N/mm2, the minimum width of the base ring, Lb
Fb 1
Lb = ×
fc 103
112900
Lb =
3.5x 103
Lb = 32.26 mm
The required thickness for thickness base ring is found by treating the ring as cantilever
21
beam:
3𝑓𝑐′
𝑡𝑏 = 𝐿𝑟 √
𝑓𝑟
Lr = the distance from the edge of the vessel to the outer edge of the ring, mm
3𝑓 ′
Base ring thickness, tb = 𝐿𝑟 √ 𝑓 𝑐
𝑟
3(3.5)
= 200√ 140
= 54.77 mm
Flanged joints are used for connecting pipes and instruments to vessels, for manhole
cover, and for removable vessel heads when ease of access is required. It also used on
the vessel body when it is required to divide the vessel into sections for transport and
maintenance. It can reduce high-stress concentration at the base of the flange by
transferring stress to the adjoining pipe. First, the welding-neck flange is the best flange
for UASB because the liquid flow is high in suspended solid and sludge may cause high
shear and vibration load. Welding-neck flange have high strength and high resistance
to dishing, it is manufactured with a long-tapered hub. The welding-neck flange
diagram is shown in Figure 2.2.
22
Next, blind flanges are also used in the UASB. The main function of blind flange
is to seal any end of the piping system. The propose of blind flange in UASB is to cover
the manhole, cleaning or drainage hole and unused inlet or outlet pipe. Figure below
shows the diagram of blind flange.
By considering the internal pressure for UASB, the mechanical calculation for the Table
2.6.
Stream 12
PRODUCTION OF BIOFLOCCULANT
AND METHANOL FROM POME
B B
MECHANICAL DESIGN OF UPFLOW
ANAEROBIC SLUDGE BLANKET
(UASB)
SUPERVISOR
1) PROF. IR DR. SITI KARTOM
KAMARUDIN
2) PROF. MADYA DR. MASLI
INLET OF CIRCULAR PUMP TOP VIEW OF INLET DISTRIBUTION PIPE IRWAN ROSLI
CROSS SECTIONAL VIEW
SYSTEM 3) HEMAVATHI SILVAMANY
OF BLIND FLANGE
D D
C GROUP
KK 4
GROUP MEMBERS
RAVINKUMAR MANIMARAN A158192
CHEAH CHING WEI A157594
SITI BARAKAH A158482
NUREDAHTUL FAEZAN A159291
12B AFIQ SHAZWAN A158912
SIVA PRIYA A158432
DRAWN BY
RAVINKUMAR MANIMARAN
DATE
23th MARCH 2020
TYPE 05 BLIND FLANGE (EN 1092-1 TYPE 05)
DIMENSION (mm)
DRAWING NOT TO SCALE
UNIT DIMENSION IN MILLIMETER
NO. NOMINAL SIZE A B C D (mm)
CROSS SECTIONAL VIEW OF WELD 12A 800 920 975 44 30
NECK FLANGE 12B 800 920 975 44 30 DESIGN SPECIFICATIONS
Stream 8A
MAN HOLE 1200 1340 1405 60 20
Design Temperature : 37°C
MAN HOLE 1200 1340 1405 60 20 Operating Pressure : 300 kPa
Design Pressure : 365 kPa
Design Thickness : 35.8 mm
12A Corrosion Allowance : 4 mm
Inside Diameter : 9924 mm
Vessel Height : 29770 mm
CLASS 150 WELD NECK FLANGE
C
DIMENSION (mm) Height of cylindrical shell : 21335 mm
NO. NOMINAL SIZE A B C D E F G H I J Height of ellipsoidal head : 2480 mm
Height of conical bottom : 5955 mm
8 150.0 279.4 25.4 215.9 192.0 168.4 154.1 88.9 241.3 12.7 50.8
D D
Stream 8B 8A 300.0 482.6 31.7 381.0 365.3 323.9 304.8 114.3 431.8 16.5 66.0 Material Used : Carbon Steel
Man Hole
8B 300.0 482.6 31.7 381.0 365.3 323.9 304.8 114.3 431.8 16.5 66.0 (SA-516)
Stream 8 11 15.0 88.9 11.2 35.1 30.2 21.3 15.8 47.8 60.5 7.4 29.2
12 150.0 279.4 25.4 215.9 192.0 168.4 154.1 88.9 241.3 12.7 50.8
MBBR REACTOR
1.1 INTRODUCTION
MBBR reactor is an open tank for aeration process in order to produce bioflocculant by
using specialised bacteria which is Bacillus marisflavi. Moving bed biofilm reactor
(MBBR) is an advanced wastewater treatment technology that gives high treatment
efficiency with low operating and maintenance cost and robust operation procedure. The
effectivity of removing up to 90% of chemical oxygen demand and 95% of biological
oxygen demand with nutrients from effluent stream had been proven when there is
sufficient retention time (Jenkins and Sanders 2012). Moreover, the process is based on bio
carriers that will attract the biomass and grow them on the surface (Ødegaard et al. 2000).
Other specialty is that the bio carriers can be used up to 10 years and can be operated
continuously without the need for backwashing, and low head-loss. ((Rusten et al. 1998).
The biofilms that grows on the surface of the bio carriers would suspended throughout the
entire volume of the reactor (Qiqi et al. 2012). Furthermore, MBBR reactor is better than
other aerated reactors such as membrane bioreactor (MBR), activated sludge process (ASP)
and sequencing batch bioreactor (SBBR) in terms of operating cost, efficiency of suspended
solids removal and installation space required. MBBR reactor takes up small space as it can
maximizes surface area through the carriers.
Figure 11.1 Schematic showing the principles of MBBR reactor
Vessel design for MBBR reactor are separated into few parts according into its design
specification. Every value and assumptions that have been made are comes with evidence.
1.2.1 Material selection
MBBR reactor is operating at 1.01 bar with temperature 30oC. The material that will be
used to construct MBBR reactor is poured reinforced concrete grade M30. Concrete been
choose as the construction material because this reactor need to hold up a huge volume of
sludge with 24 hours HRT. The volume of the tank is 979m3 while considering the safety
factor. Concrete is the best material to be choosen as it could hold high volume of sludge
and can winstand a good amount of tensile stress. Mix ratio for cement to sand to aggregate
for this concerete is 1:0.75:1.5. The compressive strength of M30 concrete is 4350psi.
The mechanical design of MBBR reactor is subjected under ASME internal pressure
procedure and EUROCODE 2 for concrete materials. MBBR reactor is lie under internal
pressure because its absolute pressure is higher than atmospheric pressure. MBBR reactor
in an open tank and rectangular in shape. It consist of air diffuser at the bottom of the tank
and MBBR carrier that will be poured before the process start. This tank is embedded on
the floor.
Criteria Value
Operating pressure, Po 1 bar
Operating temperature, T 30oC
Joint efficiency, E 1 ( full radiography)
Corrosion allowance, CA 2 mm
Length, L 14.5 m
Width, W 9.79 m
Height, h 6.9 m
h = Height, ft
PD = 25.01 psi
Diffuser design for an aerobic system is considering few aspects such as length of manifold,
number of laterals, size of diffuser hole and etc. Calculation for diffuser design is shown
below.
𝑄𝑎𝑖𝑟,𝑡𝑜𝑡𝑎𝑙
𝑡𝑜𝑡𝑎𝑙 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑜𝑟𝑖𝑓𝑖𝑐𝑒 = = 8000 𝑜𝑟𝑖𝑓𝑖𝑐𝑒
𝑄𝑜𝑟𝑖𝑓𝑖𝑐𝑒,𝑚𝑎𝑥
𝐿𝑚𝑎𝑛𝑖𝑓𝑜𝑙𝑑
𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑙𝑎𝑡𝑒𝑟𝑎𝑙𝑠 𝑝𝑒𝑟 𝑚𝑎𝑛𝑖𝑓𝑜𝑙𝑑 = + 1 = 27(𝑖𝑛𝑡𝑒𝑔𝑒𝑟)
𝐿𝑑𝑖𝑓𝑓𝑢𝑠𝑒𝑟 𝑠𝑝𝑎𝑐𝑖𝑛𝑔
Ldiffuser spacing is typically starts at the largest interval. After considering the size for
the oxygen inlet to the manifold, the Lmanifold is reduced and the total number of laterals for
manifold for this process is 24 laterals. Lorifice spacing is generally taking at the minimum
spacing which is 38mm.
3672
𝑎𝑖𝑟 𝑓𝑙𝑜𝑤𝑟𝑎𝑡𝑒 𝑝𝑒𝑟 𝑜𝑟𝑖𝑓𝑖𝑐𝑒, 𝑄′𝑜𝑟𝑖𝑓𝑖𝑐𝑒 = = 1.7 𝑚3 /ℎ𝑟
2160
Q’orifice is 1.7 m3/hr which is higher than Qorifice, min and lower than Qorifice,maz. The
value is acceptable as it is in the range for the air flowrate per orifice.
1.75 − 1.7
𝑝𝑒𝑟𝑐𝑒𝑛𝑡𝑎𝑔𝑒 𝑒𝑟𝑟𝑜𝑟 = × 100 = 2.85%
1.75
Calculated perecentage error is 2.85% and it is lower than 5%. The value is
acceptable.
𝑄𝑎𝑖𝑟 𝑓𝑙𝑜𝑤
𝑎𝑖𝑟 𝑓𝑙𝑜𝑤 𝑣𝑒𝑙𝑜𝑐𝑖𝑡𝑦 =
𝐴𝑚𝑎𝑛𝑖𝑓𝑜𝑙𝑑 × 𝑁𝑔𝑟𝑖𝑑,𝑤𝑖𝑑𝑡ℎ × 𝑁𝑔𝑟𝑖𝑑,𝑙𝑎𝑡𝑒𝑟𝑎𝑙
3672
= = 17309.1 𝑚/ℎ𝑟
22 0.3 2
( 7)×( 2 ) ×3×1
17309.1
𝑎𝑖𝑟 𝑓𝑙𝑜𝑤 𝑣𝑒𝑙𝑜𝑐𝑖𝑡𝑦 = = 4.8 𝑚/𝑠
3600
MBBR carrier is to provide a surface where biofilm can grow. Type of material for MBBR
carrier is high density poly ethylene (HDPE) material. This material been choose because
it have almost same density as water and it could been process easily in MBBR reactor.
Type of biocarrier is PE01 that have 4 room with diameter and height are 12 mm and 9 mm
respectively. By the rule of thumb, 60% of reactor is media and 40% is water. This MBBR
carrier can be used up to 10 years and could have high biofilm load,
Thickness for concrete wall is been verified based on three criteria. First, wheather the wall
is exterior or interior. In this case, the wal for MBBR reactor is fall to interior wall as is
play less inposrtant role in insulating the reactor from heat and cold. Second, what are the
wall is made of. It is either strong or weak materials. Strong materials need thinner wall
and vice versa. Lastly, the climate. As our production is in Malaysia that have tropical
climates, thinner walls is preferable. Value of thickness for the wall is based on nominal
thickness of concrete wall. Table below show the minimum thickness for few types of
concrete wall.
Based on the table above, the minimum thickness for the concrete wall of MBBR
reactor is 12.5 cm.
Type of pipe support for manifold pipe is pipe shoe clamp. It is choosen as it can stop pipes
from rubbing against dissimilar metals. It means that they are able to prevent
electrochemical transfer and galvanic corrosion. It also keep insualtion from grinding
against objects or rupturing. In the same way, they should minimize the movement and
wear that comes with heat transfer.
1.2.8 Combined loading
Combined loading must be designed to winstand the worst combination of loading without
failure. A trial thickness is assumed based on the calculated and resultant stress from all
loads determined to ensure that the maximum allowable stress intensity is not exceeded at
any point.
a. Primary stress
P = 0.1 N/mm2
Di = 14500 mm
t = 125 mm
𝑃𝐷𝑖
σL = = 1.8125 𝑁/𝑚𝑚2
4𝑡
𝑃𝐷𝑖
σh = = 3.625 𝑁/𝑚𝑚2
2𝑡
𝑊
σw =
𝜋 (𝐷𝑖 + 𝑡)𝑡
Where ;
W = Wv + WI ;
𝑊𝑣 = 240𝐶𝑣 𝐷𝑚 (𝐻𝑣 + 0.8𝐷𝑚 )𝑡
Cv = 1.02 m
Dm = 14.7 m
Hv = 6.9 m
Hence, Wv = 19072 N
Direct stress, σw = 0.0016 N/mm2
𝑀 𝐷
σb = ± 𝐼 ( 2𝑖 + 𝑡)
𝑣
𝑊𝑥 2
𝑀=
2
x = Hv = 6.9 m
Deff = 14.9 m
Pw = 1280 N/m2
W = 19072 N/m
M = 454008.96 Nmm
π
Iv = 64 (Do 4 − D1 4 ) = 2.49 x 1014 mm4
The torsional shear stresses can be neglected in preliminary vessel design because these loads will
normally be small, where, τ = 0
1
σ1 = 2 [σh + σz + √(σh − σz )2 + 4τ2 ]
1
σ2 = 2 [σh + σz − √(σh − σz )2 + 4τ2 ]
= 3.65 N/mm2 = σh
1
σ2 = 2 [𝜎ℎ + 𝜎𝑧 − √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
= 3.625 N/mm2 = σh
1
σ2 = 2 [𝜎ℎ + 𝜎𝑧 − √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
= 1.79 N/mm2 = σz (downwind)
c. Maximum allowable stress intensity (∆σMAX)
Assume τ = 0, σ3 = 0.5
For upwind condition,
σ1 – σ3 = 2.9 N/mm2
Hence, the maximum allowable stress intensity, (∆σmax) = 2.9 N/mm2. According to
EUROCODE 2, maximum allowable stress at temperature 303 oF is S = 30 N/mm2 . Since,
(∆σmax) = 2.9 N/mm2 ˂ S = 30 N/mm2, therefore, the design is safe to use.
d. Elasticity stability
E t
Critical buckling stress, c
31 v2 R
p
Modulus of elasticity, E of concrete M30 is 5.47 N/mm2.
σc = 355.06 N/mm2
(∑ 𝜎) = 0.015 𝑁/𝑚𝑚2
𝑐𝑜𝑚𝑝𝑟𝑒𝑠𝑠𝑖𝑣𝑒
Since the value of (∑ 𝜎)𝑐𝑜𝑚𝑝𝑟𝑒𝑠𝑠𝑖𝑣𝑒 ˂ σc, therefore, the design is safe to use.
From the analysis of combined loading, the material we chose has fulfilled both
requirements of maximum stress intensity and elastic stability:
The anchor bolts are assumed to share the overtuning load equallt and the bolt area
required :
1 4Ms
Ab = [ − W]
Nb fb Db
With, Ab = area of one bolt at the root of the thread, mm2
Nb = number of bolts
fb = maximum allowable bolt stress, N/mm2
Ms = bending moment at the base, Nm
W = weight of the vessel, N
Db = bolt circle diameter, m
Bolt spacing = 2278.57 mm. Bolt spacing > 600 mm, therefore the bolt spacing is
acceptable.
1 4Ms
Ab = [ − W]
Nb fb Db
1 4(90410.92 )
Ab = [ − 6502.24 ]
8 × 125 1.574
Ab = 176.95 mm2
Taking the bearing pressure as 3.5 N/mm2, the minimum width of the base ring, Lb
Fb 1
Lb = × 3
fc 10
Lb = 0.9 mm
The required thickness for thickness base ring is found by treating the ring as cantilever
beam:
3𝑓𝑐′
𝑡𝑏 = 𝐿𝑟 √
𝑓𝑟
Take Lr = 76 mm,
Actual width required = Lr + ts + 50 mm
= 171 mm
𝐹𝑏
𝑓𝑐′ = = 18.52 N/mm2
171
3𝑓 ′
Base ring thickness, tb = 𝐿𝑟 √ 𝑓 𝑐
𝑟
= 103.4 mm
1.2.10 Flanged joint
Flanged joints are used for connecting pipes to the vessels. Type of flanged joints that been
used for this reactor is slip on flanges. It is preferred because of it is the cheapest compared
to other type of flanges, easy adjustment and it is generally used for pipe work. This flanges
joint is located at the inlet and outlet stream. Type B flanges is for inlet and outlet of liquid
and type A flanges is for the gas stream inlet at the bottom of the tank.
Type BC(mm) R(mm) H(mm) T(mm) T1(mm) T2(mm) B(mm) OD(mm) ID(mm)
A 298.45 269.75 246.13 44.45 26.29 42.93 22.35 342.9 221.49
B 431.80 381.00 365.25 55.62 30.27 54.10 25.4 482.6 327.15
1.3 SUMMARY
Table below shows the overall calculation that related to the measurement for MBBR
reactor construction
Table 11.4 Summary of MBBR reactor
0.015< 355.06
Area of one bolt, Ab mm2 176.95
Distance from the edge of the skirt to the outer edge of m 0.076
the ring, Lr
Actual width required, Lb m 0.905
Base ring thickness, tb m 0.103
Type of flanged joint - Slip on flange joint
125
16
A 6900 A
9
12
MBBR CARRIER
FACULTY OF ENGINEERING AND BUILT ENVIRONMENT
C CHEMICAL ENGINEERING PROGRAMME
PROJECT TITLE :
1219
B B 14500 B PRODUCTION OF METHANOL AND BIOFLOCCULANT
FROM POME
SIDE VIEW OF MBBR REACTOR 4 38
DRAWING TITLE :
Mechanical Drawing of MBBR Reactor (T-105)
DIFFUSER GROUP KK4
914
2804 25
GROUP MEMBERS :
25 Ravinkumar A/L Manimaran (A158192)
Cheah Ching Wei (A157594)
Siti Barakah Mohd Khairi (A158482)
Sivarpriya A/P Nadaraju (A158432)
365 Afiq Syazwan Mohd Haizollizam (A158912)
Nuredahtul Faezan Mohammad Yusop (A159291)
SUPERVISORS :
Prof IR DR Siti Kartom Kamarudin
300 Prof Madya DR Masli Irwan Rosli
7961 9827
DRAWN BY:
C Siti Barakah Mohd Khairi (A158482)
B 152
300
DETAILS C (pipe shoe clamp) DESIGN SPECIFICATIONS :
ID
14500 H
TOP VIEW OF MBBR REACTOR T2 TEST AND STANDARD :
BC ASME Code Section UG-20
OD T1 ASME Code Section UG-21
ASME Code Section UG-31
ASME Code Section UG-44
EUROCODE 2 Reinforced Concrete Design
EUROCODE 2 Part 1
DRAWING NO:
G-4/MD/T-105/2
DATE:
24th March 2020
24
CHAPTER I
The operating temperature and pressure are 250oC and 50 bar respectively. Syngas that
consists of carbon monoxide, carbon dioxide, methane and hydrogen which some of
this component are corrosive gas while methanol that been formed are flammable and
extremely corrosive. This chemical needs special construction material to construct the
pressure vessel. Stainless steel SA-240 grade 304 is selected as the construction material
since its excellent resistance to corrosion and is available in a wide range of standard
forms and sizes. This grade is an austenitic chromium alloy which contains 18%
chromium and 8% nickel has the tensile strength (80 ksi) and yield strength (30 ksi).
The mechanical design of Packed Bed Reactor R-102 is subjected to ASME internal
pressure procedure. This is because the absolute pressure of the vessel is higher than the
atmospheric pressure, which is higher than 15 psi. Figure 6.2 below shows the shape of
the vessel and its dimension. Cylindrical body is chosen because this is the common
shape of reactor shell. The ellipsoidal heads are chosen for both bottom and top because
it is more economical, suitable for high pressure and domed to reduce mechanical
stresses.
25
The reactor is designed with a vertical vessel with 2:1 ellipsoidal head at the top and the
bottom. The construction material is stainless steel SA-240 grade 304, with corrosion
allowance of 2 mm. The operating condition for reactor R-102 is shown in Table 6.3.
Condition Values
Operating pressure, Po 50 bar (725.5psi)
Temperature, T 523.15K (250oC)
Joint efficiency, E 0.8 (single welded)
Corrosion allowance, CA 2 mm
Length 1.283 m
Diameter 0.366 m
26
= 0.0.915 m
Since the operating pressure of the reactor (50 bar) is greater than atmospheric pressure
(Pa > Patm), the reactor is designed under internal pressure. Firstly, the design pressure
for each part of the vessel is calculated by using equation:
PD = PO + 0.433h
PD = design pressure
h = height (ft)
Hence,
i. Ellipsoidal 2:1 top head, PD = 725.2 + 0.433 (0.300) = 725.33 psi
ii. Cylindrical shell, PD = 725.2 + 0.433 (3.609 + 0.300) = 726.89 psi
iii. Ellipsoidal 2:1 bottom head, PD = 725.2 + 0.433 (3.609 +0.300+ 0.300)
= 727.02 psi
A safety factor about 10% is added to design pressure for safety purpose. The new
design pressure is Pj = 1.10PD and the data is tabulated in the Table 6.4 below.
28
The wall thickness formulas for each part of the column are from ASME Code UG-32
(d) and UG-27 (c). The maximum allowable stress value, S is from ASME Code given
in Subpart 1 of Section II, Part D.
PD (797.86)(14.41)
Thickness, t = = =0.410 in
2SE−0.2P 2(17694.60)(0.8)−(0.2)(797.86)
PR (799.58)(14.41/2)
Thickness, t = SE−0.6P = (17694.60)(0.8)−(0.6)(799.58) =0.420 in
PD (799.72)(14.41)
Thickness, t = 2SE−0.2P = 2(17694.60)(0.8)−(0.2)(799.72) =0.410 in
Thus, the overall thickness, toverall is determined, which is the highest value of minimum
thickness calculated for each part
t = 10.70 + 2 = 12.70 mm
tmin = tnominal – CA
= 13.0 mm – 2 mm
= 11 mm (0.430 in)
The maximum allowable working pressure for any type pressure vessel, MAWP is
determined by calculating every part under internal pressure. The formula of internal
design pressure for each part of the reactor can be found in ASME Code UG-32 part (D)
and UG-27 part (c). By using tmin from the calculation above, the MAWPvessel is
calculated.
The value of internal pressure and MAWPvessel is obtained and the result is shown.
Table 1.5 Internal pressure and MAWPvessel for each part of the reactor R-102
Part of the column MAWPpart (psi) Static head, PH(psi) MAWPvessel (psi)
Top ellipsoidal head 845.81 0.13 845.68
Cylindrical Shell 821.27 1.69 819.58
Bottom ellipsoidal head 845.81 1.82 843.98
By choosing the smallest value, the MAWPvessel is 819.58 psi (56.51 bar)
Pressure vessel subjected to other loads (major and subsidiary load) in addition to
pressure. Hence, it must be designed to withstand the worst combination of loading
without failure. There are the sources of combined loading which are internal and
external pressure, weight loads, wind loads, earthquake (seismic load), and eccentric
loads (Sinnott 2005). All of these are related to primary stresses and summarized into
principal stresses in the end of calculation.
a. PRIMARY STRESSES
(iii)Bending stresses ( b )
= 45.865 N/mm2
𝑃𝐷𝑖
σh = 2𝑡
5.497 (366)
=
2(11)
= 91.730 N/mm2
Cv = 1.08
Dm = Di + t = 0.366 + 0.011 = 0.377 m
Hv = 2 2
hc + he = 1.1+ 3 (0.092) = 1.161 m
3
t = 11 mm
𝑊
Direct stress, σw = 𝜋 (𝐷𝑖+𝑡)𝑡
1.5722
= 𝜋 (366+11)11
32
𝑀 𝐷
Hence, Bending stresses, σb = ± 𝐼 ( 2𝑖 + 𝑡)
𝑣
= ± 0.280 N/mm2
1
σ1 = 2 [σh + σz + √(σh − σz )2 + 4τ2 ]
33
1
σ2 = 2 [σh + σz − √(σh − σz )2 + 4τ2 ]
= 91.730 N/mm2 = σh
1
σ2 = 2 [𝜎ℎ + 𝜎𝑧 − √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
1
= 2 [91.730 + 46.145 − √(91.730 − 46.145)2 + 4(0)2 ]
= 91.730 N/mm2 = σh
1
σ2 = 2 [𝜎ℎ + 𝜎𝑧 − √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
1
= 2 [91.730 + 45.585 − √(91.730 − 45.585)2 + 4(0)2 ]
d. Elastic Stability
E t
Critical buckling stress, c
3 1 v2 R
p
35
For steel at ambient temperature, E = 200000 N/mm2 with a safety factor of 12, the
σc = 2 x 104 (t / D0) = 2 x 104 (11 / 0.388) = 567.01 N/mm2
(∑ 𝜎)𝑐𝑜𝑚𝑝𝑟𝑒𝑠𝑠𝑖𝑣𝑒 = σb + σw = 0.280 + 0.00011725 = 0.280 N/mm2
Since the value of (∑ 𝜎)𝑐𝑜𝑚𝑝𝑟𝑒𝑠𝑠𝑖𝑣𝑒 ˂ σc, therefore, the design is safe to use.
From the analysis of combined loading, the material we chose has fulfilled both
requirements of maximum stress intensity and elastic stability:
Δσ max S and (∑ 𝜎𝑐𝑜𝑚𝑝𝑟𝑒𝑠𝑠𝑖𝑣𝑒 ) < 𝜎𝑐 Therefore, the design is safe.
The vessels support must be designed to withstand the weight of the vessel including
weight of material are packed inside and contents and any superimposed loads such as
wind loads. Support will impose localized loads on the vessel wall, and the design must
be checked to ensure resulting stress concentrations are below the maximum allowable
design stress. It is also important to allow the ease of access to the vessel and the fittings
for inspection and maintenance (Sinnott 2005).
a. THICKNESS OF SUPPORT
The skirt support had been chosen as the support for distillation column. Since the
height of distillation column, H = 1.283 m with the internal diameter, Di = 0.366 m, the
skirt support is suitable for the use of tall vessel which subject to wind loading.
𝑊
Dead weight stress in the skirt, σws = 𝜋(𝐷 +𝑡
𝑠 𝑠 )𝑡𝑠
Maximum dead weight load on the skirt will occur when the vessel is full of water.
𝜋
Approximate weight = (4 × 0.3662 ) × 1.283 × 1000 × 9.81
= 1324.182 N
Weight of vessel = 1.5722 N
Weight of catalyst = 1252.026 N
Total weight, W = 1324.182 + 1.5722 + 1252.026 = 2577.78 N
= 2.578 kN
For the bending stress in the skirt, bs
𝑊𝑥 2
Maximum bending moment, Ms = 2
(2577.78)(1.6619)2
= 2
= 685.095 Nm
Hence,
4(685.095 × 1000 )
Bending stress in the skirt, bs = 𝜋(366+11)(366)(11)
= 0.417 N/mm2
𝑊
Dead weight stress in the skirt, σws (hydraulic test) = 𝜋(𝐷 +𝑡
𝑠 𝑠 )𝑡𝑠
1.5722
=
𝜋(366+11)11
= 0.000088 N/mm2
𝑊
Dead weight stress in the skirt, σws (operating) = 𝜋(𝐷 +𝑡
𝑠 𝑠 )𝑡𝑠
2577.78
= 𝜋(366+11)11
= 0.144 N/mm2
Therefore, resultant stresses
Maximum σs (tensile) = σbs – σws = 0.417 – 0.000088 = 0.4169 N/mm2
σs (compressive) = σbs + σws = 0.417 + 0.144 = 0.561 N/mm2
37
The skirt thickness under the worst combination of wind and dead weight loading
should not exceed the following design criteria.
σs (tensile) ˂ fs J sinθs
σs (compressive) ˂ 0.125E (ts/Ds) sinθs
Assumptions:
maximum allowable stress for skirt material at Tamb = 20°C, fs = 138 N/mm2
weld joint factor, J = 0.8
base angle, θs = 90°
Yong’s modulus, E = 200000 N/mm2
Therefore,
fs J sinθs = 122(0.8) sin (90°)
= 97.533 N/mm2
Since both criteria are satisfied, thus, the assumed value of skirt thickness, ts = 0.011 m
is acceptable. With corrosion allowance of 4 mm, the design skirt thickness, ts = 0.015
m.
The loads carried by the skirt will be transmitted to the foundation slab by the skirt base
ring. The moment produced by wind and other lateral loads will tend to overturn the
pressure vessel. This will be opposed by the couple set up by the weight of the vessel
and the tensile load of the anchor bolts (Sinnott 2005).
38
The anchor bolts are assumed to share the overturning load equally and the bolt area
required:
1 4Ms
Ab = [ − W]
Nb fb Db
Assumptions:
bolt circle diameter, Db = 1.550 m = 1550 mm
circumference of bolt circle = 1550 π mm = 4869.469 mm
maximum allowable bolt stress, fb = 100 N/mm2
take number of bolts as 8
𝜋×1.550×1000
Bolt spacing = = 608.68 mm
8
Bolt spacing > 600 mm, therefore the bolt spacing is satisfactory.
1 4Ms
Ab = [ − W]
Nb fb Db
1 4(685.095 )
Ab = [ − 1.5722 ]
8 × 100 1.550
Ab = 41.080 mm2
4Ms W
Fb = [ + ]
πD2s πDs
4(685.095) 1.5722
Fb = [ + ]
π x 0.3662 π × 0.366
Fb = 6513.133 Nm−1
Taking the bearing pressure as 3.5 N/mm2, the minimum width of the base ring, Lb
Fb 1
Lb = × 3
fc 10
6513.133
Lb =
3.5x 103
Lb = 1.861 mm
Flanged joints are used for connecting pipes and instruments to vessels, for manhole
cover, and for removable vessel heads when ease of access is required for maintenance
or inspection. It also used on the vessel body when it is required to divide the vessel
into sections for transport and maintenance. It can reduce high-stress concentration at
the base of the flange by transferring stress to the adjoining pipe. Welding-neck flange
is the best-designed butt weld available because of its inherent structural value and ease
of assembly. Welding-neck flange have high strength and high resistance to dishing, it
is manufactured with a long-tapered hub. The tapered hub is created by the gradual
increase in metal thickness from the weld join to the flange facing. The welding-neck
flange diagram is shown in Figure 6.3.2
40
Table 1.7 Size of flanges used for fitting on each pipe on R-102
Stream NPS D B H OD f L K N
No (mm) (mm) (mm) (mm) (mm) (mm) (mm) (mm)
60 10 90 16 35 40 2 14 60 28
61 10 90 16 35 40 2 14 60 28
By considering the internal pressure of the vessel, reactor R-102, the conditions that are
needed for the design have been calculated through series of formulae stated. The
conditions for the design our distillation column have been summarized and tabulated
as followed in Table 6.3.8.
(88.973< 122)
Elastic stability N/mm2 (∑σ)compressive < σc
REFERENCE
Ankita, I. K., Devika, G., Lakshmi Priya, K., Remya, R. & Jayamohan, J. 2016.
Applications of Geosynthetics in Embankments- A Review. International
Advanced Research Journal in Science, Engineering and Technology (IARJSET)
5(1): 31–41. doi:10.17148/IARJSET
ASME. 2013. 2013 ASME Boiler & Pressure Vessel Code 2013. ASME Boiler &
Pressure Vessel Code 802.
PRODUCED BY AN AUTODESK STUDENT VERSION
S61
Outlet R8.60
Ø392.0
91.5
Faculty of Engineering & Built Environment
R1.2573
13
Chemical Engineering Programme
Project Title:
PRODUCTION OF METHANOL AND
Drawn By:
Afiq Syazwan bin Mohd Haizollizam(A158912)
ANCHOR BOLT DESIGN Submission Date:
6th March 2020
DIMENSION (MM)
Design Specifications:
BOLT SIZE ROOT AREA D H F C - Design temperature (°C): 250
M10 58.5 10 6.63 17 18.48 - Design pressure (bar): 50
- MAWP Vessel (bar): 56.51
WELDING NECK FLANGES - Thickness vessel (mm): 13.0
- SA-204 Type 304 Stainless Steel
DIMENSION (MM)
- Straight skirt with ASME SA-516 Grade 70 Carbon
NO. NOMINAL PIPES SIZES (MM) D B OD L K N f Steel
S60 10 90 16 40 14 60 28 2 - Flanged joint with welding-neck flange class 150
S61 10 90 16 40 14 60 28 2 for all pipes
PRODUCED BY AN AUTODESK STUDENT VERSION - Bolt size M10
2
CHAPTER I
1.1 INTRODUCTION
During designing pressure vessel, design factor such as construction material and join
efficiency, corrosion allowance and design pressure are considered. The selection of
construction material depends on the ease of fabrication, suitability and construction
cost. For mechanical design of heat exchanger CO-101, carbon steel SA-516 is used as
the construction material. This is because material used has lower melting point due to
high carbon content inside the steel. Not only that, this material also are ductile and
elastic. In addition, the corrosion allowance (CA) which is 4 mm is added as additional
method to deal corrosive material as as high temperature and pressure condition. Table
1.1 shows the operating condition in Cooler CO-101.
Condition Values
SI unit English unit
Operating pressure, Po 700 kpa 101.526 (psi)
o
Temperature, T 421 C 789.8 F
Joint efficiency, E 1.0 (full radiography)
Design Stress, S 20000 psi
Corrosion allowance, CA 4 mm 0.1575 in
Length 1.78 m 70.08 in
Shell Diameter, Ds 0.35 m 13.78 in
Inner radius of cylindrical shell, R 0.18 m 7.087 in
3
Since the operating pressure of the cooler (7 bar) is greater than atmospheric pressure
(Pa > Patm), the distillation column is designed under internal pressure. Firstly, the design
pressure for each part of the vessel is calculated by using equation:
PD = PO + 0.433h
Where h= height of each part from top shell
Po= operating pressure
PD = design pressure
h = height (ft)
Hence,
PD = 101.526 + 0.433 (13.78 in x 0.0833) = 102.23 psi
A safety factor about 10% is added to design pressure for safety purpose. The new
design pressure is Pj = 1.10PD and the data is tabulated in the Table 6.4 below.
Hence,
Pj = 1.10 (102.23) = 112.23 psi
The wall thickness formulas for each part of the column are from ASME Code UG-32
(d) and UG-27 (c). The maximum allowable stress value, S is from ASME Code given
in Subpart 1 of Section II, Part D.
To account for the corrosion that might happen in the vessel, corrosion allowance is
added to each of the thickness obtained. Since the operating pressure of the vessel is
high, we choose the maximum corrosion alloance, CA = 4 mm (0.1575in)
t1 = 0.0199 + 0.1575 t2 = 0.0399 + 0.1575 T3 = 0.0199 + 0.1575
= 0.1774 in = 0.1974 in = 0.1774 in
= 4.505 mm = 5.013 mm = 4.503 mm
After going through the process of overall thickness uniformity, the overall wall
thickness can be calculated as below:
toverall = 0.1974 in = 5.013 mm
After considering the corrosion allowance of 4mm (0.1575 in).
tcalc = tuser – CA
= 0.1974 in – 0.1575 in
= 0.0399 in (2.35 mm)
toverall = 0.1974 in (5.013 mm)
The maximum allowable working pressure for any type pressure vessel, MAWP is
determined by calculating every part under internal pressure. The formula of internal
design pressure for each part of the column can be found in ASME Code UG-32 part
(D) and UG-27 part (c). By using tmin from the calculation above, the MAWPvessel is
calculated.
Longitudinal
2SEt 2(20000)(1)(0.0925)
Internal pressure = R−0.4t = = 524.96 psi
(0.18)+0.4(0.0925)
The value of internal pressure and MAWPvessel is obtained and the result is shown.
Table 1.2 Internal pressure and MAWPvessel for each part of the distillation column C-101
Part of the column MAWPpart (psi) Static head, PH(psi) MAWPvessel (psi)
Hemispherical head 520.86 0.50 520.36
Cylindrical shell
Circumferential 259.08 0.50 258.58
Longitudinal 524.96 0.50 524.47
Pressure vessel subjected to other loads (major and subsidiary load) in addition to
pressure. Hence, it must be designed to withstand the worst combination of loading
without failure. There are the sources of combined loading which are internal and
external pressure, weight loads, wind loads, earthquake (seismic load), and eccentric
loads (Sinnott 2005). All of these are related to primary stresses and summarized into
principal stresses in the end of calculation.
6
𝑃𝐷𝑖
σL = 4𝑡
0.7738 (0.35𝑥1000)
= 4(6.35)
= 10.663 N/mm2
𝑃𝐷𝑖
σh = 2𝑡
0.7738 (0.35𝑥1000)
= 2(6.35)
= 21.325 N/mm2
b. Direct stress, σw
𝑾
𝛔𝐰 = 𝝅 (𝑫𝒊+𝒕)𝒕
where, W = Wv + WI
Cv = 1.08
Height between tangent lines, Ht = 0.35 m
Mean diameter of vessel, Dm = 7.167 m
7
Hence,
Weight of shell, Wv = 1.08π(7750)(0.3564)(9.81)(0.35 +
0.8 (0.3564))(6.35x10−3 )
= 370.75 N
= 887.83 N
= 7.1376 N
𝜋(7750)(0.0162 )(1.78)(58)(9.81)
Weight of tube side fluid flow =
4
= 1578.4 N
Hence,
Total weight = 370.75 + 887.83 + 7.1376 + 1578.4 + 133.23
8
= 2977.3 N = 2.9773 kN
𝑊
Direct stress, σw = 𝜋 (𝐷𝑖+𝑡)𝑡
2977.3
= 𝜋 (350+6.35)6.35
c. Bending stresses, σb
Since the heat exchanger is in horizontal position and not considered tall, there is assued
to be no wind loads and hence the bending stress, σb = 0.
Torsional shear stresses, τ results from torque caused by loads offset from the vessel
axis. These loads will normally be small and can be neglected in preliminary vessel
designs
1
σ1 = 2 [σh + σz + √(σh − σz )2 + 4τ2 ]
1
σ2 = 2 [σh + σz − √(σh − σz )2 + 4τ2 ]
σ3 = 0.5p
Since torsional shear stress can be neglected and σ3 negligible for thin walled vessels,
the formulas above hence become:
σ1 = σh (Circumferential stress)
σ2 = σz (Longitudinal stress)
Since the bending stress, σb can be neglected for horizontal and short vessels, there will
only be one value of σz .
σz = σL + σW + σb
σz = 10.663 + 0.4188 + 0
= 11.081 N/mm2
9
Therefore,
σ1 − σ2 = 𝜎ℎ − 𝜎𝑧
= 21.325 − 11.081
= 10.244 N/𝑚𝑚2
The maximum allowable stress intensity, ∆𝜎𝑚𝑎𝑥 = 10.244 𝑁/𝑚𝑚2 . The maximum
allowable stress of Carbon steel is 20000 psi which is equivalent to 137.895 N/mm2.
Therefore, the design is partially accepted since∆𝜎𝑚𝑎𝑥 < 𝑆𝑑𝑒𝑠𝑖𝑔𝑛 .
f. Elastic Stability
Under conditions where the resultant axial stress σz due to the combined loading is
compressive, the vessel may fail by elastic instability (buckling). Local buckling will
normally occur at a stress lower than that required to buckle the complete vessel. For a
curved plate subjected to and axial compressive load, the critical buckling stress, σc is:
E t
Critical buckling stress, c
31 v2 R
p
For steel at ambient temperature, E = 200000 N/mm2, the poisson’s ratio is 0.339 and
taking safety factor of 12.
𝐷𝑜
Radius of curvature, 𝑅𝑝 =
2
10
0.35 + (2x0.0381)
= = 0.23𝑚
2
1 159068 0.0064
𝜎𝑐 = 𝑥 ( )
12 √3(1 − 0.3392 ) 0.23
= 226.36 𝑁/𝑚𝑚2
The vessels support must be designed to withstand the weight of the vessel and contents
and any superimposed loads such as wind loads. Horizontal vessel are installed on two
saddle supports as shown in figure 1.1. A vessel supported on two saddles can be known
as simple beam. The location in which the limit at the supports and at the mid is equal
in magnitude would be at an equally uniform charge and the distribution of the
longitudinal axial bending moment.
The total weight loads that have to be withstand by the saddle support is 2977.3 N with
a vessel diameter of 0.35 m. From Chemical Engineering Design (Sinnot 2009), the
11
dimension of the standard saddle support should be designed according to the following
conditions in table 1.4 where figure 1.2 illustrates the dimensions of the conditions.
Table 1.4 Standard Dimensions for Saddle Supports with Vessel Diameter 0.4m
V Y C E J G t1 t2
Bolt Diameter (mm) Bolt Holes (mm)
(m) (m) (m) (m) (m) (m) (mm) (mm)
0.32 0.1 0.37 0.16 0.127 0.063 5 4 13.33 16.67
Flanged joints are used for connecting pipes and instruments to vessels, for manhole
cover, and for removable vessel heads when ease of access is required. It also used on
the vessel body when it is required to divide the vessel into sections for transport and
maintenance. It can reduce high-stress concentration at the base of the flange by
transferring stress to the adjoining pipe. Welding-neck flange is the best-designed butt
weld available because of its inherent structural value and ease of assembly. Welding-
neck flange have high strength and high resistance to dishing, it is manufactured with a
long-tapered hub. The tapered hub is created by the gradual increase in metal thickness
from the weld join to the flange facing. The welding-neck flange diagram is shown in
Figure 6.3.
12
Table 1.5 Size of flanges used for fitting on each pipe on CO-101
Pipe A B C D H J K P Diameter
Size (mm) (mm) (mm) (mm) (mm) (mm) (mm) (mm) of bolt
holes
3.5 228.6 139.7 30.16 90.12 101.6 133.35 80.96 184.15 22.23
By considering the internal pressure of the vessel, Cooler CO-101, the conditions that
are needed for the design have been calculated through series of formulae stated. The
conditions for the design our cooler have been summarized and tabulated as followed
in Table 6.8.
(21.235< 226.36)
Type of vessel support - Saddle Support
Type of flanged joint - Welded flanged joint
25
a a
350 350
G J J
t2 Y E E
WELDING NECK FLANGE
CONNECTION NOMINAL SIZE (in) A B C D H J K
No of Bolt Holes
(NBH)
Diameter of Bolt
Holes (DBH)
P Approx. Weight (ib) AW DRAWING NOT TO SCALE
C T1 2 165.1 92.1 22.2 52.5 60.3 84.1 69.9 8 19.1 127.0 9
UNITS DIMENSION IN MILLIMETER
SADDLE SUPPORT AND VIEW FROM A
T2 2 165.1 92.1 22.2 52.5 60.3 84.1 69.9 8 19.1 127.0 9
(MM)
Stream 53a 3 1/2 228.6 139.7 30.2 90.1 101.6 133.4 81.0 8 22.2 184.0 18
Stream 54 3 1/2 228.6 139.7 30.2 90.1 101.6 133.4 81.0 8 22.2 184.0 18
Date : 14th March 2020
1
CHAPTER I
Phase separator (S-102) in the process is to separate liquid from the gaseous mixture
containing methane, carbon dioxide, carbon monoxide, hydrogen, before the further
separation of the methanol from the waste water in distillation column (C-101). The inlet
of the phase separator consists of methane, carbon dioxide, carbon monoxide, hydrogen,
water and methanol. At the end of the separation, water and methanol will be leave as
bottom product while methane, carbon dioxide, carbon monoxide, hydrogen, and some
amount of water and methanol will leave as top product. The inlet temperature and pressure
of the stream are 50 oC and 30 bar. Figure 1.1 shows the phase separator to be designed and
the flow rate of each component at the inlet and outlet after flash calculation . In order to
know the vapor fraction of the phase separator, isothermal flash calculation is being done
first. F63CH4 = 149 kg/h
F63CD = 201.8 kg/h
F63CM = 381.4 kg/h
F63H = 17.6 kg/h
F62CH4 = 149 kg/h F62W = 1.8 kg/h
F62CD = 201.8 kg/h F62M = 6.4 kg/h
F62CM= 381.4 kg/h
F62H = 17.6 kg/h
F62W = 237.7 kg/h
F62M= 181.4 kg/h
F66W = 235.9 kg/h
F66M = 175 kg/h
Then by using Roult’s law, find the K-value for each compenent,
Ki = Psat/P
Make an initial guess for the vapor fraction, V which is ranging from 0 to 1 and
iterative procedure is repeated until total moles of vapor with its mole fraction, y is 1. Table
1.1 shows the Vguess and the ∑y obtained. ∑y is 1 when vapor fraction is at 0.64. After
obtaining the V and y value, x can be calculated. Table 1.2 shows the summary of the
calculation.
zi K i
∑ yi = ∑ =1
1 + V(K i − 1)
i i
xi = yi/Ki
Vguess ∑y
0.83 1.1
0.72 1.07
0.64 1
3
Vessel Diameter
Physical properties of the liquid and vapor in the vessel were determined and shown in
table In order to start calculating the diameter and height of the phase separator, some of
the physical properties of the streams need to be determined first.Table 1.3 shows the
physical properties needed to calculate the diameter and height of vessel.
Terminal velocity,
ut = 0.58 m/s
As the separation design at k value already includes an exit mist eliminator, a design
factor of 100% is apply. Thus, ut = ud = 0.58 m/s
Dv calculated is too small, iteration have been made and vessel diameter is 0.86m.
Vessel Height
Figure 1.2 shows the schematic diagram of phase separator. The height of the separator will
be calculated by section as shown in the diagram.
h7
h6
D
h5
h4
h3
h2
h1
For height from low liquid level (LLL) to bottom tangent line, h1,
V = 0.00013 x 25 x 60 = 0.195 m3
For surge height or height from normal liquid level (NLL) to HLL, hn
hn = 0.078 m
6
h2 = hL + hn =0.466 m
For height from HLL to the inlet nozzle, if h3 calculated is less than 0.3, then h3 is 0.3m.
For inlet nozzle diameter, if h4 calculated is less than 0.4064m, then set h4 at 0.4064m.
𝑣𝐿
λ=𝑣 = 0.001
𝐿 +𝑣𝑉
Where vm = vL + vv (m3/s),
ρm = ρL λ + ρV (1 − λ) (kg/m3)
h6 = 0.15 m
7
For height from mist eliminator to the top tangent line, if h7 calculated is less than
0.3 m, set h7 at 0.3 m.
Height of separator,
hT = h1 + h2 + h3 + h4 + h5 + h6 + h7
hT = 2.37 m
VT = π(Dv/2)2hT = 1.367 m3
Table 1.4 shows the summary of the results obtained from manual calculation of the
phase separator S-102.
8
CHAPTER II
Phase separator (S-102) is used to carry out the phase separation to purify methanol. Since
the operating pressure for this reaction is greater than the atmospheric pressure, the phase
separator is designed based on the internal pressure. Table 2.1 summarizes the operating
conditions and dimension of S-102.
Types of head and shell are assumed based on the operating conditions and process in order
to design the mechanical drawing for phase separator S-102. A vertical cylinder is chosen
as the shell whereas ellipsoidal type head is chosen for both top and bottom head of phase
separator . The selection parts for mechanical design for S-102 are listed in Table 2.2.
The shape of ellipsoidal head is defined by the ratio of the major and minor axis. This will
have a depth of head which is quarter of the vessel’s internal diameter, D as shown in Figure
2.1. Ellipsoidal head is chosen compared to spherical and torispherical head because
ellipsoidal can withstand high pressure better compare to others.
Before proceeding with detailed mechanical drawing for this process equipment, there are
some design factors that need be considered and justified first.
a. Design Pressure
Design pressure is being calculated by adding hydrostatic pressure to the operating pressure
of the vessel.
PD = Po + 0.433h
Therefore,
Safety factor about 10 % is considered to the design pressure, PD to prevent vessel failure
during minor process upsets. The new design pressure added with safety factor will be PJ
= 1.10PD and shown in Table 2.4.
12
Table 2.4 Design pressure for each part of phase separator, S-102
Parts of phase separator PD (psi) PF (psi)
Ellipsoidal 2:1 top head 435.417391 478.9591297
Cylindrical shell 438.787676 482.6664439
Ellipsoidal 2:1 bottom head 439.091854 483.0010391
b. Design temperature
The design temperature of vessel, T is taken as the maximum operating temperature of the
phase separator which is 50 ºC.
c. Materials of construction
Stainless Steels Type 304 is used as our material to construct this phase separator because
these steels exhibit excellent corrosion resistance to a wide range of atmospheric, chemical,
textile, petroleum and food industry exposures. Since the vessel operate at a considerably
pressure and acidic condition(vapor mixture consist of carbon dioxide which is acidic),
stainless steel type 304 is suitable as the material of construction for the vessel.
The maximum allowable stress for Austenitic Stainless Steels Type 316 the at temperature
50ºC is 𝑆 = 19290 𝑝𝑠𝑖.
e. Joint efficiency
A double–welded butt joint with partial degree of radiography is used where the joint
efficiency is 0.85 (ASME code, Table UW-12 Section VIII Part D, 2010).
13
f. Corrosion allowance
A minimum corrosion allowance of 2 mm will be used since the reactants and the product
produce is not highly corrosive substance.
g. Design Loads
The vessel is generally subjected to major and subsidiary loads. Proper care must be taken
to determine the combination of possible loads which gives the worst situation and design
for that loading conditions. Summary of all design specifications is listed in Table 2.5
below
According to UG16, the vessel is classified as thin-walled vessels since value of t/D is
0.007, significantly smaller than 1.10. In this case, all calculations are performed upon each
parts of vessel on determining thickest tmin which is then is used to determine the maximum
allowable working pressure of vessel, MAWPvessel.
14
i. Cylindrical Shell
Circumferential Stress
Referring to ASME Code Part UG.27(c) (1), thickness for circumferential cylinder is
PR
t=
SE − 0.6 P
(482.67)(16.86)
𝑡=
(19290)(0.85) − 0.6(482.67)
𝑡 = 0.502 𝑖𝑛
= 12.83 mm
Longitudinal Stress
Referring to ASME Code Part UG.27(c) (2), thickness for longitudinal cylinder is
PR
t=
2 SE + 0.4 P
(482.67)(16.86)
𝑡=
(2)(19290)(0.85) + 0.4(482.67)
𝑡 = 0.505 𝑖𝑛
= 12.833 mm
15
Top Head
Referring to ASME Code Part UG.32 (d) (1), thickness for top cover of vessel is
PD
t=
2 SE − 0.2 P
(478.96)(16.86)
𝑡=
(2)(19290)(0.85) − 0.2(478.96)
𝑡 = 0.494 𝑖𝑛
= 12.55 mm
Bottom Head
Referring to ASME Code Part UG.32 (d) (1), thickness for bottom cover of vessel is
PD
t=
2 SE − 0.2 P
(483)(16.86)
𝑡=
(2)(19290)(0.85) − 0.2(483)
𝑡 = 0.4981 𝑖𝑛
= 12.65 mm
16
Summary of design pressure and thicknesses calculated from each part is tabulated in Table
2.6
The minimum thickness for whole vessel is chosen from the highest value of thickness
calculated for each part. Therefore, the calculated minimum thickness of vessel is 12.83
mm since this is the largest value.
tuser = tcalc + CA
= 12.83 + 2 mm
= 14.83 mm
The thickness obtained is then compared with the nominal thickness available for austenitic
stainless steel SA-316. The nearest value of nominal thickness is chosen as tnominal which is
16 mm. Minimum thickness for vessel is calculated by subtracting back the corrosion
allowance from the nominal thickness.
= 14 mm
Therefore, after uniformity the minimum thickness for the vessel is 14 mm.
17
MAWPpart for each part of phase separator, S-102 are calculated by using minimum
thickness, tmin = 14 mm as in previous part.
a. Cylindrical Shell
i. Circumferential Stress
Referring to ASME Code Part UG.27(c) (1), pressure for circumferential cylinder is
SEt
P=
R + 0.6t
(19290)(0.85)(0.55)
𝑃=
(16.86) + 0.6(0.55)
𝑃 = 1051.45 𝑝𝑠𝑖
Referring to ASME Code Part UG.32 (d) (1), pressure for both ellipsoidal top and bottom
head is
2 SEt
P=
D + 0.2t
2(19290)(0.85)(0.55)
𝑃=
(1.1) + 0.2(0.55)
𝑃 = 534.29 𝑝𝑠𝑖
18
By taking the lowest MAWPvessel as the MAWP for the vessel, the maximum allowable
pressure of the vessel is 530.31 psi.
As discussed previously, pressure vessels are subjected to other loads as well other than
pressure such as major and subsidiary loads. Therefore, combined loading analysis is
performed to the vessel so that it can withstand any worst combination of loadings without
failure. However, the main objective of this analysis is to make sure that the pressure vessel
is safely designed by analyzing the primary stresses and elastic stability.
For a cylindrical shell, primary stresses are required to achieve a static equilibrium
which includes longitudinal and circumferential stresses due to internal or external
pressure, direct stress, bending stress and torsional shear stress.
a. Weight of Vessel, Wv
Cv = 1.08
19
= 0.87 m
Hv = 2.37 m
Wv = 11.1 kN
a. Primary Stresses
i. Longitudinal Stress, σL
PDi
L =
4t
20
(3)(856)
𝜎𝐿 =
4(16)
𝜎𝐿 = 40.11 𝑁/𝑚𝑚2
PDi
h =
2t
(3)(856)
𝜎ℎ =
2(16)
𝜎ℎ = 80.24 𝑁/𝑚𝑚2
b. Direct Stress
WV
w =
( Di + t )t
11109
𝜎𝑤 =
𝜋(872)16
𝜎𝑤 = 0.253 𝑁/𝑚𝑚2
w is a compressive stress and the value will be -0.253 N/mm2 since the points are above
the support.
21
c. Bending Stress
M x Di
b = ( + t)
IV 2
Do = Di + 2(t)
= 0.888 m
IV = ( Do 4 − Di 4 )
64
𝜋
𝐼𝑉 = (8884 − 8564 )
64
𝐼𝑉 = 4.17𝑥109
22
Deff = Do
= 0.888 m
wx 2
Mx =
2
x = hv = 2.37 m
(1137.25)(2.37)2
𝑀𝑥 =
2
𝑀𝑥 = 3200.46 𝑁. 𝑚
M x Di
b = ( + t)
IV 2
23
3200.46 856.47
𝜎𝑏 = ± ( + 16)
4.17𝑥109 2
𝜎𝑏 = 0.34 𝑁/𝑚𝑚2
The torsional shear stresses can be neglected in preliminary design because these loads will
normally be small, τ = 0.
By using values that obtained from longitudinal stresses, direct stress and bending stress,
principal stresses are determined by performing calculation below.
σz (upwind) = σ L + σw + σb
= 40.71 N/mm2
σz (downwind) = σL + σw - σb)
= 40.03 N/mm2
Since torsional shear stress is negligible, therefore σ1 = 80.24 N/mm2 ,σ2 = 40.03 N/mm2
and σ3 =1.5 N/mm2.
24
The maximum intensity of stress allowed will depend on the theory of failure adopted in
the design method. The maximum shear-stress theory is normally used for pressure vessel
design. The vessel wall thickness must be enough to ensure the maximum stress intensity
does not exceed the design stress for the material of construction.
(Δσ) max = σ 1 - σ3
= 78.74 N/mm2
For austenitic stainless steel, SA-304 maximum allowable stress is 11700 psi, (ASME code
Subpart 1 Stress Table 1A).
= 132.9 N/mm2
Value of (Δσ)max must be smaller than Sdesign in order for the material to be safely used for
construction.
g. Elastic Stability
Under conditions where the resultant axial stress σz due to the combined loading is
compressive, the vessel may fail by elastic instability (buckling). Local buckling will
normally occurs at a stress lower than that required to buckle the complete vessel.
Therefore, the mechanical design must be checked to ensure that the maximum value of
resultant axial stress does not beyond the critical value at which the buckling occur.
i. Critical buckling, σc
E t
c = ( )
3(1 − v 2 ) Rp
t
c = 2 x104
Do
16
𝜎𝑐 = 2𝑥104
888.47
𝜎𝑐 = 360.17 𝑁/𝑚𝑚2
∑σcompressive = σ b + σw
= 0.087 N/mm2
26
σcompressive < σc
From comparison above, it is found that the maximum allowable compressive stress is well
above the critical buckling stress. Thus, the design is safe and the buckling process does
not occur. Material chosen is suitable for design purpose.
The support chosen must be able to carry weight of the vessel, contents and any
superimposed loads, for example wind loads. Moreover, the design must be checked to
ensure the resulting stress concentrations are below the maximum allowable design stress
and the vessels as well as fittings are able for inspection and maintenance.
Phase separator S-102 is assumed arranged vertically. Straight skirt support is being chosen
for this phase separator since it is usually used for vertical vessels as they do not impose
concentrate loads on the vessel shell.
27
Skirt supports consists of a cylindrical shell welded to the base of the vessel. A
flange at the bottom of the skirt transmits load to the foundations. Secondly, the design
must consist a reinforced opening. Skirt thickness is a core in supports design. The skirt
thickness must be sufficient to withstand the dead-weight loads and bending moments
imposed on it by the vessel and it will not be under the vessel pressure.
where:
4M s
bs =
( Ds + ts )ts Ds
W
ws =
( Ds + ts )ts
= 4.05
wx 2
Ms =
2
= 7.46 kN/mm2
4M s
Bending stress in the skirt, bs =
( Ds + ts )ts Ds
W
Dead weight stress in the skirt, ws =
( Ds + ts )ts
= 0.666 N/ mm2
The skirt thickness under any worst combination of wind and dead weight loading should
follow the below design criteria:
σs (tensile) < fs J sin θs and σs (compressive) < 0.125E (ts / Ds) sin θs
From the calculations and justifications, it is shown that the skirt thickness fulfill both
conditions. Since both the criteria are satisfied, assumptions for the value of skirt thickness,
t = 16 mm is acceptable.
30
The loads carried by the skirt will be transmitted to the foundation slab by skirt base ring.
The moment produced by wind and other lateral loads will tend to overturn the pressure
vessel and this will be opposed by the couple set up by the weight of vessel and tensile load
of the anchor bolts. For this phase separator S-102, double plate with gusset is chosen in
order to make the vessel more stable and strongly built as shown in Figure 11.2
The anchor bolts are assumed to share the overturning load equally, and the bolt area
required is given by:
1 4M s
Ab = [ −W ]
N b fb Db
Where,
Nb = Number of bolts
31
Assumptions made:
1) Db = 1.6 m
1 4M s
Ab = [ −W ]
N b fb Db
𝐴𝑏 = 7.54 𝑚𝑚2
The base ring must be sufficiently wide to distribute the load to the foundation. The total
compressive load on the base ring per unit length,
4M s W
Fb = +
DS DS
2
𝐹𝑏 = 17.08 𝑘𝑁/𝑚
Fb 1
Lb =
f c 1000
With maximum allowable bearing pressure within range 3.5 N/mm2 – 7.0 N/mm2
𝐿𝑏 = 4.88 𝑚𝑚 (theoretical)
3 fc
tb = Lr
fr
Where
Lr = distance from the edge of the skirt to the outer edge of the ring (mm)
3 fc
tb = Lr
fr
3(3.5)
𝑡𝑏 = 76√
0.127
𝑡𝑏 = 3.97 𝑚𝑚
Thus, the required minimum thickness for the base ring is 3.79 mm. It is concluded
that the designed straight skirt support is suitable for phase separator S-102 because the
calculated bolt root area is 7 mm2 which is much lower than the M24 bolt root area.
Minimum number of bolt is used which is 8.
The flanges chosen to be used for the design of this vessel are welding neck flanges joints.
The optimum size of the stainless steel pipe can be determined using the below equation.
ρ = density, kgm-3
34
Figure 12.6.5 Dimensions of weld flange joint, Class 150 steel Pipe
Source: Global Supply Line 2019
SUPERVISOR:
1) PROF. IR DR. SITI KARTOM KAMARUDIN
600
2) PROF. MADYA DR. MASLI IRWAN ROSLI
INDUSTRIAL SUPERVISOR:
1) HEMAVATHI SILVAMANY
C C
PREPARED BY:
CROSS-SECTIONAL SINGLE PLATE
AREA OF MANHOLE CROSS SECTIONAL OF KK 4
WELDING NECK FLANGE WITH GUSSET
406
GROUP MEMBERS:
1) RAVINKUMAR
2) CHEAH CHING WEI
S62 100
300
3) NUREDAHTUL FAEZAN
4) SITI BARAKAH
152 5) AFIQ SYAZWAN
R914 6) SIVA PRIYA
SCALE:
914 DRAWING NOT TO SCALE
485
140 DIMENSION:
ALL DIMENSIONS IN MM
103.9 d3
DRAWN BY:
150
CHEAH CHING WEI (A157594)
d1 24 SUBMISSION DATE:
23/03/2020
T DESIGN SPECIFICATIONS:
S66 1250
d2 Phase Separator (S-102)
76
B
Top head height (mm) : 214
f
Shell height (mm) : 2372
Bottom head height (mm) : 214
134
d4 Design temperature (°C) : 50
6 Design pressure (kPa) : 3000
k
8 Design thickness (mm) : 16
D
Corrosion allowance(mm) :2
WELDING NECK FLANGES
Ellipsoidal heads and cylindrical shell with
DIMENSION (MM) ASME UNS 30400 / SA-240 Type 304 Stainless Steel
NO NOMINAL PIPES SIZES (MM) d1 D B T d4 f d2 k d3
S62 406 438 711 60 158.75 533 2 35 629 533 Straight skirt with ASME SA-516 Grade70
S63 14 16 95 14 52 35 2 16 67 38 Carbon Steel
S66 33 41 155.45 21 68.33 73 2 22 114 70
Bolt size M24 with BS 4190:1967
1.1 INTRODUCTION
Distillation column is a unit operation used to separate components which have different
volatility by using boiling point as a reference. In C-101, the feed contains methanol
and water. The function of C-101 is to separate methanol from water to increase the
purity of final product. Methanol is identified as the light key component (LK) while
water as the heavy key (HK) component since methanol has lower boiling point
compared to water. Figure 1.1 shows distillation column C-101 with its operating
condition tabulated in Table 1.1. Table 1.2 shows the flow rate of each stream
connecting to the column.
69 CO-104 Distillate
RD-101 70
66 P-107
Feed
Bottom
67 68
C-101
H-102
The type of tray that has been used in this distillation column is sieve tray column
because sieve tray column has good efficiency due to its minimum back mixing. Besides
that, the cost for sieve tray is relatively low.
The pressure vessel design codes and standards include lists of acceptable materials, in
accordance with the appropriate material standards. Since flash tank deals with
relatively clean fluids which is free of corrosive and erosive components, hence a
carbon steel SA-516 is selected as construction material.
3
Assumptions:
Assumptions:
At steady state there are no any material losses, material accumulation and
material generation.
There is no any chemical reaction inside the column
F=D+W
18.85 = D + W
Material balance:
Fx = Dx + Wx
D = 8.054 kmol/hr
W = 10.796 kmol/hr
4
0 0 100
0.3 0.66 78
0.9 0.96 66
1 1 64.5
85
80
Vapour
75
Liquid
70
65
60
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Methanol composition
q=1
For many systems the optimum selection of the design reflux ratio will lie between 1.2
to 1.5 times the minimum reflux ratios. Assume operating reflux ratio is 1.25 of
minimum reflux ratio.
𝑅𝑚𝑖𝑛
= 0.4872
𝑅𝑚𝑖𝑛 + 1
𝑅𝑚𝑖𝑛 = 0.95
R = 1.25 × 𝑅𝑚𝑖𝑛
R = 1.25 × 0.95
R = 1.1875
1.1875
= 1.1875+1
= 0.5429
y = 0.5429x + 0.45
6
According to Figure 1.3, the vapour- liquid equilibrium curve counts number of
theoretical plates.
There are total condenser and partial reboiler. Total condenser does not act as
equilibrium stage, but partial reboiler acts as equilibrium stage. So, reboiler stage need
to reduce from total theoretical stages.
= 14
1.1875 = 𝐿𝑜 /8.054
𝐿𝑜 = 9.564 𝑘𝑚𝑜𝑙/ℎ𝑟
Ln = Lo = 9.564 kmol/hr
7
Material balance:
Vn = Lo + D
Vn = 9.564 + 8.054
Vn = 17.618 kmol/hr
According to given data, feed is at saturated liquid condition therefore all feeding
liquids join with stripping section liquid.
Lm = F + Ln
Lm = 18.85 + 9.564
Lm = 28.414 kmol/hr
Vm = Vn
Vm = 17.618 kmol/hr
Temperature (◦C) Density of liquid mixture (kg/m3) Density of vapour mixture (kg/m3)
77 892.15 1.45
65 761.12 1.11
ρL = 826.6 kg/m3
ρV = 1.28 kg/m3
8
Similarly;
𝐿 𝜌𝑉
𝐹𝐿𝑉 = √
𝑉 𝜌𝐿
9.564 1.28
𝐹𝐿𝑉 = √
17.618 826.6
𝐹𝐿𝑉 = 0.0214
K1 = 0.084
The flooding velocity can be estimated from the correlation given by Fair.
𝜌𝐿 − 𝜌𝑉
𝑈𝑓 = 𝐾1 √
𝜌𝑉
826.6 − 1.28
𝑈𝑓 = 0.084√
1.28
𝑈𝑓 = 2.13 𝑚/𝑠
Ua = 0.8 × 2.13
Ua = 1.71 m/s
9
= 32 × 0.5 + 18 × 0.5
= 25 kg/kmol
Vn = 0.122 m3/s
𝑉𝑛
= 𝑈𝑎
𝐴𝑛
0.122
𝐴𝑛 =
1.71
𝐴𝑛 = 0.0717𝑚2
An = Ac – Ad
Assume Ad = 12% of Ac
An = Ac – 0.12Ac
An = 0.88Ac
0.0717 = 0.88 × Ac
Ac = 1.85 m2
𝜋𝐷𝑐2
𝐴𝑐 =
4
𝜋𝐷𝑐2
1.85 =
4
Dc = 1.534 m
28.414 1.095
𝐹𝐿𝑉 = √
17.618 922.6
10
𝐹𝐿𝑉 = 0.0556
K1 = 0.08
922.64 − 1.095
𝑈𝑓 = 0.08√
1.095
𝑈𝑓 = 2.32 𝑚/𝑠
Ua = 0.8 × 2.32
Ua = 1.86 m/s
Vm = 0.122 m3/s
𝑉𝑛
= 𝑈𝑎
𝐴𝑛
0.122
𝐴𝑛 =
1.86
𝐴𝑛 = 0.0659 𝑚2
An = 0.88Ac
Ac = 1.75 m2
Dc = 1.49 m
Hole size less than 6.5 mm. Entrainment may be greater with larger hole sizes. (Page
No. 568 Coulson & Richardson 6th volume 4th edition).
For a plate, there is one downcomer on the plate and top downcomer also affected to
bottom plate. Therefore, two downcomer areas need to be reduced from the active area.
Aa = Ac – 2Ad
Aa = Ac – (0.12 × 2Ac)
Aa = 0.0619 m2
Ah = 0.1Aa
= 0.00619 m2
0.0062
Area of a hole =π× 4
= 2.83 × 10-5 m2
0.00619
Number of hole in a plate = 2.83 × 10−5
= 219
Aa = 0.0569 m2
Ah = 0.1Aa
Ah = 0.00569 m2
0.00569
Number of hole in a plate = 2.83 × 10−5
= 201
12
Maximum and minimum temperatures of inside the column are respectively 100˚C and
65˚C. Assume liquid temperature is average temperature of column. Assume properties
of liquid mixture equal to water properties.
100+65
Average temperature of column = 2
= 82.5˚C
Surface tension of liquid at 82.5˚C is calculated according to their molar basis of feed.
σL = 0.0513 N/m
Uv = Ua
Uv = 1.86 m/s
Since there are both vapour and liquid densities, the average density is taken.
ρV = 1.19 kg/m3
ρL = 874.62 kg/m3
𝑎𝑟𝑒𝑎 𝑜𝑓 ℎ𝑜𝑙𝑒𝑠
FA = Fractional Area = 𝑡𝑜𝑡𝑎𝑙 𝑐𝑜𝑙𝑢𝑚𝑛 𝑐𝑟𝑜𝑠𝑠 𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑎𝑙 𝑎𝑟𝑒𝑎
0.005691
FA = 0.625
FA = 0.00911
0.0513
𝐷𝑔 =
0.0004862 × 1.86
Dg = 56.83
0.0004862
𝑆𝑐 =
874.62 × 5 × 10−9
Sc = 111
ℎ𝑤 × 𝑈𝑣 × 𝜌𝑣
𝑅𝑒 =
𝜇𝐿 × 𝐹𝐴
Therefore,
14
0.89 =
𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑎𝑐𝑡𝑢𝑎𝑙 𝑠𝑡𝑎𝑔𝑒𝑠
= 0.08 m
= 7.69 m
Feed composition of methanol is 0.29. This value is at 11th plate (theoretical) of the
column. To calculate the actual feed tray location, the value need to be divided with
column efficiency.
11
Therefore feed tray location = 0.89
= 12.33
= 13th plate
15
2.1 INTRODUCTION
The operating temperature and pressure are 50oC and 28 bar respectively. Methanol is
a flammable gas. This chemical needs special construction material to construct the
pressure vessel. Carbon steel SA-516 grade 70 is selected as the construction material
since it has a lower price than other materials and is available in a wide range of standard
forms and sizes (Towler & Sinnot 2013). Iron is the main composition of this material.
Carbon steel SA-516 grade 70 has the highest tensile strength (70-90 ksi) and yield
strength (38 ksi) among the other grades.
Di
The distillation column is designed with a vertical vessel with 2:1 ellipsoidal head at
the top and the bottom. This column is designed under internal pressure, 406.1 psi (28
bar). The construction material is carbon steel SA-516 grade 70, with corrosion
allowance of 2 mm. The operating condition for distillation column C-101 is shown in
Table 2.1.
= 0.375 m
Since the operating pressure of the distillation column (28 bar) is greater than
atmospheric pressure (Pa > Patm), the distillation column is designed under internal
pressure. Firstly, the design pressure for each part of the vessel is calculated by using
equation:
PD = PO + 0.433h
Where h= height of each part from top shell
19
A safety factor about 10% is added to design pressure for safety purpose. The new
design pressure is Pj = 1.10PD and the data is tabulated in the Table 11.4 below.
The wall thickness formulas for each part of the column are from ASME Code UG-32
(d) and UG-27 (c). The maximum allowable stress value, S is from ASME Code given
in Subpart 1 of Section II, Part D.
For top ellipsoidal head:
PD (447.35)(60.534)
Thickness, t = 2SE−0.2P = 2(20015.2)(1)−(0.2)(447.35) =0.6780 in
Thus, the overall thickness, toverall is determined, which is the highest value of minimum
thickness calculated for each part.
toverall = 0.7024 in = 17.874 mm
The maximum allowable working pressure for any type pressure vessel, MAWP is
determined by calculating every part under internal pressure. The formula of internal
design pressure for each part of the column can be found in ASME Code UG-32 part
(D) and UG-27 part (c). By using tmin from the calculation above, the MAWPvessel is
calculated.
Longitudinal
2SEt 2(20015.2)(1)(0.7074)
Internal pressure = R−0.4t = 60.534 = 944.39 psi
( )+0.4(0.7074)
2
The value of internal pressure and MAWPvessel is obtained and the result is shown.
Table 2.5 Internal pressure and MAWPvessel for each part of the distillation column C-101
Part of the column MAWPpart (psi) Static head, PH(psi) MAWPvessel (psi)
Top ellipsoidal head 466.69 0.568 466.12
Cylindrical shell
Circumferential 461.31 10.37 455.76
Longitudinal 944.39 10.37 934.03
Bottom ellipsoidal head 466.69 10.938 458.75
Pressure vessel subjected to other loads (major and subsidiary load) in addition to
pressure. Hence, it must be designed to withstand the worst combination of loading
without failure. There are the sources of combined loading which are internal and
external pressure, weight loads, wind loads, earthquake (seismic load), and eccentric
loads (Sinnott 2005). All of these are related to primary stresses and summarized into
principal stresses in the end of calculation.
22
a. Primary stresses
= 67.583 N/mm2
𝑃𝐷𝑖
σh = 2𝑡
3.164 (1538)
= 2(18)
= 135.165 N/mm2
b) Direct stress, σw
𝑊
σw = (𝐷𝑖+𝑡)𝑡
where, W = Wv + WI
𝜋
Cv = 1.15
Dm = Di + t = 1.538 + 0.018 = 1.556 m
Hv = 2 2
hc + h = 6.9+ 3 (0.375) = 7.167 m
3 e
t = 18 mm
23
𝑊
Direct stress, σw = 𝜋 (𝐷𝑖+𝑡)𝑡
6502.24
= 𝜋 (1556+18)18
c) Bending stresses, σb
𝑀 𝐷
σb = ± 𝐼 ( 2𝑖 + 𝑡)
𝑣
𝑀 𝐷
Hence, Bending stresses, σb = ± 𝐼 ( 2𝑖 + 𝑡)
𝑣
= ± 1.529 N/mm2
1
σ1 = 2 [σh + σz + √(σh − σz )2 + 4τ2 ]
1
σ2 = 2 [σh + σz − √(σh − σz )2 + 4τ2 ]
= 135.165 N/mm2 = σh
1
σ2 = 2 [𝜎ℎ + 𝜎𝑧 − √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
1
= 2 [135.165 + 69.038 − √(135.165 − 69.038)2 + 4(0)2 ]
25
= 135.165 N/mm2 = σh
1
σ2 = [𝜎ℎ + 𝜎𝑧 − √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
2
1
= 2 [135.165 + 65.980 − √(135.165 − 65.980)2 + 4(0)2 ]
d. Elastic Stability
E t
Critical buckling stress, c
31 v2 R
p
For steel at ambient temperature, E = 200000 N/mm2 with a safety factor of 12, the
σc = 2 x 104 (t / D0) = 2 x 104 (18 / 1.574) = 228.717 N/mm2
26
From the analysis of combined loading, the material we chose has fulfilled both
requirements of maximum stress intensity and elastic stability:
The vessels support must be designed to withstand the weight of the vessel and contents
and any superimposed loads such as wind loads. Support will impose localized loads on
the vessel wall, and the design must be checked to ensure resulting stress concentrations
are below the maximum allowable design stress. It is also important to allow the ease
of access to the vessel and the fittings for inspection and maintenance (Sinnott 2005).
a. Thickness of support
The skirt support had been chosen as the support for distillation column. Since the
height of distillation column, H = 7.69 m with the internal diameter, Di = 1.538 m, the
skirt support is suitable for the use of tall columns which subject to wind loading. One
of the most important factors is they do not impose concentrated loads on the vessel
shell (Sinnott 2005).
The resultant stresses in the skirt,
σs (tensile) = σbs – σws ; σs (compressive) = σbs + σws
4𝑀
Bending stress in the skirt, σbs = 𝜋(𝐷 +𝑡 𝑠)𝑡
𝑠 𝑠 𝑠 𝐷𝑠
𝑊
Dead weight stress in the skirt, σws = 𝜋(𝐷 +𝑡
𝑠 𝑠 )𝑡𝑠
Maximum dead weight load on the skirt will occur when the vessel is full of water.
𝜋
Approximate weight = (4 × 1.5382 × 10) × 1000 × 9.81
= 140333.7998 N
Weight of vessel = 6502.24 N
Total weight, W = 140333.7998 + 6502.24 = 146836.04 N
For the bending stress in the skirt, bs
𝑊𝑥 2
Maximum bending moment, Ms = 2
(2014.72 )(9.474)2
= 2
= 90410.92 Nm
Hence,
4(90410.92 × 1000 )
Bending stress in the skirt, bs = 𝜋(1538+45)(45)(1538)
= 1.0507 N/mm2
𝑊
Dead weight stress in the skirt, σws (hydraulic test) = 𝜋(𝐷 +𝑡
𝑠 𝑠 )𝑡𝑠
6502.239
= 𝜋(1538+45)45
= 0.0291 N/mm2
𝑊
Dead weight stress in the skirt, σws (operating) = 𝜋(𝐷 +𝑡
𝑠 𝑠 )𝑡𝑠
146836.04
= 𝜋(1538+45)45
= 0.6561 N/mm2
Therefore, resultant stresses
Maximum σs (tensile) = σbs – σws = 1.0507 – 0.0291 = 1.0217 N/mm2
σs (compressive) = σbs + σws = 1.0507 + 0.6561 = 1.7068 N/mm2
The skirt thickness under the worst combination of wind and dead weight loading
should not exceed the following design criteria.
σs (tensile) ˂ fs J sinθs
σs (compressive) ˂ 0.125E (ts/Ds) sinθs
28
Assumptions:
maximum allowable stress for skirt material at Tamb = 20°C, fs = 138 N/mm2
weld joint factor, J = 1.0
base angle, θs = 90°
Yong’s modulus, E = 200000 N/mm2
Therefore,
fs J sinθs = 138(1.0) sin (90°)
= 138 N/mm2
Since both criteria are satisfied, thus, the assumed value of skirt thickness, ts = 0.045 m
is acceptable. With corrosion allowance of 2 mm, the design skirt thickness, t s = 0.047
m.
The loads carried by the skirt will be transmitted to the foundation slab by the skirt base
ring. The moment produced by wind and other lateral loads will tend to overturn the
pressure vessel. This will be opposed by the couple set up by the weight of the vessel
and the tensile load of the anchor bolts (Sinnott 2005).
The anchor bolts are assumed to share the overturning load equally and the bolt area
required:
1 4Ms
Ab = [ − W]
Nb fb Db
Nb = number of bolts
fb = maximum allowable bolt stress, N/mm2
Ms = bending moment at the base, Nm
W = weight of the vessel, N
Db = bolt circle diameter, m
Assumptions:
bolt circle diameter, Db = 1.574 m = 1574 mm
circumference of bolt circle = 1574 π mm = 4944.87 mm
maximum allowable bolt stress, fb = 125 N/mm2
take number of bolts as 8
𝜋×1.574×1000
Bolt spacing = = 618.11 mm
8
Bolt spacing > 600 mm, therefore the bolt spacing is satisfactory.
1 4Ms
Ab = [ − W]
Nb fb Db
1 4(90410.92 )
Ab = [ − 6502.24 ]
8 × 125 1.574
Ab = 223.26 mm2
Use M24 bolts (BS4190:1967) root area = 353 mm2 (Towler & Sinnott 2013)
Taking the bearing pressure as 3.5 N/mm2, the minimum width of the base ring, Lb
Fb 1
Lb = × 3
fc 10
47779.48
Lb =
3.5x 103
Lb = 13.651 mm
The required thickness for thickness base ring is found by treating the ring as cantilever
beam:
3𝑓𝑐′
𝑡𝑏 = 𝐿𝑟 √
𝑓𝑟
Take Lr = 76 mm,
Actual width required = Lr + ts + 50 mm
= 76 + 45 + 50 mm
= 171 mm
𝐹𝑏 47.7795
𝑓𝑐′ = = = 0.2794 N/mm2
171 171
3𝑓 ′
Base ring thickness, tb = 𝐿𝑟 √ 𝑓 𝑐
𝑟
3(0.2794)
= 76√ 140
= 5.881 mm
31
c. Flanged Joint
Flanged joints are used for connecting pipes and instruments to vessels, for manhole
cover, and for removable vessel heads when ease of access is required. It also used on
the vessel body when it is required to divide the vessel into sections for transport and
maintenance. It can reduce high-stress concentration at the base of the flange by
transferring stress to the adjoining pipe. Welding-neck flange is the best-designed butt
weld available because of its inherent structural value and ease of assembly. Welding-
neck flange have high strength and high resistance to dishing, it is manufactured with a
long-tapered hub. The tapered hub is created by the gradual increase in metal thickness
from the weld join to the flange facing. The welding-neck flange diagram is shown in
Figure 1.2.
Table 2.7 Size of flanges used for fitting on each pipe on C101
D B1 t T1 X t2 t1 A h K G f
(mm) (mm) (mm) (mm) (mm) (mm) (mm) (mm) (mm) (mm) (mm) (mm)
584.20 336.55 53.85 142.75 425.45 71.12 17.78 355.60 31.75 514.35 412.75 1.60
95.25 15.75 14.22 52.32 38.10 30.48 7.62 21.34 15.75 66.55 35.05 1.60
444 254.51 47.75 117.35 320.55 55.68 13.92 273.05 28.45 387.35 323.85 1.60
584.20 336.55 53.85 142.75 425.45 71.12 17.78 355.60 31.75 514.35 412.75 1.60
584.20 336.55 53.85 142.75 425.45 71.12 17.78 355.60 31.75 514.35 412.75 1.60
32
By considering the internal pressure of the vessel, distillation column C-101, the
conditions that are needed for the design have been calculated through series of
formulae stated. The conditions for the design our distillation column have been
summarized and tabulated as followed in Table 2.8.
450.95 80
80 450.95
DC 001
2020
1500
S69 Top view of distillation column
Cross sectional view of skirt
375
Manhole 1 S69a
1200
78
Department of Chemical Engineering
Project Title:
Production of Methanol and
1500 Skirt support Bioflocculant from POME
18
Top view of sieve plate Group KK4
6
B1
Supervisors:
1. Prof. Ir. Dr. Siti Kartom Kamarudin
7690
Group members:
2300
45
1. Cheah Ching Wei
2. Ravinkumar Manimaran
S66 3. Nuredahtul Faezan
4. Siti Barakah
1000 5. Sivapriya Nadaraju
6. Afiq Syazwan
Welding neck flange B2
Mechanical Drawing of Distillation
Column (C-101)
Submission date:
S67 23rd March 2020
X
Drawing not to scale
A
Unit: Millimeter
t2
t1
T1
B1
h Diameter: 1500 mm
Height: 7690 mm
G t
Operating pressure: 2800 kPa
K f Operating temperature: 50 °C
D
Material type: Carbon steel SA516
Welding-neck flange dimension (mm) Grade 70
Stream Component D B1 t T1 X t2 t1 A h K G f Height of ellipsoidal head: 375 mm
66 Methanol + Water 584.20 336.55 53.85 142.75 425.45 71.12 17.78 355.60 31.75 514.35 412.75 1.60 Height of cylindrical shell: 6900 mm
67 Water 95.25 15.75 14.22 52.32 38.10 30.48 7.62 21.34 15.75 66.55 35.05 1.60 Minimum wall of thickness: 18 mm
69 Methanol 444.50 254.51 47.75 117.35 320.55 55.68 13.92 273.05 28.45 387.35 323.85 1.60
Skirt thickness: 45 mm
Corrosion allowance: 2 mm
67a Methanol + Water 584.20 336.55 53.85 142.75 425.45 71.12 17.78 355.60 31.75 514.35 412.75 1.60
Design pressure: 3109.19 kPa
69a Methanol + Water 584.20 336.55 53.85 142.75 425.45 71.12 17.78 355.60 31.75 514.35 412.75 1.60
MAWP vessel: 3162.97 kPa
PRODUCED BY AN AUTODESK STUDENT VERSION
226
APPENDIX D
FACULTY OF ENGINEERING
53 64 65
54
56 AND BUILT ENVIRONMENT
57 58 63
FUEL
59 61 62
CO-101 CHEMICAL ENGINEERING
51a K-103
S-101
PROGRAMME
49 50 R-101 CO-102 K-104 CO-103
51
K-102 HE-102
51b H-101 52 66
HE-101 60 S-102
48
WATER 55
45 TITTLE
PRODUCTION OF METHANOL AND
20 44 R-102 BIOFLOCCULANT FROM POME
47 69 CO-104
SODIUM
HYDROXIDE
24
K-101 RD-101 PROCESS FLOW DIAGRAM (PFD)
70 71
AFTER HEAT INTEGRATION
NUTRIENT 3
GH-101 CO-105
SR-101 P-108 METHANOL SUPERVISOR
1) PROF. IR DR. SITI KARTOM
11 KAMARUDIN
ETHANOL
24f 2) PROF. MADYA DR. MASLI
12 IRWAN ROSLI
19
2
B.marisflavi INDUSTRIAL SUPERVISOR
Vent air
67 68 68a 1) HEMAVATHI SILVAMANY
1 T-101 C-101
37
CP-101 H-102
WATER
8 13 46
GROUP
POME P-101 5 SF-101
KK4
LEAN SODIUM
25 HYDROXIDE
P-102 14
4
25a GROUP MEMBERS:
24b
39 SLUDGE OIL
1) RAVINKUMAR
T-102
9 17
27a WASTEWATER
2) CHEAH CHING WEI
15
6
T-106 CF-102 3) NUREDAHTUL FAEZAN
23 35 43a
30 WASTEWATER
16 T-105 29 36 CO-106 4) SITI BARAKAH
P-103
40 43 5) AFIQ SYAZWAN
22 P-106
10
18 CF-101 38 6) SIVA PRIYA
T-103 M-101
P-107 42
7 CV-102
P-105
31 D-101 RAW MATERIAL
28
24c
24d 24e T-104 BIOFLOCCULANT
P-104 33
32
24a
PRODUCT
CV-101
SODIUM 21 34 FERTILIZER
HYDROXIDE 27 41 41a
26 26a BP-101
WASTEWATER
DATE : 23th MARCH 2020
F-101 HE-103
B-101
AIR
Stream 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 24a 24b 24c 24d 24e 24f 25 26 26a 27 27a 28 29 30 31 32 33 34 35 36 37 38 39 40 41 41a 42 43 43a
Temperature (°C) 80 80 37 37 37 37 37 37 37 37 37 37 37 37 37 37 37 37 37 30 30 30 30 30 30 30 37 37 37 37 37 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 90 80 90 30
Pressure (bar) 1 1.5 1 1 1 1 1 3 3 3 1 1 1 1 1 1 1 1 1 1 1 3 1.5 1 1 1 1 1 1 1 1 1 1.5 1.5 1.5 1 3 1 1 1 1 1 3 1 1.5 1 1 1.4 1.3 1 1.2 1
Phase L L L L L L L L L L G S+L G S+L G S+L S+L S+L G G S+L L L L L L S+L S+L S+L S+L S+L G G G G G L L S S+L S L L L L L L S G G S V G+L
Hydrogen Sulphide (ppm) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1600.0 0.0 1600.0 0.0 1600.0 0.0 0.0 0.0 1600.0 1600.0 0.0 0.0 0.0 - - - - - - - 0.0 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
B.marisflavi (kg/hr) - - - 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - - - - - - - - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Water (kg/hr) 34000.0 34000.0 0.0 34000.0 11333.3 11333.3 11333.3 11333.3 11333.3 11333.3 0.0 11333.3 0.0 11333.3 0.0 11333.3 22666.7 34000.0 0.0 0.0 510.0 33490.0 33490.0 - - - - - - - - 0.0 0.0 0.0 - 0.0 33487.8 33487.8 3.3 513.3 144.4 368.9 33484.4 33484.4 53.2 33537.8 33460.8 77.1 0.0 0.0 40.3 36.8 36.8
Suspended Solid (kg/hr) 1800.0 1800.0 0.0 1800.0 600.0 600.0 600.0 600.0 600.0 600.0 0.0 124.8 0.0 124.8 0.0 124.8 249.6 374.4 0.0 0.0 3.7 370.7 370.7 - - - - - - - - 0.0 0.0 0.0 - 0.0 36.7 36.7 0.0 0.0 4.1 0.0 36.7 36.7 0.0 36.7 36.7 0.0 0.0 0.0 0.0 0.0 0.0
Sludge Oil (kg/hr) 216.0 216.0 216.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - - - - - - - - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Methane (kg/hr) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 73.3 0.0 73.3 0.0 73.3 0.0 0.0 0.0 146.7 222.6 0.0 0.0 0.0 - - - - - - - - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Carbon Dioxide (kg/hr) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 143.2 0.0 143.2 0.0 143.2 0.0 0.0 0.0 286.3 429.5 0.0 0.0 0.0 - - - - - - - - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Biomass (kg/hr) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 285.9 0.0 285.9 0.0 285.9 571.8 857.7 0.0 0.0 771.9 85.8 85.8 - - - - - - - - 0.0 0.0 0.0 - 0.0 26.2 26.2 26.2 798.1 758.2 39.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Nutrient medium (kg/hr) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - - - - - - - - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Bioflocculant (kg/hr) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - - - - - - - - 0.0 0.0 0.0 - 0.0 329.2 329.2 0.0 0.0 0.0 0.0 329.2 329.2 0.0 329.2 0.0 329.2 0.0 0.0 329.2 0.0 0.0
Ethanol (kg/hr) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - - - - - - - - 0.0 0.0 0.0 - 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 310.7 310.7 62.1 248.6 0.0 0.0 0.0 248.6 248.6
Air (kg/hr) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 - - - - - - - - 5268.7 5268.7 5188.7 80.0 3672.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1516.7 1516.7 0.0 1516.7 1516.7
Total (kg/hr) 36016.0 36016.0 216.0 35800.0 11933.3 11933.3 11933.3 11933.3 11933.3 11933.3 216.5 11744.0 216.5 11744.0 216.5 11744.0 23488.0 35232.1 433.0 652.1 1285.6 33946.4 33946.4 - - - - - - - 0.0 5268.7 5268.7 5188.7 80.0 3672.0 33879.9 33879.9 29.6 1311.5 906.7 408.8 33850.3 33850.3 363.9 34214.3 33559.6 654.8 1516.7 1516.7 369.5 1802.1 1802.1
Stream no 44 45 46 47 48 49 50 51 51a 51b 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 68a 69 70 71
Temperature(℃) 30 30 30 30 30 30 160 75 350 690 700 700 350 350 350 450 350 150 250 250 50 50 50 30 50 103 103 103 68 68 30
Pressure (bar) 3 1 1 2 1 1 1.2 1 28 26 25 18 3 3 3 30 30 20 50 45 30 25 24 10 23 1.5 1.5 1.5 1.5 1.5 1
Phase G L L G G V V V V V V V V+L L V V V V V V V+L V V V L L L L G L L
Water (kg/hr) 0.0 23.0 23.0 0.0 0.0 250.8 250.8 250.8 250.8 250.8 250.8 136.8 136.8 0.7 136.1 136.1 136.4 136.4 136.4 237.7 237.7 1.8 0.3 1.5 235.9 235.9 235.9 236.6 0.1 0.1 0.1
Methane (kg/hr) 222.6 0.0 0.0 222.6 222.6 0.0 0.0 222.6 222.6 222.6 222.6 99.2 99.2 0.0 99.2 99.2 149.0 149.0 149.0 149.0 149.0 149.0 49.6 99.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Carbon Dioxide 429.5 0.0 0.0 429.5 429.5 0.0 0.0 429.5 429.5 429.5 429.5 369.3 369.3 0.0 369.3 369.3 449.3 449.3 449.3 201.8 201.8 201.8 80.8 123.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Carbon Monoxide (kg/hr) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 253.8 253.8 0.0 253.8 253.8 381.4 381.4 381.4 381.4 381.4 381.4 127.1 254.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Hydrogen (kg/hr) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 43.8 43.8 0.0 43.8 43.8 51.6 51.6 51.6 17.6 17.6 17.6 7.8 9.8 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Methanol (kg/hr) 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.2 1.2 1.2 181.4 181.4 6.4 1.2 5.2 175.0 24.6 24.6 24.6 150.3 150.3 150.3
Sodium Hydroxide (kg/hr) 0.0 1.2 1.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.0 0.0 0.0 0.0
Total (kg/hr) 652.1 24.2 24.2 652.1 652.1 250.8 250.8 902.9 902.9 902.9 902.9 902.9 902.9 0.7 902.2 902.2 1168.8 1168.8 1168.8 1168.8 1168.8 757.9 266.7 494.2 410.9 260.5 260.5 262.2 150.4 150.4 150.4
227
APPENDDIX E
B-102 Blower P-101 Pump T-104 Aeration Tank P-103 Pump P-105 Pump
R-101 Moving Bed Bioreactor T-105 Settling Tank CF-101 Decanter Centrifuge
FACULTY OF ENGINEERING
LIQUID DISCHARGE 7 AND BUILT ENVIRONMENT
FROM SCREW PRESS SPENT AIR
19 23
2
9
TREATED POME CHEMICAL ENGINEERING
3 13 PP-101 TREATED WATER
8 16 18
PROGRAMME
T-102 T-103 T-104 T-106
METHANOL,WATER T-101 P-101 22 P-103 24
20
4 6
12 15 17 20a
TITTLE
SLUDGE WASTE TREATMENT PLANT
21
B-101
ETHANOL, WATER,AIR FOR PRODUCTION OF
10 11 14
5 METHANOL AND
BIOFLOCCULANT FROM POME
B-102
AIR 28
32
SPENT AIR
31
P-104
SUPERVISOR
25 SODIUM HYDROXIDE
35 SOLUTION 1) PROF. IR DR. SITI KARTOM
29
KAMARUDIN
LEAN SODIUM 30
HYDROXIDE
2) PROF. MADYA DR. MASLI
R-101 34
P-105
IRWAN ROSLI
T-105 33
26
P-102 INDUSTRIAL SUPERVISOR
CF-101 1) HEMAVATHI SILVAMANY
27 36
NUTRIENT SOLID
MEDIUM SULPHUR
GROUP MEMBERS:
Stream 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 20a 21 22 23 24
COD concentration (mg/L) - 2893.9 141271.1 1264598.6 - 1264598.6 - 14278.8 14278.8 - - - 3434.0 - - 999.2 - 285.6 285.6 285.6 - - - 17.1 - 1) RAVINKUMAR MANIMARAN
BOD concentration (mg/L) - 2025.7 98889.7 885219.0 - 885219.0 - 9995.1 9995.1 - - - 2403.8 - - 699.5 - 199.9 199.9 199.9 - - - 8.0 -
2) CHEAH CHING WEI
APPENDIX F
FACULTY OF ENGINEERING
ETHANOL 24f
AND BUILT ENVIRONMENT
B.marisflavi 24
CHEMICAL ENGINEERING
PROGRAMME
NUTRIENT
3
SLUDGE OIL
FT
30
2
FC 20 TITTLE
30 PRODUCTION OF METHANOL AND
BIOFLOCCULANT FROM POME
pHT (P&ID 1)
29 TT BIOGAS
1 TIC 28 Vent Air
28
CP-101 pHC
29 C.w out
P-101 11
POME C.w in
SF-101 SUPERVISOR
4a 1) PROF. IR DR. SITI KARTOM
KAMARUDIN
12
2) PROF. MADYA DR. MASLI
pHC pHT IRWAN ROSLI
04 04 24b
T-101 37
INDUSTRIAL SUPERVISOR
4 19
27a 25 1) HEMAVATHI SILVAMANY
Mainten ance
FIC FT discharge point
01 01 24d
5 25a
36
13
8
P-102
GROUP KK 4
FT
4b 10 TT M-101
14 TIC 11 LT LC
11 12 12 38
39 GROUP MEMBERS:
pHC pHT C.w in P-107
05 05 C.w out
FC T-105
T-102 10
WASTEWATER 1) RAVINKUMAR
T-106
9 FIC FT 43a
CF-102
6
02 02
Maintenance
17 2) CHEAH CHING WEI
discharge point
29 WASTE
3) NUREDAHTUL FAEZAN
30 35
P-103 VAPOUR
40 CO-106 4) SITI BARAKAH
10 FIC FT 28
PRODUCT
03 03
7 Maintenance
discharge point
21 32 33 FT
P-104
13 INTERMEDIATE
PRODUCT
24c CV-101
FERTILIZER
34
BP-101
B-101 HE-102
AIR
F-101 From R-101
H-101 Kettle Reboiler GH-101 Gas Holder HE-101 Heat Exchanger HE-102 Heat Exchanger R-102 Reactor S-102 Phase Separator CO-104 Cooler
K-101 Compressor K-102 Compressor R-101 Reactor CO-102 Cooler CO-103 Cooler C-101 Distillation Column RD-101 Reflux Drum
Sr-101 Scrubber K-103 Compressor CO-101 Cooler S-101 Phase separator K-104 Compressor P-108 Pump CO-105 Cooler
FACULTY OF ENGINEERING
PIC
AND BUILT ENVIRONMENT
19
To flare
PT
TT 19
18
61 CHEMICAL ENGINEERING
TIC
18 FFC PROGRAMME
25a 65
C.w in C.w out FT2 FT1
25a 25a
R-101 PIC
64 To flare 25 FUEL
53 63 TITTLE
52
PIC
23 PRODUCTION OF METHANOL AND
62 PT
58 59 To 25 BIOFLOCCULANT FROM POME
51 51a 51b H-101 TT flare
22
K-104 PT
CO-103
CO-102 23
K-102 HE-101 P&ID 2
TIC
22 LT S-102
24
PT PIC
GROUP
48 To flare 20 20 PIC
SODIUM 28 KK4
HYDROXIDE 56
PT
PC To flare 28 To flare GROUP MEMBERS:
17 K-103 69 CO-104 LT
PT
LT To flare 29
17
21
LIC
44 47 S-101 RD-101
70
29
71
1) RAVINKUMAR
LC
21 2) CHEAH CHING WEI
Sampling point
BIOGAS K-101 P-108 CO-105
METHANOL 3) NUREDAHTUL FAEZAN
LT AT AIC
16 30 30
INTERMEDIATE
PRODUCT
From B-101 To D-101
46 LEAN SODIUM
HYDROXIDE
HE-102
APPENDIX G
PLANT LAYOUT
s
E
W
Weighing station
Surau Toilet
Guard Post
Sabah Electricity Wind
Direction
Parking Area Sdn Bhd (SESB)
FACULTY OF ENGINEERING
AND BUILT ENVIRONMENT
CHEMICAL ENGINEERING
PROGRAMME
TITLE:
PRODUCTION OF
BIOFLOCCULANT AND
Administration Office Laboratory Future Expansion
Parking area
PLANT LOCATION:
MERCU PUSPITA MILL,
LAHAD DATU SABAH.
Assembly Area
Warehouse SUPERVISOR
Maintenance & Workshop
1) PROF. IR DR. SITI KARTOM
Emergency Response KAMARUDIN
Store Toilet Control Room 2) PROF. MADYA DR. MASLI
Team
IRWAN ROSLI
Loading Bay
Sludge Oil Fertilizer
INDUSTRIAL SUPERVISOR
Tank Tank
1) HEMAVATHI SILVAMANY
Ethan
ol
Nutrie BioFloccul Methanol
Tank
CF-101 D-101 nt Tank ant Tank Tank
GROUP MEMBERS:
M-101
1) RAVINKUMAR MANIMARAN