METHOD OF STATEMENT
TRAFFIC CONTROL
ITAFA ENGINEERING SERVICES LIMITED
TABLE OF CONTENT
1.0 INTRODUCTION 3
2.0 OBJECTIVE 3
3.0 REFERENCE 3
4.0 MACHINERY AND EQUIPMENT 3
5.0 MANPOWER REQUIREMENT 4
6.0 PROCEDURE 4
6.1 DEFINITION 4
6.2 PLANNING 4
6.3 WORK INSTRUCTION 4
6.4 STAGE OF TRAFFIC AND SAFETY MANAGEMENT SCHEME 4
6.5 DUTIES AND RESPONSIBILITY OF TRAFFIC MANAGEMENT OFFICER 5
6.6 ROAD AND SIGNAGE MAINTENANACE 5
6.7 TRAFFIC MANAGEMENT SCHEME PREPARATION PROCEDURE 5
6.8 TRAFFIC MANAGEMENT ARRANGEMENT 6
6.9 TRAFFIC DIVERSION PLANNING 6
6.10 TRAFFIC MANAGEMENT EQUIPMENT 9
6.11 SIGNAGE 9
7.0 INSPECTION AND TESTING 10
8.0 QUALITY CONTROL 10
9.0 SAFETY AND HEALTH 10
ITAFA ENGINEERING SERVICES LIMITED
1.0 INTRODUCTION
This method statement introduces the proposed activities to be undertaken and acts as a
general methodology for traffic diversion during road construction in KWS site. This has been
prepared to identify the work stages and the construction methodology for ensuring the works
are carried out in compliance with contract requirements.
2.0 OBJECTIVE
This method statement describes the overall sequence of the traffic diversion that will carry out
at KWS site. It also outlines the materials used, machinery and equipment involved for ensuring
the works are carried out safely and in compliance with contract requirements.
3.0 REFERENCE
Compliance to Local Authority Requirement
6.0 PROCEDURE
6.1 Definition
The traffic management shall be implemented in a safe and accident free manner and the
following measures shall be carried out without fail at site. The details stages of
temporary internal/external road, control of junction with flag (men) or traffic signage,
cones, barriers and blinkers shall be shown sufficiently at site for the information of
project site workers.
6.2 Planning
Before any road closure can be implemented, the Work Package Contractor will submit the
proposed road closure plan complete with schedule of closure for review and approval. The
road closure will only be implemented after the approval is obtained from KWS
To ensure that the preventive maintenance of the road and signage's are carried out
on daily basis.
To ensure that all flagman are always in their designated area at all time
To ensure to comply with all requirement as per stated in the traffic management
write up.
To carry out investigation, report to relevant parties and coordinate if there are any
accident happened at the site.
Duration categories
Classification Duration
Temporary < 1 day
Short term diversion < 1 month
Long term diversion >1 month
Bridge 17
in
constructi
on
progress
(Working
Bridge 18
Area)
to be
construct
ed earlier
For one side working condition, one lane will be opened and plastic barrier or traffic cone
will be placed at the work area. Proper signage will be erected. Refer to Figure 3 for the
detail work diversion.
ITAFA ENGINEERING SERVICES LIMITED
For work zone which is at the middle of the road, two lanes will be opened on the both side
of the road. Plastic barrier or traffic cone will be placed at the respective location and proper
signage will be erected. Refer to Figure 4 for the detail. The temporary equipments and
signage will be removed accordingly upon the completion.
6.11 Signage
A proper signage which classified as advance warning area will be placed according to the
condition. Within the advance warning area, approaching drivers are informed that they
are entering a work zone, and given an initial indication of any action to be taken ahead.
If a temporary reduce speed limit applies in the work zone, signing for this is located in
the advanced warning area.
ITAFA ENGINEERING SERVICES LIMITED
All sampling testing of road materials will be carried out in the Material Testing Laboratory which is
set up at the site, equipped and operated by the Contractor under the supervision of the Engineer.
8.2 Work Quality Plan and Material Quality Plan are the documents that to be referred to
identify the key parameter of inspection and testing. It is also to ensure that the work is
complying with the specifications.
8.3 The related site personnel shall review all the test reports based on the criteria set in the
Work Quality Plan or Material Quality Plan for all completed works and materials.
8.4 All inspection and test record are to be kept and maintained.
9.2 All the work to be carried out shall comply and in accordance to the approved Job Hazard
Analysis (JHA) requirement set up by the OWNER.
9.3 All workers shall be equipped with sufficient Personal Protective Equipment (PPE) such as
safety helmets, safety shoes, safety vest, hand gloves, goggles and etc. whichever suitable to
the activity to be carried out.
9.4 Toolbox meeting shall be carried out weekly in order to ensure the safety procedures are
compiled at all times through-out the construction period.