Sei sulla pagina 1di 10

ITAFA ENGINEERING SERVICES LIMITED

METHOD OF STATEMENT
TRAFFIC CONTROL
ITAFA ENGINEERING SERVICES LIMITED

TABLE OF CONTENT

1.0 INTRODUCTION 3
2.0 OBJECTIVE 3
3.0 REFERENCE 3
4.0 MACHINERY AND EQUIPMENT 3
5.0 MANPOWER REQUIREMENT 4
6.0 PROCEDURE 4
6.1 DEFINITION 4
6.2 PLANNING 4
6.3 WORK INSTRUCTION 4
6.4 STAGE OF TRAFFIC AND SAFETY MANAGEMENT SCHEME 4
6.5 DUTIES AND RESPONSIBILITY OF TRAFFIC MANAGEMENT OFFICER 5
6.6 ROAD AND SIGNAGE MAINTENANACE 5
6.7 TRAFFIC MANAGEMENT SCHEME PREPARATION PROCEDURE 5
6.8 TRAFFIC MANAGEMENT ARRANGEMENT 6
6.9 TRAFFIC DIVERSION PLANNING 6
6.10 TRAFFIC MANAGEMENT EQUIPMENT 9
6.11 SIGNAGE 9
7.0 INSPECTION AND TESTING 10
8.0 QUALITY CONTROL 10
9.0 SAFETY AND HEALTH 10
ITAFA ENGINEERING SERVICES LIMITED

1.0 INTRODUCTION
This method statement introduces the proposed activities to be undertaken and acts as a
general methodology for traffic diversion during road construction in KWS site. This has been
prepared to identify the work stages and the construction methodology for ensuring the works
are carried out in compliance with contract requirements.

2.0 OBJECTIVE
This method statement describes the overall sequence of the traffic diversion that will carry out
at KWS site. It also outlines the materials used, machinery and equipment involved for ensuring
the works are carried out safely and in compliance with contract requirements.

3.0 REFERENCE
Compliance to Local Authority Requirement

4.0 MACHINERY AND EQUIPMENT


 Light weight movable plastic barriers
 Light weight movable plastic hoardings
 Concrete Barriers
 Arrow flasher (power by solar)
 Light weight movable traffic cone
 Temporary signage

5.0 MAN POWER


 Construction Manager
 HSSE Manager
 HSE Supervisor
 Site Engineer
 Supervisor
 Skilled Workers
 General Workers
 Operator
 Flagman
 Traffic Controller
ITAFA ENGINEERING SERVICES LIMITED

6.0 PROCEDURE
6.1 Definition

Lorries with gross weight of less than 10 tons, pick up


LIGHT VEHICLES
trucks and saloon cars
.
Lorries exceeding gross weight up to 10 tons or more such as
HEAVY VEHICLES mobile and crawler cranes, dump trucks, concrete mixer
lorries, and etc.
Crawlers cranes, trailers, low loaders, excavators, forklifts
SLOW VEHICLES
backhoe and etc.
Vehicles consist of TOURIST AND KWS cars,
IN HOUSE VEHICLES
consultant and clients vehicles
PUBLIC VEHICLES All non-in-house vehicles

The traffic management shall be implemented in a safe and accident free manner and the
following measures shall be carried out without fail at site. The details stages of
temporary internal/external road, control of junction with flag (men) or traffic signage,
cones, barriers and blinkers shall be shown sufficiently at site for the information of
project site workers.

6.2 Planning
Before any road closure can be implemented, the Work Package Contractor will submit the
proposed road closure plan complete with schedule of closure for review and approval. The
road closure will only be implemented after the approval is obtained from KWS

6.3 Work Instruction


The persons involved should be informed about the possible presence of traffic diversion in
the working and transportation area, the safety clearances and the possible instructions from
the local authority. Also, the persons involved should be acquainted with the local authority
and its telephone number. Local authority will be informed about all incidents in relation to
traffic diversions.

6.4 Stage of Traffic and Safety Management Scheme


 Traffic control during road closure
 Traffic diversion
 Traffic control during construction stage (haul road)
6.5 Duties and Responsibility of Traffic Management Officer (HSSE Manager)
 To ensure all roads signages are in place and in good condition at all time.
 To ensure that all permits are obtained before any diversion, closure, changes of
traffic flow are made.
 To ensure to coordinate to all parties and to brief all parties from time to time on the
traffic management issues.
ITAFA ENGINEERING SERVICES LIMITED

 To ensure that the preventive maintenance of the road and signage's are carried out
on daily basis.
 To ensure that all flagman are always in their designated area at all time
 To ensure to comply with all requirement as per stated in the traffic management
write up.
 To carry out investigation, report to relevant parties and coordinate if there are any
accident happened at the site.

6.6 Road and Signage Maintenance


The road will be cleaned everyday by using water browser and general workers. The traffic
officer will ensure that the road is clean and safe to use at all time. The traffic officer will also
ensure that daily inspection is carrying out.

6.7 Traffic Management Scheme Preparation Procedure

6.7.1 Collecting Data


In carry out traffic management, respective person will visit the site for field check and
collect the entire inventory on the existing facilities including:

i. Identify all roads crossings


ii. Any necessary working permit to commence utilities diversion
iii. Identify the needs of temporary road diversion
ITAFA ENGINEERING SERVICES LIMITED

6.7.2 Select the Traffic and Construction Duration Categories

Duration categories
Classification Duration
Temporary < 1 day
Short term diversion < 1 month
Long term diversion >1 month

6.7.3 Determine the Extent of Roadway Occupancy


The location of the road crossing will generally dictate the degree which the roadway will
be occupied and closed or diverted the normal traffic. To define the extent of the
occupancy, the following factors should be determined.

i. Beginning / ending points


ii. Length of the occupied roadway
iii. Portion of the roadway that will be closed / diverted
iv. Work duration on the designated location

6.8 Traffic Management Arrangement


Since the works involved are roadwork, construction of bridge and culvert across the road,
and maintenance road, a proper traffic management within site area is required.

6.9 Traffic Diversion Planning


For the bridge or culvert construction, the road will be totally closed and new route diversion
will be proposed. In case where there is two or more bridge or culvert need to be
constructed in one zone, a proper planning will be done in order to determine which area to
be constructed first. As example, in Figure 1 shown there are two bridges to be constructed.
In this case, bridge 18 will be constructed first. New road of diversion will be proposed in
order to allow the vehicle to enter the work area. Once bridge 18 is completed and ready to
use, the bridge will be opened to construct bridge 17. A proper signage will be erected. Road
at bridge 17 will be closed and NO ENTRY signage will be erected. Plastic barrier will be
placed at the proposed location. Refer to Figure 2 for the detailed proposed signage and
road condition.
ITAFA ENGINEERING SERVICES LIMITED

Bridge 17
in
constructi
on
progress
(Working
Bridge 18
Area)
to be
construct
ed earlier

Figure 1: Bridge Construction

Figure 2: Proposed Signage and Road Condition

For one side working condition, one lane will be opened and plastic barrier or traffic cone
will be placed at the work area. Proper signage will be erected. Refer to Figure 3 for the
detail work diversion.
ITAFA ENGINEERING SERVICES LIMITED

Figure 3: Road Diversion for One Side Working Condition

For work zone which is at the middle of the road, two lanes will be opened on the both side
of the road. Plastic barrier or traffic cone will be placed at the respective location and proper
signage will be erected. Refer to Figure 4 for the detail. The temporary equipments and
signage will be removed accordingly upon the completion.

Figure 4: Road Diversion for the Middle Working Condition


ITAFA ENGINEERING SERVICES LIMITED

6.10 Traffic Management Equipment


The traffic management equipment used in the project are:

 Light weight movable plastic barriers


 Light weight movable plastic hoardings
 Concrete Barriers
 Arrow flasher (power by solar)
 Light weight movable traffic cone
 Temporary signage

6.11 Signage
A proper signage which classified as advance warning area will be placed according to the
condition. Within the advance warning area, approaching drivers are informed that they
are entering a work zone, and given an initial indication of any action to be taken ahead.
If a temporary reduce speed limit applies in the work zone, signing for this is located in
the advanced warning area.
ITAFA ENGINEERING SERVICES LIMITED

7.0 Inspection and Testing


The inspection and frequency of testing shall follow the approved Inspection and Test Plan (ITP) for
Traffic Diversion found in Project Quality Plan.

All sampling testing of road materials will be carried out in the Material Testing Laboratory which is
set up at the site, equipped and operated by the Contractor under the supervision of the Engineer.

8.0 Quality Control


8.1 All the works to be carried out shall in accordance with the approved Work Quality Plan and
Material Quality Plan in the Project Quality Plan.

8.2 Work Quality Plan and Material Quality Plan are the documents that to be referred to
identify the key parameter of inspection and testing. It is also to ensure that the work is
complying with the specifications.

8.3 The related site personnel shall review all the test reports based on the criteria set in the
Work Quality Plan or Material Quality Plan for all completed works and materials.

8.4 All inspection and test record are to be kept and maintained.

9.0 Safety and Health


9.1 All the works to be carried out shall in accordance with the approved Project Safety Plan.
Safety & Health Induction shall be given to all new workers and staff before the
commencement of works at site to ensure they have full knowledge on all the precautions
for safety and health at site.

9.2 All the work to be carried out shall comply and in accordance to the approved Job Hazard
Analysis (JHA) requirement set up by the OWNER.

9.3 All workers shall be equipped with sufficient Personal Protective Equipment (PPE) such as
safety helmets, safety shoes, safety vest, hand gloves, goggles and etc. whichever suitable to
the activity to be carried out.

9.4 Toolbox meeting shall be carried out weekly in order to ensure the safety procedures are
compiled at all times through-out the construction period.

Potrebbero piacerti anche