Sei sulla pagina 1di 38

GPI - Gestão de Projectos Informáticos

Risk Management

Maria do Rosário Bernardo


1
GPI - Gestão de Projectos Informáticos

“if something can go wrong, it will;


If something can’t go wrong it will!”

(Murphy’s law)

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Risk

• Hazard
• Chance of bad consequence or loss
• Exposure to mischance

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Risk Definition

“the chance of exposure to the adverse consequences


of future events”
PRINCE2

“an uncertain event or condition that, if it occurs, has a


positive or negative effect on a project's objectives”
PMBOK®

“combination of the probability of an event and its


consequence”
ISO/IEC GUIDE 73

Maria do Rosário Bernardo


4
GPI - Gestão de Projectos Informáticos

• Risk is characterized by the relationship between potential events and


consequences.
• Multiple events and multiple consequences can generate multiple risks.
• The consequence is over one Asset.

Maria do Rosário Bernardo


5
GPI - Gestão de Projectos Informáticos
Risk Management
Increase the impact of positive events and
Decrease the impact of events adverse to the project
In 4 Steps:
Identify
• Risk identification risks

• Risk assessment Assess


risks
Risk
• Risk treatment Register
– to develop options and determine Treat
actions to enhance opportunities and risks
reduce threats to the project’s
objectives
Control
• Risk control risks
Maria do Rosário Bernardo
6
GPI - Gestão de Projectos Informáticos

Prince 2 - The Risk Management Process.

Maria do Rosário Bernardo


7
GPI - Gestão de Projectos Informáticos

ISO31000 Risk Management processes


Maria do Rosário Bernardo
8
GPI - Gestão de Projectos Informáticos

Risk Identification Tools & Techniques

• Documents revision
• Learning Cycles
• Brainstorming
• Nominal Group Technique
• Delphi Technique (described in effort estimation)
• Interviews
• SWOT Analysis
• Cause & Effect (a.k.a. Fishbone/Ishikawa)
• Checklists
Maria do Rosário Bernardo
9
GPI - Gestão de Projectos Informáticos

Risk categories

• Business risks

– Chance of profit or lost

• Insurable risks

– Only chance of lost (only negative impact)


– Usually caused by external and unpredictable factor

Maria do Rosário Bernardo


10
GPI - Gestão de Projectos Informáticos

Risk Identification - Classification

• External : Unpredictable
• External : Predictable but Uncertain
• Internal : Technical
• Internal : Non-technical
• Legal

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Risk Identification - Tools & Techniques

checklists

Maria do Rosário Bernardo 12


12
GPI - Gestão de Projectos Informáticos

Risk Identification Tools & Techniques


PM
Integration
Information
SCOPE Life cycle and
Communic.
Environment variables
Expectations Ideas, Directives,
Feasibility Data exchanges accuracy

Requirements Project Availability Human


Quality
Standards Risk Productivity Resources
Time Objectives, Services, Plant, Materials:
restraints Performance
Cost Objectives
restraints Contract/
TIME
Procurement
COST
The PMBOK Handbook Series – Volume no.6
Maria do Rosário Bernardo
13
GPI - Gestão de Projectos Informáticos
Risk Breakdown Project Risk
Structure
Commercial risks Relationship risks Requirements risks Planning and resource risks Technical risks Subcontract risks

Unclear
No or poor Requirements PM not involved in No / little experience of
customer New environment
business case not agreed initial planning suppliers
structure

More than one Poor access to Requirements Project very large with Development and live Suppliers in poor
customer stakeholders incomplete quick building-up environment differ financial state

Internal Requirements
Inappropriate Estimates not based Restricted access to Difficulty to stage tests
customer not detailed
contract type in metrics environment of items
policies enough

Multiple Ambiguity in Excessive reliance Unfamiliar system


Penalties on key staff No choice of supplier
stakeholders requirements software

No single
Poor scope Users not Developers lack key Lack of technical Use of proprietary
document of
definition committed skills support products
requirements

Unclear Stringent non- Subcontractors not


Unwillingness Inexperience in Unfamiliar tools /
payment functional ‘back-to-back’ with
to change business area methods / standards
schedule requirements main contract

Payments not Management Acceptance


Inexperience in New / unproved
linked to and users criteria not
technology technology
deliverable disagree agreed

Maria do Rosário Bernardo


14
GPI - Gestão de Projectos Informáticos

Risk assessment

Risk of Impact = P(R) * consequence


or

Risk of Impact = P(R) * consequence * Public perception

Consequence (Ri) = €500.000


Probability (Ri) = 0,01
Impact (Ri) = €500.000 * 0,01 = €5.000

Maria do Rosário Bernardo


15
GPI - Gestão de Projectos Informáticos

Risk Impact Table 0 - 100% 0-10 P*I


Ranking

Probability Conseq. Impact

Risk (Threats)

Key project team member leaves project 40% 4 1.6


4
Client unable to define scope and
requirements 50% 6 3.0 3

Client experiences financial problems 10% 9 0.9

Response time not acceptable to users/client 80% 6 4.8


1
Technology does not integrate with existing 2
application 60% 7 4.2
Functional manager deflects resources away
from project 20% 3 0.6

Client unable to obtain licensing agreements 5% 7 0.4


Maria do Rosário Bernardo IT Project Risk Impact Analysis
16
GPI - Gestão de Projectos Informáticos

Risk Assess

Risk Impact Matrix


Probability x Consequence Matrix

Use of suitable Scales, for


Consequence vs Probability Scales:

- 3 levels: LOW ; MED ; HIGH


- 5 levels: VLO ; LO ; MED ; HI ; VHI

3 x 3 ; 4 x 4 ; 5 x 5 ...
LOW ; MED ; HIGH
VLO ; LO ; MED ; HI ; VHI

Maria do Rosário Bernardo 17


17
GPI - Gestão de Projectos Informáticos

Risks Impact Evaluation


VHI
High
Project Revaluation
HI IF "GO" ==>
R2 Reduction actions
Probability

MED
Medium
R1
==>
LO Reduction actions
R3
VLO
Low
Only Control
VLO LO MED HI VHI

Consequence
Maria do Rosário Bernardo
GPI - Gestão de Projectos Informáticos

Risk assessment
Evaluation scale example
Base : IT Project – 1 year; 1.000 K€
Consequences

Grade P(R) Time Cost (K€) Performance


(weeks)
VHI > 70% >8 > 80 System

HI 50 – 70% 4a8 50 – 80 Some important parameters

MED 30 – 50% 2a4 20 – 50 One important parameter

LO 10 – 30% 1a2 5 – 10 Some less important parameters

VLO 5 – 10% <1 5 One no important parameter

NIL -- 0 0

Maria do Rosário Bernardo


19
GPI - Gestão de Projectos Informáticos

Risk Assessment

Prabability
Team assessment Historical Recors

VL Not Identified But sporadic occurrence

L Not probable and sporadic occurrence

M Lower Probability and “some” frequent occurrence

H High Probability or frequent occurrence

VH Very High Probability and frequent occurrence

Maria do Rosário Bernardo


20
GPI - Gestão de Projectos Informáticos

Risk Assessment
Impact on other
Direct Consequence elements of the Impact on project Impact on business
project

VL 1 project activity No No No

Set of activities
L Reduced No No
or 1 WP

May compromise one


May impact on
M More than 1 WP or more project Reduced
other WPs
components

May compromise limited to project


H
project implementation success
Significant number Significantly affects
of WPs overall project may compromise
Compromise project
VH other projects or the
realization
company image

Maria do Rosário Bernardo


21
GPI - Gestão de Projectos Informáticos

Combining the impact of several risks

• Individual risks can interact


• The WBS is a key tool in the integration of the risk

Top-down approach
– Key risk factors are identify and assessed at high level of WBS
– Allows to analyse interrelationships
Bottom-up approach
– Risks are identified at a low level of WBS
– Prepare contingency plans

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Risk Treatment
• Avoidance:
– decision not to become involved in, or action to withdraw from, a risk
situation

• Mitigation:
– actions taken to lessen the probability, negative consequences, or
both, associated with a risk

• Deflection:
– sharing with another party the burden of loss or benefit of gain, for a
risk (deflect the risk)

• Contingency:
– Create a plan to react to the risk, if it occurs
Maria do Rosário Bernardo
23
GPI - Gestão de Projectos Informáticos

Risk Avoidance

“decision not to become involved in, or action to


withdraw from, a risk situation”:

Under avoidance we change the project plan :


• Scope
• Time
• Costs
• Quality
• Organization

Maria do Rosário Bernardo


24
GPI - Gestão de Projectos Informáticos

Risk Transfer

sharing with another party the burden of loss or


benefit of gain, for a risk

3 ways of deflecting a risk:


Insurance
Bonding (using secure account)
Contract
We only can transfer risks within a limit.
Risks transfer has additional costs.

Maria do Rosário Bernardo


25
GPI - Gestão de Projectos Informáticos

Risk - Contingency

 Make an allowance (provisão), by increasing


time and/or cost budgets
 Plan to change the scope, by drawing up
contingency plans to implement if the risks occur

Allowances (provisões)
• Add it to WBS level – where the risk was identified
• Project
• Work Package
• Activity
Maria do Rosário Bernardo
GPI - Gestão de Projectos Informáticos

Risk – Contingency
Example : Allowance

Activity Requirement identification


Duration 10 days
Cost (resources) Senior 50% a € 400/d+
Junior 100% a € 200/d
Risk Users unavailability
Probability High
Consequence High
ID Task Name Duration
January 2007 February 2007
01 04 07 10 13 16 19 22 25 28 31 03 06 09
1 PT1 20 d
2 a1 2d
3 a2 3d
4 Levantamento Requisitos 10 d
5 a3 2d
6 a4 3d

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Risk – Contingency
Example : Allowance

To calculate an allowance we need a quantitative


approach, e.g.

Grade Probability Consequence


VHI 0.9 0.8
HI 0.7 0.4
MED 0.5 0.2
LO 0.3 0.1
VLO 0.1 0.05

Maria do Rosário Bernardo


28
GPI - Gestão de Projectos Informáticos

0,9
VHI
0,045 0,09 0,18 0,36 0,72 HIGH

Proj Reevaluation
0,7 IF "GO" ==>
0,035 0,07 0,14 0,28 0,56 reduction actions
HI
Probability

0,5
MED
0,025 0,05 0,1 0,2 0,4 MED

==>
0,3 reduction actions
0,015 0,03 0,06 0,12 0,24
LO

0,01
VLO
0,005 0,01 0,02 0,04 0,08 LOW

0,05 0,1 0,2 0,4 0,8 Only control


VLO LO MED HI VHI
Consequence

Maria do Rosário Bernardo


29
GPI - Gestão de Projectos Informáticos

Activity Requirement identification I(R) = 0,28


Duration 10 days Allowance = 10d*0,28=
2,28 aprox 3 days
Cost Senior 50% a € 400/d+ Allowance =
(resources) Junior 100% a € 200/d 3d *( 0,5 * €400 + €200 ) =
€1.200
Risk Users unavailability
Probability High
Consequence High
ID Task Name Duration
January 2007 February 2007
01 04 07 10 13 16 19 22 25 28 31 03 06 09
1 PT1 23 d
2 a1 2d
3 a2 3d
4 Levantamento Requisitos 10 d
5 Provisão 3d
6 a3 2d
7 a4 3d
Maria do Rosário Bernardo
GPI - Gestão de Projectos Informáticos

Risk management plan

Identifies the risks associated with a project, the means


by which they be assessed, and the strategy for their
reduction. 4 W + 2 H
• Why • Why the risk is significant
• What • What is to be done to reduce it
• When • When the risk will have its impact
• Who • Who is responsible to resolving it
• How • How the reduction will be archived
• How much • How much it will cost to resolve it

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Risk Register

Maria do Rosário Bernardo


32
GPI - Gestão de Projectos Informáticos

Risk register example


Risk Description Assumptions Probability Consequence Probability/Consequence Treatment Risk
ID VL L M H VH VL L M H VH Justification Type Measure(s) Owner
Why should we
consider this Risk Description

Maria do Rosário Bernardo


33 33
GPI - Gestão de Projectos Informáticos

Risk communication

• Customer (evaluation and value)


• Sponsors (commitment and support)
• Project Manager (project strategy)
• Integrators (implementation risks management)
• Team (knowledge)
• Users (commitment and limits understanding)

Maria do Rosário Bernardo


GPI - Gestão de Projectos Informáticos

Risk Response Plan should include:

• A trigger which flags that the risk has occurred


• An owner of the risk (i.e., the person or group responsible
for monitoring the risk and ensuring that the appropriate
risk response is carried out)
• A response based on one of the four basic risk responses
• Adequate resources

We can add a column : when


Maria do Rosário Bernardo
35
GPI - Gestão de Projectos Informáticos

Control Risks

Purpose
minimise disruption to the project by determining
whether the risk responses are executed and
whether they have the desired effect

Source: ISO DIS 21500


Maria do Rosário Bernardo
36
GPI - Gestão de Projectos Informáticos

Control Risks
Control is achieved by
– keeping track of the identified risks,
– identification and analysis of newly arising risks,
– monitoring trigger conditions for contingency plans
– reviewing progress on risk responses,
– evaluating risk responses effectiveness

Project risks should be periodically evaluated when


– a new risk arises or
– a milestone is reached
Source: ISO DIS 21500
Maria do Rosário Bernardo
37
GPI - Gestão de Projectos Informáticos

Risks re-evaluation

Should be done when new risks are identified

Should be done when a milestone is achieved

Maria do Rosário Bernardo

Potrebbero piacerti anche