Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
2
Executive Summary (Continued)
Shed-8 (Dyeing Finishing-Stenter) is a single storied steel shed which is being used for dyeing
finishing. The shed was constructed between December 2018 and March 2019. Factory occupied
the shed since June 2019.
Shed-9 (Chemical Store) is a single storied steel shed which is being used for chemical store only.
The Shed was constructed between February 2018 and June 2018. Factory occupied the structure
since July 2018.
Shed-16 (Fire Hydrant Pump) is a single (B+G) storied RC structure with steel roof shed which is
being used for fire hydrant pump (basement) and maintenance office at the top. The Shed was
constructed between February 2018 and June 2018. Factory occupied the structure since July
2018.
Shed-19 (Boiler & Generator) is a single storied steel shed which is being used for boiler &
generator. The shed was constructed between February 2019 and June 2019. Factory occupied the
shed since July 2019.
We were provided with copies of permit drawings for all the structures except New Washing Shed
from RAJUK dated 27th May 2015. We were also provided with copies of industrial layout drawings
dated 27th June 2019 from Department of Inspection for Factories and Establishments (DIFE).
We were also presented with:
• Copies of Architectural and Structural drawings for all the structures & load plan (105 psf) for
Building-3 (Extension) prepared by “Design Development Solution (DDS)”.
• Copies of Design Report & cylinder test reports from BUET.
• Soil investigation report was provided based on data from 7 boreholes for the Building-3
(Extension) dated August 2014 prepared by Innovative Engineers. The report recommends pile
foundation.
3
Executive Summary (Continued)
The information provided in the architectural and structural drawings for the buildings are
generally found indicative with the as-built conditions. We have checked the column capacity
considering 3 kPa live load on typical floor and 1.5 Kpa on roof for building-3 (Extension).
Individual color codes for each significant factory building surveyed are outlined below as per
current condition:
Building-3 Green
All Sheds Yellow
We see no reason to suspend operations in the facility due to structural concerns (subject to the
required actions noted in this report).
4
Executive Summary (Continued)
Further actions with associated priorities and timeframes are given at the end of this report.
Please note that these actions should be completed as soon as practically possible and certainly
within the time frame noted.
We have reviewed the property from an outline seismic perspective and would consider that the
building, along with many others in the Dhaka region, to be at significant risk of damage in a major
Seismic event.
Our Limitations and Assumptions are also noted at the end of this report.
5
5
Building Extents
6
6
23.642251, 90.512839
Shed-19: New Boiler
& Generator
Shed-8: Dyeing
Finishing (Stenter)
Shed-16: Fire
Hydrant Pump
Building-3: Extension
Shed-7: Finishing
North
East
South Elevation
Canteen
Arial view
South Elevation
West Elevation
South & East Elevation
South Elevation
17 17
2.05 Structural System:
m
RC beam and column frame with two-way slab.
1.12 Stability System:
m Moment resisting frame.
Aggregate: Stone chips.
2.05 Floor to Ceiling Height : 3.07 m (Avg.)
m Maximum Grid: 6.16 m X 4.5 m
3.68 m Maximum cantilever distance : 2.05 m
6.52 m 5.79 m
Column sizes (without plaster):
7.7 m 7.7 m
Internal – 610 mm X 610 mm
Edge & Corner – 455 mm X 455 mm
4.5 m
Beam Size: both longitudinal and transverse
305 mm X 405 mm (d/s)
Slab thickness:
150 mm (without finishes)
4.5 m Foundations: Pile Foundation as per drawing.
4.3 m
Beam-Column Layout
Structural System: Building-3 (Extension) 18
Pile cap section layout
Old New
building building
3.96 m
6.70 m 5.91 m
3.96 m Column-Truss connection
21
Structural System: Shed-7 (Finishing) 21
Footing layout Column and Footing section
4.12 m 5.58 m
4.91 m
6.85 m 4.29 m
2.69 m
Column-Truss connection
Structural System:
Steel truss on RCC column
3.61 m Stability System:
3.86 m Double HOWE steel truss in
Truss short direction.
3.61 m
Aggregate: Brick chips. Connections: bolted with RCC
Grid: Shown in layout column
3.61 m
Rafter Size: ‘I’ section (mm) Column Size: RCC (mm)
3.32 m
5.56 m 5.18 m
W 200X5 F 100X5 Typical: 300 mm X 300 mm
Tie Beam in the north side Foundation type: Isolated
Dimension : 305 mm X footing (as per drawing)
RCC Column layout 305mm
5.34 m 4.29 m
4.37 m
4.37 m
Structural System:
RCC column with portal frame and partial RCC
Portal frame roof
slab roof and mezzanine floor.
Stability System: Moment resisting frame system
Grid: Shown in layout
Aggregate: Brick chips.
RCC Connections: unknown
slab Column Size: RCC (mm) : 300 X 300
roof Tie Beam (mm): 250 X 375
Foundation type: Isolated footing (as per
drawing)
Tie beam layout
Structural System: Shed-19 (Boiler & Generator)
29
Footing layout Column schedule and Footing section
Portal frame roof Internal steel stair for mezzanine floor access
Structural System: Shed-19 (Boiler & Generator) 30
30
Observations
31
31
Discrepancies between drawings
and on-site condition
Prayer room
Reinforcement details
36 Observations: Shed-7, 8, 9, 19 36
Vertical bracings were provided for the stability system against lateral loading. But no compression
strut was observed in long direction. Moreover, bracings were found missing. Also, connection
details were not provided in structural drawing. Poor connections were found during inspection.
37 Observations: Shed-7, 8, 9, 19 37
Tests Carried Out
38
38
Rebar was checked on site by Ferro-scanner
Stone Aggregate
Column layout
40
40
Item 1 and actions
Discrepancies between drawings and on-site condition. (Building-3 Extension)
•
Priority 2 Building Engineer to survey the structures and prepare accurate
as-built drawings.
(within 6-weeks)
41
Item 2 and actions
Prepared load plans and design reports required to be reviewed. (Building-3
Extension)
•
Priority 3 Complete remedial works arising from design report after
reviewed by ACCORD.
(within 6-months) • Continue to implement load plan.
42
Item 3 and actions
Lack of lateral Stability. (Shed-7, 8, 9, 16, 19)
43
Survey Limitations and Assumptions
This report is for the private and confidential use of Accord for whom it was prepared together with their professional advisors as appropriate. It
should not be reproduced in whole or in part or relied upon by third parties for any use without the express written permission of ACCORD.
This report can be used in discussion with the supplier or factory owner as a means to rectify or address any observations made. The report is not
comprehensive and is limited to what could be observed during a visual inspection of the building.
This Report is not intended to be treated as a generalised inspection and does not cover the deterioration of structural members through dampness,
fungal or insect attack, nor does it deal with problems and defects of a non-structural nature. Other non structural aspects of the building such as fire
safety have not been assessed in this survey.
Except as otherwise noted, drains and other services were not viewed or tested during our inspection and are therefore similarly excluded from this
Report. We have not inspected any parts of the structure which are covered, unexposed or inaccessible and we are therefore unable to report that
any such part of the property is free from defect.
External inspection of the façade walls has generally been carried out from ground level only by visual sighting. No opening up works were carried out
(except as noted) and we rely on the Architects and Engineers drawings provided to us for our views on concealed parts of the structure and in
particular foundations. Strengths of materials and components are untested and we recommend that the factory owners Building Engineer carries out
in situ testing over and above those suggested to satisfy themselves with the material strengths and component details.
Recommendations, where given, are for the purpose of providing indicative advice only, are not exhaustive, relate solely to identifying key and
obvious structural defects as identified in this presentation, and do not take the form of or constitute a specification for works. We take no
responsibility for the works as constructed. This report does not interfere with the factory owners Building Engineers responsibility for the structural
performance of this building, The Building Engineer remains fully responsible for the structural adequacy of the building.
This report does not comment in detail on the future seismic performance of the building and only highlights the fact that the building may experience
significant damage or collapse in a seismic event along with many others in the Dhaka region.
The observations in this report are based on the Engineering Judgement of the lead surveyor/engineer at the time of the survey. We assume in making
these observations that no covering up of faults defects, filling or plastering over cracking or significant repair work has been carried out by the
building owner. Any future alteration or additional work by the building owner will void this report.
44