BILL OF QUANTITY FOR CIVIL WORK

LOT-1

Name of the Rate Amount


Structure BOQ Number Description of Item of Work Qty Unit (SAR) (SAR)

PUMPING STATION TREATED EFFLUENT (PST)


BOQ. NO. 3
Ref: Drawings H652-PTE-EPC-PID-0005, H652-PTE-EPC-GEN-0005,
H652-PTE-EPC-CIV-0005
BOQ. NO. 3.1 PST Civil Structure

Pumping Station Building:


Excavation and Substructure
Excavation and erection of substructure including clearing of site,
excavation works, bracing and dewatering of construction pit,
construction of foundation including all layers according detail
design, backfilling of excavation.

Earth Work excavation - Buildings 6,610.00 CUM 29.00 191,690.00


Road base filling with required compaction 203.90 CUM 12.00 2,446.80
Backfilling with Selected Material 1,569.50 CUM 11.00 17,264.50
Disposal of Surplus Excavated earth away from site 5,040.00 CUM 6.70 33,768.00
Dewatering (To be quoted as actuals later on) 1.00 L.S -
Pump Hall - Sub Structure Works (To be quoted as actuals later on) -
1000 Gauge Polyethylene sheet 1,020.00 SQM 2.00 2,040.00
75mm tk Blinding Concrete; Grade C20 (Class 'D' Concrete) 74.14 CUM 110.00 8,155.40
Horizontal Water proofing Works - Tanking Membrane Type-1 (one
coat of Bitumen primer + Tourch applied 4mm tk bitumen 988.50 SQM 20.00 19,770.00
membrane laying)

50mm tk Protection Screed Concrete on over the Waterproofing 49.43 CUM 90.00 4,448.25
Membrane - Grade C35 Screed (Class 'C' concrete)

RCC Concrete Works -


BOQ. NO. 3.1.20
RCC Raft / Footing Concrete; Grade C45 Concrete (Class 'B'
601.28 CUM 220.00 132,281.60
Concrete)
RCC Wall Concrete; Grade C45 Concrete (Class 'B' Concrete) 808.56 CUM 280.00 226,396.80
RCC Column / Pedestal Concrete; Grade C45 (Class 'B'Concrete) 26.80 CUM 260.00 6,968.00
C20 Leanmix Concrete filling - inbetween the Pump plinth wall 464.50 CUM 190.00 88,255.00
RCC Slab Concrete; Grade C45, (Class 'B' Concrete) 72.41 CUM 220.00 15,930.20
Form Works -
Shuttering works for RCC Raft Concrete 129.90 SQM 190.00 24,681.00
Shuttering Works for RCC Wall concrete 3,243.46 SQM 270.00 875,734.20
Shuttering works for RCC Column / Pedestal Concrete 202.54 SQM 210.00 42,533.40
Shuttering works for RCC Slab / Roof slab 81.56 SQM 200.00 16,312.00
Reinforcement Works (Sub Structure) -
Reinforcement Steel works - Raft, Column, Wall, Slab etc., 227.43 TON 850.00 193,315.50
Vertical Waterproofing Works with Joints -

Vertical Waterproofing works - (one coat primer + torch applied 761.60 SQM 30.00 22,848.00
4mm tk membrane + 6mm tk fibre impregnated board)

Waterproofing Termination at Ground level 134.00 RM 30.00 4,020.00


Expansion Joints with Waterproofing Systems 81.00 RM 35.00 2,835.00
Construction Joints with Waterproofing Systems 578.43 RM 40.00 23,137.20
-
Pumping Station Building: -
Superstructure

Erection of superstructure including columns and beams, ceilings,


load-bearing and non-load-bearing walls of different materials,
stairs, etc., including roof construction and facade construction
-
with all extra works like flaschings, sealants, connection joints,
etc., including installation openings in roofs and walls, including
roof drainage.
kathirvel:
Pump Hall - Super Structure Works - Total Wall cladding area
= 746 sqm
RCC Concrete Works -
RCC Stiffner Column Concrete Works; C45 Grade 47.84 CUM 260.00 12,438.40 kathirvel:
RCC slab/ drop beams for unloading bay 174.59 CUM 220.00 38,409.80 Total Plan area = 899.57
sqm
RCC Lintel Concrete Works - C45 grade 1.73 CUM 230.00 397.90kathirvel:
Total Plan area = 899.57
- sqm
Form Works -
Shuttering works for Stiffner Column 353.56 SQM 210.00 74,247.60
Shuttering works for RCC Lintel 17.28 SQM 230.00 3,974.40
-
Reinforcement Works (Super Structure) -
Reinforcement Steel works - Column, Lintel, Slab etc., 77.83 TON 850.00 66,155.50
Metal Works -

Page: 1 / 16
BILL OF QUANTITY FOR CIVIL WORK
LOT-1

Supply & Erection of Steel beams for crane erection (crane Runway
beam) - As per Design 6,521.00 KG 4.00 26,084.00

External Roof Access Ladder - Galvanised steel Cage Ladder 23.42 LM 120.00 2,810.40
Pre Engineered building Roof Structure -

Supply, Fabrication, Delivery & Erection of PEB Steel Structure for


the Pump Room building for the size of 49.70m x 18.1m (outer to
outer side) and a height of 9.5m (ridge height) including support
BOQ. NO. 3.1.21 structure for rainwater Gutter, edge & ridge flashing, roof walkway
if required all complete as per the Drawings and NWC standards & 900.00 SQM 68.00 61,200.00
Specifications.
Roof Plan Area = 899.57 Sqm
(Please Provide Erection Cost only;
Supply, Fabrication & delivery of PEB structure by TECTON)

Supply, Delivery & installation of Roof sheeting for Aluminium


double skin insulated sheets (0.7mm tk outer layer + 50mm tk
Polyurethene foam insulation + 0.5mm tk internal sheet layer)
including Steel purlins, fixing of rain water gutters, ridge and Edge
flashings all complete as per the attached Drawings and
specifications. 900.00 SQM 30.00 27,000.00
size of roof = 49.70m x 18.10m
Roof Plan Area = 899.57 Sqm
(Please Provide Erection Cost only;
Supply & delivery of Roof Sheeting by TECTON)

Supply, Delivery & installation of Wall cladding for Aluminium


double skin insulated sheets (0.7mm tk outer layer + 50mm tk
Polyurethene foam insulation + 0.5mm tk internal sheet layer)
including Steel purlins, Edge flashings at the end of Block wall all
complete as per the attached Drawings and specifications.
size of roof = 49.70m x 18.10m 746.00 SQM 40.00 29,840.00
Block wall height = 4.0m from FFL
Wall cladding height = 5.5m height from Block wall to edge (Total
height is 9.50m)
(Please Provide Erection Cost only;
Supply & delivery of Wall cladding Sheets by TECTON)

-
Pumping Station Building:
Doors and Windows -

Production, delivery and installation of external and internal doors


of different materials and types, external and internal windows of
-
different materials and types (also rooflight domes) including
window sills and sunscreens.
BOQ. NO. 3.1.22
Automatic Rolling Shutter 18.49 SQM 140.00 2,588.60
Powder Coated Insulated Aluminium Door 6.30 SQM 120.00 756.00
Aluminium Glazed windows - Fixed Double Glazing with Powder 46.00 SQM 120.00 5,520.00
coated Aluminium frames
-
Pumping Station Building:
-
Finishing Works

Internal finishing works including internal plaster, screeds,


suspended ceilings, noise protection boards, painting and coating, -
tiling of walls and floors, floorings of different materials, double
floors, etc.
Block Work 618.08 SQM 48.00 29,667.84
Internal Plastering works - 12mm tk 631.00 SQM 30.00 18,930.00
Ceiling Plastering works - 12mm tk 1,385.25 SQM 27.00 37,401.75
External Plastering works - 20mm tk 816.11 SQM 32.50 26,523.58
50mm tk Screed Concrete with Floor hardener; Grade C35 42.66 CUM 270.00 11,518.20

BOQ. NO. 3.1.23 50mm tk Screed concrete with Reinforced mesh - on loading bay 393.45 SQM 130.00 51,148.50

Painting Works -
Heavy duty Epoxy Screed + One coat Primer + Epoxy Finish coat on 836.19 SQM 38.00 31,775.22
Pump hall over the screed concrete
Epoxy Painting works - rendering + one coat primer + two coats of 1,061.33 SQM 35.00 37,146.55
Epoxy paint finish
Emulsion Paint finish - one coat primer + 2 coats of Emulsion paint
finish 1,181.43 SQM 20.00 23,628.60

External Paint - Texture paint finish 816.11 SQM 25.00 20,402.75


150 dia uPVC pipe laying for Drains under the raft 34.20 RM 20.00 684.00
DI Manhole Cover for Drain Sump (0.9 x 0.9m) 2.00 NUMBER 150.00 300.00
-

Page: 2 / 16
BILL OF QUANTITY FOR CIVIL WORK
LOT-1

Pumping Station Building:


Platforms, Stairs, Railings, Grating -

Production, delivery and installation of platforms, stairs, railings and -


gratings of galvanized steel.
BOQ. NO. 3.1.24 GI Gratings 72.45 SQM 70.00 5,071.50
Structural Steel works - inner Pump hall 3.00 MT 2,000.00 6,000.00
GI Cage Ladder 26.80 RM 390.00 10,452.00
GI Handrail 68.50 RM 270.00 18,495.00
-

PUMPING
STATION
TREATED
EFFLUENT
PST

Page: 3 / 16
BILL OF QUANTITY FOR CIVIL WORK
LOT-1

ELECTRICAL BUILDING -
CIVIL WORKS -
Electrical Building:
-
Excavation and Substructure
Excavation and erection of substructure including clearing of site,
excavation works, bracing and dewatering of construction pit,
construction of foundation including all layers according detail -
design, backfilling of excavation.

Earth Work excavation - Buildings 917.28 CUM 29.00 26,601.12


Road base filling with required compaction 97.77 CUM 12.00 1,173.24
Backfilling with available earth 197.18 CUM 11.00 2,168.98
Disposal 720.10 CUM 6.70 4,824.67
-
Concrete Works -
1000 Guage polythene sheet 286.11 SQM 2.00 572.22
BOQ. NO. 3.1.30 Blinding concrete PCC: C20 N/mm2 28.61 CUM 110.00 3,147.10
RCC Raft Concrete - C40 198.65 CUM 220.00 43,703.00
RCC Wall Concrete - C40 156.57 CUM 280.00 43,839.60
Form Works -
Shuttering Works for Raft 143.52 SQM 190.00 27,268.80
Shuttering Works for Wall 771.79 SQM 270.00 208,383.30
-
Reinforcement -
Reinforcement steel works - Raft, Wall 42.19 TON 850.00 35,861.50
Water-Proofing works -
Horizontal Water proofing Works - Tanking Membrane Type-1 (one
coat of Bitumen primer + Tourch applied 4mm tk bitumen 286.11 SQM 20.00 5,722.20
membrane laying)
-
Electrical Building:
-
Superstructure

Erection of superstructure including columns and beams, ceilings,


load-bearing and non-load-bearing walls of different materials,
stairs, etc., including roof construction and facade construction with
-
all extra works like flaschings, sealants, connection joints, etc.,
including installation openings in roofs and walls, including roof
drainage.

RCC Concrete Works -


RCC Column Concrete - C40 19.54 CUM 260.00 5,080.40
RCC Plinth Concrete - C40 30.00 CUM 290.00 8,700.00
RCC Roof Slab/Ramp/beam /Parapet wall Concrete - C40 152.38 CUM 230.00 35,047.40
Form Works -
BOQ. NO. 3.1.31 Shuttering for Column 173.69 SQM 210.00 36,474.90
Shuttering for Plinth 56.55 SQM 230.00 13,006.50
Shuttering for Roof slab, ramp, beam & Parapet wall 574.38 SQM 200.00 114,876.00
-
Reinforcement -
Reinforcement steel works - Column, Slab, Plinths & P.Wall 26.02 TON 850.00 22,117.00
-
Water-Proofing works -

Vertical Waterproofing works - (one coat primer + torch applied


156.54 SQM 30.00 4,696.20
4mm tk membrane + 6mm tk fibre impregnated board)
PUMPING Roof water proofing 281.79 SQM 27.00 7,608.33
STATION
TREATED Aluminium Flashing - Roof waterproofing Termination 76.00 RM 45.00 3,420.00
EFFLUENT -
PST
Electrical Building:
-
Doors and Windows

Production, delivery and installation of external and internal doors


of different materials and types, external and internal windows of -
different materials and types (also rooflight domes) including
BOQ. NO. 3.1.32 window sills and sunscreens.
Powder Coated Insulated Aluminium Door 6.00 NUMBER 120.00 720.00
Aluminium Glazed windows - Fixed Double Glazing with Powder 4.00 NUMBER 120.00 480.00
coated Aluminium frames
-
Electrical Building:
Finishing Works -

Internal finishing works including internal plaster, screeds,


suspended ceilings, noise protection boards, painting and coating, -
tiling of walls and floors, floorings of different materials, double
floors, etc.
Block Work 200mm thk 396.35 SQM 48.00 19,024.80
BOQ. NO. 3.1.33
Page: 4 / 16
BILL OF QUANTITY FOR CIVIL WORK
LOT-1

BOQ. NO. 3.1.33 Internal wall plastering : 12mm thk plastering with paint 633.04 SQM 31.00 19,624.24
External wall plastering : 20mm thk with paint 399.03 SQM 34.00 13,567.02
Ceiling Plastering works - 12mm tk 240.36 SQM 27.00 6,489.72
Acid resistant Painting 14.40 SQM 30.00 432.00
Acid resistant ceramic tiles 14.40 SQM 55.00 792.00
Heavy duty industrial flooring 290.16 SQM 65.00 18,860.40
Acid resistant ceramic tile skirting 1.52 SQM 75.00 114.00
-
Electrical Building: -
Platforms, Stairs, Railings, Grating
Production, delivery and installation of platforms, stairs, railings and -
gratings of galvanized steel.
BOQ. NO. 3.1.34
Metal Works -
GI Gratings 25.00 SQM 70.00 1,750.00
GI Ladder - Roof access 6.50 RM 390.00 2,535.00
-
Electrical Building: -
BOQ. NO. 3.1.35 Furnishing
-
Electrical Building:
-
BOQ. NO. 3.1.37 Sanitary Installation
-
-
EXTERNAL WORKS -
Station Area: -
Foundation Plate Surge Vessels
Foundation Plate for Surge Vessels incl. Excavation, construction,
backfilling -

Earth Work excavation 480.87 CUM 29.00 13,945.23


Road base filling with required compaction 81.22 CUM 12.00 974.59
Backfilling with available earth 50.87 CUM 11.00 559.57
Disposal 430.00 CUM 6.70 2,881.00
1000 Guage polythene sheet 406.00 SQM 2.00 812.00
Blinding concrete PCC: C20 N/mm2 40.60 CUM 110.00 4,466.00
RCC Concrete Works - C40 (Raft & Supports) 318.50 CUM 230.00 73,255.00
BOQ. NO. 3.1.50
Form Works 135.20 SQM 210.00 28,392.00
Reinforcement Steel 47.77 TON 850.00 40,604.50
Horizontal Waterproofing 400.00 SQM 30.00 12,000.00
Vertical Waterproofing 60.00 SQM 30.00 1,800.00
Heavy duty industrial Flooring - ( Epoxy Screed + Primer + 2 coats of
Epoxy paint) 400.00 SQM 65.00 26,000.00

GI Gratings 60.00 SQM 70.00 4,200.00


GI Cage Ladder 18.00 RM 390.00 7,020.00
GI Chequer plate 13.20 SQM 45.00 594.00
GI Handrail 7.85 RM 270.00 2,119.50
-
Station Area:
-
Shafts
Shafts for valve, drain, flowmeter incl. Excavation, construction,
-
backfilling
Drains including shaft, drain pipes, valves and all equipment
according drawing H652-PDW-EPC-CIV-0040 -
Drains DN 200 from main pipe DN 800 or 900
Earth Work Excavation 40.00 CUM 29.00 1,160.00
1000 Gauge polythene sheet 13.00 SQM 2.00 26.00
Blinding Concrete & Screed 1.02 CUM 110.00 112.20
Screed for Inside chamber 0.15 CUM 200.00 30.00
RCC Concrete Works - C40 8.36 CUM 230.00 1,922.80
Form Works 45.30 SQM 210.00 9,513.00
Reinforcement Steel 1.00 Ton 850.00 850.00
RCC Precast Top cover slab 1.06 CUM 105.00 111.09
Waterproofing Works 30.00 SQM 35.00 1,050.00
Epoxy Painting 21.00 SQM 35.00 735.00
Vent pipe 1.00 NO 50.00 50.00
Manhole Cover D.I 600 x 750 1.00 NO 100.00 100.00
Chamber Indication Plate 1.00 NO 100.00 100.00
Aluminium Surface Box 2.00 NO 200.00 400.00
Aluminum Ladder & Supports 1.00 NO 300.00 300.00
Grating for Sump-150 x 150 1.00 NO 120.00 120.00
SS Grab Bar 1.00 NO 120.00 120.00
Lifting hook 4.00 NO 30.00 120.00
Backfilling with available earth 24.00 CUM 45.00 1,080.00
-

Page: 5 / 16
BILL OF QUANTITY FOR CIVIL WORK
LOT-1

Shaft for valve at IF1 incl. Excavation, construction, backfilling,


according drawing H652-PDW-EPC-CIV-0005, incl. all equipment -
excl. delivery main line valve -Valve Shaft IF1

Earth Work Excavation 50.00 CUM 29.00 1,450.00


1000 Gauge polythene sheet 20.00 SQM 2.00 40.00
Blinding Concrete & Screed 1.80 CUM 110.00 198.00
Screed for Inside chamber 0.30 CUM 200.00 60.00
RCC Concrete Works - C40 11.76 CUM 230.00 2,704.80
Form Works 50.00 SQM 210.00 10,500.00
BOQ. NO. 3.1.51 Reinforcement Steel 1.40 Ton 850.00 1,190.00
RCC Precast Top cover slab 1.96 CUM 105.00 205.80
Waterproofing Works 33.00 SQM 35.00 1,155.00
Epoxy Painting 25.00 SQM 35.00 875.00
Vent pipe 1.00 NO 50.00 50.00
Manhole Cover D.I 600 x 750 1.00 NO 100.00 100.00
Chamber Indication Plate 1.00 NO 100.00 100.00
Aluminium Surface Box 2.00 NO 200.00 400.00
Aluminum Ladder & Supports 1.00 NO 300.00 300.00
Grating for Sump-150 x 150 1.00 NO 120.00 120.00
SS Grab Bar 1.00 NO 120.00 120.00
Lifting hook 4.00 NO 30.00 120.00
Backfilling with available earth 25.00 CUM 45.00 1,125.00
-
Shaft for flowmeter and valve at IF1 incl. Excavation, construction,
backfilling, according drawing H652-PDW-EPC-CIV-0005, incl. all
-
equipment excl. delivery main line valve and flowmeter- Flowmeter
Shaft IF1
Earth Work Excavation 59.00 CUM 29.00 1,711.00
1000 Gauge polythene sheet 23.00 SQM 2.00 46.00
Blinding Concrete & Screed 2.15 CUM 110.00 236.50
Screed for Inside chamber 0.40 CUM 200.00 80.00
RCC Concrete Works - C40 13.68 CUM 230.00 3,146.40
Form Works 56.00 SQM 210.00 11,760.00
Reinforcement Steel 1.64 Ton 850.00 1,394.00
RCC Precast Top cover slab 2.43 CUM 105.00 255.15
Waterproofing Works 37.00 SQM 35.00 1,295.00
Epoxy Painting 30.00 SQM 35.00 1,050.00
Vent pipe 1.00 NO 50.00 50.00
Manhole Cover D.I 600 x 750 1.00 NO 100.00 100.00
Chamber Indication Plate 1.00 NO 100.00 100.00
Aluminium Surface Box 2.00 NO 200.00 400.00
Aluminum Ladder & Supports 1.00 NO 300.00 300.00
Grating for Sump-150 x 150 1.00 NO 120.00 120.00
SS Grab Bar 1.00 NO 120.00 120.00
Lifting hook 4.00 NO 30.00 120.00
Backfilling with available earth 27.00 CUM 45.00 1,215.00
-
-
Station Area:
-
Earthworks

BOQ. NO. 3.1.52 Earthworks according to the specifications in the tender documents
including necessary soil explorations, excavation, backfill, 2,088.00 CUM 60.00 125,280.00
compaction
-
Station Area:
Roads and Traffic Areas -

Roads and traffic areas according to the specifications in the tender


documents including preparation of access road, reinstatement of -
traffic areas of the station including the truck filling sector

Sub grade 2,375.00 SQM 13.00 30,875.00


BOQ. NO. 3.1.53 Granular sub base 475.00 CUM 65.00 30,875.00
Bitumen Prime coat 1.5 kg/ m2 2,375.00 SQM 2.00 4,750.00

Page: 6 / 16
BILL OF QUANTITY FOR CIVIL WORK
BOQ. NO. 3.1.53 LOT-1

Ashpalt base course 80mm tk 2,375.00 SQM 24.00 57,000.00


Ashpalt base course 120mm tk 2,375.00 SQM 28.00 66,500.00
Tack coat 0.5 kg/ m2 2,375.00 SQM 2.50 5,937.50
Ashpalt wearing course 50mm tk 2,375.00 SQM 18.00 42,750.00
Kerb stone fixing 1,079.00 RM 15.00 16,185.00
-
Station Area:
-
External Finishing Works

External finishing works according to the specifications in the tender


documents including provision of new fences and gates, humus -
layer and grass seeding etc. and all other required finishing works
for the station including the separately fenced truck filling sector

60mm tk Interlock pavement with Edge kerb -


BOQ. NO. 3.1.56
Edge Kerb 1,125.00 RM 18.00 20,250.00
60mm tk Interlock 1,295.00 SQM 65.00 84,175.00
Landscaping - Grass plantation with sweet soil 375.00 SQM 78.00 29,250.00
Landscaping - Supply & Fixing of Palm Trees (DACTYLIFERA) 8.00 NO 200.00 1,600.00
Street light foundation 18.00 NO 800.00 14,400.00

Gravel Filling on open areas (up to 150mm tk) 10-20mm sized gravel 2,297.00 SQM 11.00 25,267.00

-
Truck Filling Sector: -
Civil and piping works

Complete civil works for truck filling station including connection


pipes, valve shaft, operator/guard building, filling column -

CIVIL WORKS -
Subgrade preparation 1,239.00 SQM 13.00 16,107.00
Granular sub-base 371.70 CUM 65.00 24,160.50
Bitumen Prime coat 1.5 kg/ m2 1,239.00 SQM 2.00 2,478.00
Ashpalt base course 80mm tk 1,239.00 SQM 12.00 14,868.00
Ashpalt base course 120mm tk 1,239.00 SQM 18.00 22,302.00
Tack coat 0.5 kg/ m2 1,239.00 SQM 2.00 2,478.00
Ashpalt wearing course 50mm tk 1,239.00 SQM 15.00 18,585.00
BOQ. NO. 3.1.57 Drinage Channel - 300mm width 80.00 RM 90.00 7,200.00
RCC Precast Catch pit 3.00 NO 300.00 900.00
Manual Sliding Gate - 13m wide 2.00 NO 1,200.00 2,400.00
Double wings Access gate/Pedestrian gate 1.00 NO 600.00 600.00
TFS Guard house (10 m x 5m x 4m ht size of Building including all 50.00 SQM 510.00 25,500.00
civil works)
300 dia VC pipelaying 50.00 RM 30.00 1,500.00
Valve Chamber for 600mm dia pipeline 1.00 NO 450.00 450.00
Interlock pavements - 60mm tk 186.00 SQM 65.00 12,090.00
Edge kerb stone 205.00 RM 18.00 3,690.00
Fencing - Polisade boundary fence 200.00 RM 120.00 24,000.00

Gravel Filling on open areas (up to 150mm tk) 10-20mm sized gravel 183.00 CUM 11.00 2,013.00

-
Drains DN 150 from main pipe DN 500 -
Drains including shaft, drain pipes, valves and all equipment
-
according drawing H652-PTE-EPC-CIV-0030, pressure class 300
CIVIL -
Earth Work Excavation 41.00 CUM 29.00 1,189.00
1000 Gauge polythene sheet 13.00 SQM 2.00 26.00
Blinding Concrete & Screed 1.02 CUM 110.00 112.20
Screed for Inside chamber 0.15 CUM 200.00 30.00
RCC Concrete Works - C40 8.36 CUM 230.00 1,922.80
Form Works 45.00 SQM 210.00 9,450.00
Reinforcement Steel 1.00 Ton 850.00 850.00
BOQ. NO. 4.3.30 RCC Precast Top cover slab 1.06 CUM 105.00 111.30
Waterproofing Works 30.36 SQM 35.00 1,062.60
Epoxy Painting 21.00 SQM 35.00 735.00
Vent pipe 1.00 NO 50.00 50.00
Manhole Cover D.I 600 x 750 1.00 NO 100.00 100.00
Chamber Indication Plate 1.00 NO 100.00 100.00
Aluminium Surface Box 2.00 NO 200.00 400.00
Aluminum Ladder & Supports 1.00 NO 300.00 300.00
Grating for Sump-150 x 150 1.00 NO 120.00 120.00
SS Grab Bar 1.00 NO 120.00 120.00
Lifting hook - MS 4.00 NO 30.00 120.00
Backfilling with available earth 24.00 CUM 45.00 1,080.00

Page: 7 / 16
BILL OF QUANTITY FOR CIVIL WORK
LOT-1

TOTAL VALUE OF SUB CONTRACT WORKS IN SAR = 4,410,211.61

Page: 8 / 16
BILL OF QUANTITY FOR CIVIL WORK
LOT-3

TECTON Proposed Rate


Name of the BOQ Number Description of Item of Work QTY UNIT
Structure
RATE AMOUNT
(SAR) (SAR)

BOQ.NO.2 SHAFTS FOR PIPELINE DRINKING WATER (PDW)


Pipeline Drinking Water PDW -

BOQ. NO. 2 Ref: Drawings H652-PDW-EPC-HYD-0005, H652-PDW-EPC-SFD-0005,


H652-PDW-EPC-CIV-0005, H652-PDW-EPC-CIV-0035, H652-PDW-EPC- -
CIV-0040

Drains DN 200 from main pipe DN 800 or 900


Drains including shaft, drain pipes, valves and all equipment 89,645.45
according drawing H652-PDW-EPC-CIV-0040
Total No.of Shaft is 5 Nos -
Earth Work Excavation 205.00 CUM 29.00 5,945.00
1000 Gauge polythene sheet 65.00 SQM 2.00 130.00
Blinding Concrete & Screed 5.10 CUM 110.00 561.00
Screed for Inside chamber 0.75 CUM 200.00 150.00
RCC Concrete Works - C40 41.80 CUM 230.00 9,614.00
Form Works 226.50 SQM 210.00 47,565.00
Reinforcement Steel 5.00 Ton 850.00 4,250.00
BOQ. NO. 2.3.30 RCC Precast Top cover slab 5.29 CUM 105.00 555.45
Waterproofing Works 150.00 SQM 35.00 5,250.00
Epoxy Painting 105.00 SQM 35.00 3,675.00
Vent pipe 5.00 NO 50.00 250.00
Manhole Cover D.I 600 x 750 5.00 NO 100.00 500.00
Chamber Indication Plate 5.00 NO 100.00 500.00
Aluminium Surface Box 10.00 NO 200.00 2,000.00
Aliminum Ladder & Supports 5.00 NO 300.00 1,500.00
Grating for Sump-150 x 150 5.00 NO 120.00 600.00
SS Grab Bar 5.00 NO 120.00 600.00
Lifting hook 20.00 NO 30.00 600.00
Backfilling with available earth 120.00 CUM 45.00 5,400.00

Automized aeration for main pipe DN 800 or 900


Aerations including shaft, X-piece DN 600 and aeration pipe, valves
and all equipment according drawing H652-PDW-EPC-CIV-0035 55,138.75
Total No.of Shaft is 5 Nos

Earth Work Excavation 115.00 CUM 29.00 3,335.00


1000 Gauge polythene sheet 60.00 SQM 2.00 120.00
Blinding Concrete & Screed 4.32 CUM 110.00 475.20
Screed for Inside chamber 0.75 CUM 200.00 150.00
RCC Concrete Works - C40 21.35 CUM 230.00 4,910.50
Form Works 135.00 SQM 210.00 28,350.00
Reinforcement Steel 2.60 Ton 850.00 2,210.00
BOQ. NO. 2.3.40
RCC Precast Top cover slab 4.41 CUM 105.00 463.05
Waterproofing Works 85.00 SQM 35.00 2,975.00
Epoxy Painting 70.00 SQM 35.00 2,450.00
Vent pipe 5.00 NO 50.00 250.00
Manhole Cover D.I 600 x 750 5.00 NO 100.00 500.00
Chamber Indication Plate 5.00 NO 100.00 500.00
Aluminium Surface Box 10.00 NO 200.00 2,000.00
Aliminum Ladder & Supports 5.00 NO 300.00 1,500.00
Grating for Sump-150 x 150 5.00 NO 120.00 600.00
SS Grab Bar 5.00 NO 120.00 600.00
Lifting hook 20.00 NO 30.00 600.00
Backfilling with available earth 70.00 CUM 45.00 3,150.00
Manual aeration for main pipe DN 800 or 900
Aerations including shaft, aeration pipe, valves and all equipment 22,055.50
according drawing H652-PDW-EPC-CIV-0035
Total No.of Shaft is 2 Nos -
Earth Work Excavation 46.00 CUM 29.00 1,334.00
1000 Gauge polythene sheet 24.00 SQM 2.00 48.00
Blinding Concrete & Screed 1.73 CUM 110.00 190.08
Screed for Inside chamber 0.30 CUM 200.00 60.00
RCC Concrete Works - C40 8.54 CUM 230.00 1,964.20
Form Works 54.00 SQM 210.00 11,340.00
Reinforcement Steel 1.04 Ton 850.00 884.00
BOQ. NO. 2.3.50 RCC Precast Top cover slab 1.76 CUM 105.00 185.22

Page: 9 / 16
BILL OF QUANTITY FOR CIVIL WORK
BOQ. NO. 2.3.50 LOT-3
Waterproofing Works 34.00 SQM 35.00 1,190.00

PIPELINE
DRINKING
WATER PDW

Page: 10 / 16
BOQ. NO. 2.3.50 BILL OF QUANTITY FOR CIVIL WORK
LOT-3
Epoxy Painting 28.00 SQM 35.00 980.00
Vent pipe 2.00 NO 50.00 100.00
Manhole Cover D.I 600 x 750 2.00 NO 100.00 200.00
Chamber Indication Plate 2.00 NO 100.00 200.00
Aluminium Surface Box 4.00 NO 200.00 800.00
Aliminum Ladder & Supports 2.00 NO 300.00 600.00
Grating for Sump-150 x 150 2.00 NO 120.00 240.00
SS Grab Bar 2.00 NO 120.00 240.00
PIPELINE Lifting hook 8.00 NO 30.00 240.00
DRINKING Backfilling with available earth 28.00 CUM 45.00 1,260.00
WATER PDW Valve Shaft IF1 -
Shaft for valve at IF1 incl. Excavation, construction, backfilling,
according drawing H652-PDW-EPC-CIV-0005, incl. all equipment excl. 20,813.60
delivery main line valve
Total No.of Shaft is 1 No -
Earth Work Excavation 50.00 CUM 29.00 1,450.00
1000 Gauge polythene sheet 20.00 SQM 2.00 40.00
Blinding Concrete & Screed 1.80 CUM 110.00 198.00
Screed for Inside chamber 0.30 CUM 200.00 60.00
RCC Concrete Works - C40 11.76 CUM 230.00 2,704.80
Form Works 50.00 SQM 210.00 10,500.00
Reinforcement Steel 1.40 Ton 850.00 1,190.00
BOQ. NO. 2.3.60
RCC Precast Top cover slab 1.96 CUM 105.00 205.80
Waterproofing Works 33.00 SQM 35.00 1,155.00
Epoxy Painting 25.00 SQM 35.00 875.00
Vent pipe 1.00 NO 50.00 50.00
Manhole Cover D.I 600 x 750 1.00 NO 100.00 100.00
Chamber Indication Plate 1.00 NO 100.00 100.00
Aluminium Surface Box 2.00 NO 200.00 400.00
Aliminum Ladder & Supports 1.00 NO 300.00 300.00
Grating for Sump-150 x 150 1.00 NO 120.00 120.00
SS Grab Bar 1.00 NO 120.00 120.00
Lifting hook 4.00 NO 30.00 120.00
Backfilling with available earth 25.00 CUM 45.00 1,125.00
Flowmeter Shaft IF1 23,499.05

Shaft for flowmeter and valve at IF1 incl. Excavation, construction,


backfilling, according drawing H652-PDW-EPC-CIV-0005, incl. all
equipment excl. delivery main line valve and flowmeter -
Total No.of Shaft is 1 No

Earth Work Excavation 59.00 CUM 29.00 1,711.00


1000 Gauge polythene sheet 23.00 SQM 2.00 46.00
Blinding Concrete & Screed 2.15 CUM 110.00 236.50
Screed for Inside chamber 0.40 CUM 200.00 80.00
RCC Concrete Works - C40 13.68 CUM 230.00 3,146.40
Form Works 56.00 SQM 210.00 11,760.00
BOQ. NO. 2.3.61 Reinforcement Steel 1.64 Ton 850.00 1,394.00
RCC Precast Top cover slab 2.43 CUM 105.00 255.15
Waterproofing Works 37.00 SQM 35.00 1,295.00
Epoxy Painting 30.00 SQM 35.00 1,050.00
Vent pipe 1.00 NO 50.00 50.00
Manhole Cover D.I 600 x 750 1.00 NO 100.00 100.00
Chamber Indication Plate 1.00 NO 100.00 100.00
Aluminium Surface Box 2.00 NO 200.00 400.00
Aliminum Ladder & Supports 1.00 NO 300.00 300.00
Grating for Sump-150 x 150 1.00 NO 120.00 120.00
SS Grab Bar 1.00 NO 120.00 120.00
Lifting hook 4.00 NO 30.00 120.00
Backfilling with available earth 27.00 CUM 45.00 1,215.00

Tap-off Shaft KKMC 22,468.65

Shaft for Tap-off DN300 KKMC incl. Excavation, construction,


backfilling, according drawing H652-PDW-EPC-PID-0010, incl. all
-
equipment
Total No.of Shaft is 1 No
Earth Work Excavation 59.00 CUM 29.00 1,711.00
1000 Gauge polythene sheet 23.00 SQM 2.00 46.00
Blinding Concrete & Screed 2.15 CUM 110.00 236.50
Screed for Inside chamber 0.40 CUM 200.00 80.00

BOQ. NO. 2.3.62 Page: 11 / 16


BILL OF QUANTITY FOR CIVIL WORK
LOT-3
RCC Concrete Works - C40 13.00 CUM 230.00 2,990.00
Form Works 52.00 SQM 210.00 10,920.00
BOQ. NO. 2.3.62 Reinforcement Steel 1.60 Ton 850.00 1,360.00
RCC Precast Top cover slab 2.43 CUM 105.00 255.15
Waterproofing Works 37.00 SQM 35.00 1,295.00
Epoxy Painting 30.00 SQM 35.00 1,050.00
Vent pipe 1.00 NO 50.00 50.00
Manhole Cover D.I 600 x 750 1.00 NO 100.00 100.00
Chamber Indication Plate 1.00 NO 100.00 100.00
Aluminium Surface Box 2.00 NO 200.00 400.00
Aliminum Ladder & Supports 1.00 NO 300.00 300.00
Grating for Sump-150 x 150 1.00 NO 120.00 120.00
SS Grab Bar 1.00 NO 120.00 120.00
Lifting hook 4.00 NO 30.00 120.00
Backfilling with available earth 27.00 CUM 45.00 1,215.00
BOQ.NO.4 SHAFTS FOR PIPELINE TREATED EFFLUENT (PTE)
Drains DN 150 from main pipe DN 500 17,878.90
Drains including shaft, drain pipes, valves and all equipment
-
according drawing H652-PTE-EPC-CIV-0030, pressure class 300
Total No.of Shafts = 1 No -
Earth Work Excavation 41.00 CUM 29.00 1,189.00
1000 Gauge polythene sheet 13.00 SQM 2.00 26.00
Blinding Concrete & Screed 1.02 CUM 110.00 112.20
Screed for Inside chamber 0.15 CUM 200.00 30.00
RCC Concrete Works - C40 8.36 CUM 230.00 1,922.80
Form Works 45.00 SQM 210.00 9,450.00
Reinforcement Steel 1.00 Ton 850.00 850.00
BOQ. NO. 4.3.30 RCC Precast Top cover slab 1.06 CUM 105.00 111.30
Waterproofing Works 30.36 SQM 35.00 1,062.60
Epoxy Painting 21.00 SQM 35.00 735.00
Vent pipe 1.00 NO 50.00 50.00
Manhole Cover D.I 600 x 750 1.00 NO 100.00 100.00
Chamber Indication Plate 1.00 NO 100.00 100.00
Aluminium Surface Box 2.00 NO 200.00 400.00
Aliminum Ladder & Supports 1.00 NO 300.00 300.00
Grating for Sump-150 x 150 1.00 NO 120.00 120.00
SS Grab Bar 1.00 NO 120.00 120.00
Lifting hook 4.00 NO 30.00 120.00
Backfilling with available earth 24.00 CUM 45.00 1,080.00
Drains DN 200 from main pipe DN 800 or 900 89,645.45
Drains including shaft, drain pipes, valves and all equipment
-
according drawing H652-PTE-EPC-CIV-0030, pressure class 300
Total No.of Shafts = 5 Nos -
Earth Work Excavation 205.00 CUM 29.00 5,945.00
1000 Gauge polythene sheet 65.00 SQM 2.00 130.00
Blinding Concrete & Screed 5.10 CUM 110.00 561.00
Screed for Inside chamber 0.75 CUM 200.00 150.00
RCC Concrete Works - C40 41.80 CUM 230.00 9,614.00
Form Works 226.50 SQM 210.00 47,565.00
Reinforcement Steel 5.00 Ton 850.00 4,250.00
BOQ. NO. 4.3.31 RCC Precast Top cover slab 5.29 CUM 105.00 555.45
Waterproofing Works 150.00 SQM 35.00 5,250.00
Epoxy Painting 105.00 SQM 35.00 3,675.00
Vent pipe 5.00 NO 50.00 250.00
Manhole Cover D.I 600 x 750 5.00 NO 100.00 500.00
Chamber Indication Plate 5.00 NO 100.00 500.00
Aluminium Surface Box 10.00 NO 200.00 2,000.00
Aliminum Ladder & Supports 5.00 NO 300.00 1,500.00
Grating for Sump-150 x 150 5.00 NO 120.00 600.00
SS Grab Bar 5.00 NO 120.00 600.00
Lifting hook 20.00 NO 30.00 600.00
Backfilling with available earth 120.00 CUM 45.00 5,400.00
Automized aeration for main pipe DN 500 11,034.55
Aerations including shaft, X-piece DN 500 and aeration pipe, valves
and all equipment according drawing H652-PTE-EPC-CIV-0025, -
pressure class 300
Total No.of Shafts = 1 No -
Earth Work Excavation 23.00 CUM 29.00 667.00

Page: 12 / 16
BILL OF QUANTITY FOR CIVIL WORK
LOT-3
1000 Gauge polythene sheet 12.00 SQM 2.00 24.00
Blinding Concrete & Screed 0.87 CUM 110.00 95.15
Screed for Inside chamber 0.15 CUM 200.00 30.00
RCC Concrete Works - C40 4.30 CUM 230.00 989.00
Form Works 27.00 SQM 210.00 5,670.00
Reinforcement Steel 0.52 Ton 850.00 442.00
BOQ. NO. 4.3.40
RCC Precast Top cover slab 0.88 CUM 105.00 92.40
Waterproofing Works 17.00 SQM 35.00 595.00
Epoxy Painting 14.00 SQM 35.00 490.00
Vent pipe 1.00 NO 50.00 50.00
Manhole Cover D.I 600 x 750 1.00 NO 100.00 100.00
Chamber Indication Plate 1.00 NO 100.00 100.00
Aluminium Surface Box 2.00 NO 200.00 400.00
Aliminum Ladder & Supports 1.00 NO 300.00 300.00
Grating for Sump-150 x 150 1.00 NO 120.00 120.00
SS Grab Bar 1.00 NO 120.00 120.00
Lifting hook 4.00 NO 30.00 120.00
Backfilling with available earth 14.00 CUM 45.00 630.00
Automized aeration for main pipe DN 800 or 900 55,138.75
Aerations including shaft, X-piece DN 600 and aeration pipe, valves
and all equipment according drawing H652-PTE-EPC-CIV-0025, -
pressure class 300
Total No.of Shafts = 5 Nos -
Earth Work Excavation 115.00 CUM 29.00 3,335.00
1000 Gauge polythene sheet 60.00 SQM 2.00 120.00
Blinding Concrete & Screed 4.32 CUM 110.00 475.20
Screed for Inside chamber 0.75 CUM 200.00 150.00
RCC Concrete Works - C40 21.35 CUM 230.00 4,910.50
Form Works 135.00 SQM 210.00 28,350.00
Reinforcement Steel 2.60 Ton 850.00 2,210.00
BOQ. NO. 4.3.41
RCC Precast Top cover slab 4.41 CUM 105.00 463.05
Waterproofing Works 85.00 SQM 35.00 2,975.00
Epoxy Painting 70.00 SQM 35.00 2,450.00
Vent pipe 5.00 NO 50.00 250.00
Manhole Cover D.I 600 x 750 5.00 NO 100.00 500.00
Chamber Indication Plate 5.00 NO 100.00 500.00
Aluminium Surface Box 10.00 NO 200.00 2,000.00
Aliminum Ladder & Supports 5.00 NO 300.00 1,500.00
Grating for Sump-150 x 150 5.00 NO 120.00 600.00
SS Grab Bar 5.00 NO 120.00 600.00
Lifting hook 20.00 NO 30.00 600.00
Backfilling with available earth 70.00 CUM 45.00 3,150.00
Manual aeration for main pipe DN 500 - 900 22,055.50
Aerations including shaft, aeration pipe, valves and all equipment
according drawing H652-PTE-EPC-CIV-0025, pressure class 300 -

Total No.of Shafts = 2 Nos -


Earth Work Excavation 46.00 CUM 29.00 1,334.00
1000 Gauge polythene sheet 24.00 SQM 2.00 48.00
Blinding Concrete & Screed 1.73 CUM 110.00 190.08
Screed for Inside chamber 0.30 CUM 200.00 60.00
RCC Concrete Works - C40 8.54 CUM 230.00 1,964.20
Form Works 54.00 SQM 210.00 11,340.00
Reinforcement Steel 1.04 Ton 850.00 884.00
PIPELINE BOQ. NO. 4.3.50
RCC Precast Top cover slab 1.76 CUM 105.00 185.22
TREATED
EFFLUENT Waterproofing Works 34.00 SQM 35.00 1,190.00
(PTE) Epoxy Painting 28.00 SQM 35.00 980.00
Vent pipe 2.00 NO 50.00 100.00
Manhole Cover D.I 600 x 750 2.00 NO 100.00 200.00
Chamber Indication Plate 2.00 NO 100.00 200.00
Aluminium Surface Box 4.00 NO 200.00 800.00
Aliminum Ladder & Supports 2.00 NO 300.00 600.00
Grating for Sump-150 x 150 2.00 NO 120.00 240.00
SS Grab Bar 2.00 NO 120.00 240.00
Lifting hook 8.00 NO 30.00 240.00
Backfilling with available earth 28.00 CUM 45.00 1,260.00
Split Shaft 47,294.00

Page: 13 / 16
PIPELINE
TREATED
EFFLUENT
(PTE)

BILL OF QUANTITY FOR CIVIL WORK


LOT-3
Split shaft including shaft, aeration pipe, minor valves and all
equipment according drawing H652-PTE-EPC-CIV-0020, excluding -
main line valves and fittings, pressure class 300
Total No.of Shafts = 1 No -
Earth Work Excavation 140.00 CUM 29.00 4,060.00
1000 Gauge polythene sheet 55.00 SQM 2.00 110.00
Blinding Concrete & Screed 6.20 CUM 110.00 682.00
Screed for Inside chamber 1.35 CUM 200.00 270.00
RCC Concrete Works - C40 26.00 CUM 230.00 5,980.00
Form Works 113.00 SQM 210.00 23,730.00
Reinforcement Steel 3.13 Ton 850.00 2,660.50
BOQ. NO. 4.3.60
RCC Precast Top cover slab 7.30 CUM 105.00 766.50
Waterproofing Works 72.00 SQM 35.00 2,520.00
Epoxy Painting 90.00 SQM 35.00 3,150.00
Vent pipe 1.00 NO 50.00 50.00
Manhole Cover D.I 600 x 750 2.00 NO 100.00 200.00
Chamber Indication Plate 1.00 NO 100.00 100.00
Aluminium Surface Box 6.00 NO 200.00 1,200.00
Aliminum Ladder & Supports 2.00 NO 300.00 600.00
Grating for Sump-150 x 150 1.00 NO 120.00 120.00
SS Grab Bar 2.00 NO 120.00 240.00
Lifting hook 6.00 NO 30.00 180.00
Backfilling with available earth 15.00 CUM 45.00 675.00
Flowmeter Shaft IF5 23,499.05
Shaft for flowmeter and valve at IF5 incl. Excavation, construction,
backfilling, according drawing H652-PTE-EPC-CIV-0035, incl. all
-
equipment excl. delivery main line valve and flowmeter, pressure
class 300
Total No.of Shafts = 1 No -
Earth Work Excavation 59.00 CUM 29.00 1,711.00
1000 Gauge polythene sheet 23.00 SQM 2.00 46.00
Blinding Concrete & Screed 2.15 CUM 110.00 236.50
Screed for Inside chamber 0.40 CUM 200.00 80.00
RCC Concrete Works - C40 13.68 CUM 230.00 3,146.40
Form Works 56.00 SQM 210.00 11,760.00
BOQ. NO. 4.3.61 Reinforcement Steel 1.64 Ton 850.00 1,394.00
RCC Precast Top cover slab 2.43 CUM 105.00 255.15
Waterproofing Works 37.00 SQM 35.00 1,295.00
Epoxy Painting 30.00 SQM 35.00 1,050.00
Vent pipe 1.00 NO 50.00 50.00
Manhole Cover D.I 600 x 750 1.00 NO 100.00 100.00
Chamber Indication Plate 1.00 NO 100.00 100.00
Aluminium Surface Box 2.00 NO 200.00 400.00
Aliminum Ladder & Supports 1.00 NO 300.00 300.00
Grating for Sump-150 x 150 1.00 NO 120.00 120.00
SS Grab Bar 1.00 NO 120.00 120.00
Lifting hook 4.00 NO 30.00 120.00
Backfilling with available earth 27.00 CUM 45.00 1,215.00
Flowmeter Shaft IF6 26,662.55
Shaft for flowmeter and valve at IF6 incl. Excavation, construction,
backfilling, according drawing H652-PTE-EPC-CIV-0035, incl. all
-
equipment excl. delivery main line valve and flowmeter, pressure
class 300
Total No.of Shafts = 1 No -
Earth Work Excavation 69.00 CUM 29.00 2,001.00
1000 Gauge polythene sheet 27.00 SQM 2.00 54.00
Blinding Concrete & Screed 2.64 CUM 110.00 290.40
Screed for Inside chamber 0.51 CUM 200.00 102.00
RCC Concrete Works - C40 16.00 CUM 230.00 3,680.00
Form Works 63.00 SQM 210.00 13,230.00
BOQ. NO. 4.3.62 Reinforcement Steel 1.92 Ton 850.00 1,632.00
RCC Precast Top cover slab 3.03 CUM 105.00 318.15
Waterproofing Works 41.00 SQM 35.00 1,435.00
Epoxy Painting 36.00 SQM 35.00 1,260.00
Vent pipe 1.00 NO 50.00 50.00
Manhole Cover D.I 600 x 750 1.00 NO 100.00 100.00
Chamber Indication Plate 1.00 NO 100.00 100.00
Aluminium Surface Box 2.00 NO 200.00 400.00
Aliminum Ladder & Supports 1.00 NO 300.00 300.00

Page: 14 / 16
BOQ. NO. 4.3.62

BILL OF QUANTITY FOR CIVIL WORK


LOT-3
Grating for Sump-150 x 150 1.00 NO 120.00 120.00
SS Grab Bar 1.00 NO 120.00 120.00
Lifting hook 4.00 NO 30.00 120.00
Backfilling with available earth 30.00 CUM 45.00 1,350.00
Tap-off Shaft KKMC 22,468.65
Shaft for Tap-off DN200 KKMC incl. Excavation, construction,
backfilling, according drawing H652-PTE-EPC-PID-0010, incl. all -
equipment, pressure class 300
Total No.of Shafts = 1 No -
Earth Work Excavation 59.00 CUM 29.00 1,711.00
1000 Gauge polythene sheet 23.00 SQM 2.00 46.00
Blinding Concrete & Screed 2.15 CUM 110.00 236.50
Screed for Inside chamber 0.40 CUM 200.00 80.00
RCC Concrete Works - C40 13.00 CUM 230.00 2,990.00
Form Works 52.00 SQM 210.00 10,920.00
Reinforcement Steel 1.60 Ton 850.00 1,360.00
BOQ. NO. 4.3.63
RCC Precast Top cover slab 2.43 CUM 105.00 255.15
Waterproofing Works 37.00 SQM 35.00 1,295.00
Epoxy Painting 30.00 SQM 35.00 1,050.00
Vent pipe 1.00 NO 50.00 50.00
Manhole Cover D.I 600 x 750 1.00 NO 100.00 100.00
Chamber Indication Plate 1.00 NO 100.00 100.00
Aluminium Surface Box 2.00 NO 200.00 400.00
Aliminum Ladder & Supports 1.00 NO 300.00 300.00
Grating for Sump-150 x 150 1.00 NO 120.00 120.00
SS Grab Bar 1.00 NO 120.00 120.00
Lifting hook 4.00 NO 30.00 120.00
Backfilling with available earth 27.00 CUM 45.00 1,215.00
BOQ.NO.7 SHAFTS FOR PIPELINE WASTE WATER (WW) - PRESSURE LINE
Drain Shafts DN200 from main pipe DN800 143,031.20
Drains including shaft, drain pipes, valves and all equipment
-
according drawing H652-PWW-EPC-CIV-0055
Total No.of Shafts = 8 Nos -
Earth Work Excavation 328.00 CUM 29.00 9,512.00
1000 Gauge polythene sheet 104.00 SQM 2.00 208.00
Blinding Concrete & Screed 8.16 CUM 110.00 897.60
Screed for Inside chamber 1.20 CUM 200.00 240.00
RCC Concrete Works - C40 66.88 CUM 230.00 15,382.40
Form Works 360.00 SQM 210.00 75,600.00
Reinforcement Steel 8.00 Ton 850.00 6,800.00
BOQ. NO. 7.3.30 RCC Precast Top cover slab 8.48 CUM 105.00 890.40
Waterproofing Works 242.88 SQM 35.00 8,500.80
Epoxy Painting 168.00 SQM 35.00 5,880.00
Vent pipe 8.00 NO 50.00 400.00
Manhole Cover D.I 600 x 750 8.00 NO 100.00 800.00
Chamber Indication Plate 8.00 NO 100.00 800.00
Aluminium Surface Box 16.00 NO 200.00 3,200.00
Aliminum Ladder & Supports 8.00 NO 300.00 2,400.00
Grating for Sump-150 x 150 8.00 NO 120.00 960.00
SS Grab Bar 8.00 NO 120.00 960.00
Lifting hook 32.00 NO 30.00 960.00
Backfilling with available earth 192.00 CUM 45.00 8,640.00
Automized aeration for main pipe DN 800 88,276.40
Automized Aerations and De-aeration in sections with pressurised
pipeline, including shaft, T-piece DN 600, aeration/de-aeration valves,
odour treatment measures by activated carbon cartridge, aeration -
pipe, valves and all equipment according drawing H652-PWW-EPC-
CIV-0050

Total No.of Shafts = 8 Nos -


Earth Work Excavation 184.00 CUM 29.00 5,336.00
1000 Gauge polythene sheet 96.00 SQM 2.00 192.00
Blinding Concrete & Screed 6.92 CUM 110.00 761.20
Screed for Inside chamber 1.20 CUM 200.00 240.00
RCC Concrete Works - C40 34.40 CUM 230.00 7,912.00
PIPELINE Form Works 216.00 SQM 210.00 45,360.00
WASTE BOQ. NO. 7.3.40
Reinforcement Steel 4.16 Ton 850.00 3,536.00
WATER
(WW)- RCC Precast Top cover slab 7.04 CUM 105.00 739.20
PRESSURE Waterproofing Works 136.00 SQM 35.00 4,760.00
LINE Epoxy Painting 112.00 SQM 35.00 3,920.00

Page: 15 / 16
PIPELINE
WASTE BOQ. NO. 7.3.40
WATER
(WW)-
PRESSURE BILL OF QUANTITY FOR CIVIL WORK
LINE LOT-3
Vent pipe 8.00 NO 50.00 400.00
Manhole Cover D.I 600 x 750 8.00 NO 100.00 800.00
Chamber Indication Plate 8.00 NO 100.00 800.00
Aluminium Surface Box 16.00 NO 200.00 3,200.00
Aliminum Ladder & Supports 8.00 NO 300.00 2,400.00
Grating for Sump-150 x 150 8.00 NO 120.00 960.00
SS Grab Bar 8.00 NO 120.00 960.00
Lifting hook 32.00 NO 30.00 960.00
Backfilling with available earth 112.00 CUM 45.00 5,040.00
Flow Meter Shaft 23,499.05

Supply and construction of structure of precast / cast in-situ concrete


including excavating, dewatering, backfilling, internal and external
coating, stairs, cover, including all related equipment and electrical -
connections, according drawing H652-GEN-EPC-TYP-0035

Total No.of Shafts = 1 No -


Earth Work Excavation 59.00 CUM 29.00 1,711.00
1000 Gauge polythene sheet 23.00 SQM 2.00 46.00
Blinding Concrete & Screed 2.15 CUM 110.00 236.50
Screed for Inside chamber 0.40 CUM 200.00 80.00
RCC Concrete Works - C40 13.68 CUM 230.00 3,146.40
Form Works 56.00 SQM 210.00 11,760.00
BOQ. NO. 7.3.60 Reinforcement Steel 1.64 Ton 850.00 1,394.00
RCC Precast Top cover slab 2.43 CUM 105.00 255.15
Waterproofing Works 37.00 SQM 35.00 1,295.00
Epoxy Painting 30.00 SQM 35.00 1,050.00
Vent pipe 1.00 NO 50.00 50.00
Manhole Cover D.I 600 x 750 1.00 NO 100.00 100.00
Chamber Indication Plate 1.00 NO 100.00 100.00
Aluminium Surface Box 2.00 NO 200.00 400.00
Aliminum Ladder & Supports 1.00 NO 300.00 300.00
Grating for Sump-150 x 150 1.00 NO 120.00 120.00
SS Grab Bar 1.00 NO 120.00 120.00
Lifting hook 4.00 NO 30.00 120.00
Backfilling with available earth 27.00 CUM 45.00 1,215.00
-
TOTAL VALUE OF SUB CONTRACT WORKS IN SAR = 804,105.05