Sei sulla pagina 1di 1

Form No: DDSM/RA 08

RISK ASSESSMENT Date: 01.08.2018


RISK ASSESSMENT CALCULATOR Issue Number: 1
Page: 1 of 1
This form to be used when filling RA 01 & RA 02

Step 1. Determine Likelihood


Likelihood Description
Almost Certain (AC) Common or frequent occurrence (i.e. More than once per month)
Likely (L) Is known to occur or “it has happened” (i.e. Less than once per month, but more than once per year)
Could occur or “I’ve heard of it happening”
Possible (P) (i.e. Less than once per year, but more than once per 5 years)
Unlikely (U) Not likely to occur (i.e. Less than once per 5 years)
Rare (R) Practically impossible (i.e. Unlikely to ever recur)

Step 2. Determine Consequence


Consequence Rating People Consequence Plant, Operational & Environmental Consequences
More than MRU 1,000,000 damage. Major disruption to operation. Major environmental
Catastrophic (C) Death
damage.
MRU 10,000 - MRU 1,000,000 damage. Damage control or SOPEP applied. Major
Major (Ma) Lost time injury or illness
ondoard release or minor release to surrounding environment.
MRU 5,000 - MRU 10,000 damage. Moderate disruption to operation. Moderate on
Moderate (Mo) Medical treatment
deck release contained.
MRU 1,000 - MRU 5,000 damage. Slight disruption to operation. Minor onboard release
Minor (Mi) First aid injury
immediately contained.

Insignificant (I) No injury Under MRU 1,000 damage. Minimal disruption to operation. No environmental impact.

Step 3. Calculate Risk


Likelihood Consequences
Insignificant (I) Minor (Mi) Moderate (Mo) Major (Ma) Catastrophic (C)
Almost Certain (AC) Serious Serious High High High
Likely (L) Moderate Serious Serious High High
Possible (P) Low Moderate Serious High High
Unlikely (U) Low Low Moderate Serious High
Rare (R) Low Low Moderate Serious Serious

# Sensitivity: Internal