Bar – Boljare Highway,

Section Smokovac – Uvač – Mateševo


MSE Wall / Zid od armirane zemlje
RK 1+093 – RK 1+334
Expert’s Witness Report on Unforeseeable Physical
Condition under the Sub-Clause 4.12 / Stručni nalaz
o nepredvidivim fizičkim uslovima prema
potklauzuli 4.12

August 2020
Supervision of Design and Works
Nadzor nad Projektovanjem i Izgradnjom

Revision 01
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Document Control Sheet

Client: Ministry of Transport and Maritime Affairs

Project: Supervision of Design and Works on the Bar - – Boljare Highway


Section Smokovac – Uvač – Mateševo

Title: MSE Wall on RK 1+093 – RK 1+334; Expert’s Witness Report on Unforeseeable


Physical Condition under the Sub-Clause 4.12-Rev01. August 2020 / Zid od armirane
zemlje na RK 1+093 – RK 1+334; Stručni nalaz o nepredvidivim fizičkim uslovima
prema potklauzuli 4.12-Rev01

Revision History

Prepared by Checked by Approved by

ORIGINAL Darko Muza Jan Lorange Jan Lorange

SIGNATURE

DATE Rev00 10 July 2020 11 July 2020 11 July 2020


DATE Rev01 06 August 2020 06 August 2020 06 August 2020

1
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

LIST OF CONTENTS

1. INTRODUCTION / UVOD................................................................................................................................3
2. CLAIM EVENT / DOGAĐAJ POTRAŽIVANJA.......................................................................................... 3
3. TECHNICAL REVIEW OF CONTRACTOR’S DOCUMENTATION / TEHNIČKI PREGLED
DOKUMENTACIJE IZVOĐAČA RADOVA .................................................................................................. 23
3.1. GENERAL COMMENTS / OPŠTI KOMENTARI....................................................................................... 23
3.2. TECHNICAL COMMENTS / TEHNIČKI KOMENTARI........................................................................... 42
3.3. TECHNICAL CONCLUSION / TEHNIČKI ZAKLJUČAK .................................................................. 44
4. GENERAL DESCRIPTION / OPŠTI OPIS.................................................................................................. 46
5. PRELIMINARY DESIGN / IDEJNI PROJEKAT....................................................................................... 48
6. CONCLUSION ON PRELIMINARY DESIGN / ZAKLJUČAK O IDEJNOM PROJEKTU................ 51
7. CONTRACTOR’S CLAIM ANALIZY / ANALIZA POTRAŽIVANJA IZVOĐAČA RADOVA...........53
8. FINAL CONCLUSION / KONAČAN ZAKLJUČAK................................................................................. 59

2
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

1. INTRODUCTION 1. UVOD
Due to Contractor's claim for unforeseeable Zbog Izvođačevih potraživanja za nepredvidive
geological conditions in occasions of changed geološke uslove u slučaju izmjenjenih geoloških
geological conditions, and accordingly uslova, i sukladno tome fundiranju zida od
foundation of MSE Wall; observed during armirane zemlje, uočenih tokom iskopa,
excavation, herewith the Engineer is providing Inženjer dostavlja svoje stručno mišljenje kako
our expert witness opinion below. This particular slijedi. U ovom konkretnom Izvještaju dajemo
Report shows our opinion on the Contractor's mišljenje o Izvođačevim potraživanjima br. 128,
Claims No. 128, 132 and 132-1, described in 132 i 132-1, koja su opisana u poglavlju 2 ovog
chapter 2 of this Report; and related to Sub- Izvještaja; i odnose se na Poddionicu 1.1.1 - Zid
Section 1.1.1 – MSE Wall on chainage RK od armirane zemlje na stacionaži RK 1+093 –
1+093 – RK 1+334. RK 1+334.

2. CLAIM EVENT 2. DOGAĐAJ POTRAŽIVANJA

In Contractor’s submitted Fully Detailed U dostavljenom Izvođačevom potpunom


Overall Claim – The Description of ERE detaljnom sveobuhvatnom potraživanju –
Under Claim No. AP/EoT 128, Contractor Opis ERE shodno Potraživanju br. AP/EoT
stated as follow: “During the preparation work 128, Izvođač je izjavio slijedeće:
of the reinforced soil embankment (MSE wall) „Tokom pripremnih radova na nasipu od
construction at chainage RK 1+093 – RK armiranog tla (MSE zid), na stacionaži RK
1+334, the unfavourable geological condition – 1+093 – RK 1+334 pronađeno je nepovoljno
geological category P was found at part of geološko stanje, kategorija P na dijelu zone
foundation zone in thickness exceeding 35,5 m. temelja u debljini većoj od 35,5 m.

As in the Preliminary Design, which is the Kao u Idejnom projektu, koji predstavlja
design documents provided by Employer at the projektnu dokumentaciju koju je obezbijedio
tender stage, the geology at the target zone was Investitor u fazi Tendera, geologija ciljne zone
categorised as K22 (defined as dominanted by je kategorizovana kao K22 (definisana kao zona
dolomites, dolomitic limestone) with barely u kojoj dominiraju dolomiti, dolomitični
existind dilluvial deposition on the surface. It is krečnjak) s jedva postojećim deluvijalnim
therefore expected that MSE wall was directly nanosima na površini. Stoga je očekivano da će
located on the natural terrain with very limited MSE zid biti smješten direktno na prirodnom
excavation. terenu, s ograničenom količinom iskopavanja.

Obviously, the geological information provided Očigledno je da se geološke informacije date u


in Preliminary Design was different and at the Idejnom projektu razlikuju i istovremeno se
same time it could not enable the Contractor to Izvođaču nije omogućilo da predvidi tako veliki
predict such large extent of the geology category opseg geologije kategorije P s kojom se suočio
P encountered on site, which have caused a na gradilištu, a koja je prouzrokovala
delay and disruption to the progress of the kašnjenje i remećenje napretka radova i za
Works and resulted in unplanned additional rezultat imala neplanirane dodatne troškove i
costs and loss of time. gubitak vremena.

This ERE must be recognized by the CA and has Ovaj ERE mora biti priznat u US i mora imati
to have a contractual meaningfull, so that ugovorno značenje, tako da Izvođač smatra da
Contractor considers this ERE fall within ERE spada u nepredvidljive uslove na terenu
unforeseeable site conditions (SC 4.12 and SC (PK 4.12 i PK 1.1.6.8).
1.1.6.8).

3
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

In the chapter The description of the ERE U poglavlju Opis ERE shodno Potraživanju
Under Claim No. AP/EoT 132, Contractor br. AP/EoT 132, Izvođač je izjavio slijedeće: S
stated as follow: “Wiith the occurance of javljanjem nepredvidljivih geoloških uslova
Unforeseeable geological condition during the tokom izgradnje, neophodno je napraviti
construction phase, it is necessary to make a izmjenu Glavnog projekta, tj. Prilagoditi
Main Design change, i.e. to adjust the geometry geometriju MSE zida u skladu sa stvarnom
of the MSE wall in accordance with the actual geologijom, da bi se zadovoljili uslovi za
geology to satisfy the structure stability. stabilnost konstrukcije.

However, several months have passed since the


first submission on 07.18.2019, the Main Design Međutim, prošlo je nekoliko mjeseci od prvog
change of MSE wall RK 1+093 – RK 1+334 dostavljanja dana 18.07.2019., a izmjena
was still not being approved. The main reason Glavnog projekta za MSE zid RK 1+093 – RK
was that SRP does not accept the compressive 1+334 još nijje odobrena. Glavni razlog je što
modulus that adopted in the Main Design DKR ne prihvata modul stišljivosti koji je
change, regardless the fact that this parameter usvojen u izmjeni Glavnog projekta, uprkos
was defined in the additional geological činjenici da je taj parametar bio definisan u
elaborate which was already approved by SRP dodatnom Geološkom elaboratu koji je odobrila
on 24.07.2019 DKR dana 24.07.2019.

In order to address the SRP doubts and move


forwards the review progress, the Contractor Da bi odagnale sumnje DKR-a i krenulo dalje s
has performed in situ test (which is the only way revizijom, Izvođač je sproveo in-situ ispitivanje
to get the real compressive modulus) and the (što je jedini način da se dobije stvarni modul
results confirmed the parameters that previously stišljivosti), i rezultati su potvrdili da su
defined in the additional geological parametri koji su prethodno definisani u
elaborateand adopted in the Main Design dodatnom Geološkom elaboratu i usvojeni u
change are reasonable. izmjeni Glavnog projekta razumni.

Despite all the efforts that the Contractor made , Uprkos naporima Izvođača, dana 07.10.2019.
on 07.10.2019 the SRP again returned the Main DKR je ponovo vratila izmjenu Glavnog
Design change that was updated with real projekta koja je ažurirana stvarnim
parameter, and strongly suggest the Contractor parametrima, i toplo preporučila Izvođaču da
to consider other solutions than MSE walls. razmisli o drugim rješenjima, osim MSE zida.
Having in mind the prolonged review process of Imajući u vidu da je produženi proces revizije
the Main Design change has caused delay and izmjene Glavnog projekta doveo do kašnjenja i
disruption to the progress of the Works and remećenja napretka radova i rezultirao
resulted in unplanned additional costs and loss neplaniranim dodatnim troškovima i gubitkom
of time, the Notice of intention to the claim No. vremena, Obaviještenje o potraživanju br. 132
132 under Sub-clause 20.1 was served on prema potklauzuli 20.1 je dostavljeno
01.11.2019. 01.11.2019.

In the chapter The description of the ERE U poglavlju Opis ERE shodno Potraživanju
Under Claim No. AP/EoT 132/1, Contractor br. AP/EOT 132/1, Izvođač izjavljuje slijedeće:
stated as follow: “Follow up to the SRP’s „Nakon odbijanja izmjene Glavnog projekta od
rejection of the Main Design change, the strane DKR-a, Izvođač je komunicirao s DKR-
Contractor has communicated with the SRP and om i postigao dogovor o alternativnom
reached an agreement on the alternative rješenju, tj. da se MSE zid zamijeni opštim
solution, which is, to replace MSE wall with nasipom, uključujući i AB potporni zid.
general embankment, including RC retaining
wall.
Shodno tome, radi preciznijeg definisanja

4
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Accordingly, for the more precise definition of geološkog okruženja za novo rješenje za nasip,
the geological setting for the new solution of Izvođač je dostavio Dodatak Projektu dodatnih
embankment, the Annex to the Design of geotehničkih ispitivanja dana 22.10.2019., koji
additional geotechnical investigations was je, međutim, DKR odbacila dana 29.10.2019.,
submitted by the Contractor on 22.10.2019, ponovo iz razloga što pitanje parametara nije
which, however, was rejected by SRP on bilo rješeno (istinu rečeno, Izvođač je dana
29.10.2019 again for the reason that parameter 10.10.2019 jasno zatražio od DKR-a da
issue was not resolved. (The truth is, the naznači metodu koju smatra pouzdanom za
Contractor on 10.10 2019 has clearly requested dobijanje primjenjivih parametara, ali odgovor
SRP to indicate which method they consider as noikad nije dat).
reliable to get applicable parameter, but the
answer was never provided).
Kroz naknadnu komunikaciju s DKR-om,
From the subsequent communication with the Izvođaču je preporučeno da sprovede dodatna
SRP, Contractor was recommended to conduct ispitivanja za modul stišljivosti. Kako je ovaj
additional test for the compressive modulus. As zahtjev postavljen tri mjeseca nakon odobrenja
this requirement was conducted three months dodatnog geološkog elaborata (dokumenta u
after the approval of additional geotechnical kom je parametar definisan), i nadolazeće
elaboration (the document wherein parameter nepovoljno kišno vrijeme će imati negativan
was defined), and the upcoming unfavourable uticaj na ispitivanja na gradilištu, to će bez
rainy season will adversely impact the testing on sumnje još odložiti odobravanje izmjene
site, it, without doubt will further delay the Glavnog projekta. U takvim okolnostima, dana
approval of Main Design change. In this 02.11.2019. dostavljeno je Obaviještenje o
circumstance, on the date of 02.11.2019 the namjeri potraživanja br. 132/1 prema
Notice of intention to the claim No. 132/1 under potklauzuli 20.1.
Sub-clause 20.1 was served.
Potrebno je napomenuti da je DKR dala još
To be noted, there were more requirements / zahtjeva / komentara o ovom pitanju tokom
comments given by SRP thereafter during the procesa revizije (koji su takođe bili
review process (which were also unjusted and neopravdani i nosili negativne implikacije, a o
with negative implication and which will be čemu će se detaljnije raspravljati u poglavlju
elaborated in section of this Claim which deals ovog Potraživanja koje se bavi analizom
with factual matter), for which Contractor činjeničnog stanja) za što je Izvođač odlučio da
choose not to submit new claim notices ne dostavlja nova Potraživanja pojedinačno,
separately, but consider them to be covered već smatra da su pokriveni Potraživanjima br.
under Claim No. 132 & 132-1, as they belong to 132 i 132/1, budući da spadaju pod isti
the same subject, that is, prolonged review of the predmet, tj. Produženi proces revizije izmjene
Main Design change. Glavnog projekta.

The Contractor’s submission of the fully detailed Izvođačevo dostavljanje punog detaljnog
Claim is to be considered as an overall claim, Potraživanja se treba smatrati za sveobuhvatno
due to a fact that all of the events giving a rise to Potraživanje, uslijed činjenice da su svi
Claim 120, Claim 132 and Claim 132/1 are događaji koji su doveli do Potraživanja br. 128,
interstrickably linked, and all analyses are 132 i 132/1 neraskidivo povezani, i sve analize
inseparably connected, and therefore the effectt neodvojivo povezane, pa se stoga efekti
of the events should be presented under događaja trebaju predstaviti u okviru
Contractor’s final overall entitlement to EOT Izvođačevog finalnog sveobuhvatnog prava na
and additional payment. produženje roka za završetak i dodatno
plaćanje.

In the same Report, in the chapter The Events U istom Izvještaju, u poglavlju Događaji koji
giving rise to Claim (Factual-matter analyses) su doveli do potraživanja (Analiza

5
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

– The Occurance of Unforeseeable geological činjeničnog stanja) – Javljanje


condition, Contractor stated as follow: nepredvidljive geološke situacije, Izvođač je
“According to the approved Main Design of Sub- izjavio slijedeće: U skladu sa odobrenim
Section 1.1.1 (Enclosure 5), the preparation projektom Poddionice 1.1.1 (Prilog 5),
work of the reinforced soil embankment (MSE obavljeni su pripremni radovi na nasipu od
wall) construction at chainage RK 1+093 – RK armiranog tla (MSE zid) na stacionaži RK
1+334 on Sub-Section 1.1.1 was performed on 1+093 – RK 1+334, na Poddionici 1.1.1.
site. However, during excavation the Međutim, tokom iskopavanja se naišlo na
unforeseeable geological condition – geology nepredvidljivo geološko stanje – geologiju
category P was found at the designed elevation kategorije P na označenoj koti temelja gdje se
of foundation level where the firm rock očekivalo da će se naići na čvrstu stijenu
(limestone) was expected to be reached. (krečnjak). Kategorija P se uglavnom sastoji od
Category P mainly consist of scree material, drobine, uključujući koluvijum, krečnjačku
including colluvium, limestone debris, with the osulinu, s niskim sadržajem glina-pijesak
low content of clay-send component, and it is komponente, i samo djelomično je povezana.
partly bounded. As confirmed by the results of Kako su potvrdili rezultati naknadnog istražnog
the subsequent exploration drilling in the bušenja na navedenoj lokaciji (Prilog 6), tlo na
mentioned location (Enclosure 6), the soil lokaciji RK 1+093 – RK 1+334 se sastoji od
located at RK 1+093 – RK 1+334 is made of the geološke kategorije P debljine preko 35,5 m.
geological category P, with thickness exceeding
35,5 m.

In the Preliminary Design, which is the design U idejnom projektu, koji predstavlja projektnu
documents provided by Employer at the tender dokumentaciju koju obezbijeđuje Investitor u
stage, and on which bases Contractor’s Offer fazi tendera, i na osnovu kojeg je pripremljena
was prepared, the geology was defined in the Izvođačeva Ponuda, geologija je definisana u
longitudinal profile and cross sections drawing nacrtima podužnog profila i poprečnog
(Enclosure 7 – Complete geotechnical cross presjeka (Prilog 7 - Puni geotehnički poprečni
section of the terrain km 0+000 – 3+70; presjek terena km 0+000 do 3+70; Prilog 8 –
Enclosure 8 – Engineering-geological cross Inženjersko-geološki poprečni presjeci profila
section profiles from km 0+000 – 2+500; km 0+000 – 2+500; Prilog 9 – Poprečni
Enclosure 9 – Cross sections km 1+100 – presjeci km 1+100 – 1+275), Preciznije, u
1+275). Specifically, the target zone was ciljanoj zoni dominiraju dolomiti, dolomitični
dominated by dolomites, dolomitic limestone, krečnjaci, kategorizirani kao K22, s jedva
categorized as K22, with bearly existed dilluvial postojećim deluvijalnim nanosima na površini.
deposition on the surface. It is therefore Stoga je bilo predviđeno da predloženi MSE
predicted that the proposed MSE wall was zid bude smješten direktno na prirodnom
directly located on the nature terrain with very terenu s veoma ograničenom količinom
limited excavation. iskopavanja.

Obviously, the geological information provided


in Preliminary Design was different, i.e. Očigledno, geološke informacije date u Idejnom
geological conditions have changed compared to projektu se razlikuju, tj. Geološka situacija se
those given in Preliminary Design, at the same izmjenila u poređenju na onu datu u Idejnom
time it could not enable the Contractor to projektu, a istovremeno se Izvođaču nije
foresee the condition actually encountered on omogućilo da predvidi situaciju na koju se
the Site as stated above.” naišlo na licu mjesta, kako je gore opisano“.

In the chapter The Process of Making Main U poglavlju Proces pravljenja izmjene
Design Change, it is stated: “As in the Glavnog projekta navedeno je: „ Kako je
approved Main Design, the MSE wall was in odobrenom Glavnom projektu MSE zid
mainly designed and calculated as located on the uglavnom projektovan i proračunat kao da stoji

6
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

rock (see Enclosure 5), with the occurance of na stijeni (v Prilog 5), s javljanjem
Unforeseeable geological condition during the nepredvidljive geološke situacije tokom faze
construction phase, it is necessary to develop a izgradnje, neophodno je bilo sprovesti izmjenu
Main Design change in comply with the actual Glavnog projekta u skladu sa stvarnom
geology, i.e. to re-check all the representative geologijom, tj. Ponovo provjeriti sve
cross sectionsand adjust the geometry of MSE reprezentativne poprečne presjeke i prilagoditi
wall to sattisfie the structure stability. geometriju MSE zida da bi se zadovoljili uslovi
stabilnosti konstrukcije.
On 26.04.2019 the Contractor by letter RB-
BBH/1422/EM-P1 (Enclosure 10) submitted to Dana 26.04.2019. Izvođač je dopisom RB-
SRP the Design of additional geotechnical BBH/1422/EM-P1 (Prilog 10) dostavio DKR-u
investigation, which includes 5 borehole drilling Projekat dodatnih geotehničkih ispitivanja,
to the depth of 20 m, followed by testing. The koji obuhvata bušenje pet rupa dubine do 20 m,
purpose of work was to provide more details of nakon čega slijedi ispitivanje. Svrha ovih
actual geological situation for making the Main radova je da se dobije više detalja o stvarnom
Design change. geološkom stanju radi izvođenja izmjene
Glavnog projekta.
On 17.05.2019, the Enployer by letter
PJ/5166/DB (Enclosure 11) sent to the
Contractor SRP’s approval of Design of Dana 17.05.2019 Investitor je dopisom
additional geotechnical investigation. PJ/5166/DB (Prilog 11) poslao Izvođaču
odobrenje DKR-a za Projekat dodatnih
On 24.06.2019 the Contractor by letter RB- geotehničkih istpitivanja.
BBH/2237/EM-P1 (Enclosure 12) submitted to
SRP the Elaboration of additional geotechnical Dana 24.06.2019. Izvođač je dopisom RB-
investigations, that is based on investigation BBH/2237/EM-P1 (Prilog 12) dostavio DKR-u
results, the soil located at RK 1+093 – RK Elaborat dodatnih geotehničkih ispitivanja, tj.
1+334 is made of category P1 with thickness na temelju rezultata ispitivanja se pokazalo da
exceeding 13 m, conditions for construction of tlo na RK 1+093 – RK 1+334 pripada
the reinforced soil retaining wall should be kategoriji P1 sa debljinom preko 13 m, pa
adjusted accordingly; instead of the original uslove za izvođenje potpornog zida od
method on the Main Design – a reinforced soil armiranog tla treba prilagoditi shodno tome:
embankment founded on the rock (in that case, umjesto originalne metode u Glavnom projektu
there will be a very deep foundation, which is a – nasip od armiranog tla utemeljen na stijeni (u
low economic benefit solution), it is tom slučaju bi temelji bili veoma duboki, što je
recommended that a reinforced soil embankment rješenje niske ekonomske koristi), preporučuje
with buttress to be applied, which, analized from se primjena nasipa od armiranog tla s
aspect of stability and bearing capacity has good podupiračima, što sa aspekta stabilnosti i
results. nosivosti ima dobre rezultate.

On 06.07.2019, the Enployer by letter


PJ/7193/DB (Enclosure 13) sent to the Dana 05.07.2019 Investitor je dopisom
Contractor the SRP’s review report on PJ/7193/DB (Prilog 13) poslao Izvođaču
Elaboration of additional geotechnical izvještaj DKR-a o Elaboratu dodatnih
investigations, which give comment that 4 geotehničkih ispitivanja, s komentarom da 3
boreholes were not drilled up to the designed bušotine nisu izbušene do projektovane
depth, and concluded that the geotechnical dubine, zaključivši da geotehnički model tla
model of the ground was not fully defined; nije u potpunosti definisan, pa shodno tome
accordingly the interpretation of the tumačenje inženjersko-geološke sekcije terena
engineering-geological section of the terrain nije pouzdano.
were not reliable.

7
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

On 18.07.2019 the Contractor by letter RB- Dana 18.07.2019. Izvođač je dopisom RB-
BBH/2630/EM-P1 (Enclosure 14) submitted to BBH/2630/DS-DS1 (Prilog 14) dostavio DKR-u
SRP the updated version of Elaboration of ažuriranu verziju Elaborata dodatnih
additional geotechnical investigations, which geotehničkih ispitivanja, u kom se dalo
provided explanation for the adjustments of the objašnjenje za prilagođavane dubine bušotina.
designed depth of the boreholes. Namely, based Naime, na temelju iskustava Projektanta i
on the experience of the Designer and developed sprovedenih geostatičkih proračuna, P1 može
geostatic calculations, P1 can be the subsoil for biti podtlo za planirani nasip od armiranog tla,
planned reinforced soil embankment, for two a za dvije bušotine dubine 13 i 15 m respektivno
boreholes that were drilling down to recpectivly u kategoriji P1, informacije dobijene s tih
15 m and 13 m depth in category P1, the dubina su dovoljne za pravljenje izmjene
information provided from such depths is enough Glavnog projekta; što se tiče treće koja je
for making Main Design change; for the third izbušena u kategoriji P2 na dubinu od 12 m,
one that was drilled to category P2 at the depth kategorija tla je već bila jasna i karakteristike
of 12 m, the soil categorywas already made clear tla se mogu samo povećavati s dubinom, te u
and the soil characteristicscan only be increased tom slučaju nije bilo neophodno nastaviti s
with depth, in such case it was unnecessary to dubljim bušenjem.
continue drilling down. In Contractor’s opinion, Po mišljenju Izvođača, istražni radovi i
the investigation works and tests performed are ispitivanja koja su sprovedena su odgovarajuća
adequate and can provide reliable input data for i mogu pružiti pouzdane podatke za vršenje
making the adjustment ofr Main Design solution prilagođavanja rješenja Glavnog projekta.
.
On 24.07.2019, the Enployer by letter
PJ/8039/DB (Enclosure 15) sent to the Dana 24.07.2019 Investitor je dopisom
Contractor the SRP’s approval of Elaboration PJ/8039/DB (Prilog 15) poslao Izvođaču
on additional geotechnical investigations, with a odobrenje Elaborata od strane DKR-a za
condition that the solution itself (the proposed dodatna geotehnička ispitivanja, uz uslov da
adjustment of the Main Design solution) can samo rješenje predloženo prilagođavanje
latter be accepted. rješenja Glavnog projekta)može kasnije biti
prihvaćeno.
On 18.07.2019 the Contractor by letter RB-
BBH/2629/EM-P1 (Enclosure 16) submitted to Dana 18.07.2019. Izvođač je dopisom RB-
SRP the Main Design change for Reinforced Soil BBH/2629/DS-DS1 (Prilog 16) dostavio DKR-u
Embankment RK 1+093 – RK 1+334 (“Version izmjenu Glavnog projekta za nasip od
1” for easy reference). Namely, based on actual armiranog tla RK 1+093 – RK 1+334
geological situation and evidenced by („Verzija 1“ – radi lakše reference). Naime, na
calculation, the MSE wall solution can be kept, temelju stvarne geološke situacije i kako je
but with the following adjustment: lower down a posvjedočeno proračunima, može se zadržati
part of wall foundation and increase the length rješenje za MSE zid, ali uz slijedeća
of geogrids; lift up a part of wall foundation; prilagođavanja: spustiti dio temeja zida i
and apply ballast solution at a certain zone. povećati dužinu geo-mreža; podići dio temelja
zida i podići balast u određenoj zoni.
On 02.08.2019, the Enployer by letter
PJ/8490/DB (Enclosure 17) sent to the
Contractor the SRP’s report on review of the Dana 02.08.2019. Investitor je dopisom
Main Design change – Version 1, in which SRP PJ/8490/DB (Prilog 17) poslao Izvođaču
gave comments that used geological and izvještaj revizije DKR-a o izmjeni Glavnog
geotechnical parameters in calculation have not projekta – Verzija 1, u kom je DKR dala
been taken correctly from the Elaboration of komentare da primjenjeni geotehnički i geološki
additional geotechnical investigations, also the parametri pri izračunavanju nisu bili pravilno
Designer should provide more details of preuzeti iz Elaborata dodatnih geotehničkih
comparison of the original solution and newly ispitivanja, i takođe da Projektant treba da

8
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

designed solution. pruži više detalja u pogledu poređenja


originalnog rješenja i novoprojektovanog
On 05.08.2019 the Contractor by letter RB- rješenja.
BBH/2918/DS-DS1 (Enclosure 18) submitted to
SRP the updatedMain Design change – Version
2, which provided more details as SRP Dana 05.08.2019. Izvođač je dopisom RB-
required.But, as it was latter found that BBH/2918/DS-DS1 (Prilog 18) dostavio DKR-u
parameters remain uncorrected, on 14.08.2019, ažuriranu izmjenu Glavnog projekta – Verzija
the Contractor by letter RB-BBH/3092/DS-DS1 2, u kojoj je dato više detalja, kako je
(Enclosure 19) withdrow the above submission, zahtijevala DKR. Međutim, kako se kasnije
and the same day by letter RB-BBH/3097/DS- uvidjelo da parametri nisu korigovani, dana
DS1 (Enclosure 20)resubmitted the Main Design 14.08.2019 Izvođač je dopisom RB-
change – updated Version 2. BBH/3092/DS-DS1 (Prilog 19) povukao gornji
podnesak, i istog dana dopisom RB-
On 19.08.2019, the Employer by letter BBH/3097/DS-DS1 (Prilog 20) ponovno
PJ/9189/DB (Enclosure 21) sent to the dostavio izmjenu Glavnog projekta – ažuriranu
Contractor the SRP’s report on review of the verziju 2.
Main Design change – Version 2, but the
comments of SRP were given to the withdrowen Dana 19.08.2019. Investitor je dopisom
version, as it is stated that the parameters were PJ/9189/DB (Prilog 21) poslao Izvođaču
still not corrected; also, it stated that the izvještaj revizije DKR-a o izmjeni Glavnog
Designer made calculation with “insufficiently projekta – Verzija 2, ali komentari DKR-a su
reliable interpretation of the engineering- dati na povučenu verziju, budući da je
geological section of the terrain”. navedeno kako parametri još nisu korigovani,
takođe je navedeno da je Projektant vršio
On 22.08.2019 the Contractor by letter RB- proračun sa „nedovoljno pouzdanim
BBH/3226/DS-DS1 (Enclosure 22) submitted to tumačenjem inženjersko-geološke sekcije
SRP Main Design change – Version 3, which terena“.
provided clarification that the parameters were
already corrected and the calculation was also
updated; regarding SRP questioning to the Dana 22.08.2019. Izvođač je dopisom RB-
reliability of the geological information used as
BBH/3226/DS-DS1 (Prilog 22) dostavio DKR-u
the bases for calculation, Contractor replied that
izmjenu Glavnog projekta – Verzija 3, u kojoj
there is no assumption or interpretation ofsu data pojašnjenja da su parametri već
geological models, because all of them are from
korigovani i da je proračun ažuriran; što se tiče
approved additional geotechnical elaboration,
ispitivanja od strane DKR-a u pogledu
which met the requirements of the structurepouzdanosti geoloških informacija korišćenih
design and provided reliable and sufficientkao temelj za proračun, Izvođač je odgoovorio
bases for the structure calculation, no more
da nema pretpostavke tumačenja geotehničkih
geological investigation works will be needed.
modela, budući da svi potiču iz odobrenog
Contractor emphasized that MSE wall is flexible
Geotehničkog elaborata, čime se osiguravaju
structure which is suitable for most of thezahtjevi projekta i konstrukcije i osigurava
geology. To be noted, the given geology pouzdana i dovoljna osnova za strukturne
profileand parameters in the additional proračune, i nisu potrebni dodatni istražni
geological elaboration were more conservative
radovi. Izvođač je naglasio da je MSE zid
than the real situation (the foundation already
fleksibilna konstrukcija koja je odgovarajuća
excavated), and even according to the more za većinu geologija. Potrebno je navesti da su
conservative data, the newly designed solution
dati geološki profil i parametri u dodatnom
of MSE wall was verified to be satisfying. geološkom elaboratu bili konzervativniji, od
stvarnog rješenja (temelj već iskopan), te je čak
In the chapter Claim Notice No. AP/EOT 128 u skladu s konzervativnijim podacima novo
Contractor stated as follow: projektno rješenje za MSE zid provjereno

9
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

“On 02.09.2019 the Contractor by letter RB- zadovoljavajuće.


BBH/3444/CD-P1 (Enclosure 1) submitted to
the Engineer the Notice of intention to claim
Extension of Time for Completion and Addition
Payment No. 128 under Sub-clause 20.1, as the U poglavlju Obaviještenje o Potraživanju br.
occurrence of Unforeseeable geological AP/EOT 128, Izvođač izjavljuje slijedeće:
condition at the foundation of reinforced soil „Dana 02.09.2019. Izvođač je dopisom RB-
embankment chainage RK 1+093 – RK 1+334 BBH/3444/CD-P1 (Prilog 1) dostavio Inženjeru
on Sub-Section 1.1.1 and subsequent need of Obaviještenje o namjeri potraživanja
making Main Design change have made the Produženja roka za završetak i Dodatnog
activity “MSE wall construction and backfilling” plaćanja br. 128 u skladu sa Pkl 20.1 budući da
unable to start on the scheduled date of je pojava nepredvidivih geoloških uslova na
29.08.2019 in accordance with the latest temelju nasipa od armiranog tla, stacionaža RK
Programme Gant Chart as a part of 1+093 – RK 1+334, na poddionici 1.1.1 i
Contractor’s Proposal for Appendix 5 naknadna neophodnost izmjene Glavnog
Subsequent Works with Completion date of projekta onemogućila početak aktivnosti
30.09.2020). „Izgradnja i zatrpavanje MSE zida“ planiranog
datuma 29.08.2019. u skladu s najnovijim
On 05.09.2019, the Employer by letter gantogramom programa kao dijelove
PJ/9189/DB (Enclosure 23) sent to the Izvođačevog predloga za Naknadne radove iz
Contractor 23the SRP’s review report of Main Priloga 5 s datumom završetka 30.09.2020.).
Design change – updated Version 2, in which
the SRP stated that Designer did not provide Dana 05.09.2019. Investitor je dopisom
responses or amendments to their previous PJ/10576/DB (Prilog 23) poslao Izvođaču
objections on used geological information; in izvještaj revizije DKR-a o izmjeni Glavnog
addition, the new comments were given: the projekta – ažurirana Verzija 2, u kojoj je DKR
compression module for category P1 used in navela da Projektant nije dao odgovor ili
calculation was overestimatedand should be ispravke na prethodne primjedbe o
reduced; it is necessary to make an upotrijebljenim geološkim informacijama;
improvements to the ground by grouting, pored toga, dati su novi komentari: modul
throught the entire width of excavation. stišljivosti za kategoriju P1 korišten u
proračunima je precijenjen i trebalo bi ga
On 10.09.2019, the Employer by letter umanjiti; neophodno je sprovesti pobaljšanje
PJ/10830/DB (Enclosure 24) sent to the tla injektiranjem kroz čitavu širinu nasipa.
Contractor the SRP’s review report of Main
Design change – updated Version 3, which
confirmed that “the design engineers have, for Dana 10.09.2019. Investitor je dopisom
the most part, met the objections and made PJ/10830/DB (Prilog 24) poslao Izvođaču
proper amendment”, but “the question of the izvještaj revizije DKR-a o izmjeni Glavnog
compaction modul for the category (P) used in projekta – ažurirana Verzija 3, kojom se
calculations remains open…the value of 15 MPa potvrdilo da su Projektanti uglavnom „ispunili
is overestimated”. zahtjeve date u primjedbama i sproveli
odgovarajuće ispravke“, ali pitanje modula
It should be noted the fact that the parameter – stišljivosti upotrijebljenom za kategoriju (P) u
compression modul for category P1 was first proračunima ostaje otvoreno...vrijednost od 15
defined in additional geotechnical elaborate, no MPa je precijenjena.
comment was given by SRP on it at that time,
and the document was approved on 24.07.2019 Potrebno je napomenuti činjenicu da je
(Enclosure 15). Now, in the late phase of parametar – modul stišljivosti za kategoriju P1
reviewing of the Main Design change, SRP went prvo definisan u dodatnom geološkom
back to question the parameter that was defined elaboratu, i da u to vrijeme DKR nije dala
in the already approved document and nikakav komentar, a dokument je odobren dana

10
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

consequently rejectied the Main Design change 24.07.2019. (v Prilog 15). Sada, u kasnoj fazi
two times, this approach undoubtly would impact revizije izmjene Glavnog projekta, DKR se
the approval process. vraća na pitanje parametra koji je definisan u
već odobrenom dokumentu, i shodno tome dva
While the Contractor is of the firm opinion that puta odbija izmjenu Glavnog projekta, a takav
the parameter applied in the Main Design pristup će bez sumnje uticati na proces
change is reasonable, having in mind SRP’s odobravanja.
doubts on it, the Contractor decided to prove the
load bearing capacity of the soil category P1 by
in situ test (the circular plate method), which is Iako je Izvođač uvjeren da je parametar
the only way to get a real compression module. usvojen u izmjeni Glavnog projekta razuman,
The results, subsequentlyobtained were much imajući u vidu sumnje DKR-a, Izvođač odlučuje
larger than 15 MPa (ranged from 50 MPa to 100 da dokaže nosivost tla kategorije
MPa), which means, the parameter used in P1ispitivanjem in-situ (metoda kružne ploče),
calculations was not overestimatedas SRP stated što je jedini način da se dobije stvarni modul
(instead, it’s moe conservative). stišljivosti. Rezultati koji su dobijeni su mnogo
veći od 15 MPa (kretali su se od 50 MPa do
On 16.09.2019 the Contractor by letter RB- 100 MPa), što znači da parametar upotrijebljen
BBH/3629/CD-P1 (Enclosure 25) invited SRP to u proračunu nije precijenjen, kako je tvrdila
be present on site for testing. DKR (štoviše, isti je konzervativniji).

On 17.09.2019 the Contractor by letter RB-


BBH/3660/EM-P1 (Enclosure 26) explained to
the Engineer about the parameter (compression Dana 16.09.2019. Izvođač je dopisom RB-
module) issue, and invited the Engineer to be BBH/3629/CD-P1 (Prilog 25) pozvao DKR da
also on site to supervise the testing. prisustvuje ispitivanju na gradilištu.

On 18.09.2019 the Engineer by letter Dana 17.09.2019. Izvođač je dopisom RB-


IG/12511/VMR (Enclosure 27) replied that the BBH/3660/EM-P1 (Prilog 26) Inženjeru dao
additional test for providing further evidence objašnjenje o parametru (modul stišljivosti) i
was neither introduced in SRP’s review reports pozvao ga da takođe prisustvuje na gradilištu i
nor approved by the SRP. nadzire ispitivanje.

On 23.09.2019 the Contractor by letter RB- Dana 18.09.2019. Inženjer je dopisom


BBH/3777/CD-P1 (Enclosure 28) gave further IG/12511/VMR (Prilog 27) odgovorio da
explanation: in view of different opinion from dodatno ispitivanje za pružanje dodatnih
SRP on parameter issue, the only possible option dokaza nije niti uvedeno kroz izvještaj DKR-a
is to re-establish the factual situation by o reviziji, niti ga je DKR odobrila.
performing in situ testing and that’s was what
Contractor did. However, the SRP and Dana 23.09.2019. Izvođač je dopisom RB-
Engineer bothhave rejected to come to site. The BBH/3777/CD-P1 (Prilog 28) dao daljnja
testing was then performed with presence of the pojašnjenja; što se tiče mišljenja DKR-a o
Contractor’s designer and the geological pitanju parametra, jedino je moguće rješenje je
engineers from Geoproject (the company da se utvrdi činjenično stanje izvođenjem
authorized to perform the additional ispitivanja in situ, i to je Izvođač i učinio.
geotechnical works), test report will be Međutim, i DKR i Inženjer su odbili da dođu
submitted soon. The Contractor highlighted that na gradilište. Ispitivanje je stoga provedeno uz
he has made a great efforts in solving the current prisustvo Izvođačevog Projektanta i geoloških
issue to expedite the review process, but the inženjera iz Geoprojekta (kompanije ovlaštene
approval of the Main Design change cannot be za izvođenje dodatnih geotehničkih radova), i
achieved by the one-side effort, it required more izvještaj sa ispitivanja će biti uskoro dostavljen.
involvement aaand understanding of all parts Izvođač je naglasio da je uložio velike napore u

11
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

concerned. rješavanje tekućeg pitanjada bi ubrzao proces


revizije, ali odobrenje izmjene Glavnog
On 26.09.2019 the Contractor by letter RB- projekta se ne može postići jednostranim
BBH/3806/DS-DS1 (Enclosure 29) submitted to naporima, i potrebno je više uključenosti i
SRP Main Design change – Version 4, razumijevanja od svih zainteresovanih strana.
supplemented with the test report for
compressive module of categories P1 and P2.
This time, the compression modules from the Dana 26.09.2019. Izvođač je dopisom RB-
additional geological report are based on in situ BBH/3806/DS-DS1 (Prilog 29) dostavio DKR-u
test at the designed foundation level, which are izmjenu Glavnog projekta – Verzija 4, uz
the real parameters of the soil. Specifically, the dodatak izvještaja sa ispitivanja za modul
values for category P1 are ranged with 42,4 to stišljivosti za kategorije P1 i P2.Ovog puta su
132 MPa, and for P2 they are 55,6 – 134,5 MPa, moduli stišljivosti iz dodatnog geološkog
which proves that the previous used parameter izvještaja temeljeni na ispitivanju in situ na
15 MPa was not “overestimated”. The projektovanom nivou temelja, što su stvarni
calculations were updated by adopting the most parametri tla. Preciznije, vrijednosti za
adverse case, that is 45 MPa for P1 and 50 MPa kategoriju P1 su u rasponu 42,4 do 132 MPa, a
for P2, the conclusion is that the newly designed za P2 se kreću 55,6 – 134,5 MPa, što dokazuje
solution is fully adequate, no more grouting is da prethodno korišteni parametar 15 MPa nije
needed. precijenjen. Proračuni su ažurirani usvajanjem
najnepovoljnijeg slučaja, tj 45 MPa za P1 i 50
MPa za P2, iz čega se zaključuje da je
On 08.10.2019, the Employer by letter novoprojektovano rješenje u potpunosti
PJ/11939/DB (Enclosure 30) sent to the adekvatno i da nije potrebno dodatno
Contractor the SRP’s review report of Main injektiranje.
Design change –Version 4. This time, the SRP
unexpectably brought up his comment given to Dana 08.10.2019. Investitor je dopisom
additional geological Elaborate three months PJ/11939/DB (Prilog 30) poslao Izvođaču
ago, i.e. three boreholes were not drilled up to izvještaj DKR-a o reviziji izmjene Glavnog
the designed depth, and requested Contractor to projekta –Verzija 4. Ovaj put je DKR
complete those investigation works. (Clearly the neočekivano potegla svoj komentar dat na
Contractor had already provided explanations in dodatni geološki elaborat tri mjeseca ranije, tj.
the updated elaborate which were latter da 3 bušotine nisu izbušene do projektovane
accepted by SRP in its approval on 24.07.2019). dubine, i zatražila da Izvođač sprovede te
In addition, SRP stated the applied test method istražne radove. (jasno je da je Izvođač već dao
(circular plate with diameter of 30 cm)”may not objašnjenje u ažuriranom Elaboratu koga je
be deemed as valid-adequate for testing of the kasnije prihvatila DKR svojim odobrenjem
established ground (environment P1), so the dana 24.07.2019.). Pored toga, DKR je izjavila
obtained measurement results are deceiving”. da se korištena metoda ispitivanja (kružna
Therefore, Contractor should “apply rellible ploča prečnika 30 cm) ne može smatrati
methods for determing the module of valjanom-adekvatnom, za ispitivanje utvrđenog
compression of scree material (category 1) at tla (kategorije P1), tako da dobiveni rezultati
greather depths”. Meanwile, SRP emphasised mjerenja zavaravaju. Prema tome, Izvođač bi
the characteristics of geological category P1 trebao primjeniti pouzdane metode za
and “strongly recommend to the Contractor to određivanje modula stišljivosti drobinskog
consider alternative solutions.” materijala (kategorija P1) na većoj dubini“. U
međuvremenu, DKR je naglasila karakteristike
On 10.10.2019 the Contractor by letter RB- geološke kategorije P1 i „toplo preporučila
BBH/4030/DS-DS1 (Enclosure 31) summarized Izvođaču da razmotri alternativna rješenja“.
the Main Design change review process and
expressed Contractor’s stances and objections to
SRP comments. Namely, during the past three Dana 10.10.2019. Izvođač je dopisom RB-

12
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

months the Contractor have submitted four BBH/4030/DS-DS1 (Prilog 31) sumarno
versions of the Main Design change document, predstavio proces odobrenja izmjene Glavnog
but still not got approval. The main reason was projekta i izrazio stavove i primjedbe Izvođača
that SRP does not accept the applied na stavove DKR-a. Naime, u protekla tri
compressive modulus, regardless of the fact that mjeseca je Izvođač dostavio četiri verzije
this parameter was the first defined in the dokumentacije izmjene Glavnog projekta, ali i
approved additional geological elaborate, then dalje nije dobio odobrenje. Glavni razlog je što
was confirmed by in situ test (technical DKR ne prihvata primjenjeni modul stišljivosti,
explanation to the validation of the test method uprkos činjenici da je taj parametat prvotno
was further given in the subject letter). In definisan u odobrenom dodatnom geološkom
addition, SRP insisted that category P1 could elaboratu i potom potvrđen in situ ispitivanjima
not be a foundation soil for any structure thus (tehničko obaviještenje za valjanost metode
strongly recommended Contractor to consider ispitivanja je dato u predmetnom dopisu).
alternative design solutions, but it is also Pored toga, DKR je insistirala da kategorija
verified by the calculation that category P1 can P1ne može biti temeljno tlo za bilo koju
be foundation for MSE wall. konstrukciju, pa je stoga toplo preporučila
Izvođaču da razmotri alternativna rješenja, ali
In conclusion, the test method is reliable, the je takođe proračunom utvrđeno da kategorija
parameter is realistic and applicable, and the P1 može biti temelj za MSE zid.
adjusted design solution could work adequately,
the Contractor considered the SRP’s rejection of
the Main Design change is ungrounded and U zaključku, metoda ispitivanja je pouzdana,
unjustified. But the Contractor is still willing toparametar je realan i primjenjiv, a
consider other possible solutions according to prilagođeno projektno rješenje se može
the SRP suggestion, in order for the imphasse to adekvatno primjeniti, Izvođač smatra da je
be sooner overcome. The problem is, the soil DKR-ovo odbijanje izmjene Glavnog projekta
parameters are the basic data for any kind of the neutemeljeno i neopravdano. Međutim, Izvođač
structure solution, if this issue remain unsolved, je i dalje voljan da razmotri druga moguća
no substantial progress could be made, so the rješenja u skladu sa sugestijama DKR-a, da bi
Contractor asked SRP to clearly advise what is se što prije izašlo iz ćorsokaka. Problem je što
the reason of rejecting of defined parameters; su parametri tla osnovni podaci za bilo kakvu
ooor, to instruct which testing method in their vrstu konstrukcijskog rješenja, i ako se to
opinion is “reliable” to provide applicable pitanje ne riješi, nije moguće načiniti bilo
parameters. kakav značajan napredak, tako da je Izvođač
There is no reply from SRP. zatražio od DKR-a da jasno posavjetuje što je
razlog za odbijanje definisanih parametara, ili
da uputu koja metoda ispitivanja je po
In the chapter Claim Notice No. AP/EOT 132 njihovom mišljenju „pouzdana“ za dobijanje
Contractor stated as follow: primjenjivih parametara.
“On 23.10.2019, having in mind the SRP’s Nismo dobili nikakav odgovor od DKR-a.
unjustified rejection has prolonger the approval
process of Main Design change for Reinforced U poglavlju Obaviještenje o Potraživanju br.
Soil Embankment RK 1+093 – RK 1+334 and AP/EOT 132, Izvođač izjavljuje slijedeće:
led to further delay, the Contractor by letter RB- „Dana 23.10.2019. imajući u vidu da je
BBH/4189/CD (see Enclosure 2) submitted to neopravdano odbijanje od strane DKR-a
the EngineerNotice of intention to claim produžilo proces odobravanja izmjene Glavnog
Extension of Time for Completion and projekta nasipa od armiranog tla RK 1+093 –
Additional Payment No. 132 under Sub-clause RK 1+334 i dovelo do daljnjeg kašnjenja,
20.1. Izvođač je dopisom RB-BBH/4189/CD (v Prilog
2)dostavio Inženjeru obaviještenje o namjeri
Meanwhile, heaving in mind the huge time huge potraživanja produženja Roka za završetak i
time loss incurred and in order to push forward Dodatnog plaćanja br. 132 u skladu sa Pkl

13
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

the review process as SRP rejected the Main 20.1.


Design change, the Contractor communicated
with the SRP and reached an agreement on the U međuvremenu, imajući u vidu već pretrpljeni
alternative solution, that is, to replace MSE wall veliki gubitak vremena, i kako bi se krenulo
with general embankment, including RC naprijed s procesom revizije kako je DKR
retaining wall. odbijala izmjene Glavnog projekta, Izvođač je
bio u komunikaciji s DKR-om i postigao
Accordingly, for the more precised definition of dogovor o alternativnom rješenju, tj. da se
geological setting for the new solution of MSE zid zamijeni opštim nasipom, uključujući
embankment, on 22.10.2019, the Contractor by AB potporni zid.
letter RB-BBH/4177/EM-P1 (Enclosure 32)
submitted to the SRP the Annex to the Design of Shodno tome, radi definisanja geološkog
additional geotechnical investigations for okruženja za novo rješenje za nasip, dana
approval. Namely, the boreholes that were early 22.10.2019. Izvođač je dopisom RB-
finished drilling will be re-drilled to the full BBH/4177/EM-P1 (Prilog 32) dostavio DKR-u
depth as required. The trial pits will be dodatak Projekta detaljnih geotehničkih
excavated in the area of possible retaining wall ispitivanja na odobrenje. Naime, bušotine koje
down to the P2 category in which the structure su ranije završene će biti ponovo izbušene do
will be founded, and the compressibility modul pune dubine, kako je zahtijevano. Probne jame
for categories P1 and P2 will be determinated by će se iskopati u područjima mogućeg potpornog
circular plate method. zida do kategorije P2 u kojoj će konstrukcija
biti utemeljena, a modul stišljivosti za
On 29.10.2019, the Employer by letter kategorije P1 i P2 će se odrediti metodom
PJ/12879/DB (Enclosure 33) sent to the kružne ploče.
Contractor the SRP’s review report, in which the
SRP gave specific comment that the boreholes
should be 2 m into the rock. However, the fact is
that this requirement could not be a mandatory Dana 29.10.2019. Investitor je dopisom
one, as defined in approved Design of additional PJ/12879/DB (Prilog 33) poslao Izvođaču
geological investigation works: depth of the izvještaj DKR-a o reviziji, u kojem je DKR dala
boreholes will be 2 m of entry into solid rock or specifičan komentar da bušotine treba da idu 2
20 m depth”. In addition, SRP insisted the test m u stijenu. Međutim, činjenica je da taj
method of soil compaction modulus is not zahtjev ne može biti obavezan, jer je odobrenim
reliable. Regarding this objection, the Projektom dodatnog geološkog ispitivanja
Contractor has already in previous letter (see navedeno „dubina bušotina će biti 2 m do
Enclosure 31) provided technical explanations ulaska u čvrstu stijenu ili dubine 20 m“. Pored
and explicitly asked SRP to instruct which toga, DKR je insistirala da metoda ispitivanja
method they consider as reliable, but the answer modula stišljivosti tla nije pouzdana. Što se
was never provided, now, SRP is only repeating tiče primjedbe, Izvođač je već u prethodnom
the same comment that they previously given and dopisu (v Prilog 31) dao tehničko objašnjenje i
still not providing the requested answer, which, direktno pitao DKR da uputi koju metodu
would only led to further loss of time. smatra za pouzdanu, ali odgovor nikad nije
dobio. Sad DKR samo ponavlja isti komentar
Upon the receipt of this negative review report, koji su prethodno dali, a i dalje ne daje traženi
there has been unofficial communication odgovor, što samo vodi do daljeg gubitka
between Contractor and SRP about above stated vremena.
objections, according to which the Contractor is
recommended to conduct test, that is, to still
apply the circular plate method, but adjust the
plate diameter from 30 cm to 60 cm. Po prijemu ovog negativnog izvještaja o
reviziji, obavljala se nezvanična komunikacija
između Izvođača i DKR-a oko gore navedenih

14
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

It should be noted, that this requirement of primjedbi, u skladu s čime je Izvođač


additional test for obtaining parameter (soil preporučio izvođenje ispitivanja po istom
compaction modulus) was introduced by SRP in principu kao prethodna ispitivanja, tj. da se i
significant delay, that is, after three months, has dalje primjenjuje metoda kružne ploče, ali
passed since the approval of additional prilagodi prečnik ploče sa 30 na 60 cm.
geological elaborate on 24.07.2019 in which
parameter was defined, not to mention whether Potrebno je napomenuti da je ovaj zahtjev za
this requirement has the justified couse. dodatnim ispitivanjem radi dobijanja
Furthermore, with the coming of unfavourable parametra (modul stišljivosti tla) DKR dala sa
rainy season, the progress of in situ testing will značajnim kašnjenjem, tj. da je prošlo nekoliko
be significantly impacted considering its weather mjeseci od odobrenja Dodatnog geološkog
sensitive nature, this, without the doubt will elaborata dana 24.07.2019. u kom je parametar
further delay with the approval of Main Design definisan, a da se ne govori o tome da li je taj
change. zahtjev uopšte bio opravdan. Nadalje, s
dolaskom nepovoljne kišne sezone, napredak in
In the chapter Claim Notice No. AP/EOT 132-1 situ ispitivanja će pretrpjeti značajan uticaj,
Contractor stated as follow: imajući u vidu da je osjetljivo na vremenske
“On 01.11.2019 the Contractor by letter RB- prilike, što će bez sumnje još dovesti dojoš
BBH/4347/CD (see Enclosure 3)submitted to the daljeg kašnjenja izmjene Glavnog projekta.
Engineer Notice of Notice to Claim Extension of
Time for Completion and Additional Payment U poglavlju Obaviještenje o Potraživanju br.
No. 132/1 under Sub-clause 20.1, due to further AP/EOT 132-1, Izvođač izjavljuje slijedeće:
prolonged review process for the Main Design Dana 01.11.2019. Izvođač je dopisom RB-
change for Reinforced Soil Embankment RK BBH/4347/CD (v Prilog 3) dostavio Inženjeru
1+093 – RK 1+334. Obavještenje o namjeri potraživanja
Produžetka roka za završetak i Dodatnog
On 07.11.2019 the Contractor by letter RB- plaćanja br. 132/1 prema Pkl 20.1, uslijed još
BBH/4415/EM-P1 (Enclosure 34) submitted to više produženog procesa revizije izmjene
SRP the new Design of additional geotechnical Glavnog projekta za nasip od armiranog tla RK
investigations. Namely, according to SRP’s 1+093 – RK 1+334.
requirement, the circular plate test will use the
plate with diameter 60 cm.
Dana 07.11.2019. Izvođač je dopisom RB-
On 15.11.2019, the Employer by letter BBH/4415/EM-P1 (Prilog 34) dostavio DKR-u
PJ/13687/DB (Enclosure 35) sent to the novi Projekat dodatnih geotehničkih ispitivanja.
Contractor the SRP’s review report. In the Naime, sa zahtjevima DKR-a , za test kružnom
report, SRP gave requirement that two more pločom će se koristiti ploča prečnika 60 cm.
boreholes should be conducted at the foundation
of the wall. This was again a new comment,
which was not given to Contractor’s previous Dana 15.11.2019. Investitor je dopisom
submission of Annex to Design of additional PJ/13687/DB (Prilog 35) poslao Izvođaču
geotechnical investigations, whereby the izvještaj DKR-a o reviziji. U izvještaju je DKR
embankment and RC retaining wall solution was dala zahtjev da se još dvije bušotine trebaju
already proposed. In addition, SRP required to izvesti u temelju zida. To je opet bio novi
adopt the minimum value of the soil parameters komentar, koji nije dat na Izvođačeve prethodne
in the design, which was an unjustified podneske dodatka Projekta dodatnih
requirement and will only increase the cost of geotehničkih ispitivanja, gdje su već predložena
alrernative solution, as well as the time rješenja za nasip i AB potporni zid. Pored toga,
consumed. DKR je zahtjevala da se usvoji minimalna
vrijednost parametra tla u projektu, što je
On 19.11.2019 the Contractor by letter RB- neopravdan zahtjev i samo će povećati troškove
BBH/4564/DS-DS1 (Enclosure 36) submitted to alternativnog rješenja, kao i vrijeme potrebno

15
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

SRP the updated Design of additional za izvođenje.


geotechnical investigations with the required
two more boreholesin zone of retaining wall,
and gave technical explanation of the Dana 19.11.2019. Izvođač je dopisom RB-
Contractor’s objection on adopting the BBH/4564/DS-DS1 (Prilog 36) dostavio DKR-u
minimum value. ažurirani Projekat dodatnih geotehničkih
ispitivanja sa zahtjevane 2 dodatne bušotine u
On 25.11.2019, the Employer by letter zoni potpornog zida, i dao tehničko objašnjenje
PJ/14040/DB (Enclosure 37) sent to the za Izvođačevu primjedbu na usvajanje
Contractor SRP’s approval of Design of minimalne vrijednosti.
additional geotechnical investigation.
Dana 25.11.2019. Investitor je dopisom
On 10.12.2019 the Contractor by letter RB- PJ/14040/DB (Prilog 37) Izvođaču poslao
BBH/4881/DS-DS1 (Enclosure 38) submitted to DKR-ovo odobrenje Projekta dodatnog
SRP the new Elaboration of additional geotehničkog ispitivanja.
geotechnical investigation. The compressibility
module of categories P1 and P2 that obtain from Dana 10.12.2019. Izvođač je dopisom RB-
circular plate test (plate diameter 60 cm)are BBH/4881/DS-DS1 (Prilog 38) dostavio DKR-u
respectively 100 MPa and 38 MPa, which only novi Elaborat dodatnog geotehničkog
again, prove that parameters defined in the ispitivanja. Modul stišljivosti za kategorije P1 i
previous approved additional geotechnical P2 dobijen ispitivanjem kružnom pločom
elaborate and further evidence by in-situ test (prečnik ploče 60 cm) je respektivno 100 MPa i
are reliable. 38 MPa, čime se još jednom dokazuje da su
parametri definisani prethodno odobrenim
On 20.12.2019, the Employer by letter geološkim elaboratom i dalje dokazani in situ
PJ/15112/DB (Enclosure 39) sent to the ispitivanjem pouzdani.
Contractor SRP’s approval of Elaboration of
additional geotechnical investigation, in which
the SRP confirmed that a clear picture of the Dana 20.12.2019. Investitor je dopisom
geological composition of the ground and a PJ/15112/DB (Prilog 39) Izvođaču poslao
reliable geotechnical model of the terrain was DKR-ovo odobrenje Elaborata dodatnog
presented. geotehničkog ispitivanja, u kom je DKR
potvrdila da je predstavljena jasna slika
On 20.12.2019 the Contractor by letter RB- geotehničkog sastava tla i pouzdan geotehnički
BBH/5033/DS-DS1 (Enclosure 40) submitted to model terena.
SRP the Main Design change – version 5, i.e. to
replace a MSE wall with general embankment,
including two reinforced concrete walls; and to Dana 20.12.2019. Izvođač je dopisom RB-
adjust a drainage in the certain area BBH/5033/DS-DS1 (Prilog 40) dostavio DKR-u
accordingly. The additional expropriation izmjenu Glavnog projekta - verzija 5, tj.
required as per Main Design change is zamjena MSE zida opštim nasipom, uključujući
10.510,40 m2. 2 AB zida; i prilagođavanje drenaže u
određenom području s tim u skladu. Dodatna
On 17.01.2020, the Employer by letter eksproprijacija zahtjevana izmjenom Glavnog
PJ/332/DB (Enclosure 41) sent to the projekta je 10.510,40 m2.
Contractor SRP’s review report, in which the
Contractor was required to reduce the material Dana 17.01.2020. Investitor je dopisom
parameters, specifically the friction angle of PJ/332/DB (Prilog 41) poslao Izvođaču
filling material and mechanical parameters of izvještaj DKR-a o reviziji, u kom se od izvođača
founding soil in retaining wall and slope stability traži da smanji parametre materijala,
calculation. In Contractor’s opinion, the preciznije ugao trenja materijala za ispunu i
requirements from SRP were in very mehaničke parametre za temeljno tlo u

16
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

conservative level comparing with the Eurocode potpornom zidu i proračun stabilnosti kosine.
7 (which is required design standard), and the Po mišljenju Izvođača, zahtjevi DKR-a su na
fact is that submitted design solution is more veoma konzervativnom nivou u poređenju sa
than adequate in term of safety. Eurocode 7 (što je zahtijevani projektni
On 17.02.2020 the Contractor by letter RB- standard)i činjenica je da je dostavljeno
BBH/424/DS-DS1 (Enclosure 42) submitted to projektno rješenje više nego adekvatno u
SRP the Main Design change – version 6, which pogledu bezbjednosti.
was updated according to the requirement of Dana 17.02.2020.. Izvođač je dopisom RB-
SRP, i.e. to adopt more conservative friction BBH/424/DS-DS1 (Prilog 42) dostavio DKR-u
angle of filling material and foundation soil in izmjenu Glavnog projekta - verzija 6, koja je
retaining wall calculation. ažurirana u skladu sa zahtjevima DKR-a, tj. da
se usvoji konzervativniji ugao trenja
On 28.02.2020, the Employer by letter materijala za ispunu i temeljno tlo kod
PJ/1816/DB (Enclosure 43) sent to the proračuna za potporni zid.
Contractor SRP’s review report. Among five
books of Main Design change documents (Route, Dana 28.02.2020. Investitor je dopisom
Additional expropriation, Slope stability and PJ/1816/DB (Prilog 43) poslao Izvođaču
protection, Retaining wall and Drainage), the izvještaj DKR-a o reviziji. Od 5 knjiga
comments were only regarding a part of dokumentacije Glavnog projekta (Trasa,
Drainage design – to provide a drainage Dodatna eksproprijacija, Stabilnost i zaštita
capability analyses of existing culvert on the kosina, Potporni zid i Drenaža), komentari su
E80, which is out of expropriation line, as well dati samo na dio koji se odnosi na Projekat
as to provide a detailed drawing of the joint part drenaže – da se obezbjedi analiza drenažne
of the ditch and entrance portal of the culvert. sposobnosti postojećeg propusta na E80, što je
izvan linije eksproprijacije, kao i da se daju
On 03.03.2020 the Contractor by letter RB- detaljni nacrti spojnog dijela kanala i ulaznog
BBH/591/DS-DS1 (Enclosure 44) submitted to portala propusta.
SRP the Main Design change – version 7, which
was updated by providing the dimensions of Dana 03.03.2020.. Izvođač je dopisom RB-
existing culvert entrance portal (to prove BBH/591/DS-DS1 (Prilog 44) dostavio DKR-u
existing culvert is capable to discharge water izmjenu Glavnog projekta - verzija 7, koja je
from drainage ditch) and the detailed drawing of ažurirana tako što su date dimenzije postojećeg
joint zone. ulaznog portala propusta (kako bi se dokazalo
da je postojeći propust u stanju ispustiti vodu iz
On 04.03.2020, the Employer by letter drenažnog kanala) i detaljni nacrti spojne zone.
PJ/2044/DB (Enclosure 45) sent to the
Contractor SRP’s review report, in which the
SRP approved the Main Design change. To this Dana 04.03.2020. Investitor je dopisom
date, the soft copy of Main Design change PJ/2044/DB (Prilog 45) poslao Izvođaču
documents is fully approved. izvještaj DKR-a o reviziji u kom je DKR
odobrila ažuriranu izmjenu Glavnog
The final solution is therefore determinated as: projekta.Do danas, elektronska verzija Izmjene
to replace MSE wall with general embankment, Glavnog projekta je u potpunosti odobrena.
including wall of reinforced concrete structure
along the embankment toe on the positions Konačno rješenje je stoga određeno da bude:
where the embankment exceeds the height of 30 zamjena MSE zida opštim nasipom, uključujući
m; and to adjust a drainage in certain area zid od armiranog betona duž nožice nasipa na
accordingly. The additional expropriation pozicijama gdje nasip prelazi visinu od 30 m;
required by the Main Design change is 9.798,6 prilagođavanje drenaže u određenom dijelu s
m2. tim u skladu. Dodatna eksproprijacija
zahtjevana izmjenom Glavnog projekta je
On 16.03.2020 the Contractor by letter RB- 9.798,6 m2.

17
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

BBH/700/CD-P1 (see Enclosure 4) requested


for Engineer’s issurance of Variation order, as
the above Main Design change Works should be Dana 16.03.2020.. Izvođač je dopisom RB-
treated as SC 13.9 Unforeseeable works, and BBH/700/CD-P1 (v Prilog 4) zatražio od
represents a variation of the scope of work due Inženjera izdavanje Naloga za izmjenu, budući
to chainged geological conditions in relation to da bi gore navedene radove iz Izmjene Glavnog
Preliminary Design. projekta trebalo tretirati kao PK 13.9
There is no reply received from Engineer. Nepredvidljivi radovi, i predstavlja izmjenu
obima radova uslijed izmjenjenih geoloških
In the chapter Conclusion, Contractor stated as uslova u odnosu na Idejni projekat.
follow: Od Inženjera nije dobijen nikakav odgovor.
“It follows from above that the review process of
Main Design change for Reinforced Soil U poglavlju Zaključak, Izvođač izjavljuje
Enbankment RK 1+093 – RK 1+334 took 230 slijedeće:
days (18.07.2019 – 04.03.2020) to complete, „Iz gore navedenog se vidi da je za proces
which was significantly prolonged due to SRP revizije izmjene Glavnog projekta za nasip od
questionioning of geotechnical imformation used armiranog tla RK 1+093 – RK 1+334 trebalo
as input for making Main Design change(i.e. 230 dana (18.07.2019. do 04.03.2020.) da se
borehole depth, compression module of category završi, što je značajno produženo jer je DKR
P) and the questioning of Main Design change preispitivala geotehničke informacije korištene
solution itself (i.e. MSE wall cannot be founded za ulazne podatke pri pravljenju izmjene
in category P1, and the alternative solution Glavnog projekta (tj. dubina bušotina, modul
should be considered), however, as showen stišljivosti za kategoriju P))i preispitivala samo
above, this questioning were all proved to be as rješenje izmjene Glavnog projketa (tj. MSE zid
unjustified. se nemože temeljiti na kategoriji P1, i treba
In addition, there were inpropper approaches of razmotriti alternativno rješenje). Međutim,
the SRP in review process, such as: kako je gore prikazano, sva ta preispitivanja su
1. Questioning the document that was already se pokazala kao neopravdana.
approved without justified reason; Pored toga, u pristupu DKR-a procesu revizije
2. The questioning/requirement/comment se javljao neprikladan pristup, kao npr:
given was either unfounded or was already 1. Preispitivanje već odobrene dokumentacije
answered by Contractor and should be bez opravdanog razloga;
considered as closed/solved; 2. Preispitivanje / davanje zahtjeva /
3. Giving repeated comments instead of komentara koji su bili ili neutemeljeni ili je
providing clear instruction, even after na njih Izvođač već odgovorio i trebalo ih
Contractor’s request; je smatrati riješenim / zatvorenim;
4. Giving requirement in a very late phase; 3. Ponavljanje komentara, umjesto davanje
5. Giving new requirement after Contractor jasnog naloga, čak i nakon zahtjeva
fulfilled all previous etc. Izvođača;
4. Davanje zahtjeva u veoma kasnoj fazi;
5. Davanje novih zahtjeva nakon što je
These approaches, without a doubt, have Izvođač ispunio sve prethodne itd,
delayed the approval process and consequently
caused delay and disruption to the progress of Ovakav pristup je bez sumnje prouzrokovao
the Works and resulted in unplanned additional kašnjenje procesa odobravanja i shodno tome
costs and loss of time. doveo do kašnjenja i remećenja napretka
radova, i za rezultat imao neplanirane dodatne
In the chapter Contractor’s entitlement to EoT, troškove i gubitak vremena.
Contractor states as follow:
U poglavlju Izvođačevo pravo na Produžetak
Roka za Zavržetak, Izvođač izjavljuje
slijedeće:

18
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Claim No. / ERE description / Opis SC applicable to this ERE Kvalifikacija EOT
Potraživanje ERE and gives entitlement to
br. EOT / PK primjenjiva na
ovaj ERE i daje pravo na
EOT
128 Unforeseeable 4.12 (unforeseeable
Explained in Delay
geological condition at physical difficulties) Analysis below /
the foundation of 8.4 (Extension of time for Objašnjeno u Analizi
reinforced soilcompletion) – (b) / kašnjenja – u nastavku
embankment RK 1+093 4.12 (nepredvidljive fizičke
– RK 1+334 on Sub- poteškoće)
section 1.1.1 /8.4 (produženje roka za
Nepredvidljivi geološki završetak) – (b)
uslovi na temelju nasipa
od armiranog tla RK
1+093 – RK 1+334 na
poddionici 1.1.1
132 Prolonged review 8.4 (Extension of time for Explained in Delay
132/1 process for Main Design completion) – (e) Analysis below /
change of reinforced 8.4 (produženje roka za Objašnjeno u Analizi
soil embankment RK završetak) – (e) kašnjenja – u nastavku
1+093 – RK 1+334 at
Sub-section 1.1.1 /
Produženi proces
revizije za izmjenu
Glavnog projekta za
nasip od armiranog tla
RK 1+093 – RK 1+334
na poddionici 1.1.1
The Contractor is “experienced”but he couldn’t Izvođač je iskusan, ali u vrijeme datuma
foresee reasonably, at the tender date, that he tendera nije mogao objektivno predvidjeti da je
encountered geological conditions – category P naišao na nepovoljne geološke uslove – tlo
soil with thickness exceeding 35,5 m at RK kategorije P, debljine veće od 35,5 m kod RK

19
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

1+093 – RK 1+334. 1+093 – RK 1+334.

According to SC 4.12, this falls within Prema PK 4.12 ovo spade u nepredvidljive
unforeseeable conditions, which the Contractor uslove sa kojima se Izvođač susreo na
encountered at the Site and therefore the gradilištu i, stoga, Izvođač ima parvo na
Contractor is entitled to the following… slijedeće…”

In the chapter Illustration of relevant


provisions in the Contract; in the sub-chapter U poglavlju Prikaz relevantnih odredbi
4.12 Unforeseeable Physical Conditions (The Ugovora; u potpoglavlju 4.12 Nepredvidljivi
General Conditions), Contractor states as fizički uslovi (Opšti uslovi), Izvođač izjavljuje
follow: slijedeće:
“…According to the above provisions, the „...U skladu sa iznad navedenim odredbama,
Contractor has a right to ask a price adjustment Izvođač ima pravo da traži korekciju cijene na
due to following: osnovu slijedećeg:
 A – Variation in the volume of work due to  A - Izmjena u obimu radova zbog
changed geological condition in relation to promjenjenih geoloških uslova u odnosu na
the submitted Preliminary Design dostavljeni Idejni projekat (Okvirni
(Framework agreement Article 4) sporazum, Član 4),
 B – Change of geological conditions, such as  B – Promjena geoloških uslova, kao što su
soil and water which is inconsistent with the zemljište i voda koja nije u skladu sa
design documentation, which was also projektnom dokumentacijom, što je
confirmed by Employer’s letter 01-492/2 of potvrđeno i putem dopisa Investitora 01-
14.02.2013. (Letter of Offer and Employer’s 492/2 od 14.02.2013. (Pismo Ponude i
reply letter) odgovor Investitora)
 C – To the extent that the Contractor  C – u mjeri u kojoj Izvođač susreće fizičke
encounters physical conditions which are uslove koji su nepredvidljivi (PK 4.12)
unforeseeable (SC 4.12) Zadatak Izvođača je da sada pronađe odgovor
 D – Variation of the scope of work due to na gore navedena pitanja.
changed geological conditions in relation to
the delivered Preliminary Design (SC 13.9).

There is an observed discrepancy in English Uočena je razlika u Engleskom i


and Montenegrin text observed! Crnogorskom tekstu!

AD A AD. A

Variation in volume of work means that change Izmjena obima radova znači da promjena
to specific work must appear (Framework određenih radova se mora desiti (Okvirni
agreement Article 4). The reason for this change Sporazum Član 4). Razlog ove promjene treba
should be “change in geological condition” in da bude “promjena geoloških uslova” u odnosu
relation to Preliminary Design. It is not na Idejni projekat. Nije sporno da promjena
disputable that the change in foundation uslova tla podrazumijeva promjenu geoloških
condition means that it is a change of geological uslova, i zbog ove promjene geoloških uslova,
condition, and due to this change of geological dolazi do promjene obima radova, tj. zamjenu
condition, there is a variation in volume of work, zida od armirane zemlje sa nasipom,
i.e. to replace MSE wall with general uključujući armirani betonski zid. Dodatna
embankment, including reinforced concrete wall. eksproprijacija tražena izmjenom Glavnog
The additional expropriation required by the projekta je 9.798,6 m2.
Main Design change is 9.798,6 m2.

20
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

It could be concluded that the Contractor is Može se zaključiti da Izvođač ima pravo na
entitled to adjustment of price under Artice 4 of korekciju cijene u skladu sa Članom 4 Okvirnog
Framework agreement. Sporazuma.

AD B Ad. B

The Letter of offer also gives the Contractor Pismo Ponude takođe pruža pravo Izvođaču na
right to claim in order to be recovered from potraživanje, kako bi se oporavio od bilo kojih
whatever negative consequences (this means negativnih posljedica (ovo se odnosi i na aspekt
either acpects of money or time) due to change novca ili roka) usljed promjene geoloških
of geological conditions, which is inconsistent uslova koji nisu u saglasnosti sa projektnom
with design documentation (available to the dokumentacijom (dostupnom Izvođaču u
Contractor at the moment of submission of the vrijeme podnošenja ponude, što je u našem
Offer, in our case is Preliminary Design). The slučaju Idejni projekat)...
term “inconsistent” means “in opposition to,
conflicting with, in conflict with” (according to ...zaključak je da nepovoljni uslovi tla na koje
Oxford dictionary) and according to “Black’s se naišlo na gradilištu nakon iskopa znače da
Law Dictionary” it means “lacking agreement su se geološki uslovi promijenili i to predstavlja
among parts”. nešto što nije u saglasnosti sa uslovima
navedenim u Idejnom projektu.
Conclusion is that unforeseeable foundation
condition encountered on site after excavation
does mean that geological conditions were
changed and that represent something which is
not in agreement with conditions reflecting by
Preliminary Design.
AD. C
AD C
PK 4.12 se odnose na uslove na koje Izvođač
The SC 4.12 refers to conditions which the naiđe na gradilištu u toku izvođenja Radova.
Contractor encounters at the Site when Neophodno je uporediti ove uslove sa uslovima
executing the Works. It is necessary to compare „u fazi ponude“. U takvoj situaciji ni moramo
these conditions with the conditions “at offer dokazati da su bili nepredvidljivi... U fazi
stage”. In such situation we must prove that they tendera (tj. U vrijeme kad je Izvođač formirao i
were unforeseeable. nakon toga podnio svoju Ponudu), Investitor je
The definition of unforeseeable (SC 1.1.6.8) is obezbijedio Idejni projekat, koji pokazuje da je
“not reasonably foreseeable by an experienced ciljana zona kategorisana kao K22 (dominiraju
Contractor by the date of submition of tender.” dolomiti, dolomitski krečnjak). Stoga je
An adverse physical condition or obstruction can predviđeno da je predloženi zid od armirane
be said to have been foreseen only if an zemlje direktno lociran na prirodnom terenu, sa
experienced contractor considers there could be jako ograničenim iskopom. Dalje, nije
substantial risk of such conditions or obstruction uključivao evidenciju rizika za pitanja zemljišta
arising. i klauzula 5.1 Opštih obaveza projektovanja
At the tender stage (i.e. time when Contractor navodi „Investitor će preuzeti potpunu
formed and subsequently submitted their offer), odgovornost za Idejni projekat Projekta“.
the Preliminary Design was provided by the Slijedi da je Investitor garantovao za Idejni
Employer, which shows that target zone was projekat i da se Izvođač oslanjao na to.
categorized as K22 (dominated by dolomites, Stoga je očigledno da je značajan stepen uslova
dolomitic limestone), with bearly existing nepovoljnog tla – geološka kategorija P na
dilluvial deposition on the surface. It is therefore dijelu zone temelja debljine veće od 35,5 m, na
predicted that the proposed MSE wall was koji se naišlo nakon iskopa , nepredvidljiv iskop

21
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

directly located on the natural terrain with very tla, i da Izvođač ima pravo na dodatna
limited excavation. Furthermore, it did not plaćanja.
include a risk register for issues in the ground Na osnovu navedenog, očigledno je da
and class 5.1. General Design Obligations state predmetni ERE predstavlja:
“the Employer should take a full responsibility  Promjenu uslova zemljišta u odnosu na
for the Preliminary Design of the Project.” It Idejni projekat (ispunjavajući preduslov
follows that the Employer warranted the Člana 4 Okvirnog Sporazuma)
Preliminary Design and the Contractor relied on  Promjenu uslova zemljišta, što nije u
it. saglasnosti sa projektnom dokumentacijom
Therefore, it is obvious that the significant extent (ispunjavajući preduslov Pisma Ponude)
of geological conditions – geological category P  Nepredvidljive nepovoljne uslove zemljišta
at part of the foundation zone in thickness (ispunjavajući preduslov PK 4.12)
exceeding 35,5 m that encountered after
excavation, are unforeseeable ground I Izvođač u poglavlju Analiza troškova, dalje
conditions, and the Contractor is entitled to pokazuje da to prouzrokuje:
additional payments.  Izmjenu obima radova (ispunjavajući
preduslov Člana 4 Okvirnog Sporazuma)
 Promjenu projektnog obima radova
(ispunjavajući preduslov Pisma Ponude)
 Kašnjenje i/ili dodatni neplanirani trošak
(ispunjavajući preduslov PK 4.12)

AD D
AD D Navedeno poglavlje ne postoji u Crnogorskoj
verziji!
By SC 13.9 it is envisaged that adjustment on the
contract price is possible based on
Unforeseeable Works in accordance to
paragraphs 3, 4 and 5of the Article 4 of the
Framework Agreement (please see above item A
about this Article 4 of the Framework
Agreement.

Due to difference between geological conditions


provided in the Preliminary Design and actual
geological conditions encountered during the
works, the varied Works were generated
including general embankment with wall
ofreinforced concrete structure along the
embankment toe on the positions where
embankment exceeds the hight of 30 m. These
works have to be defined as Unforeseeable
Works.
Based on above, it is evident that the subject
ERE represents:
 Change in ground conditions in relation to
the Preliminary Design (fulfilling the
precondition of Article 4 of Framework
Agreement)
 Change in ground condition which is
22
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

inconsistent with the design documentation


(fulfilling the precondition of Letter of
Offer)
 Unforeseeable adverse ground conditions
(fulfilling the precondition of SC 4.12)
 Unforeseeable Works (fulfilling the
precondition of SC 13.9)
And the Contractor in Cost Analyses section,
further shown that it causes:
 Variation in volume of work ((fulfilling the
precondition of Article 4 of Framework
Agreement)
 Change of project works scope (fulfilling
the precondition of Letter of Offer)
 Delay and/or additional unplanned Cost
(fulfilling the precondition of SC 4.12)
 Variation of the scope of work (fulfilling the
precondition of SC 13.9)

3. TECHNICAL REVIEW OF 3. TEHNIČKI PREGLED


CONTRACTOR'S DOCUMENTATION DOKUMENTACIJE IZVOĐAČA RADOVA
3.1. General comments 3.1. Opšti komentari
Contractor also reffering to defects from the Izvođač se poziva na nedostatke iz Glavnog
Main Design – absence of the category P. Due projekta – nepostojanje kategorije P. Iz
to above mentioned reason, herewith we are navedenog razloga donosimo osnovne detalje
providing basic details form Geotechnical iz Elaborata o detaljnim geotehničkim
Final Report for Main Design for Open istraživanjima za nivo Glavnog
Route (Smokovac-Tunnel Suka; Tunnel građevinskog projekta za otvorenu trasu
Suka -Tunnel Vežešnik; Tunnel Vežešnik (Smokovac – Tunel Suka; Tunel Suka –
-Bridge Mrke). In chapter 3.2 Tunel Vežešnik; Tunel Vežešnik – Most
GEOMORPHOLOGICAL PROPERTIES Mrke). U poglavlju 3.2
OF THE TERRAIN it is stated: „The GEOMORFOLOŠKE ODLIKE TERENA
following geomorphological processes exist on navedeno je slijedeće: „Od geomorfoloških
this part of the terrain: procesa na ovom dijelu terena dominanti su:
- Karst process, represented by surface karst - Karstni proces, koji je označen pretežno
forms (valleys, sinkholes, vices); površinskim karstnim oblicima (dolovi, vrtače,
škrape);
- Physical-mechanical decay of rock masses,
especially pronounced in the surface area; - Fizičko-hemijsko raspadanje stijenskih masa,
što je posebno izraženo u površinskom dijelu;
- Rock falling- slope process, rotary motions of
debris which was made by mechanical decaying - Osipanje – padinski proces, rotaciono
of stone rock masses that formed screestones at kretanje drobine stvorene mehančkim

23
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

the hilly slope in thickness of up to 8 m.“ raspadanjem kamenitih stijenskih masa kojim
su formirani sipari na brdskoj padini debljine i
In chapter 3.3 Geological Properties of Wider
do 8 m.
Investigation Area in the Open Route From
Smokovac to Mrke Bridge; 3.3.1 Geological U poglavlju 3.3 Geološka građa šireg
composition it is stated as follow: „The stretch područja istraživanog terena otvorene trase
from Smokovac to bridge Mrke of the open od Smokovca do mosta Mrke; 3.3.1 Geološki
route, which is the subject of this Elaboration, sastav, navedeno je slijedeće: „Na potezu od
exclusively involves carbonate rock mass of Smokovca do mosta Mrke, duž otvorene trase,
Triassic-Jurassic (T,J), Upper Cretaceous koja je predmet ovog Elaborata zastupljene su
(K21, K22) and formations of Quaternary age. isključivo karbonatne stijenske mase
trijaskojurske(T,J), gornjokredne starosti (K21,
Quaternary (Q)
K22) i tvorevine kvartarne starosti.
The Quaternary formations found at the wider
Kvartar (Q)
area of the open route from Smokovac to bridge
Mrke and along the Morača's watercourse are Na širem području otvorene trase od Smokovca
represented by: do mosta Mrke i duž vodotoka Morače
zastupljeni su kvartarni sedimenti
- Terraced glacio – fluvial sediments;
predstavljeni:
- Deluvial and deluvial – coluvial sediments;
- Terasnim glaciofluvijalnim sedimentima ;
- Aluvial sediments.
- Deluvijalnim i deluvijalno koluvijalnim
... Stratified to banked limestones of Upper sedimentima;
Cretaceous age (K21, K22) build:
- Aluvijalnim sedimentima
- Base of the terrain under the Quaternary
... Slojeviti do bankoviti krečnjaci
glaciofluvial sediments and screes at the stretch
gornjokredne starosti (K21;K22) izgrađuju:
from Smokovac to tunnel Suka (LK 0+000-
LK0+395;R0+000-RK0+400) - osnovu terena ispod kvartarnih
glaciofluvijalnih sedimenata i sipara na potezu
- Base of the terrain beneath the screes of
od Smokovca do tunela Suka (LK 0+000-
poorly bound limestone debris between the
LK0+395; R0+000-RK0+400);
tunnel Suka and tunnel Vežešnik;
- Osnovu terena ispod sipara od slabije vezane
In chapter 3.5.2 Hydrogeological properties
krečnjačke drobine između tunela Suka i tunela
and functions of rock masses at the stretch of
Vežešnik...“
open route from Smokovac to Mrke bridge it
is stated: „Based on the hydrogeological U poglavlju 3.5.2 Hidrogeološka svojstva i
properties and functions of the rock mass, funkcije stijenskih masa, na potezu otvorene
structural type of porosity and spatial position trase od Smokovca do mosta Mrke navedeno
of hydro geological phenomena, it is concluded je slijedeće: „Na osnovu hidrogeoloških
that: svojstava i funkcija stijenskih masa,
strukturnog tipa poroznosti i prostornog
... That the stretch of terrain between the tunnel
položaja hidrogeoloških pojava, može se
Suka and tunnel Vežešnik is built of thick layers
zaključiti:
of screes (slightly bound fine-grained limestone
debris over the host rock of stratified to banked ...Da potez terena između tunela Suka i tunela
limestones). Vežešnik izgrađuju debele naslage sipara
(slabije vezana sitnozrna krečnjačka drobina
In chapter 3.6.1 Engineering-geological
preko osnovne stijene slojevitih do bankovitih

24
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

properties of terrain along open route at krečnjaka).“


stretch from Smokovac to bridge Mrke it is
U poglavlju 3.6.1 Inženjerskogeološke
stated: „In terms of engineering geology, the
karakteristike terena duž otvorene trase na
terrain of the open route of stretch from
potezu od Smokovca do mosta Mrke,
Smokovac to Mrke bridge is made of:
navedeno je slijedeće: „Teren duž otvorene
a. Unbound and bound non-stoned and poorly trase, na potezu od Smokovca do mosta Mrke
stoned rocks, represented by: sa inženjerskogeološkog aspekta izgrađuju:
- Deluvial – coluvial sediments (tranquilized a. Nevezane i vezane neokamenjene i
screes of unbound and poorly bound limestone slabookamenjene stijene pretstavljene:
debris) and terra rossa...
- Deluvijalno-koluvijalnim sedimentima
General geotechnical terrain model for the (umireni sipari od nevezane i slabovezane
zone 2 at the stretch from the exit portal of krečnjačke drobine) i crvenice...
Suka tunnel to tunnel Vežešnik (LK1+127 -
Generalni geotehnički model terena za zonu 2
LK1+243; RK1+091-RK1+348) is as follows:
na potezu od izlaznog portala tunela Suka do
- 0,0 - 8,0 m tranquilized screes of unbound, tunela Vežešnik (LK1+127-LK1+243;
poorly bound to highly bound limestone debris RK1+091- RK1+348) je :
by clayey and rarely calcite binder (bound
- 0,0-8,0m umireni sipari od nevezane,slabije
small limestone debris is held in a vertical side-
do jače vezane krečnjačke drobine glinovitim i
cuts in height of up to 6m);
rjeđe kalcitskim vezivom (vezana sitna
- 8.0-30m poorly to highly cracked stratified to krečnjačka drobina drži se u vertikalnim
banked limestones and dolomitic limestones.“ zasjecima visine do 6m) ;
In chapter 4.3. GEOTECHNICAL - 8.0-30m slabije do jače ispucali slojeviti do
CONDITIONS FOR CONSTRUCTION OF bankoviti krečnjaci i dolomitični krečnjaci.“
HIGHWAY AT PART OF OPEN ROUTE
U poglavlju 4.3 GEOTEHNIČKI USLOVI
FROM SMOKOVAC TO MRKE BRIDGE;
IZGRADNJE AUTOPUTA NA DIJELU
4.3.2 Zone 2 (LK1+127,08-LK1+243,25)
OTVORENE TRASE OD SMOKOVCA DO
(RK1+091,43-RK1+348,33) it is stated: „The
MOSTA MRKE; 4.3.2 Zona 2 (LK1+127,08-
terrain of this zone is made of interbedded to
LK1+243,25) (RK1+091,43-RK1+348,33)
banked limestones and dolomitic limestones
navedeno je: „U okviru ove zone teren
with dip and strike toward the northwest at
izgrađuju slojeviti do bankoviti krečnjaci i
angle of 15-20° (EP 320-330/15-20). The host
dolomitični krečnjaci koji padaju prema
rocklimestone - is overlaid by screes of
sjeverozapadu pod uglom 15-20 stepeni (EP
unbound and poorly bound debris, by clay and
320-330/15-20). Preko osnovne stijene-
rarely by calcite binder, of varying thickness
krečnjaka zastupljeni su sipari od nevezane i
(1-8m), at the following stretches:
slabije vezane drobine, glinovitim i rijeđe
- left lane LK1+150 - LK1+195;LK1+230- kalcitiskim vezivom promijenljive debljine (1-
LK1+243 8m) i to na slijedećim potezima:
- Right lane RK1+150- RK1+230;RK1+238-
RK1+305; RK1+320-RK1+355  Lijeva traka LK1+150 -
a) Embankment at the stretch from 1+150- LK1+195;LK1+230-LK1+243
1+200 is up to 15m high (left lane) and  Desna traka RK1+150 -
25m RK1+230;RK1+238-RK1+305; RK1+320-
RK1+355
Taking into account the geomorphological
a) Nasip na potezu od 1+150-1+200 je visine

25
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

features of the terrain, which in the eastern do 15m (lijeva traka) odnosno do 25m(desna
direction of the road zone are reflected in a traka).
relatively steep hill slope that turns into a
S obzirom na geomorfološke odlike terena koje
distinct depression covered by scree of unbound
se ogledaju u relativno strmoj brdskoj padini,
and poorly bound limestone debris, this stretch
koja u pravcu istoka u zoni puta prelazi u
should be solved by applying the reinforced soil
izraženu depresiju prekrivenu siparom od
with prior removal of movable scree materials.
nevezane i slabovezane krečnjačke drobine,
At the stretch 1+200-1+348,33 (right lane) road ovaj potez riješiti primijenom armiranog tla uz
in its entire length is in a 6-18 m high prethodno uklanjanje pokretnog siparskog
embankment, which will be formed mainly on materijala.
the poorly to highly bound consolidated debris
Na potezu 1+200-1+348,33 (desna traka) put
(clay and calcite binder) or on host rock-layered
je čitavom dužinom u nasipu visine 6- 18m, koji
karstificated limestones. Embankments in height
će se formirati pretežno preko slabije do jače
up to 10m should be done at gradient 1:1.5, by
vezane konsolidovane drobine (glinovitim i
using local materials-screes of limestone debris
kalcitskim vezivom) ili preko osnovne stijene-
or limestone material from excavations, while
slojevitih karstifikovanih krečnjaka. Nasipe
embankments of greater heights by using
visine do10m izvesti pod nagibom 1:1,5,
reinforced soil. In case that classic high
korišćenjem lokalnih materijala-sipara od
embankment are undertaken, they should be
krečnjačke drobine ili krečnjačkog materijala
done at gradient 1:1.5 with a cutting by 2-3m
iz iskopa, odnosno nasipe veće visine
wide berms at every 7-8 m of height. The base of
primjenom armiranog tla. U slučaju da se
design embankments is predominantly a poorly
pristupi izradi klasičnih nasipa velike visine
to strongly bound fine-grained limestone debris
iste izvoditi pod nagibom 1:1,5 sa
and subordinated layered limestone.
presijecanjem bermama širine 2-3m na svakih
Prior to laying the embankment it is necessary 7-8 m visine. Podloga projektovanih nasipa je
to remove a loose humus layer of debris from dominantno slabo do jače vezana sitnozrna
the surface zone until a depth of 0,2-0,3m. krečnjačka drobina i podređeno slojeviti
krečnjaci.
The footing part of the embankment at this
stretch (classical embankment of reinforced Prije polaganja nasipa neophodno je ukloniti
soil) is recommeded to found on limestone or to slabovezani humificirani sloj drobine iz
secure embankment by a low retaining wall površinske zone do dubine 0,2- 0,3m.
and related drainage. Backfilling is to be Preporučuje se da se nožični dio nasipa na
complied with valid standards in nearly ovom potezu (klasični nasip, armirano tlo)
horizontal layers with proper compaction. For fundira na krečnjaku ili izvrši osiguranje
geotechnical area (right lane) stratified to nasipa nožičnim potpornim zidom sa pratećom
banked limestones and dolomitic limestones (3a) drenažom. Nasipanje izvršiti u skladu sa
which are in the surface very karstificated and važećim standardima u približno horizontalnim
cracked, recommended reference values for this slojevima uz propisno zbijanje. Za geotehničku
stretch are physical mechanical parameters for sredinu slojeviti do bankoviti krečnjaci i
category D until a depth of 4-5m and for dolomitičnikrečnjaci (3a) koji su u površinskom
category C until a depth of 15- 20m. dijelu veoma skaršćeni i ispucali, kao
mjerodavne vrijednosti na ovom potezu mogu
Slopes of throughcuts will be performed largely
se usvojiti fizičko mehanički parametri za
within the category C and to a lesser extent
kategoriju D do dubine 4-5m odnosno
within categories D and P1 which relates
kategorije C do dubine 15-20m.
mainly to the surface parts of the terrain.
Kosine usijeka izvodiće se većim dijelom u

26
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Embankments will be laid mainly on rock okviru kategorije C i manjim dijelom u okviru
masses classified into category D and P. The kategorija D i P1 što se odnosi uglavnom na
allowable capacity for categories C, D and P1 površinske dijelove terena.
is provided in tables under chapter 4.3.4.
Nasipi će se polagati uglavnom na stijenskim
b) Through cut-embankment at stretch 1+200- masama koje su izdvojene u kategoriju D i P.
1+243,25 (left lane) the road is in a through cut Dozvoljena nosivost za kategorije C,D i P1
10-14m high, which will run through layered to data je tabelarno u poglavlju 4.3.4.
banked limestones that are in the surface part
b) Usjek-nasip na potezu 1+200 - 1+243,25
very karstificated with distinct surface karst
(lijeva traka) put je u usjeku visine 10-14m, koji
forms (vices, etc.). The cut's slopes should be
će se izvoditi kroz slojevite do bankovite
formed at gradient 3:1 by fine smooth blasting
krečnjake koji su u površinskom dijelu veoma
with cutting by 3m wide berms at ½ of height. At
skaršćeni sa izraženim površinskim karstnim
the part where layered, karstified limestones are
oblicima (škrape i drugo). Kosine usijeka
covered by poorly bound debris, as is the case at
formirati pod nagibom 3:1 finim glatkim
the stretch in length of 13m, it is required in
miniranjem uz presijecanje bermom širine 3m
front of the entrance portal of the tunnel
na ½ visine. Na dijelu gdje su slojeviti
Vežešnik to mitigate the peaks of the slopes to
karstifikovani krečnjaci prekriveni
2:1 with the protection of road meshes.
slabovezanom drobinom, kakav je slučaj na
In chapter Stability analysis of embankments potezu dužine 13m, ispred ulaznog portala
it is stated as follow: „At the stretch from tunela Vežešnik, neophodno je ublažiti vršne
Smokovac 0+000 to tunnel Suka 0+405, dijelove kosine na 2:1 uz zastitu putarskim
embankments in height of up to 15m will largely mrežama.
lay over the flat and good bearing terrain.
U poglavlju Analiza stabilnosti nasipa
Given that the limestone material from the side
navedeno je slijedeće: „Na potezu od Smokovca
cuts and quality scree material are installed into
0+000 do tunela Suka 0+405 nasipi visine do
embankments at slope gradient 1:1.5 and that
15m će se najvećim dijelom polagati preko
the embankments are cut by 2m wide berm, at
pretežno ravnog i dobro nosivog terena. Uz
every 10m of height, results of the analysis show
uslov da se u nasip ugrađuje krečnjački
that the safety factor of 1,3 is met in natural
materijal iz zasijeka i kvalitetni siparski
conditions as well as Fs>1 in seismic
materijal sa nagibom kosina nasipa 1:1,5 kao i
conditions. At the stretch between the tunnels
da se nasipi presjecaju bermom širine 2m, na
Suka and Vežešnik, high embankments (15-25m)
svakih 10m visine, rezultati sprovedenih
will be formed mainly on the flat plateaus and
analiza ukazuju da je zadovoljen faktor
slope with gradient 5-15° and 25-30° at some
sigurnosti 1,3 u prirodnim uslovima i Fs>1 u
stretches.
seizmičkim uslovima. Na potezu između tunela
Embankments will usually be formed over Suka i tunela Vežešnik formiraće se visoki
bound limestone debris of screes. The high nasipi (15-25m), pretežno na zaravnjenim
embankments need to install quality limestone platoima i padini nagiba od 5-15 stepeni a na
materials from through cuts and side cuts. The pojedinim potezima i od 25-30 stepeni.
embankment 25m high will be done at gradient
Nasipi će se najčešće formirati preko vezane
1:1.5 and cut by two berms in width of 2m.
krečnjačke drobine sipara. U visoke nasipe je
neophodno ugraditi kvalitetni krečnjački
materijal iz zasjeka i usjeka. Nasip visine 25m
The stability analysis is made for 30 m high
izvesti pod nagibom 1:1,5 uz presjecanje sa
embankment with reinforced soil (figures 34 and
dvije berme širine 2m.
35) which is done by characteristic EG profile

27
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

13-13’ (app. 3.13). The analysis was done with Sprovedena je i analiza stabilnosti za nasip sa
gradient of reinforced soil 6:1 and geogrids in armiranom zemljom visine 30m(slike br.34 i
length of 9-12m (depending on position in 35) po karakterističnom IG presjeku 13-
embankment) located at every 0.3m. The results 13'(prilog br.3.13). Analiza je urađena sa
of stability analysis indicate that safety factors nagibom armirane zemlje 6:1 i geomrežama
Fs>1.3 (F=1.327) are met in natural and Fs>1 dužine od 9-12m ( u zavisnosti od položaja u
(Fs=1.165) in seismic conditions. nasipu), postavljenih na svakih 0,3m. Rezultati
sprovedene analize stabilnosti pokazuju da je
In chapter 5. RECOMMENDATIONS FOR
zadovoljen faktor sigurnosti Fs>1,3(Fs=1.327)
DESIGNER it is stated as follow:
u prirodnim uslovima i Fs>1 (Fs=1.165) u
„Geotechnical conditions for construction of
seizmičkim uslovima.
open route in the zones 1, 2 and 4 at the stretch
from Smokovac to bridge Mrke are changble U poglavlju 5. PREPORUKE
and are assessed as: PROJEKTANTU navedeno je slijedeće:
„Geotehnički uslovi izvođenja otvorene trase u
- Relatively favourable at the stretch from the
okviru zona 1,2 i 4 na potezu od Smokovca do
tunnel Vežešnik to Mrke bridge, where the open
mosta Mrke su promjenljivi i mogu se ocijeniti
route will run through the leveled karst plateau
kao:
of Mrke;
- Relativno povoljni na potezu od tunela
- Specific at the stretch from Smokovac to tunnel
Vežešnik do mosta Mrke, gdje će se otvorena
Suka, where the right lane of the highway will
trasa izvoditi preko zaravnjenog karstnog
run through the lowland terrain constructed of
platoa Mrka ;
glaciofluvial sediments, and left lane over the
mountain slope that is built of limestone and - Specifični na potezu od Smokovca do tunela
screes; Suka, gdje će se desna traka autoputa izvoditi
preko ravničarskog terena izgrađenog od
- Demanding and specific at the stretch between
glaciofluvijalnih sedimenata a lijeva preko
the tunnels Suka and Vežešnik, where at the hilly
brdske padine izgrađene od krečnjaka i sipara;
slope there are colluvial-diluvial sediments
(bound debris of screes)... - Zahtjevni i specifični na potezu između tunela
Suke i Vežešnika, gdje su na brdskoj padini
In the same chapter, ad b)Embankments it is
zastupljeni koluvijalno-deluvijalni sedimenti
stated as follow: „Due to variable geo-
(vezana drobina sipara)...
morphological properties at the stretch of the
open route from Smokovac to Mrke geotechnical U istom poglavlju, pod b)Nasipi navedeno je
conditions for excavations are different. slijedeće: „Zbog promjenljivih geomorfoloških
odlika terena na potezu otvorene trase od
- Embankments in height of up to 10m, on the
Smokovca do mosta Mrke geotehnički uslovi
section between Smokovac and tunnel Suka
izvođenja raskopa su različiti.
(right lane), which will lay over lowland terrain
that is built of glacio fluvial sediments, should - Nasipe visine do 10m, na dionici između
be made of limestone materials from the cuts Smokovca i tunela Suka (desna traka), koji će
and and screes at gradient of 1:1.5. Previously, se polagati preko ravničarskog terena,
remove a thin layer of humus over glacio fluvial izgrađenog od glaciofluvijalnih sedimenata,
sediments in thickness of 10-15cm and compact izvoditi od krečnjačkog materijala iz zasjeka i
the subsoil with appropriate mechanization sipara pod nagibom 1:1,5. Prethodno ukloniti
(vibrating rollers, etc.) tanki humusni sloj, preko glaciofluvijalnih
sedimenata, debljine 10-15cm i izvršiti zbijanje
- Embankments in height of up to 10m (section
podtla odgovarajućom mehanizaciom (vibro
Smokovac-Suka), which will be laid on the left

28
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

lane, partly through a mountain slope built of valjci i drugo)


limestones, should be made of limestone
- Nasipe visine do 10m visine (dionica
materials with prior removal of unbound and
Smokovac-Suka) koji će se polagati duž lijeve
weakly bound debris of screes from the
trake, dijelom preko brdske padine izgrađene
mountain slope.
od krečnjaka, izvoditi od krečnjačkog
Scree material from the slope should be materijala uz prethodno uklanjanje nevezane i
disposed on temporary landfill and, after tests slabo vezane drobine sipara sa brdske padine.
for physical -mechanical properties, selectively
Siparski materijal sa padine odložiti na
built into embankments.
privremene deponije a nakon ispitivanja
- Embankments in height of 12-15m, at this fizičko-mehaničkih svojstava selektivno
stretch (from Smokovac to Suka) should be done ugraditi u nasipe.
classically, of limestone material at 1:1.5 or
- Nasipe visine od 12-15m, na ovom potezu (od
reinforced soil. With regard to the height of
Smokovca do Suke) izvoditi klasično, od
embankment, morphological features of the
krečnjačkog materijala pod nagibom 1:1,5 ili
terrain and taking a part in lowland areas with
primjenom armiranog tla. S obzirom na visinu
residential objects, preference should be given
nasipa morfološke odlike terena i zauzimanje
to embankments, of reinforced soil.
dijela ravničarskog područja sa izgrađenim
- High embankments (20-25m) between the stambenim objektima prednost treba dati
tunnels Vežešnik and Suke, which will be laid nasipima od armiranog tla.
over the unbound limestone debris of calmed
- Visoke nasipe (20-25m) između tunela Suke i
screes (on flattened plateaus and hill slope)
Vežešnika, koji će se polagati preko vezane
should be made of reinforced soil or in the
krečnjačke drobine umirerenih sipara (na
classical manner inclusive of installation of
zaravnjenim platoima i brdskoj padini) izvoditi
granular limestone material from excavations,
primjenom armiranog tla ili na klasičan način
embankments to be at gradient 1:1.5, with a
sa ugradnjom granuliranog krečnjačkog
berm in width of 2m at every 10m of height and
materijala iz iskopa, nasipe izvoditi pod
with protection wall donwhill. The low wall is to
nagibom 1:1,5, sa bermom širine 2m na svakih
be footed in the host rock - limestone.
10m visine i zaštitom nožičnim zidom sa
Preceding is an adequate preparation of subsoil nizbrdne strane. Nožični zid fundirati u
which involves removal of surface humified osnovnoj stijeni – krečnjaku.
layer and less bound debris in thickness of 0,3-
Prethodno izvršiti odgovarajuću pripremu
0,5m. After that, it is necessary to thicken the
podtla što podrazumjeva uklanjanje
subsoil to the maximum dry density and
površinskog humificiranog sloja i slabije
compaction of at least 50MP. These physical-
vezane drobine debljine od 0,3-0,5m. Nakon
mechanical properties will be controlled on the
toga je potrebno zbiti podtlo do maksimalne
spot by current control with respect to
suve zapreminske težine i do zbijenosti od
appropriate standards in this area that are listed
minimalno 50Mpa. Ove fizičko-mehaničke
at the end of this chapter. Due to the general
karakteristike će se kontrolisati na licu mjesta
stability, bottom pars of the embankment are
tekućom kontrolom uz poštovanje
required to lay down the host rock (Category D)
odgovarajućih standarda iz ove oblasti koji su
which will be achieved by wide excavations in
navedeni na kraju ovog poglavlja. Zbog
these zones and by formation of embankments or
generalne stabilnosti nožični dio nasipa je
reinforced soil at the specified conditions of
obavezno položiti na osnovnoj stijeni
executions from the civil design.
(kategorija D) što će se postići širokim
On this stretch, because of high embankment, iskopima u tim zonama i formiranjem nasipa ili

29
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

slope gradient and base of bound debris, priority armirane zemlje po zadatim uslovima izvođenja
should be given to the reinforced soil iz građevinskog projekta.
embankment.“
Na ovom potezu zbog velike visine nasipa,
nagiba padine i podloge od vezane drobine
prednost treba dati izgradnji nasipa od
Due to a comparison, we are providing basic armiranog tla.“.
details from Elaboration on Additional
Geotechnical Investigations and
Engineering-Geological Properties in area of
Zbog poređenja donosimo osnovne detalje iz
the Open Route Section Planned for the
Elaborata o dopunskim geotehničkim
Reinforced Soil Retaining Wall, Chainage
istraživanjima i inženjersko-geološkim
RK 1+093 - 1+334 In chapter 3.2
odlikama terena u zoni dijela otvorene trase
Geomorphological features of the terrain it is
zid od armirane zemlje, stacionaža RK
stated: “From geomorphological processes, the
1+093 – 1+334. U poglavlju 3.2
dominant on this part of the terrain are:
Geomorfološke odlike terena navedeno je
 Karst process, as represented by surface slijedeće: „Od geomorfoloških procesa na
and underground karst forms (valleys, ovom dijelu terena dominanti su:
small caves, caverns);
- Karstni proces, koji je označen
 Physical-mechanical decay of rock masses,
površinskim i podzemnim karstnim
especially pronounced in the surface area;
oblicima (dolovi, manje pećine, kaverne);
 Rock falling- slope process, rotary motion - Fizičko-hemijsko raspadanje stijenskih
of debris which was made by mechanical masa, što je posebno izraženo u
decaying of stone rock masses that formed površinskom dijelu;
screestones at the hilly slope in thickness - Osipanje – padinski proces, rotaciono
more than 10m.” kretanje drobine stvorene mehančkim
raspadanjem kamenitih stijenskih masa
kojim su formirani sipari na brdskoj
In chapter 3.3 Engineering – Geological padini debljine i veće od 10m.
structure it is stated as follow: “The
Quaternary sediments are represented by
deluvial-colluvial scree and glacio-fluvial U poglavlju 3.3 Inženjersko-geološka građa
sand – gravel materials.” terena navedeno je slijedeće: „Kvartarni
Deluvial – colluvial sediments – passive screes sedimenti su predstavljeni deluvijalno-
(figure 4) - are represented by debris and koluvijalnim siparskim i glaciofluvijalnim
mostly limestone materials with a varying pjeskovito-šljunkovitim materijalom.
content of clay component and with a content Deluvijalno-koluvijalni sedimenti – umireni
of limestone blocks in size of over 0,5m. sipari (slika 4), su predstavljeni su
Thickness of the scree sediments exceeds 13m. drobinskim uglavnom krečnjačkim
Generally, these materials are loosely bound materijalom sa promjenjivim sadržajem
to unbound, or rarely bound by a calcite glinovite komponente i sa sadržajem
binder. At the concerned location, these krečnjačkih blokova veličine i preko 0,5m.
sediments are partly covered by an Debljina ovih siparskih sedimenata je i veća
emankment. od 13m. Uglavnom se radi o slabije vezanom
This scree is passive and accumulated over the do nevezanom materijalu a rjeđe su vezani i
glacio-fluvial sediments. In present conditions, kalcitskim vezivom. Na lokaciji su dijelom
it remains stable.”

30
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

In chapter 3.3.1 Definition of EG units, prekriveni nasipom.


subunits and geotechnical categories it is
Radi se o umirenom siparu, nataloženom
stated as follow: “Engineering-geological unit
preko glaciofluvijalnog materijala a koji je u
IG1a1 is described as the Quaternary deluvial
sadašnjim uslovima stabilan.“
– colluvial, scree material, with thickness
exceeding even 13 m. Thickness of the scree U poglavlju 3.3.1 Definicija IG jedinica,
material in the boreholes (B-3 through B-5) is podjedinica i geotehničkih kategorija
around 1.7-8.8m, while the boreholes B-1 and navedeno je slijedeće: „IG jedinica IG1a1 je
B-2 were finished inside this material. izdvojena kao kvartarni deluvijalno –
Generally, this material is loosely bound to koluvijalni, siparski materijal debljine i preko
unbound (predominant is limestone debris with 13m. Istražnim bušotinama (B-3 do B-5)
a varying grain-size distribution, sharp- registrovana je debljina siparskog materijala
angular, with various content of silt – clay oko 1.7-8.8m dok su istražne bušotine B-1 i B-
component and dm-sized blocks). This unit is 2 završene u okviru ovog materijala.
defined as P1 category.” Generalno se radi o slabije vezanom do
nevezanom materijalu (dominira krečnjačka
drobina različitog granulometrijskog sastava,
In chapter 3.4 Conditions for Section of oštrouglasta, sa promenljivim učešćem
Reinforced Soil Retaining Wall it is stated as prašinasto-glinovite komponente i blokova dm
follow: “The concerned location is intended dimenzija). Ova IG jedinica je definisana kao
for construction of the open route including a P1 kategorija.“
reinforced soil retaining wall.
U poglavlju 3.4 Uslovi fundiranja dijela
The retaining wall will be formed on a slope potpornog zida od armirane zemlje
with an inclination of 20 to 25°. navedeno je slijedeće: „Na predmetnoj
lokaciji planirana je izgradnja otvorene trase
Soil of surrounding area is characterized by
sa potpornim zidom od armirane zemlje.
scree material that is accummulated over the
sandy – gravel glaciofluvial sediments and Potporni zid će se formirati na padini sa
limestones of Upper Cretaceous age. The very nagibom od 20 do 25°.
ground surface has been affected by fillling
Teren u bližoj zoni karakteriše se siparskim
with natural materials. According to
materijalom koji je nataložen preko
information provided by the Employer, this
pjeskovito-šljunkovitih glacio-fluvijalnih
wall will be removed.
sedimenata i krečnjaka gornjokredne starosti.
On basis of findings acquired by the subject Sama površina terena je izmjenjena
investigations, a geotechnical field model is nasipanjem od prirodnog materijala. Nasip
defined and analysis of design solution is će, prema podacima dobijenim od Investitora
carried out from geotechnical point of view. biti uklonjen.
Stability analysis shows that the field is in Na osnovu podataka dobijenih izvedenim
state of boundary equilibrium under natural istraživanjima, definisan je geotehnički model
conditions and load from traffic and terena i izvršena je analiza projektnog rešanja
reinforced soil. It is recommended to build a sa geotehničkog aspekta.
small ballast on the section where the
Analiza stabilnosti, pokazuje da je teren u
reinforced soil will rely onto the scree
prirodnim uslovima uz opterećenje od
materials.”
saobraćaja i od armirane zemlje u stanju
In chapter 3.4.2 Stability analysis it is stated granične ravnoteže. Preporuka je da se na
as follow: “Stability analysis referrs to two dijelu terena gdje se armirana zemlja oslanja

31
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

cases as follows: na siparski materijal izvede manji balast.


Case I – stability analysis for adopted load U poglavlju 3.4.2 Analiza stabilnosti
from reinforced soil of 400 kPa and load from navedeno je: „Analiza stabilnosti je rađena u
traffic of 33.3 kPa, with and without seismic dva slučaja i to:
influence;
Prvi - proračun stabilnosti uz usvojeno
Case II – stability analysis with ballast in the opterećenje od armirane zemlje 400 kPa i
foot section, with and without seismic opterećenje od saobraćaja od 33.3 kPa sa i
influence. bez seizmičkog uticaja;
Drugi - proračun stabilnosti uz izgradnju
balasta u nožičnom dijelu sa i bez seizmičkog
Having in mind that the concerned area, in
uticaja;
terms of seismicity, belongs to VIII° MKS,
impacts of seismics is simulated, with Imajući u vidu da predmetno područje, u
equivalent static load, by horizontal and force pogledu seizmičnosti, pripada VIII° MKS,
of 0,1 W and vertical of 0,5W (weight of uticaj seizmike je simuliran, ekvivalentnim
sliding blocks), as in accordance with data of statičkim opterećenjem, horizontalnom silom
seismic micro reionization. od 0,1 W i vertikalnom od 0,5W (težine
kliznog bloka), shodno podacima seizmičke
Stability analysis was carried out for natural
mikrorejonizacije.
conditions, i.e. without the existing emankment
as it will be removed. Another case included Analiza stabilnosti je izvedena u prirodnom
slope analysis with construction of ballast. The stanju, odnosno bez postojećeg nasipa,
ballast shown in the stability analysis is obzirom na to da će nasip biti uklonjen. U
approximative, so as to determine possible drugom slučaju je analizirana kosina uz
solutions to slope stability. The precise sizes izgradnju balasti. Balast koji je prikazan na
and slope of the ballast should be determined analizama stabilnosti je aproksimiran u cilju
by the Designer as a modification to the Main utvrđivanja mogućnosti rešavanja stabilnosti
construction design. padine. Precizne dimenzije i nagib balasti
treba da odredi Projektant u sklopu izmjena
The analysis showed that, in conditions of
Glavnog Građevinskog Priojekta.
loads from reinforced soil and traffic, the
slope is at state of limit equillibrium and that Analizom je utvrđeno da se u uslovima
for case of seismic influence the safety factor opterećenja od armirane zemlje i od
is below 1, which implies implementation of saobraćaja kosina nalazi u stanju granične
security measures. ravnoteže i da je u slučaju seizmičkog uticaja
faktor sigurnosti ispod 1, odnosno da je
Stability analysis with ballast gave safety
potrebno uraditi osiguranje.
factors which satisfy the criterium Fs > 1,4
for slopes in natural conditions under load, Analizom stabilnosti sa balastom su dobijeni
and Fs > 1,1 for slopes in seismic faktori sigurnosti koji zadovoljavaju
conditions.” kriterijum Fs > 1,3, za kosine u prirodnim
uslovima uz opterećenje, odnosno Fs >1,1 za
In chapter 4. CONCLUSION it is stated as
kosine u seizmičkim uslovima.“
follow: “As the ground in the area of
reinforced soil retaining wall is characterized
by great thickness of rockfall sediments, the
U poglavlju 4. ZAKLJUČAK navedeno je
solution proposed by the Designer was
slijedeće: „S obzirom da se teren u zoni dijela
considered. Given the stability analysis
potpornog zida od armirane zemlje

32
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

showed that the ground is in state of boundary karakteriše velikom debljinom deluvijalno-
equlibrium under load from traffic operations koluvijalnih sedimenata siparskih sedimenata,
and reinforced soil, it is recommended that the analizirano je rešenje Projektanta. Kako je
slope should be secured with a ballast in the izvedenom analizom stabilnosti dobijeno da je
area where reinforced soil relies into the scree teren uz opterećenje od saobraćaja i armirane
material. zemlje u stanju granične ravnoteže, preporuka
je da se kosina u dijelu gdje se armirana
Precise sizes and slope of the ballast should be
zemlja oslanja na siparski materijal osigura
defined by the Designer as a part of
balastom.
modifications to the Main construction design.
Precizne dimenzije i nagib balasti treba da
Such solution was analyzed from aspect of
odredi Projektant u sklopu izmjena Glavnog
stability and bearing capacity.
Građevinskog Projekta.
Bearing capacity calcuation resulted in value
Ovakvo rešenje je analizirano sa aspekta
which exceeds the expected loads from the
stabilnosti i nosivosti.
facility and traffic.
Proračunom nosivosti je dobijena vrijednost
From stability analysis inclusive of the ballast,
koja prevazilazi očekivano opterećenje od
obtained safety factors are satisfying for the
objekta i saobraćaja.
cariteria Fs>1,3 and Fs>1.1 in seismic
conditions. Sa aspekta stabilnosti uz izradu balasta,
dobijeni su faktori sigurnosti koji
Expected settlements will take place during
zadovoljavaju kriterijum Fs>1,3 i Fs>1.1 u
construction of the Facility.”
uslovima seizmičnosti.
Due to a comparison, we are providing basic
Očekivana slijeganja će se obaviti tokom
details from Elaboration on Geotechnical
izgradnje objekta.“
Conditions for Construction of
Embankment Between the Tunnels Suka Zbog poređenja donosimo osnovne detalje iz
and Vezesnik from km RK 1+093 to RK Elaborata o geotehničkim uslovima
1+334 izvođenja nasipa između tunela Suka i
Vežešnik od km RK 1+093 do RK 1+334.
In chapter 1 INTRODUCTION it is stated as
follow: “According to the Contract concluded U poglavlju 1 UVOD navedeno je slijedeće:
between the Employer (CRBC) and Geological „Na osnovu ugovora između Naručioca
Contractor (Geoprojekt ltd.), supplementary (CRBC) i izvođača geoloških istraživanja
geotechnical investigations were carried out in (Geoprojekt d.o.o. Podgorica) izvedena su
order to, along with use of findings from dopunska geotehnička istraživanja, kako bi se,
earlier investigations, develop the Elaboration uz korišćenje ranije izvedenih istraživanja,
on geotechnical conditions for construction of izradio Elaborat o geotehničkim uslovima
embankment between the tunnels Suka and izvođenja nasipa između tunela Suka i
Vežešnik from km RK 1+095 to RK 1+334, for Vežišnik od km RK 1+095 do RK 1+334, za
level of the Main Construction Design for Bar nivo Glavnog građevinskog projekta na
– Boljare Highway, Section Smokovac – autoputu Bar – Boljare, dionica Smokovac –
Matesevo. Mateševo.
In general, natural structure of the terrain is Prirodna konstrukcija terena u ovoj zoni je
representative for valley sides of the Morača inače karakteristika dolinskih strana rijeke
river within this area. The basic rock mass is Morače u ovoj zoni. Osnovnu stijenu
limestone massif against which the Morača's predstavlja krečnjački masiv na koga je

33
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

terrace is relied, represented by sandy gravels naslonjena terasa Morače koju predstavljaju
poorly to highly bound into a conglomerate pjeskoviti šljunkovi koji su slabo do jače
and highly bound in the area where the terrace vezani u konglomerat i vrlo jako vezani u zoni
is approaching the Morača's bed. This terrace gdje se terasa približava koritu rijeke Morače.
is overlaid by deposits of colluvial materials, Preko ove terase su deponovani koluvijalni
i.e. screes from the slope in the hinterland. materijali koji predstavljaju sipare sa padine
These materials are represented by angular iz zaleđa. Ove materijali su uvidom na terenu
sandy gravels origins from limestone, with a predstavljeni pjeskovitim uglastim šljunkom
certain percentage of debris and with local krečnjalog porijekla sa određenim procentom
blocks of rocks. Also, areas with a certain drobine i sa blokovima stijene koji se lokalno
percentage of clay-silt component are javljaju. Takođe se mogu i sresti zone gdje
encountered here and there. This was a brief postoji i određeni procenat glinovito-
description of natural geology of the field in prašinaste komponente.
this area, however it should be noted that, due
Ovo je ukrato bio opis geološke građe
to intensive works for excavation of Suka and
prirodne konstrukcije terena u ovoj zoni, ali
Vežišnik, the natural structure of the field was
mora se imati u vidu da je zbog velikih radova
covered with enormous quantites of fill
na iskopu Suke i Vežišnika ova prirodna
(spilled) materials that were not compacted
konstrukcija terena zatrpana ogromnom
but landfilled at this location temporarily.
količinom nasutog (prosutog) materijala koji
Access and working roads were built on these
nije zbijan već je ovdje privremeno
materials.
deponovan. Preko ovih materijala su
The figure below reflects the actual situation formirani i pristupni i radni putevi do tunela.
at the site, where impact of the said works onto
Na sledećoj slici je prikazano trenutno stanje
the change in morphometry comparing to the
na terenu gdje se može vidjeti uticaj
natural state is evident. It has been planned by
navedenih radova na izmjenu morfometrije
the Contractor, which is also a pre-requisite
terena u odnosu na prirodno stanje. Plan
for construction of the embankment, to
Izvođača a i uslovna preporuka za izvođenje
completely remove the deposited materials
budućeg nasipa je uklanjanje kompletnog
until the natural structure of the terrain.
nabacanog materijala do prirodne
Appendices 1 and 2 clearly shows the
konstrukcije terena. U prilozima 1 i 2 data je
boundaries of the materials over the natural
dovoljno tačna, orijentaciona granica
ground.
nabacanog materijala preko prirodne
According to the Agreement signed between konstrukcije terena.
the Employer and Contractor, the Contractor
Na osnovu Ugovora između Naručioca i
developed "Design of additional geotechnical
Izvođača, Izvođač je izradio “Projekat
investigations for construction of an
dopunskih geotehničkih istraživanja za
embankment between the tunnels Suka and
potrebe definisanja geotehničkih uslova
Vežešnik from km RK 1+095 to RK 1+334",
izvođenja nasipa između tunela Suka i
for the General civil design. The Employer
Vežišnik od km RK 1+095 do RK 1+334“ za
handed the Design over to the Investor, who
nivo Glavnog građevinskog projekta.
forwarded it for perusal to the State Review
Naručilac je predao Projekat Investitoru, a on
Panel that issued its approval and auditting
ga je proslijedio na pregled Državnoj
Clause UP199/18 as of 22.11.2019.
revizorskoj komisiji, dala saglasnost i
Since this location had been investigated for revizionu klauzulu broj UP-419/19 od
construction of reinforced earth, which was 22.11.2019 god.
dismissed in the meantime, those works were
Obzirom da su na ovoj lokaciji rađena

34
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

still used and two boreholes B-1, B-2 i B-3 istraživanja za potrebe izgrdanje armirane
were redrilled, now carrying annotations B-1', zemlje od koje se u međuvremenu odustalo, ti
B-2' and B-3'. The two were drilled in the radovi su iskorišćeni a za potrebe ovog
immediate vicinity of the initial boreholes. Elaborata su ponovljene tri bušotine B-1, B-2
Also, 6 trial pits and 2 boreholes B-6 and B-7 i B-3 sada sa oznakama B-1', B-2' i B-3'. Ove
were executed in order to define the dvije bušotine su izvedene u neposrednoj
foundations of toe retaining wall.” blizini prethodnih. Takođe, za potrebe
definisanja fundiranja nožičnog potpornog
In chapter 3.4 Geotechnical conditions for
zida izvedeno je 6 raskopa i dvije bušotine B-6
embankment construction it is stated as
i B-7.“
follow: “This section of the open route is
planned for construction of embankment with U poglavlju 3.4 Geotehnički uslovi
elements as shown in field cross-sections. izgradnje nasipa navedeno je: „Na ovom
dijelu otvorene trase planira se izgradnja
It is recommended to build the embankment by
nasipa sa elementima kako je to prikazano na
using, as designed, the selected quality
poprečnim presjecima terena.
subbase materials in compliance with
applicable standards. Gradient of its sides will Preporučuje se izrada nasipa, kako je to i
be 27°, i.e. 1:2. Height of level slopes will be planirano, sa selektovanim kvalitetnim
min 10 m, with a break berm 2m wide. Line of tamponskim materijalom u svemo saglasno
the embankment is given in app. 1 and 2. standardima. Nagib kosina nasipa će biti 27°
tj. nagib 1:2. Visine etažnih kosina će biti 10
The total height of the embankment will be cca
m sa prekidnom bermom širine 2 m. Linija
30 m, while its thickness on natural material in
nasipa je data u prilozima br. 1 i 2.
the area of the right edge of the road will
range to maximum 30 m in the area of Ukupna visina nasipa će se kretati oko 30 m,
borehole B-4 (in length of cca 35 m), whereas dok će se debljina nasipa nad prirodnim
before and after this point the thickness materijalom u zoni desne ivice puta kretati od
rapidly decreases. maksimalnih oko 30 m u zoni bušotine B-4 (u
dužini oko 35 m) dok se prije ove tačke i
A basic recommendation, which was an initial
nakon nje debljina vrlo brzo smanjuje.
idea, is to remove all filled and thrown
materials from this location. This material Kao osnovna preporuka, što je i idejom
could be repacked and used as material for planirano jeste da se ukloni sav nasuti i
incorporation in the embankment providing nabacani materijal sa lokacije. Ovaj materijl
the prior proper preparation of it. se može prepakivati i koristiti za materijal koji
će se ugrađivati u nasip ali tek nakon
When removing the materials it is required to
adekvatne pripreme.
remove up to 1 m of natural material, so as to
eliminate from the ko-dl materials any surface Prilikom uklanjanja materijala potrebno je
deluvial-humus cover, which is expected to be ukloniti do 1 m prirodnog materijala kako bi
beneath the embankment. se iz ko-dl materijla uklonio površinski
deluvijlno-humusni pokrivač koji se može
Afterwards, it is required to prepare the
očekivati ispod nasipa.
subsoil in a way that in areas where gradient
of natural material exceeds 20° stairs around Nakon toga je potrebno pripremiti podtlo tako
2 m wide will be built, buried into soil, with što će se u zonama gdje je nagib prirodnog
gradient 1:1 to 2:1. For gradients between 20 materijala preko 20° izvesti stepenice širine
and 30° it is required to provide a gap of 1 m oko 2 m, usječne u teren, sa nagibom 1:1 do
between the stairs, while for gradient of over 2:1. Za nagib terena između 20 i 30° između

35
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

30° the stairs shoud be built without the gaps. stepenica se ostavljaju međuprostori od 1 m,
For gradients in area where terrain is cut by dok se za nagibe terena preko 30° stepenice
steep slopes, the embankment should be built izvode bez međuprostora. Za nagibe terena u
from the lower level until it becomes levelled zonama gdje je teren zasječen strmim
with the slope's top. nagibom to se nasip izvodi sa donjeg nivoa
dok ne se ne poravna sa škarpom kosine.
Prior to embankment works, it is required to
prepare the subsoil, i.e. to compact it until the Prije izrade nasipa potrebno je pripremiti
maximum dry density and compaction of podtlo i to tako da je potrebno izvršiti zbijanje
minimum 50 Mpa are obtained. The physical podtla do maksimalne suve zapreminske težine
mechanical parameters will be checked on i do zbijenosti od minimum 50 MPa. Ove fiz.-
spot by means of current control and with meh. karakteristike će se kontrolisati na licu
respect to applicable standards specified at the mjesta tekućom kontrolom uz poštovanje
end of this chapter. odgovarajućih standarda iz ove oblasti koji su
navedeni na kraju ovog poglavlja.
When it comes to materials for the
embankment, materials from excavation for
Suka and Vezisnik tunnels may be used.
For that, it is required to form a well grained
Što se tiče materijala koji je potrebno ugraditi
subbase material (d10/d60>9) with the
u nasip za to se može koristiti materijal iz
following properties:
iskopa tunela Suka i Vežišnik.
Maximum grain size should not exceed two
Za to je potrebno formirati dobro granulirani
thirds of the thickness of the layer in which it
tamponski materijal (d10/d60>9) koji ima
is installed. On general the grain size in
sledeće karakteristike:
embankment should not exceed 400 mm.
Maksimalna veličina zrna ne smije biti veća
Embankment of limestone material should be
od dvije trećine debljine sloja koji se
done in approximately horizontal layers in the
ugrađuje, a po pravilu zrna u nasipu ne
longitudinal direction, in appropriate
smiju biti veća od 400 mm.
thickness as per the standards, given to start
from the lowest parts of the terrain. In the Nasip od krečnjačkog materijala izvoditi u
transverse direction, layers should have a približno horizontalnim slojevima u podužnom
slope of at least 4%. pravcu, odgovarajuće debljine u skladu sa
standardima, s tim što treba početi od najnižih
The embankment must be compacted to min
djelova terena. U poprečnom pravcu slojevi
95% by the modified Proctor.
treba da imaju nagib od najmanje 4 %.
At the top of the embankment, below the sub-
Nasip mora biti zbijen na minimum 95 % po
grade, compression modulus must be Ev2>60
modifikovanom Proktoru.
MPa, and CBR > 10 % needs to be achieved.
Na ravni nasipa ispod posteljice potrebno je
As for parameters that would fit the materials
dostići modul stišljivosti Ev2 >60 MPa a CBR
prepared in such a manner, the probability
mora biti veći od 10 %.
analysis was done for 30 m high embankment
(within geological maps for the phase of the Što se tiče parametara koji bi odgovarali
Highway Main construction design), given the ovako pripremljenom materijalu rađena je
safety factor of cca 1.4 was met. The analysis probabilistička analiza za nasip visine 30 m (u
resulted in the following values: okviru geoloških podloga u fazi izrade
glavnog projekta autoputa), a da je

36
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

angle of internal friction φ = 39 (38-40); zadovoljen faktor sigurnosti od oko 1.4. Ovom
analizom su dobijene sledeće vrijednosti:
cohesion c = 1 (0-2).
ugao unutrašnjeg trenja φ = 39 (38-40);
Given the preparation of embankment
described above, these parameters are kohezija c = 1 (0-2).
absolutely met, i.e.in practice, angle of
Uz gore navedenu pripremu nasipa ovi
internal friction for embankment certainly
parametri su definitivno zadovoljeni tj. u
exceeds 40°, meaning that stability
praksi ugao unutrašnjeg trenja nasipa sigurno
requirement is satisfied.
prevazilazi 40° tako da je uslov stabilnosti
The material planned for embankment as well nasipa zadovoljen.
as natural material has good permeability
Materijal budućeg nasipa pa i prirodni
properties, i.e.the terrain leachates relatively
materijal imaju solidne vodopropusne
quickly. In any case, it is required, in order to
karakteristike u smislu da se teren relativno
minimize the impact, collect all waters forming
brzo ocijeđuje. U svakom slučaju je potrebno,
along the two gullies above the Highway. This
kako bi se što više smanjio uticaj, sve vode
could be achieved by building a drainage
koje se formiraju duž dvije jaruge pokupiti
trench above the Highway to maxpossible
iznad autoputa koliko je to moguće. Ovo je
depth in the Quaternary unbound and poorly
moguće postići izradom drenažnog rova iznad
bound material. That water as well as water
puta do maksimalne moguće dubine u
from the tunnel and road should be collected
kvartarnim nevezanim i slabovezanim
and transferred below the embankment into
materijalima. Tu vodu i vodu iz tunela i sa
the Moraca.
saobraćajnice je potrebno pokupiti i sprovesti
ispod nasipa u Moraču.
Execution of all earth works must be complied Pri izvođenju svih zemljanih radova
with valid Montenegro standards- JUS pridržavati se važećih standarda u Crnoj Gori
U.E1.010; JUS U.E8.010; JUS U.S4.064.” - JUS U.E1.010; JUS U.E8.010; JUS
U.S4.064.“
U poglavlju 3.5 Geotehnički uslovi
fundiranja zida u nožičnom dijelu nasipa
In chapter 3.5 Geotechnical conditions for navedeno je: „Kako je planirani nasip velikih
foundation of wall in the embankment's toe dimenzija to nije bilo moguće na izlazu iz
it is stated as follow: “Since the size of the Suke formirati nasip a da se ne ugrozi
planned embankment is great, it will be magistralni put. Iz tog razloga je planiran
impossible to build it at exit from the Suka potporni nožični zid u ovom dijelu dužine oko
tunnel without jeopardizing the motorway. 90 m (prilozi 1 i 2).
Therefore, it is planned to build a toe wall at
Izvođenjem istražnih raskopa i dvije istražne
this section, in length of cca 90 m (App.1 and
bušotine ovdje će temeljno tlo na većem dijelu
2).
biti fluvio-glacijalni materijal odličnih
Execution of trial pits and two boreholes in karakteristika tj. IG jedinica fl-gl (šlj,kg) –
this section showed that the dominant geotehnička kategorija P3 (prilog br. 2.2).
foundation soil is made of fluvio-glacial
Na osnovu uvida u IG građu terena u ovoj
materials with excellent properties, i.e. EG
zoni preporučuje se fundiranje zida u fluvio-
units fl-gl (šlj,kg) – geotehchnical category P3
glacijlanom materijalu sa dubinom fundiranja
(ppendix. 2.2).
od minimum 1 m u geotehničkoj sredini P3.

37
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Having in mind the EG structure of terrain in Takođe je potrebno zadovoljiti uslov da


this section, it is recommended to found the ukupna dubina fundiranja ne može biti manja
wall in fluvio-glacial material with the od 1.5 m dubine.
foundation depth of minimum 1 m in the
Na početku zida se javlja nešto deblji sloj
geotechnical unit P3. Also, the total
geotehničke sredine P2, dok u nastavku ona
foundation depth should not be less than 1.5
izostaje.
m.
U ovom početnom dijelu, dužine oko 20 m
The geotechnical Unit P2 is present in slightly
debljina P2 kategorije je veća te se
greater thickness at the wall's beginning
preporučuje fundiranje u kategoriji P2, ali uz
section, whereas further it is absent.
uslov da kota temeljnog iskopa bude 4 m niža
In this beginning section, which is cca 20 m od linije terena sa nizbrdne strane tj. moguće
long, thickness of P2 category is greater. This je fundiranje ako je najmanja dubina
is why foundation should be performed in temeljnog iskopa 4 m. Nakon toga je potrebno
category P2, providing that elevation of uraditi nasipanje oko 1 m dobro granuliranog
foundation excavation is 4 m lower than the tamponskog materijala koji je potrebno zbiti
ground line from downhill side, i.e. foundation na 100 MPa.
is feasable if minimum depth of foundation
Takođe postoji mogućnost uklanjanja
excavation is 4 m. Subsequently, it is required
kompletne kategorije P2 u temeljnom iskopu i
to fill the ground with around 1m of well
zamjena tog materijala sa mršavim betonom
grained subbase materials which should be
do potrebne kote.
compacted to 100 Mpa.
Teren u okviru izdvojenih kategorija P3 i P2
Also, it is also possible to remove complete
je dobro nosiv za projektovana opterećenja i
category P2 from the foundation excavation
sa vrlo malim primarnim slijeganjem.
and to replace that material with lean concrete
up until the given elevation.
The terrain within the defined categories P3 U poglavlju 4 ZAKLJUČAK navedeno je:
and P2 has good bearing capacity for „Na osnovu svih dopunskih istraživanja koja
designed loads and small primary settlement. su urađena za potrebe definisanja IG građe
terena u zoni između Suke i Vežišnika može se
In chapter 4 CONCLUSION it is stated as
konstatovati da je izgradnja nasipa moguća uz
follow: “With regard to all additional
poštovanje svih preporuka datih u ovom
investigations performed for definition of EG
Elaboratu.
structure of field between the Suka and
Vežišnik tunnels, it can be concluded that Na terenu, a samim tim i na grafičkim
construction of the embankment is executable prilozima su odvojeni tehnogeni sedimenti
if all suggestions given in this Elaboration are (nasip), koluvijalno-deluvijalni materijali,
respected. fluvio-glacijalni materijali kao i krečnjačka
osnova. U okviru ovih IG jedinica su
Technogenic sediments (embankment),
izdvojene različite geotehničke kategorije.
colluvial-deluvial materials, fluvio-glacial
materials and limestone base were marked on Na osnovu svih detaljno obrađenih terenskih,
site and, accordingly, in drawings. Various laboratorijskih i kabinetskih podataka
geotechnical categories were differentiated in izdvojene mjerodavne i reprezentativne
these EG units. geotehničke sredine koje imaju različite
karakteristike, a prije svega različite fiz.-meh.
On the basis of all in detail processed field,
parametre koji su neophodni za adekvatno
laboratory and cabinet data, we established

38
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

representative and important geotechnical projektovanje kako nasipa tako i nožičnog


units with their authentic properties, i.e. zida.
different phyical and mechanical parameters
Za definisanje prostornog zalijeganja
required for adequate design of both the
korišćeni su svi podaci dobijeni terenskim
embankment and its toe section.
istraživanjem kao i analizom geomorfologije
ovog dijela terena.
All data obtained from the field investigations Nosivost terena nije problematična dok će
as well as by analysing the geomorphology of slijeganja biti mala ili čak zanemarljiva u
this field section were used for definition of the pojedinim geotehničkim kategorijama.
spatial dip and strike. Svakako da je potrebno postaviti model i
odrediti prognozna slijeganja. Kolike kod
Soil bearing capacity is not problematic, while
vrijednosti budu dobijene bitno je da će ta
settlements will be small or even neglectible in
slijeganja biti obavljena tokom gradnje
some geotechnical categories. Surely it will be
objekata.
required to establish a model and define
prognostic settlements. No matter how many Što se tiče stabilnosti terena kao što je i
high values are obtained, it is important that definisano u prethodnim poglavljima, teren je
settlements will finish during the construction. stabilan za varijantu izrade nasipa sa
standardizovanim krečnjačkim materijalom.
Ono što je navedeno i definisano u Elaboratu
When the terrain stability is concerned, as
je potrebno od strane nadzornog Inženjera
defined in the previous chapters, the terrain is
pratiti na terenu i u svakom momentu kada
stable for variant of embankment construction
realno stanje na terenu odstupa od onog
with use of standardized limestone materials.
definisanog u Elaboratu potrebno je reagovati
The supervising Engineer should monitor the i izvršiti potrebnu izmjenu rešenja i
compliance of field works with this dokumentacije kako bi objekti i teren bili
Elaboration, and at any moment when a real sigurni i stabilni u budućnosti prilikom
situation on site deviates from this Elaboration eksploatacije autoputa.“
it is required to react and modify the solution
and documentation accordingly, so that the
terrain and structures will remain secured and
stable during the Highway exploitation in
future.”

39
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Picture 1: Main Design – EG Map km LK 1+127 – 1+243; DWG No. 1.2; Design code:
BBC**0MO003GL02
Slika 1: Glavni projekt – IG karta km LK 1+127 – 1+243; Crtež br. 1.2; Šifra projekta:
BBC**0MO003GL02

40
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Picture 2: Main Design – Detailed EG map with layout drawing of Investigated works; DWG No. 1;
Design code: BBC011TR_001GL03 (for option of MSE wall supported by ballast)
Slika 2: Glavni projekt – Detaljna IG karta sa položajem izvedenih istražnih radova; Crtež br. 1; Šifra
projekta: BBC011TR_001GL03 (za varijantu MSE zida sa balastnim materijalom)

41
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Picture 3: Main Design – Detailed EG map with layout drawing of Investigated works; Appendix No. 1;
Design code: BBC011TR_01GL04 (for option of Embankment with retainiing toe wall)
Slika 3: Glavni projekt – Detaljna IG karta sa položajem izvedenih istražnih radova; Prilog br. 1; Šifra
projekta: BBC011TR_01GL04 (za varijantu nasipa sa potpornim nožićnim zidom)

42
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

3.2. Technical comments 3.2. Tehnički komentari


Described “Unforeseeable geological Opisani „Nepredvidivi geološki uslovi“
condition” is manifested mostly as changed manifestuju se uglavnom kao izmjenjena
geotechnical environment of the MSE wall geotehnička sredina fundiranja zida od armirane
foundation (loose scree material instead zemlje (siparski materijal umjesto
forecasted limestones). prognoziranih krečnjaka).
In remedial measures Contractor designed: U korektivnim mjerama Izvođač je projektovao:

 Ballast (backfilling material) outside the  Balast (materijal za zatrpavanje) van kosine
foundation slope of the foundation – in the temelja – u prvom prijedlogu izmjene
first proposal of the Main Design change Glavnog projekta
Contractor haven’t took into consideration Izvođač nije razmotrio mogućnost
possibility of designing of some other solution projektovanja nekog drugog rješenja (klasični
(general embankment), even the Designer of nasip), iako je projektant Elaborata o
Elaboration on Additional Geotechnical dopunskim geotehničkim istraživanjima i
Investigations and Engineering-Geological inženjersko-geološkim odlikama terena u
Pproperties in area of the Open Route Section zoni dijela otvorene trase zid od armirane
Planned for the Reinforced Soil Retaining zemlje, stacionaža RK 1+093 – 1+334
Wall, Chainage RK 1+093 - 1+334 stated as konstatovao slijedeće: „Analizom je utvrđeno
follow: “Stability analysis shows that the field da se u uslovima opterećenja od armirane
is in state of boundary equilibrium under zemlje i od saobraćaja kosina nalazi u stanju
natural conditions and load from traffic and granične ravnoteže i da je u slučaju
reinforced soil. It is recommended to build a seizmičkog uticaja faktor sigurnosti ispod 1,
small ballast on the section where the odnosno da je potrebno uraditi osiguranje.“
reinforced soil will rely onto the scree
Nakon negativnog Izvještaja o reviziji izmjene
materials.”
Glavnog projekta –Verzija 4, (Prilog 30), DKR
After negative Report on review of the Main je „toplo preporučila Izvođaču da razmotri
Design change – Version 4, (Enclosure 30) SRP alternativna rješenja“, nakon čega je Izvođač
“strongly recommend to the Contractor to počeo sa procesom izmjene Glavnog projekta u
consider alternative solutions”, and after the tom smjeru.
Contractor started with MD change process in
Tokom cijelog postupka izmjene Glavnog
this direction
projekta evidentno je da je Izvođač pokušavao
During the entire process of the Main Design maksimalno reducirati troškove; smanjenjem
change it is evident that the Contractor tried to dubine istražnih bušotina za varijantu zida od
reduce the cists maximally; by reducing of armirane zemlje (sa balastom), kao i
borehole drilling depth for the variant of MSE neuvrštavanjem istražnih bušotina u zoni
wall (with ballast), as well as by not including of potpornog AB zida u varijanti visokog
the boreholes in the zone of RC retaining wall in klasičnog nasipa (30+ m), djelomično
the variant of the high embankment (30+ m), poduprtog AB potpornim nožićnim zidom.
partly supported by a toe wall.
Evidentno je da je navedena lokacija korištena
It is evident that mentioned location was used as kao privremena deponija materijala iz iskopa
the mucking area for excavated material from tunela Suka i Vežešnik. Deponovani materijal
tunnels Suka and Vezesnik. Stockpilled material nije uklonjen sa lokacije, što je evidentno i iz
wasn’t removed from the location, and it is navedenih Izvođačevih dokumenata, gdje je
obvious from mentioned Contractor’s navedeno: „Kao osnovna preporuka, što je i

43
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

documents, where is stated: “A basic idejom planirano jeste da se ukloni sav nasuti i
recommendation, which was an initial idea, is to nabacani materijal sa lokacije.“
remove all filled and thrown materials from this
location.”

Picture 4: Main Design – High embankments that covered the natural ground; Design code:
BBC011TR_01GL04 (for option of Embankment with retainiing toe wall)
Slika 4: Glavni projekt – Veliki nasipi koji su prekrili prirodan teren; Šifra projekta:
BBC011TR_01GL04 (za varijantu nasipa sa potpornim nožićnim zidom)

44
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

3.3. Technical conclusion 3.3. Tehnički zaključak


In his supporting documents, Contractor U pratećim dokumentima, Izvođač je objasnio
explained unforeseeable geological conditions as nepredvidive geološke uslove kao posljedice:
a consequences of:
 Izmijenjene geotehničke sredine fundiranja
 Changed geotechnical environment of the zida od armirane zemlje (siparski materijal
MSE wall foundation (loose scree material umjesto prognoziranih krečnjaka).
instead forecasted limestones).
To je u skladu sa zaključcima iz Idejnog
It is in line with conclusions from Preliminary projekta.
Design.
Otkinuti materijal se na relativno blažim
Removed material stays on relatively less steep delovima padine zadržava, odnosno, formira
sections of the slopes, i.e. forming numerious brojne aktivne sipare, karakterističnog
active scree loose materials, as it is already izduženog oblika, kako je i opisano u
described in the delivered Preliminary Design. dostavljenom Idejnom projektu.
Main issue in such geological conditions Osnovno pitanje u takvim geološkim uslovima
(surface loose scree material, usually up to 6 m (površinski siparski materijal koji je uobičajene
deep, and up to 20 m deep in the foult zones) is debljine do 6 m, a u rasjednim zonama i preko
choosing of structure, bearing in mind limited 20 m) je odabir konstrukcije, obzirom na
founding conditions. limitirane uslove fundiranja.
Also, the reason of Contractor’s execution of Takođe, nejasan je razlog zbog kojeg je u fazi
trial pits only in the phase of geotechnical geotehničkih istraživanja Izvođač izveo
investigations for this MSE wall is unclear. isključivo istražne raskope za ovaj zid od
armirane zemlje.
It seems logical to add a necessary investigations
to confirm a position of the basic rock. By acting Bilo bi logično dodati potrebne istražne radove
on that way, thick layer of loose scree material koji bi potvrdili položaj osnovne stijene. Na taj
will be confirmed in earlier stage and necessary način ranije bi bio potvrđen siparski sloj velike
Main Design change will be prepared and debljine i potrebna izmjena Glavnog projekta
approved in early stage of the Project, so thus bila bi pripremljena i odobrena u ranoj fazi
will avoid unnecessary waiting and numerous Projekta, čime bi se izbjeglo nepotrebno
revisions. čekanje i brojne revizije.
Due to a small volume of geotechnical Uslijed malog obima geotehničkih istraživanja
investigations performed for the Main Design, as za potrebe Glavnog projekta, kao i debljine
well as a scree material thickness significamtly sloja sipara znatno veće debljine od
bigger than expected, additional geotechnical pretpostavljene, bilo je potrebno izvesti dodatna
investigations should be performed. geotehnička istraživanja.
Mentioned parts of Contractor’s design Navedeni dijelovi Izvođačeve projektne
documentation shows that additional dokumentacije pokazuju da su dodatna
geotechnical investigations were mandatory, geotehnička istraživanja bila nužna, uzevši u
taking into account impossible founding of MSE obzir da je bilo nemoguće fundirati zid od
wall (without ballast material) in tranquilized armiranog tla (a bez balastnog materijala) u
loose screes. umirenim siparima.
Also, after logical change of MSE wall with Takođe, nakon logične izmjene zida od

45
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

ballast solution by the solution of heigh armirane zemlje sa balastom rješenjem visokog
embankment supported by toe wall, it was nasipa sa nožićnim potpornim zidom, bilo je
necessary to perform additional geotechnical potrebno odraditi dodatne geotehničke istražne
investigations in order to confirm a foundation radove u svrhu potvrđivanja temeljnog tla za
soil for a toe wall. fundiranje nožićnog potpornog zida.
It is important to highlight that removal of the Važno je napomenuti da je uklanjanje deponije
stock pile of excavated material from Suka and materijala iz iskopa tunela Suka i Vežešnik
Vezesnik tunnels excavation started after final počelo tek nakon konačnog odobrenja izmjene
approval of the Main Design change (heigh Glavnog projekta (varijanta visokog nasipa sa
embankment with toe wall solution), even it was nožićnim potpornim zidom), iako je to bilo
necessary to do as the site preparation for any potrebno učiniti u pripremi gradilišta za bilo
solution; showing that Contractor didn’t have a koju varijantu; iz čega se da zaključiti da
possibilities to remove stockpiled excavated Izvođač nije imao mogućnosti ukloniti odloženi
material in earlier stage, either didn’t showed iskopani materijal ranije, niti je za to pokazao
any interest to do so. interes.

46
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

4. GENERAL DESCRIPTION 4. OPŠTI OPIS


Dropping process Proces odronjavanja
By mapping of the terrain, locations where or at Kartiranjem terena registrovane su lokacije na
which rock masses of greater volume may have kojima je već došlo, ili na kojima može doći, do
occurred by dropping process have been odronjavanja stenskih masa veće zapremine.
registered. It has been observed that the Uočeno je da su pojave osipanja i odronjavanja
occurrences of rash and fall are concentrated on koncentrisane na strmim ogoljenim stenama,
steep stripped rocks, that is, on steep sections odnosno, na strmim odsecima (ekskarpmani)
(excarpmans) up to several tens, even hundreds visine i do nekoliko desetina, pa i stotina
of meters high. The tear-off material lingers on metara. Otkinuti materijal se na relativno
relatively milder parts of the slope, that is, forms blažim delovima padine zadržava, odnosno,
numerous active screes, with a characteristic formira brojne aktivne sipare, karakterističnog
elongated shape. The locations of these izduženog oblika. Lokacije ovih pojava su
occurrences are indicated by appropriate prikazane odgovarajućim oznakama na
markings on the engineering-geological map. inženjerskogeološkoj karti. Taj materijal je
This material is poorly complex, unstable and slabo složen, nestabilan i podložan stalnom
subject to constant movement. Screes and loose kretanju. Sipari i osuline formirane od
materials formed from the collapsed material are, obrušenog materijala su, samo manjim delom,
to a lesser extent, fossilized and subdued by fosilizovani i umireni vegetacijom (uz Moraču).
vegetation (along Moraca). Dropping of smaller Odronjavanje manjih blokova, metarskih
blocks, measuring in meters, takes place mainly dimenzija, odvija se uglavnom iz zaostalih
from stunts or steep cliffs, from hypsometrically ostenjaka ili strmih litica, iz hipsometrijski viših
higher zones. Most landslides occur after heavy zona. Do odrona najčešće dolazi nakon velikih
rainfall and during periods of sudden snow kiša i u periodima naglog topljenja snega, pri
melting, with rising temperatures. porastu temperature.
This process is generally represented from Ovaj proces generalno je zastupljen od
Smokovac to Bioča, in particular from km 0 + Smokovca do Bioče, a naročito izražen od st
800 to 1 +000 and km 3 + 300 to 3 +450. km 0+800 do 1 +000 i km 3+300 do 3 +450.
Quaternary age creations are represented by Tvorevine kvartarne starosti predstavljeni su
terraced glaciofacial deluvial-eluvial sediments terasnim glaciofacijalnim deluvijalno-
and terra rossa. Generally, in genetic terms the eluvijalnim sedimentima i crvenicama.
following environments can be distinguished: Generalno, u genetskom smislu mogu se
izdvojiti sljedeće sredine:
1. Terraced sediments are sandy-gravel
materials, that is, weaker and more strongly 1. Terasni sedimenti su šljunkovito-pjeskoviti
bounded conglomerates. They are represented on materijali, odnosno slabije i jače vezani
the right and left sides of the road from konglomerati. Zastupljeni su sa desne i
Smokovac to Bioča in the Morača Valley. These lijeve strane puta od Smokovca do Bioča u
are terraced deposits with sub-surface dark black dolini Morače. To su terasne naslage, kod kojih
and dusty sandy clays, from 0.5 to 1 m thick, can se mogu izdvojiti pripovršinske mrko crne i
be separated. With depth, the size of the gravel prašinaste pjeskovite gline, debljine od 0,5 do 1
grains increases and gradually these sediments m. Sa dubinom veličina zrna šljunka se
become conglomerates, where the grains are povećava i postepeno ovi sedimenti prelaze u
bound by clay and calcite binders. Several konglomerte, gdje su zrna vezana glinovitim
terraces were found, separated from each other i kalcitskim vezivom. Konstatovano je više
by cascades up to 1 m high. terasa, koje su međusobno odvojene

47
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

2. Deluvial deposits are of heterogeneous kaskadama visine do 1 m.


lithological composition. It is mainly dominated
2. Deluvijalne naslage su heterogenog
by limestone debris with sandy-dusty clay. These
litološkog sastava. Uglavnom dominira drobina
deposits are linked to the lower parts of the
krečnjaka sa pjeskovito-prašinastom glinom.
slopes, above the fluvio-glacial terraces.
Ove naslage su vezane za niže delove padina,
3. The terra rossa is represented at the bottom of iznad fluvio-glacijalnih terasa.
the sinkholes
3. Crvenica je zastupljena po dnu vrtača

5. PRELIMINARY DESIGN 5. IDEJNI PROJEKAT


We refer to the Elaborate of detailed Pozivamo se na Elaborat detaljnih

48
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

geotechnical investigations for the geotehničkih istraživanja za izradu Idejnog


development of the preliminary design; projekta; Dionica: Podgorica – Veruša km
Section: Podgorica - Veruša km 0 + 000 - 33 + 0+000 – 33+000 – Separat za otvorenu trasu,
000 – Separate for the Open route, which u kojem je navedeno slijedeće:
states the following:
ZONA 2 st km 1+081,70 - 1+352,70 (desna )
ZONE 2 CH km 1+081,70 – 1+352,70 (right) D = 271,00 m; st km 1+125,30 - 1+324,431
D = 271,00 m; CH km 1+125,30 – 1+324,431 (leva) L = 199,01 m
(left) L = 199,01 m
„Na ovoj zoni dužine 200-270 m (leva traka)
“In this zone in length 200 – 270 m (left lane) put će biti u zaseku ili useku dubine oko 10 m.
road will be in cut around 10 m deep. It is To je u suštini predusek tunela koji predstavlja
basically a tunnel open cut representing next sledeću zonu trase.
zone of the route.
Kosina zaseka-useka će se izvoditi u
Slopes in cuts will be executed in banked to krečnjacima bankovite do slojevite teksture sa
layered texture limestones, with dip towards hill padom slojeva u brdo pod uglom od 5-20°.
5-20⁰. Slopes will be mostly formed along the Kosine će se najvećim delom oformiti duž
joints perpendicular to stratification, i.e. dip 3:1 pukotina upravnih na slojevitost, tj. sa
to 4:1. nagibima od 3:1 do 4:1. Eventualne lokalne
labilne blokove treba ukloniti, a kosinu štititi
Eventual local unstable blocks should be putarskom mrežom. Vršne delove kosina, na
removed, and slope should be protected with mestima gde preko krečnjaka leže tanje naslage
hexagonal mesh. Top parts of the slopes with deluvijalnih materijala, treba posebno zaštititi
thinner diluvial compositions should be treated od spiranja i osipanja. Obzirom da se desna
especially from washing out and loosing. Due to traka praktično polaže po tlu, preporučuje se
a fact that right lane is situated on the ground, it jedinstven iskop za obe trake sa kontinualnim
is recommended to perform a unique excavation platoom za kolovozne konstrukcije i jednim
for both lanes with continual platform for the zasekom sa leve strane. Ovu zonu reprezentuje
road constructions and a cut at left hand side. dva profila: profil br. 3 st. km 1+150, prilog
This zone is represented with two profiles: 2.1 profil br. 4 st. km 1+275, prilog 2.1.“
profile No. 3 CH km 1+150, attachment 2.1
profile No. 4 CH km 1+275 attachment 2.1. "

We refer to the PARCIAL REPORT on Pozivamo se na PARCIJALNI IZVJEŠTAJ o


geotechnical research for the preparation of geotehničkim istraživanjima za izradu
geotechnical documentation for the level of geotehničke dokumentacije za nivo Idejnog
preliminary design, for the Bar - Boljare projekta, za autoput Bar – Boljare; Dionica:
highway; Section: PODGORICA - VERUSA PODGORICA– VERUŠA dio: km 0+000 do
part: km 0 + 000 to 12 + 000 (Smokovac- 12+000 (Smokovac-Klopot), u kojem je
Klopot), which states the following: navedeno slijedeće:

Zone 4 - open route (km 1+198 to km 1+259) Zona 4 – otvorena trasa (st. km 1+198 do km
1+259)
In this zone in approximate length of 60 m (left
lane) road will be in semi-cut or cut 10 m deep. Na ovoj zoni dužine oko 60 m (leva traka) put
It is basically a tunnel open cut representing će biti u zaseku ili useku dubine oko 10 m. To je
next zone of the route. u suštini predusek tunela koji predstavlja
sledeću zonu trase.
Slopes in cuts will be executed in banked to

49
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

layered texture limestones, with dip towards hill Kosina zaseka-useka će se izvoditi u
5-20⁰. Slopes will be mostly formed along the krečnjacima bankovite do slojevite teksture sa
joints perpendicular to stratification, i.e. dip 3:1 padom slojeva u brdo pod uglom od 5-20°.
to 4:1. Kosine će se najvećim delom oformiti duž
pukotina upravnih na slojevitost, tj. sa
Eventual local unstable blocks should be nagibima od 3:1 do 4:1.
removed, and slope should be protected with
hexagonal mesh. Top parts of the slopes with Eventualne lokalne labilne blokove treba
thinner diluvial compositions should be treated ukloniti, a kosinu štititi putarskom mrežom.
especially from washing out and loosing. Due Vršne delove kosina, na mestima gde preko
to a fact that right lane is situated on the krečnjaka leže tanje naslage deluvijalnih
ground, it is recommended to perform a unique materijala, treba posebno zaštititi od spiranja i
excavation for both lanes with continual osipanja. Obzirom da se desna traka praktično
platform for the road constructions and a cut at polaže po tlu, preporučuje se jedinstven iskop
left hand side. " za obe trake sa kontinualnim platoom za
kolovozne konstrukcije i jednim zasekom sa
leve strane.
The possibility of the presence of Quaternary
sediments – scree looses is present on the said
section of the highway and is foreseen in the Mogućnost prisutnosti kvartarnih sedimenata -
early stages of the Project. Therefore, in relation sipara prisutna je na pomenutoj dionici autoputa
to the Preliminary Design, the Supervisory i predviđena su u ranim fazama Projekta. Dakle,
Authority confirms that the Designers of the u odnosu na Idejni projekat, Nadzorni organ
Preliminary Design (geological part: Elaborate potvrđuje da su ga projektanti Idejnog projekta
of detailed geotechnical Investigations for the (geološki dio: Elaborat detaljnih
preparation of the Preliminary Design; geotehničkih istraživanja za izradu Idejnog
Section: Podgorica - Veruša km 0 + 000 - 33 + projekta; Dionica: Podgorica – Veruša km
000 and PARTIAL REPORT on geotechnical 0+000 – 33+000 – Separat za otvorenu trasu,
research for the preparation of geotechnical kao i PARCIJALNI IZVJEŠTAJ o
documentation for the level of the preliminary geotehničkim istraživanjima za izradu
design, for the highway Bar - Boljare; Section geotehničke dokumentacije za nivo Idejnog
PODGORICA-VERUŠA part: km 0+000 to projekta, za autoput Bar – Boljare; Dionica:
12+000 (Smokovac-Klopot) potential problem PODGORICA– VERUŠA dio: km 0+000 do
was forseen and it was stated: “…Top parts of 12+000 (Smokovac-Klopot) predvidjeli
the slopes with thinner diluvial compositions potencijalni problem, za koji je navedeno:
should be treated especially from washing out „....Vršne delove kosina, na mestima gde preko
and loosing…” krečnjaka leže tanje naslage deluvijalnih
materijala, treba posebno zaštititi od spiranja i
osipanja...“
We are reffering to the Elaborate of detailed Pozivamo se na Elaborat detaljnih
geotechnical Investigations for the geotehničkih istraživanja za izradu Idejnog
preparation of the Preliminary Design; projekta; Dionica: Podgorica – Veruša km
Section: Podgorica - Veruša km 0 + 000 - 33 + 0+000 – 33+000 – Separat za otvorenu trasu;
000 - Separate for the Open route; Enclosure Prilog 1.1 - Inženjerskogeološku karta st.
1.1 – Engineering-geological map CH km km od 0+100 do 2+000; gdje su u Zoni 2 jasno
from 0+100 to 2+000; where the Quaternary naznačeni kvartarni sedimenti – dl –
sediments are clearly marked on the map – dl – Deluvijum, padinski nanos – zaglinjena
Dilluvium, slope deposition – clayey debris. drobina.

50
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Picture 5: Elaborate of detailed geotechnical Investigations for the preparation of the Preliminary Design;
Section: Podgorica - Veruša km 0 + 000 - 33 + 000 - Separate for the Open route; Enclosure 1.1 –
Engineering-geological map CH km from 0+100 to 2+000 (Enlarged part of the Zone 2)
Slika 5: Elaborat detaljnih geotehničkih istraživanja za izradu Idejnog projekta; Dionica: Podgorica –
Veruša km 0+000 – 33+000 – Separat za otvorenu trasu; Prilog 1.1 - Inženjerskogeološku karta st. km od
0+100 do 2+000 (Uvećani dio zone 2)

6. CONCLUSION ON PRELIMINARY 6. ZAKLJUČAK U VEZI SA IDEJNIM


DESIGN PROJEKTOM

51
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

Taking into account main purpose of the Uzimajući u obzir glavnu svrhu Idejnog
Preliminary Design to provide an input data to projekta da obezbijedi ulazne podatke za
Design-and- Built Contractor; by relatively low, izvođača radova na projektovanju i izgradnji;
but sufficient level of geotechnical relativno niskim, ali dovoljnim nivoom
investigations, occurrences of Quaternary geotehničkih istraživanja, pojave kvartarnih
sediments in the form of deposits of variable sedimenata u vidu naslaga sipara promjenjive
thickness screes are described in the debljine opisane su u Geotehničkom izvještaju.
Geotechnical Report. All mentioned documents Svi navedeni dokumenti bili su dostupni
were available to the Contractor in the tendering Izvođaču u tenderskoj fazi Projekta.
stage of the Project.
Takođe, svrha geotehničkih istraživanja za nivo
Also, the purpose of geotechnical investigations Glavnog projekta svakako je dobivanje
for the level of the Main Design is certainly to pouzdanih geomehaničkih parametara u zonama
obtain reliable geomechanical parameters in the navedenim kao kritične u okviru Idejnog
zones listed as critical within the Preliminary projekta. Jedna od takvih zona svakako je i
Design. One such zone is certainly the zone zona navedena u ovom Događaju potraživanja,
mentioned in this Claim Event, bearing in mind imajući na umu navod iz Idejnog projekta, a
the statement from the Preliminary Design, koji se odnosi na zone prekrivene sipariskim
related to the zones covered with scree loose materijalima: „...Ovaj proces generalno je
materials: “...This process is generally zastupljen od Smokovca do Bioče, a naročito
represented from Smokovac to Bioča, in izražen od st km 0+800 do 1 +000 i km 3+300
particular from km 0 + 800 to 1 +000 and km 3 do 3 +450.“
+ 300 to 3 +450."
Očekivana reakcija svjetski priznatog Izvođača,
Expected reaction of experienced and worldwide uzevši u obzir podatak dostupan u vrijeme
recognized Contractor, taking into account Ponude o postojanju sipara kartiranih na
available data from the Tender stage about the površini terena (napominjemo da na navedenoj
existence of scree loose material mapped on the lokaciji nisu rađene istražne bušotine u okviru
surface of the terrain (we are highlighting that Idejnog projekta – podaci su dobijeni
not any borehole was done in the frame of geološkim kartiranjem terena, što je uobičajeno,
Preliminary Design – data were given by imajući na umu nivo Projekta – Idejni projekt) i
geological mapping of the terrain, usual, bearing kompleksnosti projektovane konstrukcije
in mind the Design level – Preliminary Design) (visoki nasip od armirane zemlje) bila bi
and complexity of designed structure (heigh detaljnije istraživanje u svrhu dobivanja ulaznih
MSE wall) will be more detail investigation in geotehničkih parametara za izradu Glavnog
order to get geomechanical input parameters for projekta. To i je glavni smisao geotehničkih
preparation of the Main Design. This is the main istraživanja za nivo Glavnog projekta.
reason of GI for level of the Main Design.
Imajući na umu sve gore navedeno, kao i
Bearing in mind all above mentioned, as well as činjenicu da se pomenute informacije smatraju
the fact that mentioned information is considered dovoljnim za nivo Idejnog projekta, kao i
as sufficient for the level of Preliminary Design, činjenicu da je Izvođač radova na projektovanju
as well as the fact that Design and Built i izgradnji iskusan i svjetski priznat Izvođač, sa
Contractor is experienced and worldwide prethodnim poznavanjem sličnih radova u
recognized Contractor, with previous knowledge sličnom okruženju, mišljenje Nadzornog organa
of similar Works in similar environment, the je da se pomenuti fenomeni ne mogu tretirati
Engineer's opinion is that mentioned kao nepredvidivi geološki uslovi.
phenomena’s cannot be treated as Unforeseeable
Geological Conditions.

52
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

7. CONTRACTOR'S CLAIM ANALIZY 7. ANALIZA POTRAŽIVANJA


IZVOĐAČA RADOVA
In this Expert's Witness Report we have also
analysed Contractor's Claim No. 128, 132 and U ovom Stručnom Izvještaju Inženjera smo

53
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

132/1 for Additional Payment (AP) (under SC analizirali Potraživanje izvođača br. 128, 132 i
20.1) and Extension of time (EoT); with new 132/1 za dopunsko plaćanje (pod SC 20.1) i
completion date (05 February 2021). Our produžetak roka za završetak radova 230 dana).
clarification is follow:
U dostavljenom Izvođačevom potpunom
In Contractor’s submitted Fully Detailed detaljnom sveobuhvatnom potraživanju –
Overall Claim – The Description of ERE Opis ERE shodno Potraživanju br. AP/EoT
Under Claim No. AP/EoT 128, Contractor 128, Izvođač je izjavio slijedeće:
stated as follow:
„Tokom pripremnih radova na nasipu od
“During the preparation work of the reinforced armiranog tla (MSE zid), na stacionaži RK
soil embankment (MSE wall) construction at 1+093 – RK 1+334 pronađeno je nepovoljno
chainage RK 1+093 – RK 1+334, the geološko stanje, kategorija P na dijelu zone
unfavourable geological condition – geological temelja u debljini većoj od 35,5 m...
category P was found at part of foundation zone
in thickness exceeding 35,5 m.
Očigledno je da se geološke informacije date u
Obviously, the geological information provided
Idejnom projektu razlikuju i istovremeno se
in Preliminary Design was different and at the
Izvođaču nije omogućilo da predvidi tako veliki
same time it could not enable the Contractor to
opseg geologije kategorije P s kojom se suočio
predict such large extent of the geology category
na gradilištu, a koja je prouzrokovala kašnjenje
P encountered on site, which have caused a
i remećenje napretka radova i za rezultat imala
delay and disruption to the progress of the
neplanirane dodatne troškove i gubitak
Works and resulted in unplanned additional
vremena.
costs and loss of time.
Opis slučaja rizika za poslodavca:
Description of Employer's risk event:
nepredvidivo fizičko stanje – izazvano
Unforeseeable Physical Condition – changes
promjenama u geološkim uslovima
of the geological condition
Izjava Nadzornog organa
The Engineer’s Statement
Poređenjem Idejnog projekta, zaključujemo da
By comparison of the Preliminary Design we are
su kvartarni sedimenti – dl – Deluvijum,
concluding that Quaternary sediments – dl -
padinski nanos – zaglinjena drobina
Dilluvium, slope deposition – clayey debris are
prikazani u Idejnom projektu; na mjestu na
showed in the Preliminary Design; at a place
kojem je naknadno utvrđena njihova debljina
where their thickness greater than 35.5 m was
veća od 35,5 m. Pozivamo se na Elaborat
subsequently determined. We are referring to
detaljnih geotehničkih istraživanja za izradu
Elaborate of detailed geotechnical
Idejnog projekta; Dionica: Podgorica –
Investigations for the preparation of the
Veruša km 0+000 – 33+000 – Separat za
Preliminary Design; Section: Podgorica -
otvorenu trasu; Prilog 1.1 -
Veruša km 0 + 000 - 33 + 000 - Separate for
Inženjerskogeološku karta st. km od 0+100
the Open route; Enclosure 1.1 – Engineering-
do 2+000 (slika 5).
geological map CH km from 0+100 to 2+000
(picture 5)

Podsjećamo da je Izvođač tri (3) puta izvodio


geotehnička istraživanja na navedenoj lokaciji:
We are reminding that the Contractor performed
GI three (3) times on the same location: 1. Geotehnička istraživanja u svrhu izrade
Glavnog projekta – 12/2015. godine
1. Geotechnical investigations for the purpose

54
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

of Main Design preparation – 12/2015 2. Dodatna geotehnička istraživanja u svrhu


2. Additional geotechnical investigations for izrade izmjene Glavnog projekta –
the purpose of the Main Design change – varijanta nasipa od armiranog tla s
MSE wall with ballast option – 06/2019 balastom – 06/2019. godine
3. Additional geotechnical investigations for 3. Dodatna geotehnička istraživanja u svrhu
the purpose of the Main Design change – izrade izmjene Glavnog projekta –
Embankment supported by toe retaining varijanta nasipa s nožićnim potpornim
wall – 12/2019 zidom – 12/2019. godine.
U sklopu Elaborata o detaljnim geotehničkim
istraživanjima za nivo Glavnog građevinskog
In the frame of Geotechnical Final Report for
projekta za otvorenu trasu (Smokovac – Tunel
Main Design for Open Route (Smokovac-
Suka; Tunel Suka – Tunel Vežešnik; Tunel
Tunnel Suka; Tunnel Suka -Tunnel Vežešnik;
Vežešnik – Most Mrke) (1) utvrđena je
Tunnel Vežešnik -Bridge Mrke) (1) category P
kategorija P u debljini do 8 m; uz napomenu da
up to 8 m thickness was determined; with the
nije izvođeno istražno bušenje u ovom diijelu
remark that no exploratory drilling was
trase.
performed in this part of the route.
U sklopu Elaborata o dopunskim geotehničkim
In the frame of Elaboration on Additional
istraživanjima i inženjersko-geološkim
Geotechnical Investigations and Engineering-
odlikama terena u zoni dijela otvorene trase na
Geological Properties in area of the Open Route
kojoj je planiran potporni zid od armirane
Section Planned for the Reinforced Soil
zemlje, stacionaža RK 1+093 - 1+334 (2)
Retaining Wall, Chainage RK 1+093 - 1+334 (2)
debljina kategorije P iznosila je 13,5 m; iz
thickness of category P in the range of 13,5 m
razloga što su bušotine umjesto uslova dubine
was determined; due to the fact that the
20 m ili uslova ulaska 2m u čvrstu stijenu
boreholes were shortened instead of the
skraćivane na zahtjev Izvođača kao naručioca
conditions of depth of 20 m or the conditions of
Elaborata, te navedena dubina odgovara dubini
entry into solid rock at request of the Contractor,
bušenja.
as the ordering party, and the stated depth
corresponds to the depth of drilling. U sklopu Elaborata o geotehničkim uslovima
izvođenja nasipa između tunela Suka i Vežešnik
In the frame of Elaboration on Geotechnical
od km RK 1+095 DO RK 1+334 (3) dubina
Conditions for Construction of Embankment
kategorije P utvrđena istražnim bušenjem
Between the Tunnels Suka and Vezesnik from
iznosila je 35,5 m. Sve bušotine su izvedene
km RK 1+093 to RK 1+334 (3) thickness of
tako da zadovolje kriterijum ulaska u fluvio-
category P in the range of 35,5 m was
glacijalni ili krečnjački materijal, a što nije bio
determined by exploration drilling. All boreholes
slučaj u prethodna dva istraživanja.
were complied with the criterium of entering
inside the fluvio-glacial or limestone materials,
which was not the case in the previous two
Sve gore navedeno dovodi do zaključka da je
studies.
posrijedi greška u projektu, a ne
All above mentioned leads to the conclusion that nepredvidivo fizičko stanje – izazvano
it is a design error and not an unforeseeablee promjenama u geološkim uslovima,
physical condition - caused by changes in uzimajući u obzir navode o siparskim
geological conditions, taking into account the materijalima u sklopu PARCIJALNOG
statements on scree materials from the IZVJEŠTAJA o geotehničkim istraživanjima
PARTIAL REPORT on geotechnical research za izradu geotehničke dokumentacije za nivo
for the preparation of geotechnical Idejnog projekta, za autoput Bar – Boljare;

55
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

documentation for the level of the preliminary Dionica: PODGORICA– VERUŠA dio: km
design, for the highway Bar - Boljare; Section 0+000 do 12+000 (Smokovac-Klopot), kao i
PODGORICA-VERUŠA part: km 0+000 to grafički prilog - Elaborat detaljnih
12+000 (Smokovac-Klopot), as well as drawing geotehničkih istraživanja za izradu Idejnog
- Elaborate of detailed geotechnical projekta; Dionica: Podgorica – Veruša km
Investigations for the preparation of the 0+000 – 33+000 – Separat za otvorenu trasu;
Preliminary Design; Section: Podgorica - Prilog 1.1 - Inženjerskogeološku karta st.
Veruša km 0 + 000 - 33 + 000 - Separate for km od 0+100 do 2+000 (slika 5).
the Open route; Enclosure 1.1 – Engineering-
Takođe, pozivamo se na navode Projektanta
geological map CH km from 0+100 to 2+000
Elaborata o detaljnim geotehničkim
(picture 5)
istraživanjima za nivo Glavnog
We are also reffering to the Designer’s građevinskog projekta za otvorenu trasu
statements from Geotechnical Final Report (Smokovac – Tunel Suka; Tunel Suka –
for Main Design for Open Route Tunel Vežešnik; Tunel Vežešnik – Most
(Smokovac-Tunnel Suka; Tunnel Suka Mrke), koji je konstatovao slijedeće:
-Tunnel Vežešnik; Tunnel Vežešnik -Bridge „Generalni geotehnički model terena za zonu 2
Mrke), with next statement: “General na potezu od izlaznog portala tunela Suka do
geotechnical terrain model for the zone 2 at the tunela Vežešnik (LK1+127-LK1+243;
stretch from the exit portal of Suka tunnel to RK1+091- RK1+348) je:
tunnel Vežešnik (LK1+127 - LK1+243;
- 0,0-8,0m umireni sipari od nevezane,slabije
RK1+091-RK1+348) is as follows:
do jače vezane krečnjačke drobine glinovitim i
- 0,0 - 8,0 m tranquilized screes of unbound, rjeđe kalcitskim vezivom (vezana sitna
poorly bound to highly bound limestone debris krečnjačka drobina drži se u vertikalnim
by clayey and rarely calcite binder (bound small zasjecima visine do 6m)...
limestone debris is held in a vertical side- cuts in
, kao i slijedeće: „Preporučuje se da se nožični
height of up to 6m)...
dio nasipa na ovom potezu (klasični nasip,
, as well as: „The footing part of the armirano tlo) fundira na krečnjaku ili izvrši
embankment at this stretch (classical osiguranje nasipa nožičnim potpornim zidom
embankment of reinforced soil) is recommeded sa pratećom drenažom.“
to found on limestone or to secure embankment
Projektant nije uzeo u obzir ove navode iz
by a low retaining wall and related drainage.“
Geotehničkog elaborata, te u Glavnom projektu
The Designer haven’t took into account this parts nije dao rješenje uklanjanja siparskog materijala
of the Final Geotechnical Report, so in the Main ili ojačanje nožićnim potpornim zidom (upravo
Design removal of scree loose material either to rješenje je na kraju prihvaćeno kao konačno).
reinforcing by the toe retaining wall wasn’t
Takođe, u svom potraživanju br. 128, 132 i
provided (this solution was adopted as the final).
132/1 Izvođač navodi slijedeće: „Iz gore
Also, in his claim No. 128, 132 and 132/1 navedenog se vidi da je za proces revizije
Contractor stated the following: “It follows from izmjene Glavnog projekta za nasip od
above that the review process of Main Design armiranog tla RK 1+093 – RK 1+334 trebalo
change for Reinforced Soil Enbankment RK 230 dana (18.07.2019. do 04.03.2020.) da se
1+093 – RK 1+334 took 230 days (18.07.2019 – završi, što je značajno produženo jer je DKR
04.03.2020) to complete, which was significantly preispitivala geotehničke informacije korištene
prolonged due to SRP questionioning of za ulazne podatke pri pravljenju izmjene
geotechnical imformation used as input for Glavnog projekta (tj. dubina bušotina, modul
making Main Design change(i.e. borehole depth, stišljivosti za kategoriju P))i preispitivala samo

56
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

compression module of category P) and the rješenje izmjene Glavnog projketa (tj. MSE zid
questioning of Main Design change solution se nemože temeljiti na kategoriji P1, i treba
itself (i.e. MSE wall cannot be founded in razmotriti alternativno rješenje)...
category P1, and the alternative solution should
Izjava Nadzornog organa
be considered)…
Ugovorom je definisano vrijeme revizije
The Engineer’s Statement
Glavnog projekta (28 dana), a iz Izvođačeve
Main Design review time (28 days) was defined prateće dokumentacije vidljivo je da niti jedan
in the Contract, and from Contractor’s Izvještaj o reviziji dostavljen od strane DKR-a
supporting documents it is observed that not a nije dostavljen izvan definisanog roka.
single Review Report submitted by the SRP was
Takođe, uzevši u obzir sve gore navedene i više
submitted outside the defined deadline.
puta ponavljane detalje komentara unutar
Also, taking into account all the above and Izvještaja revizije prijedloga izmjene Glavnog
repeated details of the comments within the projekta, osnovna namjera bila je dobivanje
Main Design Review Report of the Main Design stvarnih podataka o debljini umirenih
change proposal, the main intention was to nevezanih ili slabo vezanih sipara na lokaciji
obtain actual data on the thickness of izvođenja budućeg zida od armirane zemlje, ili
tranquilised unbounded or loosely bounded Izvođačev konkretan prijedlog odgovarajućeg
loose screes at the location of the future MSE prihvatljivog rješenja u skladu sa
wall, or the Contractor's specific proposal of the preporukama Elaborata.. Konačno rješenje
of a suitable solution in accordance with the odobrene izmjene Glavnog projekta identično je
recommendations from the Final preporuci Projektanta Elaborata o detaljnim
Geotechnical Report. The final solution of the geotehničkim istraživanjima za nivo Glavnog
approved change of the Main Design is identical građevinskog projekta za otvorenu trasu
to the recommendation of Designer of the Final (Smokovac – Tunel Suka; Tunel Suka –
Report for Main Design for Open Route Tunel Vežešnik; Tunel Vežešnik – Most
(Smokovac-Tunnel Suka; Tunnel Suka Mrke) – klasičan nasip sa nožićnim porpornim
-Tunnel Vežešnik; Tunnel Vežešnik -Bridge zidom.
Mrke) – classic embankment with toe retaining
Nadalje, komentar Izvođača o izvođenju
wall.
dodatnih istražnih bušotina za potrebe
Furthermore, Contractor’s comment on definisanja geotehničke sredine fundiranja
performing of the additional exploration nožićnog potpornog zida: „U izvještaju je DKR
boreholes executed in order to define a dala zahtjev da se još dvije bušotine trebaju
geotechnical environment for founding of the toe izvesti u temelju zida. To je opet bio novi
retaining wall: “In the report, SRP gave komentar, koji nije dat na Izvođačeve
requirement that two more boreholes should be prethodne podneske dodatka Projekta dodatnih
conducted at the foundation of the wall. This geotehničkih ispitivanja, gdje su već predložena
was again a new comment, which was not given rješenja za nasip i AB potporni zid...“ je
to Contractor’s previous submission of Annex to neopravdan, uzevši u obzir visinu samog
Design of additional geotechnical investigations, nožićnog potpornog zida, kao i generalnu visinu
whereby the embankment and RC retaining wall nasipa; a i činjenicu da je na ovoj lokaciji
solution was already proposed…” is unjustified, Izvođač uporno izbjegavao izvođenje
bearing in mind the height of the toe retaining istražnih bušotina u svrhu definisanja
wall itself, as well as a general height of the debljine sloja umirenih sipara.
embankment, and the fact that the Contractor
persistently avoided performing of
investigation boreholes at this location for the

57
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

purpose of defining the thickness of the layer


of tranquilised screes.
Takođe, neopravdan je bilo koji razlog zbog
Also, any reason is unjustifiable for which the kojeg Izvođač nije izveo predradnje potrebne za
Contractor did not perform the preparatory izvođenje bilo kojeg rješenja – uklanjanje
works required to perform any solution - deponovanog materijala iz tunelskih iskopa
removal of deposited material from the tunnel tunela Suka i Vežešnik, a što je preduslov
excavations of the tunnel Suka and Vežešnik, izvođenja sva tri predložena rješenja (zid od
which is a precondition for performing of all arnirane zemlje, zid od arnirane zemlje sa
three proposed solutions (MSE wall, MSE wall balastom i klasični nasip sa nožićnim
with ballast material and a classic embankment potpornim zidom.
with a toe retaining wall.
Formiranjem deponije materijala iz iskopa,
By forming of the landfill for excavated Izvođač je zanemario izvođenje ove zahtjevne
material, the Contractor neglected the konstrukcije (zida od armirane zemlje
construction of this complex structure (a MSE značajne dužine i visine) u ranoj fazi Projekta,
wall of significant length and height) in the te je početak radova bio u kasnoj fazi Projekta
early phase of the Project, and the start of works (prvo dostavljanje prijedloga izmjene Glavnog
was in the late phase of the Project (the first projekta nakon otkrivene veće debljine
submission of the Main Design change proposal umirenih sipara dana 18.07.2019. godine).
happen on 18 July 2019, after the discover of
tranquilized screes with significant thickness).
Takođe, smisao geotehničkih istraživanja za
Also, the purpose of geotechnical investigations
potrebe Glavnog građevinskog projekta je
for the needs of the Main Construction Design is
progušćavanje istraživanja na područjima koja
to condense investigations in areas that are
su ocijenjena kritičnima uvidom u geotehničku
assessed as critical by insight into the
dokumentaciju Idejnog projekta, u svrhu
geotechnical documentation of the Preliminary
dobivanja jasnije slike o mogućnosti fundiranja
Design, in order to obtain a clearer picture of the
i izgradnje objekata u stvarnoj geotehničkoj
possibility of funding and construction in real
sredini.
geotechnical environment.
Umireni sipari opisani su u sklopu geotehničke
The tranquilised screes were described as part of
dokumentacije u okviru Idejnog projekta, a u
the geotechnical documentation within the
okviru geotehničkih istraživanja za potrebe
Preliminary Design, and within the geotechnical
Glavnog projekta izvedeni su istražni raskopi
investigations for the needs of the Main Design
koji su završili u umirenim siparima. Takođe, u
trial pits were carried out, which ended in the
daljnjim dodatnim geotehničkim istraživanjima
tranquilised screes. Also, in further additional
izvođene su bušotine koje su uglavnom
geotechnical investigations, boreholes were
završavale u umirenim siparima, a skraćivane
performed, which mostly ended in tranquilised
su na zahtjev Izvođača (kao Naručioca ovih
screes, and were shortened at the request of the
istraživanja).
Contractor (as the ordering party of the
mentioned investigations). Iz svega navedenog nije jasan zahtjev za
produžetak radova od 230 dana.
From all the above, the request for the
extension of the time of 230 days is not clear. Nadzorni organ je uzeo u obzir stvarne fizičke
uslove uočene na lokaciji tokom događaja
The Engineer took into account actual physical
opisanih u ovom potraživanju Izvođača, kao i
conditions observed on the site during the events
dokaze o fizičkim uslovima koje Izvođač može
described in this Contractor's Claim, as well as
predvidjeti prilikom podnošenja ponude – na

58
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

the evidences of the physical conditions which raspolaganju Izvođaču.


may be foreseen by the Contractor when
Po mišljenju Nadzornog organa, Idejni projekat
submitting the Tender - available to the
- svi gore navedeni djelovi koji se odnose na
Contractor.
dio otvorene trase između tunela Suka i
As per the Engineer's opinion, Preliminary Vežešnik su validni dokumenti, poznati
Design – all the above mentioned parts related to izvođaču radova prilikom dostavljanja ponude.
open route stretch between tunnels Suka and Takođe, prekrivenost osnovne stijene umirenim
Vezesnik are valid documents, familiar to the siparima mogla se uočiti prilikom obilaska trase
Contractor when submitting the tender. Also, the u fazi pripremanja Ponude.
coverage of the base rock with tranquilized
Navedena Dokumentacija, koja je dio Idejnog
screes could be noticed during the tour of the
projekta, na osnovu izvedenih Geotehničkih
route in the phase of preparation of the Offer.
istraživanja (GI) za okvir Idejnog projekta daje
Above mentioned Documentation, part of the preliminarne ulazne geološke i geotehničke
Preliminary Design, based on executed podatke Izvođaču definisanjem opštih
Geotechnical Investigations (GI) for the frame of predviđenih geoloških uslova, pa donosimo
the Preliminary Design is providing preliminary slijedeći konačan zaključak:
input geological and geotechnical data to the
Tenderer by defining a general forecasted
geological conditions and please find final
conclusion as follow:

59
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

8. FINAL CONCLUSION 8. KONAČAN ZAKLJUČAK


Engineer's conclusion on Preliminary Design Zaključak Nadzornog organa o činjenicama u
facts is following: vezi sa Idejnim projektom je sljedeći:

 Mentioned Geotechnical elaborate was  Navedeni Geotehnički elaborat je urađen u


done for the purpose of providing an cilju obezbjeđivanja elementarnih
elementary Geotechnical data for the stage geotehničkih podataka za fazu Idejnog
of the Preliminary Design; projekta;
 Data were based on detailed Engineering –  Podaci su zasnovani na detaljnom
geological mapping of the area, inženjersko - geološkom istraživanju
Hydrogeological mapping and next onsite područja, hidrogeološkom kartiranju i
Geotechnical investigation works: Geoelectrical narednim geotehničkim istražnim
sondage and geophysical reffraction together radovima: Geoelektrična sondaža i
with compressive and tensile strength checking geofizička refrakcija zajedno sa provjerom
– as per the Engineer's point of view sufficient tlačne i vlačne čvrstoće – prema
for the stage of the Preliminary Design; Nadzornom organu dovoljnoj za fazu
Idejnog projekta;

 Contractor's description of this Claim event


is: “As in the Preliminary Design, which is  U obrazloženju ovog događaja potraživanja
the design documents provided by Izvođač navodi: “Kao u Idejnom projektu,
Employer at the tender stage, the geology koji predstavlja projektnu dokumentaciju
at the target zone was categorised as K22 koju je obezbijedio Investitor u fazi
(defined as dominanted by dolomites, Tendera, geologija ciljne zone je
dolomitic limestone) with barely existind kategorizovana kao K22 (definisana kao
dilluvial deposition on the surface. It is zona u kojoj dominiraju dolomiti,
therefore expected that MSE wall was dolomitični krečnjak) s jedva postojećim
directly located on the natural terrain with deluvijalnim nanosima na površini. Stoga
very limited excavation. je očekivano da će MSE zid biti smješten
 Obviously, the geological information direktno na prirodnom terenu, s
provided in Preliminary Design was ograničenom količinom iskopavanja.
different and at the same time it could not  Očigledno je da se geološke informacije
enable the Contractor to predict such large date u Idejnom projektu razlikuju i
extent of the geology category P istovremeno se Izvođaču nije omogućilo da
encountered on site, which have caused a predvidi tako veliki opseg geologije
delay and disruption to the progress of the kategorije P s kojom se suočio na
Works and resulted in unplanned additional gradilištu, a koja je prouzrokovala
costs and loss of time.” We are reffering to kašnjenje i remećenje napretka radova i za
the Elaborate of detailed geotechnical rezultat imala neplanirane dodatne
Investigations for the preparation of the troškove i gubitak vremena.” Pozivamo se
Preliminary Design; Section: Podgorica - na Elaborat detaljnih geotehničkih
Veruša km 0 + 000 - 33 + 000 - Separate istraživanja za izradu Idejnog projekta;
for the Open route; Enclosure 1.1 – Dionica: Podgorica – Veruša km 0+000 –
Engineering-geological map CH km from 33+000 – Separat za otvorenu trasu;
0+100 to 2+000; where in the Zone 2 Prilog 1.1 - Inženjerskogeološku karta
Quaternary sediments – dl - Dilluvium, st. km od 0+100 do 2+000; gdje su u Zoni

60
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

slope deposition – clayey debris are 2 jasno naznačeni kvartarni sedimenti – dl


showed; also part of delivered Preliminary – Deluvijum, padinski nanos –
Design zaglinjena drobina.; takođe dio
 By taking into consideration mentioned dostavljenog Idejnog projekta.
parts of the Elaborate of detailed  Uzevši u obzir navedene dijelove
geotechnical investigations for the Elaborat detaljnih geotehničkih
development of the preliminary design; istraživanja za izradu Idejnog projekta;
Section: Podgorica - Veruša km 0 + 000 - Dionica: Podgorica – Veruša km 0+000 –
33 + 000 – Separate for the Open route, 33+000 – Separat za otvorenu trasu, kao
as well as PARTIAL REPORT on i PARCIJALNOG IZVJEŠTAJA o
geotechnical research for the preparation geotehničkim istraživanjima za izradu
of geotechnical documentation for the geotehničke dokumentacije za nivo
level of the preliminary design, for the Idejnog projekta, za autoput Bar –
highway Bar - Boljare; Section Boljare; Dionica: PODGORICA–
PODGORICA-VERUŠA part: km 0+000 VERUŠA dio: km 0+000 do 12+000
to 12+000 (Smokovac-Klopot); the (Smokovac-Klopot); zaključak Inženjera
Engineer’s conclusion is that delivered je da je dostavljeni Idejni projekt u fazi
Preliminary Design in the Tender phase, Tendera, na osnovu kojeg je
base for the Offer preparation, providing pripremljena ponuda pruža Izvođaču
enough information to forseen exact dovoljnu informaciju na osnovu koje je
geological conditions. mogao predvidjeti stvarne geološke
uslove.
It is also unclear why the Contractor decided to
undertake a small (and unreliable) level of Takođe, nejasnan je razlog iz kojeg se Izvođač
geotechnical investigations for the preparation of odlučio na mali (i nepouzdani) nivo
the Main Design. By performing exclusively trial geotehničkih istraživanja u svrhu pripreme
pits, the necessary information on the depth of Glavnog projekta. Izvođenjem isključivo
the base rock was not obtained, which is crucial istražnih raskopa nije dobijena potrebna
for the design of a MSE wall, taking into informacija o dubini osnovne stijene, a što je
consideration a statement from the Technical ključno za projektovanje zida od armirane
Specifications: “All MSE walls will be founded zemlje, obzirom na navedeno iz Tehničke
on firm limestone. If at the designed foundation specifikacije: „Svi mehanički stabilizovani
level firm limestone is not found, the soil shall be zidovi se fundiraju u krečnjaku. Ukoliko se ne
furtherly excavated until firm limestone is pronađe čvrsti krečnjak na projektovanoj koti
found”. fundiranja, tlo se dalje iskopava dok se ne dođe
do čvrstog krečnjaka.“
In our view, the point of preparing the Main
Design is to detail the insufficiently elaborated Prema našem mišljenju, smisao pripreme
parts of the Preliminary Design, which was not Glavnog projekta je detaljiziranje nedovoljno
the case here. razrađenih dijelova Idejnog projekta, a što
ovdje nije bio slučaj.
The Engineer's opinion is that due to insufficient
degree of investigations, in the Main Design Mišljenje Inženjera je da se zbog nedovoljnog
phase a Design Error occurred - according to stepena istraženosti u fazi Glavnog projekta
SCl. 5.8 of the Contract Conditions, as a result dogodila Greška u projektu – prema Pkl. 5.8
of which the Contractor had to carry out Ugovornih Uslova, uslijed čega je Izvođač
additional geotechnical investigations and morao odraditi dodatna geotehnička istraživanja
prepare a modification of the Main Design i sukladno tome pripremiti izmjenu Glavnog
accordingly. projekta.

61
Supervision of Design and Works
on the Bar – Boljare Highway,
Section Smokovac – Uvač –
Mateševo

If errors, omissions, ambiguities, Ukoliko se u dokumentaciji Izvođača utvrde


inconsistencies, inadequacies or other defects greške, propusti, dvosmislenosti,
are found in the Contractor’s Documents, they neadekvatnosti i ostale manjkavosti, ona i
and the Works shall be corrected at the Radovi podležu korekcijama o trošku Izvođača,
Contractor’s cost, notwithstanding any consent bez obzira na bilo koju saglasnost ili odobrenje
or approval under this Clause. koje je bilo dato u skladu sa ovom klauzulom.
The Engineer’s opinion is that the failure Mišljenje je Inženjera da je do propusta došlo
resulted from poor selection and execution of lošim odabirom i izvođenjem nedovoljnih
insufficient geotechnical investigations – trial geotehničkih istraživanja – istražnim raskopima
pits did not confirm the depth of the basic rock nije potvrđena dubina osnovne stijene povoljne
favorable for foundation, which led to the za fundiranje, što je dovelo do neadekvatnosti
inadequacy of the approved Main Design odobrenog Glavnog projekta po pitanju
regarding the foundation of the MSE wall. fundiranja zida od armirane zemlje.
By comparison of above mentioned Engineer's Poređenjem gore navedenih zaključaka
conclusions with Sub-Clause 1.1.6.8. Nadzornog organa sa podtačkom 1.1.6.8.
Unforeseeable means not reasonably foreseeable Nepredvidivo predstavlja nešto što iskusni
by an experienced Contractor by the date for Izvođač razumno nije mogao da predvidi do
submission of the Tender; the Engineer's vremena podnošenja Ponude; Inženjer je
determination is that Experienced Contractor utvrdio da Iskusni Izvođač treba da predvidi sve
should foresee all available geotechnical / raspoložive geotehničke / geološke podatke do
geological data provided by the date for datuma za podnošenje ponude (što je glavna
submission of the Tender (what is a main svrha isporučenog Idejnog projekta, prema
purpose of Delivered Preliminary Design, as per mišljenju Nadzornog organa) i da ga uzme u
the Engineer's opinion) and took it into obzir u narednim fazama projekta projektovanja
consideration in further stages of the Design & i izgradnje.
Built Project.
Nadalje, uzimajući u obzir pod-klauzulu 13.9
Furthermore, taking into account Sub-Clause Posebnih uslova, gdje su nepredvidivi radovi
13.9 of Particular Conditions, where radovi koji se odnose na promjenu opsega
Unforeseeable works are the works that relate to radova zbog promijenjenih geoloških,
variation of the scope of work due to changed hidrogeoloških i ekoloških uslova u odnosu na
geological, hydrogeological and ecological isporučeni idejni projekat, određivanje
conditions in relation to the delivered vrednovanja Nadzornog organa da se pomenuti
Preliminary Design, the Engineer's valuation is radovi ne mogu tretirati kao nepredvidivi
that mentioned works cannot be treated as radovi, uz obrazloženje da radovi mogu biti
unforeseeable works, with an explanation that predviđeni od strane iskusnog izvođača
the works can be foreseen by an experienced radova iz dostavljenog Idejnog projekta.
contractor from the submitted Preliminary
Design.

62