Project: M/s.

Sark Projects
Form 1 Page: 1 of 9

APPENDIX I
(See paragraph– 6)

FORM 1
(I) Basic Information

S.No. Item Details


1. Name of the project/s Construction of “ Luxury Villas” by
M/s. Sark Projects
2. S. No. in the Schedule 8(a): Building and Construction projects.
3. Proposed capacity/ area/ length/ tonnage Type of project Villas
to be handled/ command area/ lease area/ Plot area 87,512.54 m
2

number of wells to be drilled Built up area 55,641.34 m


2

No. of Villas 179


No. of LIG& EWS units : 46
Parking Area 540.46 m2
Utility Area 298.76 m2
Green Area 9190.58 m2
4. New/ Expansion/ Modernization New Project
5. Existing capacity/ area etc. Nil
6. Category of project i.e. „A‟ or „B‟ Category „B‟
7. Does it attract the general condition? If No
yes, please specify.
8 Does it attract the specific condition? If No
yes, please specify.
9. Location Latitude : 17°26'38.81"N
Longitude : 78°11'3.66"E
Plot/ survey/ Khasra no. Sy. No. 72, 73, 74, & 75
Village Mokila Village
Tehsil Shankerpally Mandal
District Ranga Reddy District
State Telangana
10. Nearest railway station/ airport along with Rly station: Nagulapally railway station at 4.5 km.
distance in kms Airport: RGIA , Shamshabad at 33 km.
11. Nearest town, city, district headquarters The project is located within the Hyderabad
along with distance in kms Metropolitan Area
12. Village panchayats, zilla parisad, Greater Hyderabad Municipal Corporation
municipal corporation, local body
(complete postal addresses with
telephone nos. to be given)
13. Name of the applicant Mr. Sarin Katta
14. Registered address Sark Project, #A-86, Journalist Colony, Jubilee Hills,
Hyderabad-33.
15. Address for correspondence:
Name Mr.Sarin Katta
Designation (Owner/ partner/ CEO) Managing Partner
Address Sark Project, #A-86, Journalist Colony, Jubilee Hills,
Hyderabad-33.
Pin Code 500033
E-mail madhu@sarkprojects.in
Telephone no. 040-23541848
Fax no. -
Project: M/s. Sark Projects
Form 1 Page: 2 of 9

S.No. Item Details


16. Details of alternative sites examined, if Not Applicable
any. Location of these sites should be
shown on a topo sheet.
17. Interlinked projects Not Applicable
18. Whether separate application of Not Applicable
interlinked project has been submitted?
19. If yes, date of submission Not Applicable
20. If no, reason Not Applicable
21. Whether the proposal involves approval/
clearance under: if yes, details of the
same and their status to be given.
(a) The Forest (Conservation) Act, 1980 ? No
(b) The Wildlife (Protection) Act, 1972 ? No
(c) The C.R.Z. Notification, 1991 ? No
22. Whether there is any government order/ No
policy relevant/ relating to the site?
23. Forest land involved (hectares) Nil
24. Whether there is any litigation pending No
against the project and/or land in which
the project is propose to be set up?
(a) Name of the Court Not Applicable
(b) Case No. Not Applicable
(c) Orders/directions of the court, if any Not Applicable
and its relevance with the proposed
project.

(II) Activity

1. Construction, operation or decommissioning of the Project involving actions, which will cause
physical changes in the locality (topography, land use, changes in water bodies, etc.)

Details thereof (with approximate quantities


Information/ Checklist Yes/
S.No. /rates, wherever possible) with source of
confirmation No
information data
1.1 Permanent or temporary change in No This is a construction of new Gated Community on
land use, land cover or topography vacant plot of land, which is earmarked for
including increase in intensity of land residential development.
use (with respect to local land use
plan)
1.2 Clearance of existing land, vegetation NoThere are existing villas in the project site. No
and buildings? clearance of vegetation and structure is required.
1.3 Creation of new land uses? No
The project site is earmarked for residential
development as per the local development plan and
will be developed as per the local building by-laws.
Hence, no new land use will be created.
1.4 Pre-construction investigations e.g. Yes Soil testing is done during detailed engineering
bore houses, soil testing? study.
1.5 Construction works? Yes All construction activities will be confined within the
project premises; there will be no physical changes
outside the project boundary.
1.6 Demolition works? No Project site has villas in it. Demolition is not required.
1.7 Temporary sites used for No The construction activities including storing of raw
construction works or housing of materials will be confined within the project site only.
Project: M/s. Sark Projects
Form 1 Page: 3 of 9

Details thereof (with approximate quantities


Information/ Checklist Yes/
S.No. /rates, wherever possible) with source of
confirmation No
information data
construction workers? No temporary labour hutment is proposed.
Construction workers will be hired from the local
area.
1.8 Above ground buildings, structures Yes The proposed construction involves development of
or earthworks including linear Gated community villas which requires adequate
structures, cut and fill or excavations engineered earthworks.
1.9 Underground works including mining No No underground works including mining/ tunneling
or tunneling? will be required except construction of basement.
1.10 Reclamation works? No No reclamation work required.
1.11 Dredging? No No dredging required.
1.12 Offshore structures? No No offshore structures required.
1.13 Production and manufacturing No No production/ manufacturing process is involved.
processes?
1.14 Facilities for storage of goods or Yes Raw material will be stored at site in a covered area.
materials? Cement will be separately stored under cover in
bales. Sand will be stacked neatly under tarpaulin
cover. Bricks and steel will be laid in open.
1.15 Facilities for treatment or disposal of Yes Solid Waste:
solid waste or liquid effluents? Solid wastes to be generated in project will be of
domestic in nature. Solid wastes generated will be
segregated into biodegradable (waste vegetables
and foods etc.) and non-biodegradable (paper,
plastic, glass etc.) components and collected in
separate bins. Both the biodegradable organic
wastes and non-biodegradable inorganic wastes will
be sold to authorized vendors. Dewatered/ dried
sludge from STP will be used as manure in Green
Belt.

Liquid Effluent:
During construction phase, sewage will be treated
and disposed through septic tanks followed by soak
pits.

The wastewater in operation phase will be treated up


to tertiary level in a STP of 160 KLD capacity and the
entire (100%) treated sewage will be used for toilet
flushing, DG set cooling and Greenbelt. Therefore,
during normal operations, there will be zero
discharge, as the entire treated sewage will be
recycled.
1.16 Facilities for long term housing of No There will be no facilities for long-term housing of
operational workers? operational workers.
1.17 New road, rail or sea traffic during No In construction stage some vehicles will be operated
construction or operation? at the site for construction work and transport of
construction materials.

During operation traffic will increase to some extent


with the project. But there will be no rail or sea traffic.
1.18 New road, rail, air water born or other No Not applicable.
transport infrastructure including new
or altered routes and stations, ports,
airports etc.?
1.19 Closure or diversion of existing No Not applicable.
Project: M/s. Sark Projects
Form 1 Page: 4 of 9

Details thereof (with approximate quantities


Information/ Checklist Yes/
S.No. /rates, wherever possible) with source of
confirmation No
information data
transport routes or infrastructure
leading to changes in traffic
movements?
1.20 New or diverted transmission lines or No There will be no shifting of electrical transmission
pipelines? lines.
1.21 Impoundment, damming, culverting, No No impoundment, damming, culverting, realignment
realignment or other changes to the or other changes to the hydrology of surface
hydrology of watercourses or watercourses is proposed.
aquifers?
1.22 Stream crossings? No No Stream are Crossing
1.23 Abstraction or transfers of water form No Ground water and treated sewage will be used in
ground or surface waters? operation phase.
1.24 Changes in water bodies or the land No Surface drainage will not be affected.
surface affecting drainage or run-off?
1.25 Transport of personnel or materials Yes Transport of personnel/ material during construction
for construction, operation or and operation phase are envisaged.
decommissioning?
1.26 Long-term dismantling or No Not applicable
decommissioning or restoration
works?
1.27 Ongoing activity during No Not applicable.
decommissioning which could have
an impact on the environment?
1.28 Influx of people to an area in either No Construction workers from nearby areas will be
temporarily or permanently? hired.
1.29 Introduction of alien species? No Not applicable.
1.30 Loss of native species or genetic No Not applicable.
diversity?
1.31 Any other actions? No No

2. Use of Natural resources for construction or operation of the project (such as land, water,
materials or energy, especially any resources, which are non-renewable or in short supply):

Details thereof (with approximate quantities


Information / Checklist Yes/
S.No. /rates, wherever possible) with source of
confirmation No
information data
2.1 Land especially undeveloped or No Project site is under construction, earmarked for
agricultural land (ha) residential development by the local development
authority.
2.2 Water (expected source & competing Yes Total water requirement for the project is 189 KLD.
users) unit: KLD Source of the water is Municipal supply by
HMWSSB.
2.3 Minerals (MT) No Not applicable.
2.4 Construction material-stone, Yes Construction materials required:
aggregates, sand/ soil (expected Source: Steel and cement will be procured from
source-MT) authorized vendors. Sand & aggregate will be
procured from local material suppliers.
2.5 Forests and timber (source – MT) No None
2.6 Energy including electricity and fuels Yes Power requirement is 1125kVA that will be met from
(source, competing users) Unit: fuel Telangana State Electricity Board. (TSPDCL) DG
(MT), energy (MW) sets will be provided as backup power supply during
power failure.
Project: M/s. Sark Projects
Form 1 Page: 5 of 9

2.7 Any other natural resources (use No None


appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be


harmful to human health or the environment or raise concerns about actual or perceived risks to
human health.

S. Information/Checklist Yes/ Details thereof (with approximate quantities


No. confirmation No /rates, wherever possible) with source of
information data
3.1 Use of substances or materials No The proposed project is a residential development
which are hazardous (as per MSIHC project, and hence, no storage of hazardous
rules) to human health or the chemicals (as per MSIHC rules) will be done, except
environment (flora, fauna, and water HSD required to run backup DG sets, for which the
supplies) quantity stored will be below the threshold limit
specified in the MSIHC rules. Necessary permission
will be obtained from the Explosives Dept.
3.2 Changes in occurrence of disease or No Suitable drainage and waste management measures
affect disease vectors (e.g. insect or will be adopted in both construction and operational
water borne diseases) phase, which will restrict stagnation of water or
accumulation of waste. This will effectively restrict the
reproduction and growth of disease vectors.
3.3 Affect the welfare of people e.g. by No No use, storage, transport, handling or production of
changing living conditions? any harmful product is envisaged from the proposed
project. Thus, no major adverse impacts on the
human health / environment are envisaged.

Moreover, this project will provide employment to


local labours in the construction phase and workers
during the operation phase. Thus, the project will
have beneficial impacts.
3.4 Vulnerable groups of people who No Not applicable.
could be affected by the project e.g.
hospital patients, children, the elderly
etc.,
3.5 Any other causes No

4. Production of solid wastes during construction or operation or decommissioning (MT/ month)

Details thereof (with approximate quantities


Information / Checklist Yes/
S.No. /rates, wherever possible) with source of
confirmation No
information data
4.1 Spoil, overburden or mine wastes No No such spoil, overburden or mine wastes will be
generated.
4.2 Municipal waste (domestic and or Yes Solid wastes to be generated in project will be of
commercial wastes) domestic in nature. Composition & quantity of solid
wastes are:
Biodegradable: 347.67 kg/day (Waste vegetables
and foods etc.)
Non- 173.835 kg/day (Papers, cartons,
biodegradable: thermocol, plastics, glass etc.)
Inert 57.945 kg/day
Total: 579.45 kg/day

4.3 Hazardous wastes (as per Yes The only hazardous wastes in the project will be
Hazardous Waste Management used/ spent oil from backup DG sets, which is
Rules) classified as Hazardous Waste Category 5.1 as per
Project: M/s. Sark Projects
Form 1 Page: 6 of 9

Details thereof (with approximate quantities


Information / Checklist Yes/
S.No. /rates, wherever possible) with source of
confirmation No
information data
Hazardous Wastes (Management, Handling & Trans
boundary) Rules 2008.

Spent Oil from backup DG sets will be carefully


stored in HDPE drums in isolated covered facility.
This spent oil will be sold to authorized recyclers.
Suitable care will be taken so that spills / leaks of
spent oil from storage could be avoided.
4.4 Other industrial process wastes No Not applicable
4.5 Surplus product No Not applicable
4.6 Sewage sludge or other sludge from Yes The sludge generated from STP will be dewatered/
effluent treatment dried and used as manure.
4.7 Construction or demolition wastes Yes The construction waste will consist of excess earth
and construction debris along with cement bags,
steel in bits and pieces, insulating and packaging
materials etc.

Recyclable waste construction materials will be sold


to recyclers. Unusable and excess construction
debris will be disposed at designated places in tune
with the local norms.
4.8 Redundant machinery or equipment No Not applicable
4.9 Contaminated soils or other No Not applicable
materials
4.10 Agricultural wastes No Not applicable
4.11 Other solid wastes No -

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/ hr)
Details thereof (with approximate quantities
Information / Checklist Yes/
S.No. /rates, wherever possible) with source of
confirmation No
information data
5.1 Emissions from combustion of fossil Yes The project does not envisage any major air pollution
fuels from stationary or mobile sources except operation of backup DG sets during
sources power failure and vehicular traffic.
5.2 Emissions from production No Not applicable
processes
5.3 Emissions from materials handling Yes This will be restricted to the construction phase and
including storage or transport to the construction site only.
5.4 Emissions from construction Yes This will be restricted to the construction phase and
activities including plant and to the construction site only.
equipment
5.5 Dust or odors from handling of Yes Dust, which will be generated during construction, will
materials including construction be water sprinkled. Tarpaulin cover will be provided
materials, sewage and waste on stored raw material to reduce the dust emission.
5.6 Emissions from incineration of waste No Not applicable
5.7 Emissions from burning of waste in No Open burning of biomass/ other material will be
open air (e.g. slash materials, avoided
construction debris)
5.8 Emissions from any other sources No Not applicable
Project: M/s. Sark Projects
Form 1 Page: 7 of 9

6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Details thereof (with approximate quantities


Information/Checklist Yes/
S.No. /rates, wherever possible) with source of
confirmation No
information data
6.1 From operation of equipment e.g. Yes Source of noise in the operational phase will be from
engines, ventilation plant, crushers backup DG sets (which will be in operation only
during power failure) and pumps & motors. All the
machinery will be of highest standard of reputed
make and will comply with national/ international
standards that take care of air and noise pollution
control/ vibration control. Therefore, no significant
impact due to operation of machinery is anticipated.
6.2 From industrial or similar processes No Not applicable
6.3 From construction or demolition Yes Due to various construction activities, there will be
short-term noise impacts in the immediate vicinity of
the project site. The construction activities will
include the following noise generating activities:
• Concreting, mixing & operation of DG sets
• Construction plant and heavy vehicle movement
6.4 From blasting or piling No No blasting or mechanized piling will be used in the
construction phase.
6.5 From construction or operational Yes Some noise will be generated from vehicular
traffic movement in the construction and operational phase.
6.6 From lighting or cooling systems Yes From the DG sets suitable noise abatement
methods, like acoustically treated enclosures will be
adopted.
6.7 From any other sources No Not applicable.

7. Risks of contamination of land or water from releases of pollutants into the ground or into
sewers, surface waters, groundwater, coastal waters or the sea:

Details thereof (with approximate quantities


Information / Checklist Yes/
S.No. /rates, wherever possible) with source of
confirmation No
information data
7.1 From handling, storage, use or No The only hazardous wastes in the project will be
spillage of hazardous materials used/ spent oil from backup DG sets. The spent oil
will be carefully stored in HDPE drums under isolated
storage, and periodically sold to authorized recyclers.
All precautions will be taken to avoid spillage from
storage.
7.2 From discharge of sewage or other No There will be no discharge of untreated sewage on
effluents to water or the land water or land, as wastewater after treatment will be
(expected mode and place of reused for toilet flushing, cooling of DG sets and AC,
discharge) and horticultural. Hence no adverse effect is
envisaged.
7.3 By deposition of pollutants emitted to No There will be no deposition of pollutants in to air and
air into the land or into water water
7.4 From any other sources No Not applicable.
7.5 Is there a risk of long term build up of No Not applicable.
pollutants in the environment from
these sources?
Project: M/s. Sark Projects
Form 1 Page: 8 of 9

8. Risk of accidents during construction or operation of the Project, which could affect human
health or the environment

Details thereof (with approximate quantities


Information/Checklist Yes/
S.No. /rates, wherever possible) with source of
confirmation No
information data
8.1 From explosions, spillages, fires etc. No This is a construction project and does not involve
from storage, handling, use or major hazardous construction activity. No industrial
production of hazardous substances or process activity is involved in this project. Hence,
chances of explosions, spillages, fires are minimal.

During construction, all construction workers will be


provided with personal protective equipment (PPE)
by the contractors as required under the health &
safety norms. Training and awareness about the
safety norms will be provided to all involved in
construction activities. Suitable fire-fighting measures
will be provided.
8.2 From any other causes No Not applicable.
8.3 Could the project be affected by Yes The study area falls in Zone-II, as per the Indian
natural disasters causing environ- Standard Seismic Zoning Map. Suitable seismic
mental damage (e.g floods, earth consideration will be adopted while designing the
quakes landslides, cloudburst etc)? structures to mitigate the seismic impacts. There are
no chances of floods and landslide.

9. Factors which should be considered (such as consequential development) which could lead to
environmental effects or the potential for cumulative impacts with other existing or planned
activities in the locality

Details thereof (with approximate quantities /


S. Information / Checklist Yes/
rates, wherever possible) with source of
No. confirmation No
information data
9.1 Lead to development of supporting, The proposed project will lead to development of the
facilities, ancillary development area by providing employment of the local people
stimulated by the project which could during construction and operation phase.
have impact on the environment e.g.:
• Supporting infrastructure (roads, Yes The project will have positive impact on the ancillary
power supply, waste or waste water infrastructure like roads, markets, public health,
treatment etc.) amenities, and communication facilities in the area.
• Housing development No Not applicable
• Extractive industries No Not applicable
• Supply industries No Not applicable
• Other No Not applicable
9.2 Lead to after-use of the site, which No Not applicable
could have an impact on the
environment
9.3 Set a precedent for later No Not applicable
developments
9.4 Have cumulative effects due to No Not applicable
proximity to other existing or planned
projects with similar effects
Project: M/s. Sark Projects
Form 1 Page: 9 of 9

(III) Environmental Sensitivity

Aerial distance (within 15 km)


from
S.No. Areas Name/ Identity
proposed project location
boundary
1. Areas protected under international None -
conventions, national or local
legislation for their ecological,
landscape, cultural or other related
value
2 Areas which are important or Water Bodies
sensitive for ecological reasons- Osman Sagar 5.2 km [SE]
Wetlands, water courses or other Musi River 1.3 km [ S]
water bodies, coastal zone, Maisamma Vagu 7.5 km [ NE]
biospheres, mountains, forests.
Reserve Forests
Medpalli RF 6.6 km [ S]
3 Areas used by protected, important None -
or sensitive species of flora or fauna
for breeding, nesting, foraging,
resting, over wintering, migration
4 Inland, coastal, marine or None -
underground waters
5 State, National boundaries None -
6 Routes or facilities used by the public None -
for access to recreation or other
tourist, pilgrim areas
7 Defense installations None -
8 Densely populated or built-up area Hyderabad City -
9 Areas occupied by sensitive man- The project is within the -
made land uses (hospitals, schools, city limits so there are
places of worship, community several sensitive man
facilities) made land uses
10 Areas containing important, high None -
quality or scarce resources (ground
water resources, surface resources,
forestry, agriculture, fisheries,
tourism, minerals)
11 Areas already subjected to pollution None -
or environmental damage. (those
where existing legal environmental
standards are exceeded)
12 Areas susceptible to natural hazard None -
which could cause the project to
present environmental problems
earthquakes, subsidence, landslides,
erosion, flooding or extreme or
adverse climatic conditions)