- This document for installation, testing and commissioning as per SOHAR PORT PO number ________________, it shall be reviewed
and mutually agreed with SOHAR PORT team and shall be valid in case SOHAR PORT agreed to perform the job as per these documents
and attachments.
Name
Date
Sign
DOCUMENT HISTORY:
Rev. Remarks
Date
No. (Reason for Revision)
* Description:
2
Document issue purpose
- First Issue – Tender Under Bidding Stage.
- For Information – Tender Under Bidding Stage.
- For Review – In case the contract awarded to ARC Energy and Telecom Company. Applicable.
- For Approval (or Issued for work start) ‐ In case.
CONTENT
PAGE
S.N CONTENT NAME
NUMBER
1.0 PURPOSE 4
3.0 RESPONSIBILITIES 4
7.0 SUBCONTRACTORS 6
16.0 ATTACHMENTS 8
1.0 PURPOSE
Purpose of this method statement is to define the sequence of Refurbishment of Electrical Facilities at
Floating Pontoon Structure at Sohar Port.
o The below personnel of Sohar Port and/or ARC Energy and Telecom Company shall be responsible
for usage of this Method Statement.
4o Communication plan identified herein for which Sohar Port & ARC Energy and Telecom Company
shall be responsible properly execution of issuance, approval and/or updating of this Method
Statment
Sohar PORT
Name Position / Land Line Number Mobile Number Email Address
Designation
Business Hours: mean the hours between 08:00 AM – 5:00 PM on a Business Day Saturday through
Thursday.
Change Control Procedure: means the procedure governing the initiation, evaluation, acceptance and
implementation of any Change.
Charges: means the charges and fees for the services to be paid by SA to ARC Energy and which are set
out in ARC Energy price schedule.
Deliverable: means the output of the services.
Parties: means SA and ARC Energy collectively, and "Party" shall mean any one of them as determined by
the context.
Personnel: means officers, directors, employees, workers and agents (including any persons hired as
consultants or contract staff) engaged from time to time by ARC Energy to perform any Services required.
Relationship Manager: means each SP and ARC Energy designated project managers appointed pursuant.
Services: means the services, activities, functions and responsibilities to be performed and provided by
ARC Energy to SA as set out in this Method Statement;
Service Level: means the qualitative and quantitative performance levels required to be achieved by ARC
Energy in respect of the Services.
ARC Energy Tools: means all tools, methods, processes, templates, reports, concepts and techniques and
other used by ARC Energy in the provision of the Services.
5
Personal Protection Equipment: PPE will be provided and used in accordance with ARC Energy HSE
manual. Helmet, safety glasses, high visibility vest, and safety shoes will be used at all times. Personnel
working at high places will use approved safety harnesses. When the environment is dusty, personnel will
use protective half masks.
Project Manager
Project
Coordinator
6.0 SUBCONTRACTORS
N/A
6
7.0 EXECUTION / SERVICES
STEPS IN INSPECTION AND CORRECTION OF ELECTRICAL FACILITIES AT SOHAR PORT :-
o This activity schedule is to be used only as a guide and activities can be performed in any order to facilitate
the work activity.
o Arrange all tools and equipment at site (need to be arrange Gate Pass)
o To Check the Continuity of the Cable
o Take the Reading of the Cables
o Base Plate to install the Service Pedestals.
Matrix is initiated in case a problem or ticket Escalation. The escalation will always be initiated to the Project
Manager and then to the level 3 and will be escalated to the next level, every 3 Hours if the issue remains
unsolved/unattended
Equipment (PPE) properties such as but not limited to type, model and certification attached in
schedule in Attachment No. 4
15.0 ATTACHMENTS