BEFORE THE
MAHARASHTRA REAL ESTATE REGULATORY AUTHORITY
MUMBAI
COMPLAINT NO. CC006000000057728
Mayank Chemiplast Pvt. Ltd .Complainant
Versus
Lokhandwala Kataria Construction Pvt. Ltd, ..Respondent
MahoRERA Regn. No. 51900008204
Coram:
Hon'ble Shri Madhav Kulkarni.
Adjudicating Officer, MahaRERA.
Appearances
Complainants: Mr. Bhimani
Respondents : Adv. Sachin Kari
ORDER
(Dated 02.09.2020)
1. The complainant an ollottee who had booked ¢ flat with the
respondent / promoter seeks withdrawal from the project and
refund of the amount with interest and compensation.
2. The online complaint is very cryptic. It is only mentioned that
agreement was executed in November, 2013. As per Clause 9 of
the agreement possession was assured in December, 2016.
Complainant has made more than 80% payment. Respondent
hos foiled to give possession as per agreement. Copy of
agreement on record dated 8.11.2013, shows that it was a slum
redevelopment project and complainant booked flat no. 4101 in
Al wing for a consideration of Rs.5,49,89,000/-. Why alll these
details are not given in the complaint _is not understood.
wm.
foHowever, detailed complaint is found on record giving those
details. itis alleged that complainant have paid Rs.5,17,07,805/-
The matter came up before Hon'ble Member on 4.3.2019 and
29.03.2019. Then the matter came up before me on 27.05.2019.
Plea of the respondent wos recorded. Respondent pleaded not
guilly. Respondent did not file written explanation on 25.06.2019.
Respondent filed written explanation on 19.07.2019. Matter was
adjourned for final hearing to 27.08.2019, then to 24.09.2019,
then to 10.10.2019 and then to 13.11.2019. Arguments were
heard. As | am working at Mumbai and Pune Offices in
alternative weeks and due to huge pendency in this office and
due to lockdown due to Corona Pandemic, this matter is being
decided now.
. The respondent has alleged that complaint is not admitted. Out
of the 90 floors in the project, 66 have been completed. Work is
in progress at fastest speed. If complainant is allowed to
withdraw, it will cause hardship to respondent. Delay occurred in
obtaining permissions and policy paralysis for statutory
authorities. Due to order of Hon'ble Bombay High Court in Writ
Pelition no. 2699 of 2014 all construction activities came to a hatt.
The slum dwellers formed a society and approached respondent
for redevelopment. LO! was issued by SRA on 16.04.2005. SRA
issued stop work notice on 12.12.2007. Respondent complied
with legal formalities and obtained various NOCs. As per GR
dated 4.12.2013, a standing committee was constituted to clear
high tise building proposals around Arthur Road Jail. Respondent
was entitled for fungible FS MOAF approval came on
09.12.2018 and commencement certificate from $1 to 77 floors
came on 07.03.2017. The agreement with the complainant
stood modified. Therefore, complaint deserves to be rejected.
i
eo5. Following points arise for my determination. | have noted my
findings against them for the reasons stated below:
POINTS FINDINGS,
1 Is the complainant an allottee and respondent Affirmative
promoter?
2 If yes, has the respondent failed to deliver Affirmative
possession as per agreement, without there
being circumstances beyond his control?
3 Is the complainant entitled to the reliefs Affirmative
claimed?
4 What Order? As per
~Einal Order
REASONS
6, Point Nos. 1 to 3- Complainant has placed on record copy of
the agreement dated 8.11.2013. Respondent hos admitted that
complainant booked flat no. 4101 for Rs.5.49,89,000/- in the
project at Mahalaxmi in Mumbai. | therefore, answer point no. 1
in the affirmative.
7. As per clause 9 of the agreement, possession was to be
delivered on or before 31.12.2016. Usual circumstances under
which extension was to be granted are mentioned in the proviso
in clouse 9.
8. It is the contention of the respondent that respondent received
LOI on 16.04.2005. This wos 8 years before execution of
agreement. The agreement mentions that NOC from Municipal
Corporation and Environment Clearance was received. Now itis
alleged that there was issue about construction around the
existing prison which arose in December, 2008. The stop work
notice for 1.5 years was withdrawn on 03.07.2009. Revised LOI
was received on 18.12.2009. Various approvals were obtained in
2013 itself, There was writ pelition and order was passed on
307.01.2015. MOEF approval came on 09.12.2016 and
commencement certificate from 51 to 77 floors came on
07.03.2017 as respondent was seeking 4.0 FSI.
All the circumstances pleaded by respondent were well known
to the respondent while executing agreement on 811.2013.
Complainant booked flat on 41* floor and date for possession
was given as 31.12.2016. Out of agreed consideration of
Rs.5.49,89,000/- respondent has obtained Rs.5,17,07,805/-. If
respondent is seeking more FSI for constructing more floors to
increase his profits, he is doing it for his own sake. Almost 7 years
have gone by and respondent has failed to deliver possession to
the complainant. it was also alleged that there was proceedings
under Insolvency and Bankruptcy code. It appears that National
Company Law Appellate Tribunal has feledsed the respondent
‘and allowed to function. | therefore, answer point no. 2 in the
affirmative.
10.IN view of discussion above, complainant is entitled to refund of
))
2)
3)
Rs.5,17.07.805/- paid to the respondent which is not denied by
the respondent together with interest as provided under rule 18
‘of Maharashtra Rules. | therefore, answer point no. 3 in the
affirmative and proceed to pass following order:
ORDER
Complainant is allowed to withdraw from the project.
Respondent to pay Rs.5,17,07,805/- to the complainant together
with interest @10.40% p.a. from the daté of payments fill final
realization however, subject to Orders passed in IBC
proceedings, if any.
Respondent to pay Rs.20,000/- to the complainant as cost of this
= ws
complaint. a4) Complainant to execute Cancellation Deed at the cost of the
respondent.
5) Charge of above amount is kept on the flat booked by
compleinant. .
4) Respondent fo pay above amounts within 30 days from the date
of this Order.
woe
(Madhav Kulkarni)
Adjudicating Officer
MAGEE ‘MahaRERA
Date : 02.09.2020.