Sei sulla pagina 1di 2

SPECIFICATION

This set of Specifications shall govern the methods of construction and the kinds of materials to be
used for the proposed fence shown in the plans and detail drawings.
The plans, detail drawings and these Specifications shall be considered as complementing each,
other, so that what is mentioned or shown in one, although not mentioned or shown in the other, shall be
considered as appearing on both. In case of conflict between the two, the same should be referred to the
designing Architect/Engineer for resolution.

General Conditions-
All parts of the construction shall be finished with first class workmanship to the fullest talent and
meaning of the plans and these Specifications, and to the entire satisfaction of the Architect/ Engineer and
Owner.
The construction shall conform to all the requirements of the National Building Code, as well as the
local rules and regulations of the Municipality/ City of Mati, Davao Oriental, Philippines.

Clearing the Site-


The building site shall be leveled according to the plans and cleared of rubbish, roots and other
perishable and objectionable matters to a suitable sub grade.
All such unsuitable materials shall be removed from the building site and spread uniformly over the
areas adjacent to the proposed building, or otherwise disposed of as may be directed by the Architect or
Engineer in charge of the construction.

Staking out the Building Lines-


The building lines shall be staked out and all lines grades shown in the drawings established before
any excavation is started. Batter boards and reference marks shall be erected at such places where they will
not be disturbed during the excavation of the building.

Excavation-
All excavations shall be made to grade indicated in the drawings. Where the building site is covered with
any kind of fill, the excavation for footings should be made deeper until the stratum for safe bearing
capacity of the soil is reached.
Whenever water is encountered in the excavation process, it shall be removed by bailing or
pumping, care being taken that the surrounding soil particles are not disturbed or removed

Backfills-
After concrete for foundations is hard enough to withstand pressure resulting from fills, the
materials removed from excavation shall be used for backfill around them.
Backfills and fills shall be placed in layers not exceeding 150mm in thickness, and each layer shall be
thoroughly compacted by wetting, tamping and rolling.

Concrete Works-
All concrete shall be mixed thoroughly until there is a uniform distribution of the cement and
aggregates, and should be deposited as nearly as practicable in its final position, care being taken to avoid
segregation of the aggregates.
Water to be used for mixing concrete shall be clean and free from injurious amount of oil, acids,
alkalis, sails and other organic materials.

Proportioning of Concrete-
All concrete works shall be done in accordance with the standard specifications for plain and
reinforced concrete as adopted by the Government. Cement to be used shall be Union brand Portland
cement, or any other equivalent brands more readily available in the locality. Alternative cements so
selected must meet the requirements of Portland and pozzolan cements, and approved by the Architect or
Engineer in charge of constructions.

The following proportions of concrete mixtures shall be used for the various parts of the building:

Columns and footings - Class A (1 : 2 : : 4)


Conc. Holl. Blk. Footings - Class B (1 : 2 - ½ : 5)
Reinf. Conc. Beams and Slabs - Class A (1 : 2 : 4)
Concrete slab floor on fill - Class C (1 : 3 : 6)
Septic Vault cover - Class A (1 : 2 : 4)
1
The fine aggregate for concrete shall consist of natural sand, or of inert materials with similar
characteristics, having clean, hard and durable grains, free from organic matter or loam.
The coarse aggregate for concrete shall consist of crushed rock of durable and strong qualities, or
clean and hard gravel. Size of the coarse aggregate to be used shall vary from 20mm to 40mm (3/4” to 1 -
½).

Forms for Concrete Works-


All forms for concrete works shall be properly braced or tied together so as to maintain the correct
position and shapes of the concrete members. Forms shall be constructed sufficiently tight to prevent
bulging and seepage of water.
Forms shall not be removed until the concrete has attained sufficient strength to support its own
weight and any loads that may be placed on it. Side forms of beams and girders may be removed earlier
than the bottom forms but additional posts or shoring must be placed under the beams or girders until they
attained their strength.

Steel Reinforcing Bars-


All steel reinforcing bars to be used in this construction shall consist of round deformed bars with
lugs or projections on their sides to provide greater bond between the concrete and the steel.
All steel reinforcing bars shall be accurately placed and secured against displacement by tying them
together at each bar intersection with Gauge No. 16 GI Wire.
The steel reinforcing bars indicated for footings, columns and other concrete members shall all
conform to the number, size and spacing as indicated in the drawings or schedule of steel reinforcements.
No metal reinforcement shall be installed in placed unless it is free from rust, scale or other coatings
which will destroy or reduce the bond with concrete.

Concrete Hollow Blocks-


All exterior concrete hollow blocks to be used for first floor walls shall be at least 100mm thick, while
concrete hollow blocks for interior walls unless otherwise indicated, shall be 100mm thick. For interior CHB
walls where plumbing pipes and fittings shall be located, the thickness shall be at least 100mm.
The concrete hollow block walls shall be laid, and the cells filled with cement mortar consisting of 1
part Portland cement and 3 parts sand by volume. They shall be reinforce with round deformed bars, 10mm
diameter, space not more than 60m on centers, bothways.

The mixture of cement plaster for concrete hollow block wall finished indicated in the drawings shall
be 1 part cement, 1 part lime and 3 parts sand.

Conformed by:

Owner/Representative

Reviewed by:

Civil Engineer

PRC NO. : 0143159 PTR NO. : 3714732C


PLACE ISSUED: DAVAO CITY DATE ISSUED: 01/31/2020
TIN NO. : 702-013-579-000

Potrebbero piacerti anche