Sei sulla pagina 1di 8

Selected Papers from the WSEAS Conferences in Spain, September 2008

Santander, Cantabria, Spain, September 23-25, 2008

The change from push to pull production: effects analysis and


simulation
E. ROMANO, L.C. SANTILLO, P. ZOPPOLI
Department of Materials Engineering and Operations Management
University of Naples “Federico II”p.le Tecchio – 80125 Napoli
www.impianti.unina.it

Abstract: - The philosophy of waste continuous identification and elimination is based on the key principle that is the creation
of a "Continuous Process Flow". To implement this strategy the goal is to achieve "Interdependent connected Processes"
adopting the Pull System methodology in the Just in Time production environment. The aim of "continuous flow" for the
removal of waste at every stage, also known as "one-piece-flow", is an ideal state to be achieved, in which each individual
operation is carried out only if necessary and if requested by next operation, in order to avoid overproduction, which is the
worst waste. This logic will create a "pure" Pull System where the process is triggered by the customer request , backwards to
the upstream to the raw material supply. Pure Pull Systems are possible in theory but really seldom in practice. For example
in manufacturing production we have situations in which the order is completed by forecasts sales very frequently (push/pull
systems).
This production system therefore represents a model of Operational Excellence, which represents a target for PUSH systems.
You want to produce a single piece at a time transferring from a process to the next without waits. But process links means
reducing the lead time and waits, so that the flow extends itself as reliability is improved and waiting times (e.g. set – up
times) decrease. However, there are areas where the flow is not thought to be practically feasible: for example lots of set-ups
are necessary or "providers" do not send one piece at a time but they work in batches. In this case you can control production
implementing Pull/Push interfaces. A first solution is a system based on kanban that reintegrates downstream station, known
as "supermarket pull", where the continuous flow is “broken” and the upstream process works in batches according to a
“production pattern ", that is a sequence set by the same upstream department. This method allows controlling production
between flows and aims to provide full detailed instructions to the production process upstream.
The scope of this work is the complete re-organization of production flow according to the Lean Thinking philosophy for the
industrial applications. The complete re-organization implementation of material flow management has been performed
through the supermarket sizing for which logic the reintegration kanban has been adopted.
In the case study, developed in the Whirlpool Europe Naples factory, we have a first stage that consists of sizing the amount
of "Kanban reintegration" codes, and the second stage in which we have simulated with ARENA and verified the progress of
production flow in the hypothesized system, that has underlined the improvement of the business performances and great
flexibility.

Key-Words: - pull system, kanban, simulation, supermarket pull, Sequential Learning.

1 Introduction slight usage, of the industrial automation. The same


In modern environments, characterized by high complexity product continuous innovations are helped by the
and turbulence, the traditional Ford-like approach of integration of the new flexibility features and of the human
uncoupling production with the market, father of the mass resource involvement, generally arranged in inter-functional
production, cannot work anymore. The lean production teams, in problem solving activities, becoming a
aims to make production and market moving at the same competitive advantage for the Corporates that are capable of
time using a batch of management techniques that will give reengineering the organizations according to the new
the start to the following approaches: Just in Time, Total criteria.
Quality Management e Concurrent Engineering. The The philosophy of the waste hunting is based on the main
Japanese experience has shown that the most critical aspect principle of creating a “Continuous Process Flow”, a
is not related to the specific technological feature, but is strategy to implement this goal is that one that tends to
related to the organization of the manufacturing process generate “Interdependent connected Processes” using “Pull
flow. The lean production enabled an increase in terms of System” approach that is strictly related to the Just in Time
flexibility to new market requests (range of the responses production idea.
offered ex-ante) moving this task to the on multi-capability The objective of the “continuous flow” that is the waste
of the workforce and rearranging, with flows and for elimination inn every phase, also known as “one-piece-
processes, the overall enterprise activity, from development flow”, is a an ideal state, where every single operation is
to manufacturing and finally to the distribution. It can noted done only if requested from the next one, if for whatever
that there was an increase also of time flexibility thanks to a reason the next operation did not request the up-streamed

ISSN: 1790-2769 90 ISBN: 978-960-474-009-3


Selected Papers from the WSEAS Conferences in Spain, September 2008
Santander, Cantabria, Spain, September 23-25, 2008

one the process is stopped to avoid the overproduction that kind and the FIFO lane is a systems that guarantees a near
is, according to Ohno, the worst waste at all [14]. This to ideal material flow (Figure 1).
logics is implemented with the “pure” Pull System.
In the systems that are willing to move towards the PULL, TRADITIONAL IDEAL STATE
on the contrary, everything starts with an order that pulls the BATCH & QUEUE OF LEAN

production from each cell, with systems using the JIT


production, Just in Time, that is achieved using the Push or Supermarket Sequenced FIFO Continuous
KANBAN, creating the minimum number of uncoupling Scheduled Pull Pull Sequenced Flow
(Kanban) (Broadcast) (Flow) (1 peace
inventories and allowing to work towards the optimization Flow)
of the throughput times of each single cell.
It is wanted the production on one piece at time moving it
from one process to another without waits; but connecting Figure 1: Logic flow from push to pull
processes means lead time reduction and waits: therefore production
the flow is extended more and more that the process 2 Problem Formulation
reliability increases and the waiting times like set-ups The Kanban is a signal of product availability that needs to
decrease. Moreover, there are areas one-piece flow is not be managed, each production line bin should be done by a
possible, e.g. when frequent set-ups are needed or because well delimited space or by a rack, we generally speak of
suppliers send parts in batch. In this case it should be “Supermarket”, in a way that an easy visual check could be
avoided the planning (push approach) because it would easily carried out. The stock level among the different
mean only estimating and not knowing what the next products is directly connected to the kanban number
process or customer in reality need. On the contrary it can running around; the main objective is to minimize the
be checked the production implementing Pull/Push number of kanbans used. In case that the shop should
interfaces; a first solution could be a system based on produce different part codes, the priority is given by the
“replenishment” kanban system supplying “downstream urgency given by the kanban rack. The different rack
processes known as: columns (one for each part code) are divide in 3 zones: the
• “supermarket Pull”, where the continuous flow is cards for each code are inserted from up to down taking
broken and the upstream processes working with each time zones related to increasing urgency. The operator
lots following “pattern production”, i.e. a fixed should produce that code in which cards are in the more
sequence from the upstream production area itself. urgency positions compared with all the other codes.
This approach enables to control the production The parts of the same types are placed one after the other
among the flows and aims to supply accurate for the following 2 main reasons:
instructions of production to the upstream • F.I.F.O. (First In First Out) management, first
processes without planning based upon the material in, first to be processed;
potential downstream requests. • to streamline tare the replenishment of the missing
When it is not possible to have a product stock, because of codes.
the high customization requested or for the high costs or for The material quantities are strictly established based upon
phase-out matters, or when we got a better synchronization the requests from the customer cell: the codes placed in the
between up and down streams, we got the following supermarket have a high rotation rate e do not wait for more
available options to the supermarket pull system: than a prefixed time inside it. The upstream production then
• Sequenced Pull: the supply process produces a is pulled by the part code request in order to reintegrate the
fixed quantity in a fixed sequence from the supermarket, avoiding storage of materials and delays
downstream shop directly in front of an order from delivery. With the creation of supermarkets, the codes more
the customer process (JIS, Just in Sequence). used from the line are already present in the cell e in
• Fifo lane (or FiFo sequenced or ConWip): it suitable quantities, optimizing the space around the line in
contains constant quantity in stock in a FIFO order to help the production changes line, that mean that the
sequence and it is placed between the upstream production is managed with a pull system using kanban and
supply process and the downstream customer supermarket, where the continuous flow is broken and the
process, hence if the lane is full the first process upstream process works based on batch according to a
should not produce until the second one has not “pattern production”, that is a fixed production sequence to
used party of the available stock. In this way it is minimize the set-up and Change Over (C/O) times.
avoided upstream process overproduction. The replenishment logic (Figure 2) foresees that for
In the “flow” standpoint, it can be seen the above withdrawal by “Customer Process” corresponds a signal of
mentioned control tools of the materials as next steps replenishment, using a production card, that is collected in a
towards the “one-piece-flow” ideal state, this is to say that suitable that make it visible that oceds have being used and
the “Supermarket” set-up is the first step to this production then, picked form that rack to give the start the part
production for replenishing, according to the fixed rules of

ISSN: 1790-2769 91 ISBN: 978-960-474-009-3


Selected Papers from the WSEAS Conferences in Spain, September 2008
Santander, Cantabria, Spain, September 23-25, 2008

the upstream shop; if indeed we imagine a pattern of Production capability of the plant if around (more
production as a wheel, as we are used to seeing in practice, than) 1.000.000 of units/year. This volume could
the cards for each part code will give the start to the be increased or decreased of 20% thanks to social
production according to fixed quantities defined by the means like CIG and reduced working time form
wheel itself. Then the part code supermarket replenishment one side, the increase of the working days,
will start, in specific locations, in fixed quantities defined additional workforce and extra-time from the other
by each kanban and with each card connected to the side.
package. In this way the Customer process has always the The Frontloader Washer range currently produced
requested code available in the right and expected place in Naples has been updated from the long time
supermarket. lasting model called Delta to a new platform called
Eureka. This new range has in common the
electronic program selector (timer) compared with
the former platform Delta, new features and
options are available.
Figure 2: The Material Replenishment logics Looking to only technical aspect, 2 main
with Supermarket and Pattern Wheel differentiation parameters could be considered:
8 Drum Volume (both in kg and liters)
3 Formal procedure for the 8 Drum Max spin Speed (rpm).
The possible values are listed in the following
Supermarket Creation Table 1; instead in Table 2 it could be found
To put in place the right the appropriate kanban different possible drum volume and spin speed
control system implies firstly to define the number combinations.
of cards (and then racks) needed. In reality they Table 1: Drum speed an capacity
create a material lock-up, in order to limit the Drum speed (round per minutes - rpm)
stocked parts that mean reducing the 600 800 1000 1200 1400 1600
interpretational stocks, and then reduce the unused capacità del cestello (litri)
42 48 50 53 55 60
money. On the other hand those stocks allow a safe
condition form potential line downtimes (both up
Table 2: Relation from drum liters and speed
and down streams).
It means that we need to find the better trade off Liters 50 54 58 64
between costs related to stocks and the ones related
800 800 1000 1000
to line stops. The general rule for the sizing 1000 1000 1200 1200
consists in assuring the production fulfillment at a rpm 1200 1200 1400 1400
average rate of (Tcop) in front of the safe level that 1400 1400 1600 1600
1600 1600
we need to guarantee.
Of course for each specific combination, different
Tcop could correspond to, for example, production
drums, tubs and motors are needed in order to
lead time of a specific production code, or different
assure reliable declared performances. In the
time interval related to the different safety level, or,
specific we have 2 drum types: 473 e 490.
could be related to the length of the time interval
Among other differentiation features there is also
that is connected to the time needed to complete a
the color; white is the most market requested, but
cycle form the consumption point of the specific
UK market also asks for Silver cabinet models.
material to the point of the material replenishment
The Main components of a Washing Machine are
and the related coming back.
the following ones (Figure 3): tub, motor, Heating
Following there is a formal and general approach to
Element, Counterweight, dampers, Control Panel,
the supermarket sizing..
Drain Pump, timer, Soap Dispenser, Pressure
In order to create a supermarket fro each
Switch, valves, hoses, Door, Table Top.
production cell it is needed to gather some
information related as the following:
1. code to be placed in the supermarket;
2. quantity to keep in the supermarket;
3. available space aside each cell;
4. type and dimensions of the packaging of the
materials.

3.1 Whirlpool Naples Factory Figure 3: Product and components representation


Naples Factory produces Frontloader Washing.

ISSN: 1790-2769 92 ISBN: 978-960-474-009-3


Selected Papers from the WSEAS Conferences in Spain, September 2008
Santander, Cantabria, Spain, September 23-25, 2008

The Bill of material is made by around 210 parts, gathered possible production process variation (Cp=59, 82, 121, 145,
in 8 classes: 160 washer/h) due to absenteeism and production peaks.
1) cabinet;
2) drum; 4 Design of Supermarket Pull
3) Timer with Harness; The choice of implementing this managing strategy brought
4) motor; the production managers (in Whirlpool) to redesign the
5) PP Tub; material flow according to Lean mindset in the area of the
6) Rubber parts; Shop floor, highlighting the need to introduce a supermarket
7) Electrical parts; in the upstream of the Washing Unit that will enable to
8) Aesthetical parts and small auxiliary parts. uncouple of the drum and washing machine manufacturing
To understand the production process and the material flow, phases. The need find its rational in the attempt to reduce
it could be worth to outline as did in Figure 4. The main the relevant Change Over time for part code change, in the
production phases of the primary processes are: specific there is a set-up time of 7’ for a code change and of
1) Raw Material Supply. It looks after the procurement of about 30’ for moving from 473 to 490 drum production,
the raw material and components needed to assure the both for production speed gap between the drum line and
requested production. The relationship established with the W.U line that moves with higher speed.
suppliers is a “free-pass” type, that means that there is Finding, indeed the Pacemaker in the W.U. it could be
no in-coming inspection and the right level of quality looked at a process to continuous flow process downstream,
accountability of the raw material is given to the being the W.U perfectly time synchronized with the
suppliers with the quality written certification. Assembly line and introduce a Supermarket System that
2) Assembling: related to the production of the drum, assures pull management of line (Figure 5).
cabinet and front .
3) Mounting. Specific components are used to bring to the
final product, creating each sub-assembly and assembly.
At the edn of this operation a full safety and aesthetical
test is carried out (according to EU regulation) and the
product is finally packaged.
4) Distribution. Inventory of the washing machines
produced, waiting to be shipped to RDC. Figure 5: Production process proposed

A first step was a data analysis, starting form the


identification of the codes to be kept in the supermarket.
From the 2008 Forecast Analysis, coming from Material
Management (MM) Department, 18 codes were identified
and they have been summarized in 2 macro families related
Figure 4: Process production flow chart to the dimension of the drum diameter and then find out 3
different Timeframe for the forecasts according with sizing
Currently the drum production is carried out by an the supermarket. The identification of the 3 Timeframes is
automatic line having a cycle time of (Tc) 12 sec. and with a due to the market request variation, during which some
production capability of (Cp) 300 pz/h. codes more than others are foreseen to be requested and
The drum produced by the above described line, is produced (in the 2nd Timeframe it could be noticed that
transferred to suitable metallic racks in lots of 48 pieces, some codes disappear).
with relevant transportation, on the Washing Unit Line. Its Starting from this information it was possible, with ABC
production parameters are: Tc = 11.25 sec. e Cp= 320 pz/h. analysis to find out the codes to be kept in the for each time
In the mounting shop, there is an in-coming goods area in frame, distinguishing them in
which components coming form the supply chain are • Runner, the most requested ones that we need to be kept
placed. Then those components delivered towards the in the supermarket in bigger quantity;
inventories of each area with forklifts. • Repeater, for them it is worth to have enough parts in
The mounting is done on 2 parallel lines called: the supermarket because the requests are not negligible;
¾ Line 1; • Stranger, not possible to place supermarket, because the
¾ Line 2. requests are rare.
The manual mounting lines are thought to be every flexible Basing upon those subjective evaluations, supported by the
in terms of human workforce employed and with a max experience of the process responsible, it was established
production capability of , 160 washer/h each. This how many codes and which are to be placed in the
maximum value could be suitably tuned up to follow Supermarket.

ISSN: 1790-2769 93 ISBN: 978-960-474-009-3


Selected Papers from the WSEAS Conferences in Spain, September 2008
Santander, Cantabria, Spain, September 23-25, 2008

The next step foresaw the data analysis of the process, in the 5 Implementation and evaluation of a
specific t was settled an reference interval, each working
shift during which it was estimated the production drum line
logical model and simulation with Arena
The followed objective was that we need to set up a model
uptime defining in function of the above mentioned time,
that really reflected the logics to be implemented. The
for each timeframe, the Pattern Wheel of part code
logics formulation of the model was besides followed and
production to be implemented in the supermarket. In reality
managed by Whirlpool Itself and then under various
Pattern is a not more than a production campaign for each
standpoint under its supervision. It was decided to approach
shift done by a sequence of minimum production lots for
with different steps: firstly it was decided the logics and
each foreseen code, constituted by a certain number of
then there was a tune up phase in order also to simplify,
containers, that are assumed to be of 48 piece capacity
trying to reduce variation inputs, gathering elements by
(P.size), evaluated on the basis of the percentages of the
macro areas.
forecast and the production related to the uptime, i.e. the
The basic idea is that the one followed for the pre-sizing
overall number of parts that it cab be produced in the
faced before, that is the Kanban replenishment logics to
Production Time. The data is summarized in the following
Supermarket (Figure 7), revised in a way that could be
table:
implemented in Arena environment.
Table 3: production parameters
DATA BOX DATA BOX
Drum Line W.U.
C/T 12 s T/T 11,25 s

Cp 300pz/h Cp 320pz/h

C/O 30 min O.E.E Linea C/O 0


cesto
Maint. 15 min EPEshift 8 h Maint. 0

A.time 7,5 h P 0,9 A.time 7,33 h


Figure 7: Kanban replenishment logic proposed

Uptime 90% Q 0,97 Uptime 92% Afterwards it can be found some logical diagrams for the
P.time 405 min Downt. 0,06 P.time 7,33 h model implementation related to the following phases:
• Drum production according to a pre-
Scrap 3% Uptime 8 Scraps 0
established wheel sequence;
P.size 48 A 0,94 P.size 48 • Code storage in the supermarket;
EPEshift 8 h O.E.E 0,82 EPEshift 8 h • Code Withdrawal to supply the W.U. lines.
The logical scheme of the drum line production process
It should be noticed that an Availability of the plant at 94% Where the labeling takes into account the following code
it can be got an Available time of 7,5 h, where the shift lasts list, to which a priority will be assigned to allow their
8 h, this means that, considering the Downtime, estimable processing according to a wheel logics already settled.
taking into account that in one shift it can be decided to run
one Change over and a second one across the second shift,
in total 30 min ed one maintenance operation that takes
away 15 min, it can reached ann Uptime of 90% that given
in minutes brings to 405 min of real production. The
production batch will take into account production
capability and of the Production Time as follows:
Production batch = P.Time * Cp (1)

SHIFT WHEEL

START

MAINT 1/2 C/0

Rotazione
Ruota Avanzam ento
produttivo

PROD.time PROD.time

C/O

Figure 6: Production Pattern Wheel based on


production parameters

ISSN: 1790-2769 94 ISBN: 978-960-474-009-3


Selected Papers from the WSEAS Conferences in Spain, September 2008
Santander, Cantabria, Spain, September 23-25, 2008

Drum generation 7 50 ltr/1600 ns 473


8 50 ltr/800 ns 473
9 50 ltr/1000 ns 473
10 54 ltr/1600 473
Type
?
11 58 ltr/1000 490
473 490 12 58 ltr/1200 490
13 58 ltr/1600 490
Drum labelling = define i Drum labelling = 14 64 ltr/1000 490
cod define i cod
15 64 ltr/1200 490
16 64 ltr/1400 490
Batch until minimum lot Batch until minimum lot 17 58 ltr/1400 490
condition condition 18 64 ltr/1600 490
They were taken into account (to keep it simple) separated
Sequencing operation. Sequencing operation. the flows of the 473 e 490 drums, introducing Generators of
Pattern wheel Pattern wheel
different Entities.
The red, white and green zones represent the places in the
Hold queue bifore Hold queue bifore supermarket model with function of replenishment signal.
processing: C/O processing: C/O Washing machine
generation

Priorità processing is
respected? & Labelling j code
no The station is free? no

yes
Which drum Cod.j
Code processing in sequencing washing machine
order mounted?
473 490
Assign drum code to
washing machine j The same logic flow of
Release batch code
473 type no
ID DRUM
Figure 8: Drum production logic flow chart CODE
Compare
supermarket quantity
ID. DRUM CODE
Drum code processing

ZG is no ZB is no ZR is no
empty? empty? empty?
no no Is it n code realeased
Is it i Is it i yes yes
to drum line? W.U not
code? code?
Pick code from ZG Pick code from ZB yes alimented!
zone and update zone and update
yes yes
Pick code from ZR
Compare zone and update
supermarket
quantity Code processing

Drum process Communication:


Finite product red zone for drum code
Immediately production:
resequencing pattern wheel
Is ZR Is ZB Is ZG
empty? empty? empty?
no no no Figure 10: Replenishment flow process
yes yes yes
Add code i to ZR
and update
Add code i to ZB
and update
Add code i to ZG
and update
5.1 Logic model implemented in Arena
The model translates together the flow schemes already
Block drum processing seen that means:
• Drum creation
until ZG empty condition

• Storage in the supermarket


Figure 9: Supermarket allocation: logic flow chart
• Washing machine creation as signal for the withdrawal
Table 4: List of drum labels produced (liters/rpm) – from the supermarket and the match between withdrawal
(diameter porthole) order and availability tra with query to the Kanban rack.
The entities used are: Create , Assign, Decide, Batch,
Label drum list Match, Record , Separate and Dispose, i.e. the Basic
1 54 ltr/1400 473 Process are mostly used.
2 54 ltr/1200 473 A fist step was the introduction of a daily stopwatch to
3 54 ltr/1000 ns 473
4 50 ltr/1400 ns 473 generate an entity “maintenance per shift”, that means that
5 50 ltr/1200 ns 473 when shift is over it should be considered the time spent for
6 54 ltr/800 ns 473 maintenance.

ISSN: 1790-2769 95 ISBN: 978-960-474-009-3


Selected Papers from the WSEAS Conferences in Spain, September 2008
Santander, Cantabria, Spain, September 23-25, 2008

Then it was translated the creation of each single drum, 6 Results and Conclusions
according to a sequence matched with the relevant pattern Following the analysis processed, it is possible to think that
production. The block Process followed by “If then else” the idea to place a supermarket between the drum and W.U.
and the blocks Batch will translate the 48 lot processing production phases will guarantee the desired flow of
according to the percentages related to Whirlpool forecasts . materials. The sizing carried out fully reengineers, in the
Then the drum production is interfaced with kanban rack right way, the logics of managing of the supermarket taking
that to simplify it was gathered with the supermarket cells into account the ways of the replenishment by the drum line
counting parts present in the green, white and red zones and and that of the Washing Unit, allowing the effective
placing in the inverse order in case of empty cells that uncoupling of the process as aimed by the Company: this
means the simulator queries the counters of the red zone and means that it is possible to implement a production of the
if it is empty it routes, then the white one and finally the drums according to the wheel defined with the company
green one. support, that will fill up the supermarket according to a rate
For this scope it has been introduced an Overload Block that of depletion given by the pacemaker process, i.e. the W.U.
collects the parts in case there is an overproduction, that The launch of the model allowed, with trial and error tests,
means a potential production that we cannot storage in the to notice that it is needed a 4 h of advance of the drum line,
supermarket and in the same way Underload Block that hence, that is needed the usage of part of the 3rd shift of the
separates the units and counts how many times are needed Drum Line to avoid a stock-out and then a stop of the W.U.
in the inventory, i.e. how many times there a drum request The simulations runs related to the following situations:
that cannot be satisfied because of stock-out, quantifying it. Concurrent Start of the upstream and down stream lines
A Match module that compares and releases the queue of The Underload scenario was evaluated, i.e. underload, of 28
the products stored in the inventory with the queue Kanbans, after about 3 production hours after which the
requested by W.U. system is able to stabilize again (it is recovered the
production according to the sequence that is able to supply
the W.U.).
Start of the Drum Line in advance
It was checked that in this case increasing this advance time
the underload decreased. After 4 h, there was no more
underload conditions. It was checked that the system was
working in underload conditions, additional confirmation
that the model was and is valid. It is clear that the underload
Figure 11: Replenishment Logic even of only one entity should create the stoppage of the
It was implemented a W.U. production logics generating the system. In reality, for experimental scopes, it is useful to
withdrawal Kanban in a random fashion according to the measure the underload, and taking into account this to
forecast, in lots of 48 parts collected in Batch, that check the reduce potentially the size of the supermarket.
presence of parts in the supermarket with the block if then Start of the drum line not starting the W.U.
else that routes the code by comparison with the relevant It is supplied the overload that is an additional validation of
Match. the model. In the hypothesis of fully random sequence by
Following it could be seen the sub model of the W.U. in the W.U. and making the Drum line to work for 4 hours in
which washing machines are generated and to which it is the third shift, it was possible to check that the supermarket
assigned a code related to the rpm value and depending on sized by us is capable of supplying the downstream lines
this the drum type will be found, connected to the forecasts. without interruptions, nor filling the underload or the
When the W.U says that one code is in red zone this will overload, so without under or over production.
translate in a re-sequencing of the wheel that will imply that
the processing of the production lot is stopped and it is Finally these are the achieved results:
starter immediately the production of the lot that is in the • Sizing of a supermarket implementing Replenishment
red zone. This logics will be implemented with a block Kanban Logics;
Hold that is “linked” to a block Process. The model is • Sizing of a Kanban rack, that supplies the signals for a
launched with his parameters: suitable managing of the replenishment production;
• Two shift for both assembly lines and washing unit, • Modeling and implementation with Arena of the
with Tc = 11,25 sec.; process;
• Three shift for drum line with Tc = 12 sec. • Model validation;
We simulated a complete work day, 24 h for 10 replication. • First results with the Time frame 1, that taking into
account the random nature of the material consumption
confirm the robustness of the carried out sizing with

ISSN: 1790-2769 96 ISBN: 978-960-474-009-3


Selected Papers from the WSEAS Conferences in Spain, September 2008
Santander, Cantabria, Spain, September 23-25, 2008

the assumption to employ the Drum Line for a part of [21] Pegden, Tennis C., Shannon, Robert E., Sadowski,
the 3rd shift. Randall P, “Introduction to Simulation Using SIMAN”,
Mc Graw Hill, 1995.
References: [22] Pritsker, A. A. B., “Introduction to Simulation and
[1] Mariotti S., Verso una nuova organizzazione della SLAM II”, 3d ed., Systems Publishing Corp., West
produzione. Le frontiere del post-fordismo, Etas, 1994. Lafayette, Ind. 1986.
[2] Merli G., Total Manufacturing Management. [23] Averill M. Law, W. David Kelton, “Simulation
L’organizzazione industriale degli anni ’90, Torino, Modeling & Analysis”, III Edition, Mc Graw Hill 2001.
Petrini Editore, 1987. [24] Schmidt, J. W., and R. E. Taylor, “Simulation and
[3] Mariotti S., Soluzioni flessibili per il manufacturing, Analysis of Industrial Systems”, Richard D. Irwin,
L'Impresa 10-1994. Homewood, III 1970.
[4] Morishima M., Cultura e tecnologia nel "successo" [25] T. Rossi, “Simulation Forum 2004 – Gestire il
giapponese, Bologna, Il Mulino, 1984. cambiamento nei processi produttivi e logistici. La
[5] Schonberger R. S., Tecniche produttive giapponesi, simulazione come supporto alle decisioni”.
Milano, Franco Angeli, 1986. [26] W. David Kelton, R.P. Sadowski, D.A. Sadowski,
[6] Stalk G. - Evans P. - Shulman L. E., Competing on “Simulation with Arena”, Mc Graw Hill, 2000
Capabilitites: The New Rules of Corporate Strategy,
Harward Business Review March-April 1992.
[7] Bonfiglioli, Pensare snello, De Qualitate, 3, 45-50,
2002S.
[8] Jeffrey K. Liker, The Toyota Way: 14 Management
Principles from the World's Greatest Manufacturer,
McGraw-Hill 2004
[9] Shingo, Il sistema Giapponese Toyota, FrancoAngeli,
Milano 1987
[10] Rother M., Shook J. Leerning to see. La mappatura
del flusso del valore per creare valore ed eliminare i
muda, Lean Enterprise Institute (LEI) Brookline MA
USA, 2003.
[11] Vorne Industries Inc., Itasca IL USA, The fast
guide to OEE, 2002-2005.
[12] Jeffrey K Liker; David Meier, The Toyota Way
Fieldbook, A Pratical Guide for Implementing Toyota’s
4Ps, McGraw-Hill 2006.
[13] A.Portioli Staudacher, A.Pozzetti, Progettazione
dei sistemi produttivi, Criteri e metodologie, Ulrico
Hoelpi Milano.
[14] Nils Boysen, Malte Fliedner, Armin Scholl, “A
classification of assembly line balancing
problems”,12/2006.
[15] Christian Becker, Armin Scholl, “A survey on
problems and methods in generalized assembly line
balancing”, 21/2003.
[16] Comfort, J. C. “The Simulation of a Master-Slave
Event-Set Processor, Simulation”, 42: 117-124 (1984).
[17] Sargent, R. G. “Event Graph Modelling for
Simulation with an Application to Flexible
Manufacturing Systems”, Management Sci. , 34: 1231-
1251 (1997).
[18] Schriber, T. J., “An Introduction to Simulation
Using”, John Wiley, New York 1998.
[19] Law, A. M., “Statistical Analysis of Simulation
Output Data with SIMSCRIPT II.5”, CACI Products
Company, La Jolla, Calif. 1990.
[20] Pedgen, C. D., “Introduction to SIMAN”, Systems
Modeling Corp., Sewickley, Pa. 1989.

ISSN: 1790-2769 97 ISBN: 978-960-474-009-3

Potrebbero piacerti anche