o Location of Activity:
One Bank Substation Room at Karwan Bazar.
o Operation
Materials:
Materials used will be as per the material submittal approved by the engineer and will
be as per coordination with other services.
Storage / Protection:
LT, LT, and Transformer and Accessories shall be Replace with care to avoid any
damages. If they are shipped in packs or pallets, each pack of pallet shall be lifted
individually with suitable lifting equipment. Every precaution shall be taken to preserve
their cleanliness before installation. Store in accordance with manufacturer’s
instructions, properly protected from construction activities and weather conditions.
Installation:
o To make sure that the entire installation is in conformance and in accordance with the
design intent of the project for the Electrical and Low Voltage System in addition to the
specification and as per local and International Standards.
Responsibilities
o Site Engineer
1. To ensure that the works are carried out according to the Contract Specifications
approved method statement.
2. To provide all necessary information and distribute responsibilities to his construction
team.
3. To monitor the progress of work in relation with the work program and to report to the
Project Manager.
4. To co-ordinate with the safety officer and to ensure that the works are carried out in
safe practicing methods.
2. Foreman
1. The foreman will carry out his duties by maintaining continuous coordination with the
site engineer on daily basis, and ensure proper distribution of the workforce in the
required and planned locations.
2. To ensure that his assistant foreman/ charge hand are aware of the job requirements
and they have enough information to carry out their duties properly.
3. To ensure in consultation with the site engineer that the manpower involved in the
works are moving as agreed and planned for the work.
4. To ensure that the daily work is progressing as planned and advise the Site Engineer for
any requirement of the additional resources.
5. To control disposal of waste materials to the instructions received from the site
engineer.
6. To ensure full coordination with the safety officer to maintain safe working and proper
housekeeping of the site, following the approved safety measures and further ensure
that all his working team are aware of the same to prevent accident and losses.
7. After completion of works, Foreman shall inform the site engineer for inspection of
works.
8. Distribution and the control of materials shall be monitored by foreman and
storekeeper.
Manpower Required
10 Manpower work from 8 am to until finishing the job.
Materials Requirements
Cable lugs, Cable tie, PIB ,PVC tape and other accessories materials.
Equipment Requirement
The equipment that will be engaged for Installation of Substation equipment.
1. Wire cutters
2. Measuring tape
3. Drill machine
4. Wooden hammer
5. Flat file
6. Screw drivers
7. Open and box spanners
8. Crimping tool
9. Hydraulic punch machine
10. Unloading accessories
Supporting Documentation
This method Statement should be read in conjunction with the below referenced
documentations.