Sei sulla pagina 1di 48

Norms SN

No.
B-5 1.00 Compacting soil spreaded in 20/20 cm layers by roller(Rate per 100cum)

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Equipment
Roller (8-10Mt) hr 1.670 700.00 1,169.00 1,169.000
Sub-total 1,169.000
15% Contractor Overhead 175.350
Grand Total 13.444
Per Unit Rate
13.44 Rs

B-7 1.00 Excavation of soft soil using hydraulic excavator (0.8 cum)(Rate per 1cum)

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Material
Diesel ltr 0.125 97.00 12.11 12.106
2.00 Equipment - -
excavator(0.8cum) hr 1.670 1,800.00 3,006.00 3,006.000
Sub-total 3,018.106
15% Contractor Overhead 452.716
Grand Total 34.708
Per Unit Rate
34.71 Rs

B-7 1.00 Excavation of hard soil using hydraulic excavator (0.8 cum)(Rate per 1cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Material
Diesel ltr 0.150 97.00 14.55 14.550
2.00 Equipment - -
excavator(0.8cum) hr 0.013 1,800.00 22.50 22.500
Sub-total 37.050
15% Contractor Overhead 5.558
Grand Total 42.608
Per Unit Rate
42.61 Rs
B-1 1.00 Earthwork in excavation in soft soil including hauling disposal of soil upto distance of 30m and lift upto 1.5 m (Rate per 1 Cu.m)

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Unskilled md 0.700 770.00 539.00 539.000
2.00 Cost including 3% for tools and plants 16.170
Sub-total 555.170
15% Contractor Overhead 83.276
Grand Total 638.446
Per Unit Rate
638.45 Rs

B-1 1.00 Earthwork in excavation in medium soil including hauling disposal of soil upto distance of 30m and lift upto 1.5 m (Rate per 1 Cu.m)

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Unskilled md 0.800 770.00 616.00 616.000
2.00 Cost including 3% for tools and plants 18.480
Sub-total 634.480
15% Contractor Overhead 95.172
Grand Total 729.652
Per Unit Rate
729.65 Rs
B-1 1.00 Earthwork in excavation in hard soil including hauling disposal of soil upto distance of 30m and lift upto 1.5 m (Rate per 1 Cu.m)

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Unskilled md 3.000 770.00 2,310.00 2,310.000
2.00 Cost including 3% for tools and plants 69.300
Sub-total 2,379.300
15% Contractor Overhead 356.895
Grand Total 2,736.195
Per Unit Rate
2,736.20 Rs
H-15 1.00 Flat Brick Soling Works (Rate per 10 Sq.m)

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 0.500 1,070.00 535.00 535.000
unskilled md 1.000 770.00 770.00 770.000
2.00 Material - -
Brick Nos 420.000 15.00 6,300.00 6,300.000
SAND cum 0.710 2,000.00 1,420.00 1,420.000
-
Sub-total 9,025.000
15% Contractor Overhead 1,353.750
Grand Total 10,378.750
Per Unit Rate
1,037.88 Rs
0.0253

Plain cement concrete(PCC) in 1:2:4 ratio for foundations and flooring with approved quality of cement,sand and machine
crushed stone aggregate including supply of materials,mixing,laying,curing the work at least 7 days etc all complete as per
D-1 1 approved drawing specification and instruction of site engineer.( Rate Analysis: 1Cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 1.000 1,070.000 1,070.000 1,070.000
Unskilled Labour md 4.000 770.000 3,080.000 3,080.000
2 Material - -
Cement MT 0.320 19,350.000 6,192.000 6,192.000
40mm Aggregate Cum 0.520 2,000.000 1,040.000 1,040.000
20mm Aggregate Cum 0.220 2,100.000 462.000 462.000
10mm Aggregate Cum 0.110 2,100.000 231.000 231.000
Sand Cum 0.445 2,200.000 979.000 979.000
Water Ltr 150.000 0.340 51.000 51.000
Sub-total 13,105.000
15% Contractor Overhead 1,965.750
Grand Total 15,070.750
Per Unit Rate
15,070.75 Rs

D-4 1.00 PCC for RCC Works (1:1:2) by Using Mixture including Material.( Rate Analysis: 1Cum)

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 0.500 1,070.00 535.00 535.000
Unskilled md 3.500 770.00 2,695.00 2,695.000
2.00 Material - -
Cement MT 0.610 19,350.00 11,803.50 11,803.500
40mm-aggregrate Cum 0.640 2,000.00 1,280.00 1,280.000
20mm-aggregrate cum 0.210 2,100.00 441.00 441.000
Sand Cum 0.425 2,200.00 935.00 935.000
water ltr 300.000 0.34 102.00 102.000
Diesel ltr 3.000 97.00 291.00 291.000
Petrol ltr 0.100 108.00 10.80 10.800
3.00 Equipment - -
0.20-0.28 Cum Mixture hr 0.600 800.00 480.00 480.000
Vibrator hr 0.250 100.00 25.00 25.000
Sub-total 18,598.300
15% Contractor Overhead 2,789.745
Grand Total 21,388.045
Per Unit Rate
21,388.05 Rs

D-9 1.00 Steel Reinforcement bar of fe 500 grade including supplying, straightening, cleaning, cutting, binding & fixing in position with annealed
tying binding wire
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 12.000 1,070.00 12,840.00 12,840.000
Unskilled md 12.000 770.00 9,240.00 9,240.000
2.00 Material - -
MS Bar MT 1.050 89,850.00 94,342.50 94,342.500
Binding Wire Kg 10.000 101.00 1,010.00 1,010.000
Sub-total 117,432.500
15% Contractor Overhead 17,614.875
Grand Total 135,047.375
Per Unit Rate
135,047.38 Rs
E-1 1.00 Ply Formwork for Column (Rate per 10 sqm )
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 1.574 1,070.00 1,684.18 1,684.180
Unskilled md 2.361 770.00 1,817.97 1,817.970
2.00 Material - -
19mm-ply board sqm 0.693 731.96 507.25 507.248
Local Wood cum 0.019 68,000.00 1,292.00 1,292.000
Iron Bolt Nos 0.540 150.00 81.00 81.000
Nail kg 2.500 104.00 260.00 260.000
Sub-total 5,642.398
15% Contractor Overhead 846.360
Grand Total 6,488.758
Per Unit Rate
1,544.94 Rs
E-5 1.00 Ply Formwork for Beam (Rate per 10 sqm )
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 2.670 1,070.00 2,856.90 2,856.900
Unskilled md 4.000 770.00 3,080.00 3,080.000
2.00 Material - -
19mm-ply board sqm 1.650 731.96 1,207.73 1,207.734
Local Wood cum 0.039 68,000.00 2,652.00 2,652.000
Tron Prop Pipe Nos 0.400 1,844.12 737.65 737.650
Nail kg 2.500 104.00 260.00 260.000
Sub-total 10,794.284
15% Contractor Overhead 1,619.143
Grand Total 12,413.426
Per Unit Rate
1,241.34 Rs
E-6 1.00 Ply Formwork (Rate per 100 sqm )
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 17.200 1,070.00 18,404.00 18,404.000
Unskilled md 25.700 770.00 19,789.00 19,789.000
2.00 Material - -
19mm-ply board sqm 16.500 731.96 12,077.34 12,077.340
Local Wood cum 0.232 68,000.00 15,776.00 15,776.000
Iron Prop Pipe Nos 4.400 1,844.12 8,114.14 8,114.145
Nail kg 25.000 104.00 2,600.00 2,600.000
Sub-total 76,760.485
15% Contractor Overhead 11,514.073
Grand Total 88,274.557
Per Unit Rate
882.75 Rs

Good quality local chimney made Brickwork in 1:4 C/S mortar upto Ground Floor inclusive 30 m haulage distance in perfect
line level finish including supply of materials,wetting the bricks,racking the joints and curing the work for at least 7 days all
C-2 1 complete as per approved drawing ,specification and instruction of site engineer. (Rate Analysis: 1cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
skilled md 1.500 1,070.000 1,605.000 1,605.000
Unskilled md 2.200 770.000 1,694.000 1,694.000
Unskilled md 0.200 770.000 154.000 154.000
2 Material - -
brick no 560.000 15.000 8,400.000 8,400.000
cement MT 0.100 19,350.000 1,935.000 1,935.000
river sand cum 0.280 2,200.000 616.000 616.000
water lt 130.000 0.340 44.200 44.200
extra material 3%of Labour cost 4.000
Sub-total 14,452.200
15% Contractor Overhead 2,167.830
Grand Total 16,620.030
Per Unit Rate
16,620.03 Rs

2200 1 Iron Works with Red Oxide paint (Rate Analysis: 1 ton)
DoR S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
Norms
a Labour Cost
Technication 1.000 1,003.000 1,003.000 1,003.000
skilled md 2.000 1,070.000 2,140.000 2,140.000
simiskilled 2.000 750.000 1,500.000 1,500.000
Unskilled md 2.000 770.000 1,540.000 1,540.000
b Material - -
all type iron angle kg 1,100.000 78.000 85,800.000 85,800.000
Paint 5% of cost of material 4,290.000
drill bit, gas electrode 5% 4,290.000
nut bolt,revit 3% 2,574.000
c Equipment
crane hr 1.000 4,598.000 4,598.000 4,598.000
formwork
4 formwork and staging upto 5 m 25% of (a+b+c) 26,933.750
Sub-total 134,668.750
15% Contractor Overhead 20,200.313
Grand Total 154,869.063
Per Unit Rate
154.87 Rs

B-2 1.00 Earth back Filling


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Unskilled md 0.500 770.00 385.00 385.000
2.00 Material - -
Water Ltr 5.000 0.34 1.70 1.700
Sub-total 386.700
15% Contractor Overhead 58.005
Grand Total 444.705
Per Unit Rate
444.71 Rs

Elastocrete cementitious elastomeric water proofing coating 2 components capacity per kg 6 sq.ft for 2 coat (Rate Analysis:
K-7 1 1sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Material
Elastocrete cementitious elastomeric water
sqm 1.000 559.520 559.520 559.520
proofing material
Sub-total 559.520
15% Contractor Overhead 83.928
Grand Total 643.448
Per Unit Rate
643.45 Rs

2 coats of ready made enamel paint with one coat primer of approved colour over properly sanded surface all complete
J-5 b,c 1 (Rate Analysis: 100 sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 12.000 1,070.000 12,840.000 12,840.000
Unskilled md 8.000 770.000 6,160.000 6,160.000
2 Material - -
Astar lt 8.100 271.000 2,195.100 2,195.100
Enamel Paint lt 16.000 468.000 7,488.000 7,488.000
Sub-total 28,683.100
15% Contractor Overhead 4,302.465
Grand Total 32,985.565
Per Unit Rate
329.86 Rs

Supplying and applying 4.5X20mm steel Grill with 12X12 solid core square rod all complete as per approved drawing
M-3 1 ,specification and instruction of site engineer. (Rate Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 0.700 1,070.000 749.000 749.000
Unskilled Labour md 0.600 770.000 462.000 462.000
2 Material - -
Iron works for Grill kg 28.240 128.000 3,614.720 3,614.720
Iron Rod kg 215.000 87.100 18,726.500 18,726.500
Sub-total 23,552.220
15% Contractor Overhead 3,532.833
Grand Total 27,085.053
Per Unit Rate
2,708.51 Rs

Supplying and fitting rolling shutter all complete as per approved drawing ,specification and instruction of site engineer.
M-6 1 (Rate Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Material - -
rolling shutter sqm 10.000 2,288.000 22,880.000 22,880.000
Sub-total 22,880.000
15% Contractor Overhead 3,432.000
Grand Total 26,312.000
Per Unit Rate
2,631.20 Rs
Supplying and fitting collapsable gate all complete as per approved drawing ,specification and instruction of site engineer.
M-6 1 (Rate Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Material - -
collapsable gate sqm 10.000 4,788.200 47,882.000 47,882.000
Sub-total 47,882.000
15% Contractor Overhead 7,182.300
Grand Total 55,064.300
Per Unit Rate
5,506.43 Rs

M-9 1 GI wire kade taar(Rate Analysis: 100rm)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour cost - -
Skilled md 1.076 1,070.000 1,151.320 1,151.320
Unskilled md 5.38 770.000 4,142.600 4,142.600
2 Material - -
GI wire kade taar md 110 13.910 1,530.100 1,530.100
Nails,hook 185.000 185.000
Sub-total 7,009.020
15% Contractor Overhead 1,051.353
Grand Total 8,060.373
Per Unit Rate
80.60 Rs

Supplying and fitting 0.5mm CGI colour sheet for Roof all complete as per approved drawing ,specification and instruction of
F-1 1 site engineer. (Rate Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
skilled md 1.100 1,070.000 1,177.000 1,177.000
Unskilled Labour md 1.250 770.000 962.500 962.500
2 Material - -
CGI Sheet (0.5 mm (24 Guage)) sqm 12.000 675.110 8,101.320 8,101.320
8mm nut bolt no 30.000 23.000 690.000 690.000
J-hook no 25.000 23.000 575.000 575.000
Bitumen washer no 55.000 1.000 55.000 55.000
Sub-total 11,560.820
15% Contractor Overhead 1,734.123
Grand Total 13,294.943
Per Unit Rate
1,329.49 Rs

Providing and fixing Single Panel Swing Door of aluminium section in naturally anodized or black anodized/powder coated
color Section size (102*45*1.5 mm) fitted with 5 mm clear glass or 9 mm both side laminated board (excluding the cost of
1 handle).(Rate Analysis: 1sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

2 Material - -
Aluminium swing door sqm 1.000 6,994.000 6,994.000 6,994.000
Sub-total 6,994.000
15% Contractor Overhead 1,049.100
Grand Total 8,043.100
Per Unit Rate
8,043.10 Rs

Providing and fixing 2 or 3 Panel Sliding window of aluminium section in naturally anodized or black anodized/powder coated
color, Section size (87*56*1.2 mm) fitted with 5 mm clear glass without fly mesh shutter (Window size 6'*5' or average area 30
1 Sq. feet per window).(Rate Analysis: 1sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

2 Material - -
Aluminium sliding window without ventilator sqm 1.000 6,456.000 6,456.000 6,456.000

Sub-total 6,456.000
15% Contractor Overhead 968.400
Grand Total 7,424.400
Per Unit Rate
7,424.40 Rs

Plain cement Concrete (PCC)(38mm) in 1:2:4ratio for foundations and flooring with approved quality of cement, sand and
machine crushed stone aggregate including supply of materials,mixing, laying, curing the work at least 7 days etc all
H-1 1 complete as per approved drawing, Specification and instruction of site engineer.(Rate Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 1.250 1,070.000 1,337.500 1,337.500
Unskilled md 2.000 770.000 1,540.000 1,540.000
2 Material - -
cement sqm 0.130 19,350.000 2,515.500 2,515.500
sand cum 0.180 2,200.000 396.000 396.000
12mm aggregate cum 0.360 2,100.000 756.000 756.000
Sub-total 6,545.000
15% Contractor Overhead 981.750
Grand Total 7,526.750
Per Unit Rate
752.68 Rs

3mm punning in 1:1 ratio for flooring with approved quality of cement, sand including supply of materials,mixing, laying,
curing the work at least 7 days etc all complete as per approved drawing, Specification and instruction of site engineer..(Rate
H-20 1 Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 1.000 1,070.000 1,070.000 1,070.000
Unskilled md 1.000 770.000 770.000 770.000
2 Material - -
cement MT 0.053 19,350.000 1,029.420 1,029.420 0.0532
Sub-total 2,869.420
15% Contractor Overhead 430.413
Grand Total 3,299.833
Per Unit Rate
329.98 Rs

Supplying and SolingStone in proper line and level with sand filling all complete as per approved drawing, Specification and
C-10 1 instruction of site engineer.(Rate Analysis: 1cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
Unskilled md 1.500 770.000 1,155.000 1,155.000
2 Material - -
Block stone cum 1.000 2,400.000 2,400.000 2,400.000
Bond stone cum 0.200 2,450.000 490.000 490.000
Sub-total 4,045.000
15% Contractor Overhead 606.750
Grand Total 4,651.750
Per Unit Rate
4,651.75 Rs

Stone Masonary Work in 1:6 C/S mortar inclusive 10m haulage distance in perfect line level finish including supply of
materials, wetting the bricks, racking the joints and curing the work for at least 7 days all complete as per approved drawing,
C-6 1 Specification and instruction of site engineer. (Rate Analysis: 1cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
Skilled md 1.500 1,070.000 1,605.000 1,605.000
Unskilled md 5.000 770.000 3,850.000 3,850.000
2 Material - -
cement MT 0.106 19,350.000 2,051.100 2,051.100
sand cum 0.470 2,200.000 1,034.000 1,034.000
water ltr 70.000 0.340 23.800 23.800
Block stone cum 1.000 2,400.000 2,400.000 2,400.000
Bond stone cum 0.100 2,450.000 245.000 245.000
Sub-total 11,208.900
15% Contractor Overhead 1,681.335
Grand Total 12,890.235
Per Unit Rate
12,890.24 Rs

Good quality local chimney made Brickwork in 1:4 C/S mortar in superstructure in perfect line level finish including supply of
materials,wetting the bricks,racking the joints and curing the work for at least 7 days all complete as per approved drawing
C-2 1 ,specification and instruction of site engineer. (Rate Analysis: 1cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 1.500 1,070.000 1,605.000 1,605.000
Unskilled md 2.200 770.000 1,694.000 1,694.000
Unskilled md 0.700 770.000 539.000 539.000
2 Material - -
brick no 560.000 15.000 8,400.000 8,400.000
cement MT 0.100 19,350.000 1,935.000 1,935.000
river sand cum 0.280 2,200.000 616.000 616.000
water lt 130.000 0.340 44.200 44.200
extra material 3%of Labour cost 16.000
Sub-total 14,849.200
15% Contractor Overhead 2,227.380
Grand Total 17,076.580
Per Unit Rate
17,076.58 Rs
Well seasoned salwood chaukhats for openable doo with good finish of approved quality incuding supply of materials, fixing
in postion with necessary M.S. hold fasts all complet as per approved drawing, Specification and instruction of site engineer..
G-1 1 (Rate Analysis: 1cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 34.000 1,070.000 36,380.000 36,380.000
Unskilled Labour md 3.400 770.000 2,618.000 2,618.000
2 Material - -
Agrakh cum 1.100 186,984.000 205,682.400 205,682.400
Hold fast no 92.000 20.800 1,913.600 1,913.600
( Steel Screw nail 35mm) no 184.000 2.000 368.000 368.000
Sub-total 246,962.000
15% Contractor Overhead 37,044.300
Grand Total 284,006.300
Per Unit Rate
284,006.30 Rs

Making and fitting / fixing Plywood Panel door shutter of 38 x 100 mm size sal wood frame with 8 mm thick commercial ply on
middle and 4mm thick teak ply on both sides including supply of materials, all necessary hardware fitting all complete as per
G-9 1 approved drawing, Specification and instruction of site engineer.(Rate Analysis: 2.245sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 9.000 1,070.000 9,630.000 9,630.000
Unskilled Labour md 0.900 770.000 693.000 693.000
2 Material - -
sal wood cum 0.035 186,984.000 6,469.646 6,469.646
8mm commercial ply sqm 1.899 409.040 776.767 776.767
4mm teak ply sqm 3.798 258.340 981.175 981.175
listing rm 14.868 35.000 520.380 520.380
gum ls 60.000 60.000
100mm kabja no 3.000 33.280 99.840 99.840
150mm chaskeni no 2.000 26.000 -
mortis lock(normal) no 1.000 988.000 988.000 988.000
nail ls 45.000 45.000
Sub-total 20,263.809
15% Contractor Overhead 3,039.571
Grand Total 23,303.380
Per Unit Rate
10,380.12 Rs

Supplying and Laying of 12.5mm thick cement sand plaster in (1:4) ratio on wall of good finish including supply of materials,
racking the joint, wetting of surfaces & curing the work at least 7days all complete as per approved drawing, Specification
I-1 1 and instruction of site engineer.(Rate Analysis: 100sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 12.000 1,070.000 12,840.000 12,840.000
Unskilled Labour md 16.000 770.000 12,320.000 12,320.000
2 Material - -
Cement MT 0.538 19,350.000 10,410.300 10,410.300
sand cum 1.460 2,200.000 3,212.000 3,212.000
Sub-total 38,782.300
15% Contractor Overhead 5,817.345
Grand Total 44,599.645
Per Unit Rate
446.00 Rs

Supplying & applying Cement putty on plastered surface all complete as per approved drawing, Specification and instruction
I-17 1 of site engineer.(Rate Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 1.000 1,070.000 1,070.000 1,070.000
Unskilled Labour md 1.000 770.000 770.000 770.000
2 Material - -
white putting kg 10.640 45.000 478.800 478.800
Sub-total 2,318.800
15% Contractor Overhead 347.820
Grand Total 2,666.620
Per Unit Rate
266.66 Rs

Supplying & applying 2 coats Emulsion painting in Internal Room of approved colour with one coat of primer Painting over
porperly cleaned surface at outside of building all complete as per approved drawing, Specification and instruction of site
J-5 1 engineer.(Rate Analysis: 100sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 12.000 1,070.000 12,840.000 12,840.000
Unskilled Labour md 8.000 770.000 6,160.000 6,160.000
2 Material - -
Astar ltr 8.100 271.000 2,195.100 2,195.100
emulsion paint ltr 16.000 600.000 9,600.000 9,600.000
Sub-total 30,795.100
15% Contractor Overhead 4,619.265
Grand Total 35,414.365
Per Unit Rate
354.14 Rs

Supplying & applying 2 coats of weather paint at outside of Building of approved colour with one coat of primer Painting over
porperly cleaned surface at outside of building all complete as per approved drawing, Specification and instruction of site
J-26 1 engineer.(Rate Analysis: 100sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
skilled md 5.800 1,070.000 6,206.000 6,206.000
Unskilled Labour md 5.800 770.000 4,466.000 4,466.000
2 Material - -
Astar ltr 8.000 271.000 2,168.000 2,168.000
weathercoat ltr 16.000 1,135.000 18,160.000 18,160.000
Sub-total 31,000.000
15% Contractor Overhead 4,650.000
Grand Total 35,650.000
Per Unit Rate
356.50 Rs

supplying & Laying Supplying & laying Porcelain Non Glazed tile (1:4) on Toilet fixing in proper shape & size all complete as
H-6 1 per approved drawing, Specification and instruction of site engineer.(Rate Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 13.000 1,070.000 13,910.000 13,910.000
Unskilled Labour md 4.500 770.000 3,465.000 3,465.000
2 Material - -
Cement MT 0.056 19,350.000 1,083.600 1,083.600
sand cum 0.152 2,200.000 334.400 334.400
white cement kg 3.228 45.000 145.260 145.260
porcelain non glazed tile sqm 11.000 753.200 8,285.200 8,285.200
Sub-total 27,223.460
15% Contractor Overhead 4,083.519
Grand Total 31,306.979
Per Unit Rate
3,130.70 Rs

Sand filling including supply of filling materials, watering, ramming etc. all complete as per approved drawing, Specification
B-3 1 and instruction of site engineer.(Rate Analysis: 1cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
Unskilled md 0.700 770.000 539.000 539.000
2 Material - -
sand cum 1.100 2,200.000 2,420.000 2,420.000
water ltr 5.000 0.340 1.700 1.700
Sub-total 2,960.700
15% Contractor Overhead 444.105
Grand Total 3,404.805
Per Unit Rate
3,404.81 Rs

D-4 1.00 PCC for RCC Works M25 (1:1:2) by Using Mixture including Material

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 0.500 1,070.00 535.00 535.000
Unskilled md 3.500 770.00 2,695.00 2,695.000
2.00 Material - -
Cement MT 0.610 19,350.00 11,803.50 11,803.500
40mm-aggregrate Cum 0.640 2,000.00 1,280.00 1,280.000
20mm-aggregrate cum 0.210 2,100.00 441.00 441.000
Sand Cum 0.425 2,200.00 935.00 935.000
water ltr 300.000 0.34 102.00 102.000
Diesel ltr 3.000 97.00 291.00 291.000
Petrol ltr 0.100 108.00 10.80 10.800
3.00 Equipment - -
0.20-0.28 Cum Mixture hr 0.600 800.00 480.00 480.000
Vibrator hr 0.250 100.00 25.00 25.000
Sub-total 18,598.300
15% Contractor Overhead 2,789.745
Grand Total 21,388.045
Per Unit Rate
21,388.05 Rs

C-2 b 1.00 Brickworks (1:41) C/S motar


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 1.500 1,070.00 1,605.00 1,605.000
Unskilled md 2.500 770.00 1,925.00 1,925.000
2.00 Material - -
Brick Nos 520.000 15.00 7,800.00 7,800.000
Cement Mt 0.100 19,350.00 1,935.00 1,935.000
Sand cum 0.280 2,200.00 616.00 616.000
Water ltr 130.000 0.34 44.20 44.200
Sub-total 13,925.200
15% Contractor Overhead 2,088.780
Grand Total 16,013.980
Per Unit Rate
16,013.98 Rs
Note : Brick size 230x110x55= 520 nos
required for 1 cum

Supplying and Laying of 12.5mm thick cement sand plaster in (1:3) ratio on wall of good finish including supply of materials,
racking the joint, wetting of surfaces & curing the work at least 7days all complete as per approved drawing, Specification
I-1 1 and instruction of site engineer.(Rate Analysis: 100sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 12.000 1,070.000 12,840.000 12,840.000
Unskilled Labour md 16.000 770.000 12,320.000 12,320.000
2 Material - -
Cement MT 0.625 19,350.000 12,093.750 12,093.750
sand cum 1.280 2,200.000 2,816.000 2,816.000
Sub-total 40,069.750
15% Contractor Overhead 6,010.463
Grand Total 46,080.213
Per Unit Rate
460.80 Rs

I-1 1 16mm Marble Finishing


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 2.000 1,070.000 2,140.000 2,140.000
Unskilled Labour md 8.000 770.000 6,160.000 6,160.000
2 Material - -
Cement MT 0.130 19,350.000 2,515.500 2,515.500
sand cum 0.183 2,200.000 402.600 402.600
16mm marbel cum 11.000 1,883.000 20,713.000 20,713.000
Oxalic Acid kg 0.370 118.000 43.660 43.660
Mainn polish kg 0.118 345.000 40.710 40.710
Tarpentain lt 0.538 208.000 111.904 111.904
Carbondam stone 120.000 120.000
-
3 Marble polish manpower md 13.500 700.000 9,450.000 9,450.000
Sub-total 41,697.374
15% Contractor Overhead 6,254.606
Grand Total 47,951.980
Per Unit Rate
4,795.20 Rs
Providing and fixing Structural Glazing of aluminum section in natural or color anodized/powder coated color Section size
(60x75+13x1.6 mm) fitted with 5 mm color glass .
1 (average panel area 6.00 Sq.ft.)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Structure Glazing cum 1.000 6,843.360 6,843.360 6,843.360


Sub-total 6,843.360
15% Contractor Overhead 1,026.504
Grand Total 7,869.864
Per Unit Rate
7,869.86 Rs

B-1 1 Earthwork in excavation from 0.8cum capacity Hydraulic Excavator


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Diesel ltr 0.125 97.000 12.106 12.106


Excavator 0.8 cum capacity hr 0.010 3,150.000 32.760 32.760

Sub-total 44.866
15% Contractor Overhead 6.730
Grand Total 51.595
Per Unit Rate
51.60 Rs

Supplying and Laying of 12.5mm thick cement sand plaster in (1:4) ratio on ceiling of good finish including supply of
materials, racking the joint, wetting of surfaces & curing the work at least 7days all complete as per approved drawing,
Specification and instruction of site engineer.(Rate Analysis: 100sqm)
I-1 1
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
skilled md 15.000 1,070.000 16,050.000 16,050.000 20
Unskilled md 20.000 770.000 15,400.000 15,400.000
2 Material - -
sand cum 1.460 2,200.000 3,212.000 3,212.000
cement MT 0.538 19,350.000 10,410.300 10,410.300
Sub-total 45,072.300
15% Contractor Overhead 6,760.845
Grand Total 51,833.145
Per Unit Rate
518.33 Rs

A-4 1 Surface dressing and filling hole (Rate Analysis: 1sqm)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Unskilled md 0.010 770.000 7.700 7.700
Sub-total 7.700
15% Contractor Overhead 1.155
Grand Total 8.855
Per Unit Rate
8.86 Rs

Filling with 15-150mm broken brick all complete as per approved drawing, Specification and instruction of site engineer.(Rate
H-19 1 Analysis: 10cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
skilled md 10.000 1,070.000 10,700.000 10,700.000
2 Material - -
broken brick cum 11.000 2,200.000 24,200.000 24,200.000
Sub-total 34,900.000
15% Contractor Overhead 5,235.000
Grand Total 40,135.000
Per Unit Rate
4,013.50 Rs
Supplying & applying spiral steel ladder 4'-6"dia black pipe all complete as per approved drawing, Specification and
M-5 1 instruction of site engineer.
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
spiral staircase rm 1.000 10,004.000 10,004.000 10,004.000
Sub-total 10,004.000
15% Contractor Overhead 1,500.600
Grand Total 11,504.600
Per Unit Rate
11,504.60 Rs

Supplying & applying iron benches all complete as per approved drawing, Specification and instruction of site engineer.(Rate
Analysis: 1no)
Level Qty Unit Rate Amount Total Amount Remarks
labour cost for iron works
Skilled 0.35 Md 1070.00 374.50 374.500
Unskilled 0.45 Md 770.00 346.50 346.500
Material
iron (40x40x2.6) 49.932 Kg 102.00 5093.06 5,093.064
12mm iron strips 0.509 Kg 102.00 51.89 51.885
Paints 0.25 lit 468.00 117.00 117.000
Sub Total (M) 5,982.949
15% Contractor Overhead 897.442
Grand Total 6,880.392
Per Unit Rate
6,880.39 Rs

supplying & Laying 16mm marble in 12.5mm 1:3 cement mortar in proper shape & size all complete as per approved drawing,
H-35 1 Specification and instruction of site engineer.(Rate Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 14.000 1,070.000 14,980.000 14,980.000
Unskilled Labour md 12.000 770.000 9,240.000 9,240.000
2 Material - -
Cement MT 0.063 19,350.000 1,219.050 1,219.050
sand cum 0.128 2,200.000 281.600 281.600
main polish kg 0.118 286.000 33.748 33.748
turpentile lt 0.538 115.000 61.870 61.870
oxalic acid kg 0.370 208.000 76.960 76.960
16mm marble sqm 11.000 1,959.090 21,549.990 21,549.990
carborundum ls 120.000 120.000
Sub-total 47,563.218
15% Contractor Overhead 7,134.483
Grand Total 54,697.701
Per Unit Rate
5,469.77 Rs

Plain cement concrete(PCC) in 1:3:6 ratio inclusive 30m haulage for foundations and flooring with approved quality of
cement,sand and machine crushed stone aggregate including supply of materials,mixing,laying,curing the work at least 7
D-1 1 days etc all complete as per approved drawing specification and instruction of site engineer.( Rate Analysis: 1Cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 0.500 1,070.000 535.000 535.000
Unskilled Labour md 3.500 770.000 2,695.000 2,695.000
2 Material - -
Cement MT 0.220 19,350.000 4,257.000 4,257.000
40mm Aggregate Cum 0.650 2,000.000 1,300.000 1,300.000
20mm Aggregate Cum 0.240 2,100.000 504.000 504.000
Sand Cum 0.425 2,200.000 935.000 935.000
diesel lt 3.000 97.000 291.000 291.000
petrol lt 0.100 108.000 10.800 10.800
Water Ltr 100.000 0.340 34.000 34.000
3 Equipment - -
mixer hr 0.600 800.000 480.000 480.000
Vibrator hr 0.250 100.000 25.000 25.000
Sub-total 11,066.800
15% Contractor Overhead 1,660.020
Grand Total 12,726.820
Per Unit Rate
12,726.82 Rs
D-4 1.00 PCC for RCC Works (1:1.5:3) by Using Mixture including Material.( Rate Analysis: 1Cum)

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1.00 Labour Cost


Skilled md 0.500 1,070.00 535.00 535.000
Unskilled md 3.500 770.00 2,695.00 2,695.000
2.00 Material - -
Cement MT 0.400 19,350.00 7,740.00 7,740.000
40mm-aggregrate Cum 0.570 2,000.00 1,140.00 1,140.000
20mm-aggregrate cum 0.290 2,100.00 609.00 609.000
Sand Cum 0.425 2,200.00 935.00 935.000
water ltr 200.000 0.34 68.00 68.000
Diesel ltr 3.000 97.00 291.00 291.000
Petrol ltr 0.100 108.00 10.80 10.800
3.00 Equipment - -
0.20-0.28 Cum Mixture hr 0.600 800.00 480.00 480.000
Vibrator hr 0.250 100.00 25.00 25.000
Sub-total 14,528.800
15% Contractor Overhead 2,179.320
Grand Total 16,708.120
Per Unit Rate
16,708.12 Rs
Providing and fixing Structural Glazing of aluminum section in natural or color anodized/powder coated color Section size
(60x50+13x1.3 mm) fitted with 5 mm color glass. (average panel area 6.00 Sq.ft.) all complete as per approved drawing,
G-21 1 Specification and instruction of site engineer.( Rate Analysis: 1sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Material
structural glazing sqm 1.000 5,896.480 5,896.480 5,896.480
Sub-total 5,896.480
15% Contractor Overhead 884.472
Grand Total 6,780.952
Per Unit Rate
6,780.95 Rs

Providing and fixing Aluminium partition with 5 mm thick glass and 9 mm thick laminated board of section (101 x45x1.1) all
1 complete as per approved drawing, Specification and instruction of site engineer.( Rate Analysis: 1sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Material
aluminium partition sqm 1.000 4,745.160 4,745.160 4,745.160
Sub-total 4,745.160
15% Contractor Overhead 711.774
Grand Total 5,456.934
Per Unit Rate
5,456.93 Rs

Supplying & applying Panipatti on plastered surface all complete as per approved drawing, Specification and instruction of
I-15 1 site engineer.( Rate Analysis: 1 rm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 0.025 1,070.000 26.750 26.750
Unskilled Labour md 0.010 770.000 7.700 7.700
2 Material - -
Cement MT 0.007 19,350.000 135.450 135.450
sand cum 0.004 2,200.000 8.800 8.800
waterproofing lt 0.000 70.000 0.007 0.007
Sub-total 178.707
15% Contractor Overhead 26.806
Grand Total 205.513
Per Unit Rate
205.51 Rs

sallo planks with good finish of approved quality incuding supply of materials, fixing in postion with necessary M.S. hold fasts
1 all complet as per approved drawing, Specification and instruction of site engineer..(Rate Analysis: 1cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 34.000 1,070.000 36,380.000 36,380.000
Unskilled Labour md 3.400 770.000 2,618.000 2,618.000
2 Material - -
local wood cum 1.100 68,000.000 74,800.000 74,800.000
Hold fast no 92.000 20.800 1,913.600 1,913.600
( Steel Screw nail 35mm) no 184.000 2.000 368.000 368.000
Sub-total 116,079.600
15% Contractor Overhead 17,411.940
Grand Total 133,491.540
Per Unit Rate
133,491.54 Rs

Supplying and applying 4.5X20mm steel Grill with 12X12 solid core square rod all complete as per approved drawing
M-3 1 ,specification and instruction of site engineer. (Rate Analysis: 10sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
skilled md 0.700 1,070.000 749.000 749.000
Unskilled Labour md 0.600 770.000 462.000 462.000
2 Material - -
Iron works for Grill kg 28.240 128.000 3,614.720 3,614.720
Iron Rod kg 215.000 102.000 21,930.000 21,930.000
Sub-total 26,755.720
15% Contractor Overhead 4,013.358
Grand Total 30,769.078
Per Unit Rate
3,076.91 Rs

Spplying & applying 40mm thk vetrified tile all complete as per approved drawing, Specification and instruction of site
H-30 1 engineer.(Rate Analysis: 1sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 1.3 1,070.000 1,391.000 1,391.000
Unskillled md 0.45 770.000 346.500 346.500
2 Material - -
cement Mt 0.015 19,350.000 290.250 290.250
sand cum 0.050 2,200.000 110.000 110.000
vetrified clay sqm 1.100 1,000.680 1,100.748 1,100.748
Sub-total 3,238.498
15% Contractor Overhead 485.775
Grand Total 3,724.273
Per Unit Rate
3,724.27 Rs

for staircase:Supplying & applying 38 mm dia stainless steel handrail pipe with 38mm dia stainless steel vertical post at 2m
interval with two layers of 25mm dia stainless steel member in between handrail and floor all complete as per approved
M-15 1 drawing, Specification and instruction of site engineer.(Rate Analysis: 9.15sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks

1 Labour Cost
skilled md 7.78 1,070.000 8,324.600 8,324.600
Unskillled md 11.35 770.000 8,739.500 8,739.500
2 Material - -
38mm steel pipe m 15.490 385.000 5,963.650 5,963.650
25mm steel pipe m 20.000 260.000 5,200.000 5,200.000
gas welding 500.000 500.000
Sub-total 28,727.750
15% Contractor Overhead 4,309.163
Grand Total 33,036.913
Per Unit Rate
3,610.59 Rs
Norms no:- 6-1 ka, 3 Per m3
Name of work: Stone Masonry (Rubble) work in 1:6 Cement sand mortar
S.N. Resources Type Unit Quantity Rate Amounts Remarks
1 Manpower Skilled pd 1.50 1070.00 1605
Unskilled pd 5.00 770.00 3850.00
Sub-Total 5455.00
2 Materials Cement MT 0.106 19350.00 2051.10
Sand cum 0.47 2200.00 1034.00
Block ston cum 1.00 2400.00 2400.00
Bond stond cum 0.10 2450.00 245.00
Sub-total 5730.10
Total 11185.10
Overhead @ 15%
Grand Total 11185.10

Norms no :- 11-18 Per: 10m2


Pointing Works on the Stone Paving (Size of stone 46cmx46cm) with 1:1 Cement Sand Mortar
S.N. Resources Type Unit Quantity Rate Amounts Remarks
1 Manpower Skilled pd 0.50 1070.00 535
Unskilled pd 0.500 770.00 385.00
Sub-Total 920.00
2 Materials Cement Kg 4.200 19.35 81.27
Sand cum 0.003 2200.00 6.60
Sub-total 87.87
Total 1007.87
Overhead @ 15% 151.18
Grand Total 1159.05
Rate per m2 115.905
Norms Page no 52-53

Norms Page no 52-53

Norms Page no 52-53


Norms Page no 52-53

Norms Page no 52-53


Norms Page no 52-53

Norms Page no 97
Norms Page no 66-75

Norms Page no 75
Norms Page no 75-78
Norms Page no 75
17.1

0.00050868
Norms Page no 66-75
Norms Page no 75
DISTRICT RATE

SN Item Name District Rate Transportation rate Adopted rate UNIT Remarks

A Labour
1 skilled 1,070.00 1,070.00 man/day
2 semi-Skilled 855.00 855.00 man/day
3 Unskilled 770.00 770.00 man/day
4 Technician 855.00 855.00 man/day
B Material -
1 Brick 15.00 15.00 no
2 Sand 2,200.00 2,200.00 cum
2' sand for soling 2,000.00 2,000.00 cum
3 Cement 16,600.00 2750 19,350.00 MT
4 40 mm Aggregate 2000 2,000.00 cum
5 20 mm Aggregate 2100 2,100.00 cum
6 10 mm Aggregate 2100 2,100.00 cum
7 Water 0.34 0.34 lt
8 TMT Rod 87,100.00 2750 89,850.00 MT
9 Gi Binding Wire 101.00 101.00 KG
10 19mm Ply Board 731.96 731.96 sqm
11 12 mm Ply board 527.44 527.44 sqm
12 Local Wood 68,000.00 68,000.00 cum
13 Iron Bolt for Formworks 150.00 150.00 KG
14 Nails 104.00 104.00 KG
per kg=Rs
15 Iron Prop Pipe 1,795.71 48.41375 1,844.12 no 102(5.03 kg/m)
16 All Type Iron Angle 78.00 78.00 KG
17 Red Oxide Paint 315.00 315.00 LT
Elastocrete cementitious
18 elastomeric water proofing 559.52 559.52 sqm
material
19 Enamel Paint 468.00 468.00 lt
20 Astar 271.00 271.00 lt
21 Iron works for Grill 128.00 128.00 KG
22 iron square pipe 102.00 102.00 KG
23 Iron Rod 87.10 87.10 KG
CGI Sheet (0.5 mm (24
24 675.11 675.11 SQM
Guage))
25 8mm nut Bolt 138.00 138.00 KG
26 8mm nut Bolt 23.00 23.00 no 1kg=6no
27 J hook 322.00 322.00 KG
28 J hook 23.00 23.00 NO 1kg=14no
29 Bitumen Washer 1.00 1.00 NO
30 ( Steel Screw nail 35mm) 2.00 2.00 no

31 Aluminium door swing type 6,994.00 6,994.00 sqm

Aluminium sliding window


32 6,456.00 6,456.00 sqm
without ventilator

33 Block stone 2,400.00 2,400.00 cum


34 Bond stone 2,450.00 2,450.00 cum
35 Agrakh 186,984.00 186,984.00 cum
36 Hold fast 20.80 20.80 no
37 8mm commercial ply 409.04 409.04 sqm
38 4mm teak ply 258.34 258.34 sqm
39 listing 35.00 35.00 rm
40 100mm kabja 33.28 33.28 no
41 150mm chaskeni 26.00 26.00 no
42 mortis lock(normal) 988.00 988.00 no
43 emulsion paint 600.00 600.00 ltr
44 weathercoat 1,135.00 1,135.00 ltr
45 porcelain non glazed tile 753.20 753.20 sqm
46 white putting 45.00 45.00 kg
47 diesel 97.00 97.00 lt
48 petrol 108.00 108.00 lt
49 vibrator 100.00 100.00 hr
50 roller(8-10 Mt) 700.00 700.00 hr
51 mixer 800.00 800.00 hr
52 excavator(0.8 cum) 1,800.00 1,800.00 hr
53 broken brick 2,200.00 2,200.00 cum
54 main polish 286.00 286.00 kg
55 turpentile 115.00 115.00 lt
56 oxalic acid 208.00 208.00 lt
57 waterproofing 70.00 70.00 lt
58 16mm marble 1,959.09 1,959.09 sqm
59 25mm steel pipe 260 260.00 sqm
60 38mm steel pipe 385 385.00 sqm

61 collapsable gate inclusive 5,380.00


fitting 5,380.00 sqm
62 iron gate 16 gauge inclusive 6,994.00
fitting 6,994.00 sqm
63 10 SWGG chain link 2"x2'' 517.00
mesh size 517.00 sqm
64 spiral staircase 10,004.00 10,004.00 no
65 rolling shutter 2,288.00 2,288.00 sqm
66 collapsable gate 4,788.20 4,788.20 sqm
67 Gi barbed wire 13.91 13.91 m
68 gray interlocking block 527.24 527.24 sqm
69 vetrified clay 1,000.68 1,000.68 sqm
Sn Description Rate
Earthwork in excavation in soft soil including hauling disposal of soil upto
1.01 distance of 30m and lift upto 1.5 m
638.45
Earthwork in excavation in medium soil including hauling disposal of soil
1.02 upto distance of 30m and lift upto 1.5 m
729.65
Earthwork in excavation in hard soil including hauling disposal of soil upto
1.03 distance of 30m and lift upto 1.5 m
2,736.20
supplying and soling local flat brick in proper line and level with sand filling
2.00 all complete as per approved drawing,specification and instruction of site
engineer. 1,037.88
Plain cement concrete(PCC) in 1:2:4 ratio for foundations and flooring
with approved quality of cement,sand and machine crushed stone
3.00 aggregate including supply of materials,mixing,laying,curing the work at
least 7 days etc all complete as per approved drawing specification and
instruction of site engineer. 15,070.75
Plain cement concrete(PCC) in 1:3:6 ratio for foundations and flooring
with approved quality of cement,sand and machine crushed stone
4.00 aggregate including supply of materials,mixing,laying,curing the work at 12,726.82
least 7 days etc all complete as per approved drawing specification and
instruction of site engineer.

Plain Cement Concrete(PCC) for RCC works M25 (1:1:2) for


slab/lintels/columns/beams with approved quality of cement,sand and
5.00 machine crushed stone aggregate including supply of
materials,mixing,laying,curing the work at least 7 days etc all complete as
per approved drawing specification and instruction of site engineer.
21,388.05

Plain Cement Concrete(PCC) for RCC works M20 (1:1.5:3) for


slab/lintels/columns/beams with approved quality of cement,sand and
6.00 machine crushed stone aggregate including supply of
materials,mixing,laying,curing the work at least 7 days etc all complete as
per approved drawing specification and instruction of site engineer.
16,708.12
TMT steel reinforcement bar of Fe 500 grade including
supplying,straightening,cleaning,cutting,binding and fixing in position with
7.00 annealed tying binding wire all complete as per approved drawing
specification and instruction of site engineer 135,047.38
Formwork,for Column with 19mm thick waterproof ply board and steel
post for all works necessary propping,scaffolding,staging,supporting
8.00 inclusive of wedging and cutting holes for utilization till the support if fully
unyielding nett all complete as per approved drawing ,specification and
instruction of site engineer. 1,544.94
Formwork,for Beam with 19mm thick waterproof ply board and steel post
for all works necessary propping,scaffolding,staging,supporting inclusive
9.00 of wedging and cutting holes for utilization till the support if fully unyielding
nett all complete as per approved drawing ,specification and instruction of
site engineer. 1,241.34
Formwork,for Slab with 15mm thick waterproof ply board and steel post
for all works necessary propping,scaffolding,staging,supporting inclusive
10.00 of wedging and cutting holes for utilization till the support if fully unyielding
nett all complete as per approved drawing ,specification and instruction of
site engineer. 882.75
Good quality local chimney made Brickwork in 1:4 C/S mortar upto
Ground Floor in perfect line level finish including supply of
11.00 materials,wetting the bricks,racking the joints and curing the work for at
least 7 days all complete as per approved drawing ,specification and
instruction of site engineer. 16,620.03
Good quality local chimney made Brickwork in 1:4 C/S mortar in
Superstructure in perfect line level finish including supply of materails,
12.00 wetting the bricks, racking the joints and curing the work for at least 7
days all complete as per approved drawing, Specification and instruction
of site engineer. 17,076.58
Supplying and fitting of Iron Works with Red Oxide paint as per approved
13.00 drawing ,specification and instruction of site engineer.
154.87

Earth filling of Excavated surface in 150 mm thick layer watering ,ramming


14.00 including supply of filling materials within 10m distance all complete as
per approved drawing ,specification and instruction of site engineer.
444.71
Elastocrete cementitious elastomeric water proofing coating 2
components capacity per kg 6 sq.ft for 2 coat including supplying and
15.00 applying all complete work as per approved drawing ,specification and
instruction of site engineer. 643.45
Supplying and applying 2 coats of ready made enamel paint of approved
colour over 1 coat of primer Painting over properly sanded surface all
16.00 complete as per approved drawing ,specification and instruction of site
engineer. 329.86
Supplying and applying 4.5X20mm steel Grill with 12X12 solid core
17.00 square rod all complete as per approved drawing ,specification and
instruction of site engineer. 2,708.51

Supplying and fitting 0.5mm CGI colour sheet for Roof all complete as per
18.00 approved drawing ,specification and instruction of site engineer.
1,329.49
Providing and fixing Single Panel Swing Door of aluminium section in
naturally anodized or black anodized/powder coated color Section size
19.00 (102*45*1.5 mm) fitted with 5 mm clear glass or 9 mm both side laminated
board (excluding the cost of handle). 8,043.10
Providing and fixing 2 or 3 Panel Sliding window of aluminium section in
naturally anodized or black anodized/powder coated color, Section size
20.00 (87*56*1.2 mm) fitted with 5 mm clear glass without fly mesh shutter
(Window size 6'*5' or average area 30 Sq. feet per window). 7,424.40
Plain cement Concrete (PCC)(38mm) in 1:2:4ratio for foundations and
flooring with approved quality of cement, sand and machine crushed
21.00 stone aggregate including supply of materials,mixing, laying, curing the
work at least 7 days etc all complete as per approved drawing,
Specification and instruction of site engineer. 752.68
3mm punning in 1:1 ratio for flooring with approved quality of cement,
sand including supply of materials,mixing, laying, curing the work at least
22.00 7 days etc all complete as per approved drawing, Specification and
instruction of site engineer. 329.98
Supplying and SolingStone in proper line and level with sand filling all
23.00 complete as per approved drawing, Specification and instruction of site
engineer. 4,651.75
Stone Masonary Work in 1:6 C/S mortar in perfect line level finish
including supply of materials, wetting the bricks, racking the joints and
24.00 curing the work for at least 7 days all complete as per approved drawing,
Specification and instruction of site engineer. 12,890.24
Well seasoned salwood chaukhats for openable doo with good finish of
approved quality incuding supply of materials, fixing in postion with
25.00 necessary M.S. hold fasts all complet as per approved drawing,
Specification and instruction of site engineer. 284,006.30
Making and fitting / fixing Plywood Panel door shutter of 38 x 100 mm size
sal wood frame with 8 mm thick commercial ply on midle and 4mm thick
26.00 teak ply on both sides including supply of materials, all necessary
hardware fitting all complete as per approved drawing, Specification and
instruction of site engineer. 10,380.12

Supplying and Laying of 12.5mm thick cement sand plaster in (1:4) ratio
on ceiling of good finish including supply of materials, racking the joint,
27.00 wetting of surfaces & curing the work at least 7days all complete as per 518.33
approved drawing, Specification and instruction of site engineer.

Supplying and Laying of 12.5mm thick cement sand plaster in (1:4) ratio
on wall of good finish including supply of materials, racking the joint,
28.00 wetting of surfaces & curing the work at least 7days all complete as per
approved drawing, Specification and instruction of site engineer.
446.00

Supplying & applying Cement putty on plastered surface all complete as


29.00 per approved drawing, Specification and instruction of site engineer.
266.66
Supplying & applying 2 coats Emulsion painting in Internal Room of
approved colour with one coat of primer Painting over porperly cleaned
30.00 surface at outside of building all complete as per approved drawing,
Specification and instruction of site engineer. 354.14
Supplying & applying 2 coats of weather paint at outside of Building of
approved colour with one coat of primer Painting over porperly cleaned
31.00 surface at outside of building all complete as per approved drawing,
Specification and instruction of site engineer. 356.50
supplying & Laying Supplying & laying Porcelain Non Glazed tile on Toilet
32.00 fixing in proper shape & size all complete as per approved drawing,
Specification and instruction of site engineer. 3,130.70
Sand filling including supply of filling materials, watering, ramming etc. all
33.00 complete as per approved drawing, Specification and instruction of site
engineer. 3,404.81
34.00 Surface dressing and filling hole (Rate Analysis: 1sqm) 8.86
Supplying & fitting benches(1.5X0.6X0.75) all complete as per approved
35.00 drawing, Specification and instruction of site engineer.
6,880.39
Supplying & applying grass for Picnic spot portion(dubo) all complete as
36.00 per approved drawing, Specification and instruction of site engineer.
322.80
Filling with 15-150mm broken brick all complete as per approved
37.00 drawing, Specification and instruction of site engineer. 4,013.50

Supplying & applying spiral steel ladder 4'-6"dia black pipe all complete
38.00 as per approved drawing, Specification and instruction of site engineer. 11,504.60

supplying & Laying 16mm marble in 12.5mm 1:3 cement mortar in proper
39.00 shape & size all complete as per approved drawing, Specification and 5,469.77
instruction of site engineer.(Rate Analysis: 10sqm)

Providing and fixing Structural Glazing of aluminum section in natural or


color anodized/powder coated color Section size (60x50+13x1.3 mm)
40.00 fitted with 5 mm color glass. (average panel area 6.00 Sq.ft.) all complete 6,780.95
as per approved drawing, Specification and instruction of site engineer.

Providing and fixing Aluminium partition with 5 mm thick glass and 9 mm


41.00 thick laminated board of section (101 x45x1.1) all complete as per 5,456.93
approved drawing, Specification and instruction of site engineer.
Supplying & applying 3mm thick skirting on plastered surface all complete
42.00 as per approved drawing, Specification and instruction of site engineer
205.51
supplying & Laying 10 SWGG chain link 2"x2'' mesh size in proper shape
43.00 & size all complete as per approved drawing, Specification and
instruction of site engineer 517.00
sallo planks with good finish of approved quality incuding supply of
materials, fixing in postion with necessary M.S. hold fasts all complet as
44.00 per approved drawing, Specification and instruction of site engineer.
133,491.54
Supplying and applying 4.5X20mm steel Grill with 12X12 solid core
46.00 square rod all complete as per approved drawing ,specification and
instruction of site engineer. 3,076.91
Spplying & applying 40mm thk vetrified tile all complete as per approved
48.00 drawing, Specification and instruction of site engineer. 3,724.27

Supplying and fitting rolling shutter all complete as per approved


49.00 drawing ,specification and instruction of site engineer. 2,631.20

Supplying and fitting collapsable gate all complete as per approved


50.00 drawing ,specification and instruction of site engineer. 5,506.43

51.00 GI wire barbed wire 80.60

for staircase:Supplying & applying 38 mm dia stainless steel handrail pipe


with 38mm dia stainless steel vertical post at 2m interval with two layers of
53.00 25mm dia stainless steel member in between handrail and floor all 3,610.59
complete as per approved drawing, Specification and instruction of site
engineer.
54.00 Compacting soil spreaded in 20/20 cm layers by roller 13.44
55.00 Excavation of soft soil using hydraulic excavator (0.8 cum) 34.71
56.00 Excavation of hard soil using hydraulic excavator (0.8 cum) 42.61
Providing ruled pointing work on exposed face of retaining stone
wall stucture in cement sand (1:3) mortar including wetting, raking
57.00
of joints as per drawings, specifications and instructions of the site
engineer. 115.90505
Providing, laying and curing random rubble stone masonry works in
cement, sand mortar (1:6) in foundation and above finished upto
58.00 Plinth level in perfect lines & level including wetting the stones,
packing the joints as per specification, drawings & instructions of
the site engineer. 11185.10
Black Gravel
S.N TYPE UNIT District Rate UNIT WT. Topped Rate per Road(km) Rate per Transportation
(Surkhet) (Kg/m3) Road(km) kg/km kg/km Cost
1 Cement Kg 50.00 0.043 10.00 0.06 2.75
4 TMT rod kg 50.00 0.043 10.00 0.06 2.75
5 Iron prop pipe kg 50.00 0.043 10.00 0.06 2.75

Prepared By: Checked By: Approved By:

Potrebbero piacerti anche